1206. 1 1206. 3(a)
1206.1DESCRIPTION —This work is to furnish, install, modify, repair, replace, and remove non -device
specific ITS components and equipment essential to a fully functional and operational system.
1206.2MATERIAL —Section 12 01.2
1206.3CONSTRUCTION —Section 12 01.3 and as follows:
Publication 697, and the following: Submit , for approval, an annual schedule of all PM activities within 2 weeks of receiving notice to proceed . Comply with the following example submission schedule:
Preventive Maint. Report No. Complete Field Inspection Submit PM Report
PM is required before and after the winter season annually . Report all deficiencies on the PM checklist directly to the Department within 24 hours. Report all critical deficiencies directly to the Department immediately while on -site. Submit one typed hard copy or electronic copy of the monthly status report showing all PM completed during each month. Include the following in the report :
• Detailed description of the PM performed .
• Copies of payroll records and work reports .
• PM Checklists ; including test results .
and service poles associated with ITS devices. Provide required tree trimming and brush clearing work. Spray and place weed control measures around each device. Remove snow and ice buildup around enclosure(s), maintenance area(s), and device(s). This also includes removing snow and ice from solar panels , camera housings, beacons, transmitters, detectors, and wireless communication devices.
powered supply enclosures , hub enclosures , delineator posts, service poles, and junction and pull boxes, for damage, corrosion, water damage, and leaks. Verify absence of water from the inside bottom of enclosure . If water is present, ensure the means for drainage ha ve not become obstructed. Remove obstructions, if present . Apply caulking, if required, to prevent water from entering enclosure . Remove all objects or debris inconsistent with control enclosure materials such as nests made by rodents, birds , or flying insects, etc. Spray for insect prevention. Install or replace rodent control measures as necessary. Ensure conduit openings into the enclosure are sealed with metal meshing material to prev