1216.1DESCRIPTION—This work is to furnish, install, modify, repair, replace, and remove components
of a Closed Circuit Television (CCTV) Camera subsystem.
1216.2MATERIAL—Section 1210.2
1216.3CONSTRUCTION—Section 1210.3 and as follows:
or bent sections. Inspect and test lowering device. Check bolts for rust and tightness. Install or replace screening at the base plate as necessary.
loose connections, frayed cables, lowering device, and general condition. Ensure proper ventilation. Check attachment hardware. Clean, repaint, and repair as necessary.
trained, experienced, and qualified hoist inspection, maintenance, and repair personnel. The hoist operator will not perform frequent and periodic inspections, maintenance, or repairs on a manually operated hoist, unless the operator has been trained to perform such inspections, maintenance, or repairs on a manually operated hoist and is designated by the hoist manu facturer to perform such inspections, maintenance, and repairs. For information on hoist inspection, maintenance, and repairs, always refer to the manual furnished by the manufacturer of the hoist or contact the manufacturer directly.
After On-call Maintenance (OM) has been completed, perform Preventive Maintenance (PM) as specified in Section 1216.3(a).
1216.4MEASUREMENT AND PAYMENT—
All labor, materials, and equipment required for routine preventive maintenance are incidental to this item including, but not limited to , the Statewide Device Identification Number, cleaning materials, caulk, metal meshing, lubricants, filters, lamps, paint, surge suppressors, fuses, circuit breakers, attachment hardware, insect prevention measures, rodent control measures, clearing and grubbing, selective tree trimming, snow and ice removal, and weed control measures. Mobilization is incidental to this item.
Mobilization will not be paid for procurement of parts. Travel to and from the site and district stockpile is incidental to this item.
Repair time will not be paid for procurement of parts. Travel to and from the site and district stockpile is incidental to this item. Site specific snow and ice removal requested by the Department is included within this item.
Includes all cables, connectors, equipment racks, conductor(s), and other parts necessary for proper installation and configuration of a CCTV Camera subsystem.
Get an email when 1216 changes
Pennsylvania revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.