1−26 directed, and will be paid for as provided under Subsection 109.04; Differing Site Conditions, Changes, Extra Work, and Force Account Work .
104.06 SUSPENSIONS OF WORK ORDERED BY THE ENGINEER . If the performance of all
or any portion of the work is suspended or delayed by the Engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and the Contractor belie ves that additional compensation and/or Contract time is due as a result of such suspension or delay, the Contractor shall submit to the Engineer in writing a request for adjustment within seven calendar days of receipt of the notice to resume work. The request shall set forth the reasons and support for such adjustment. Upon receipt, the Engineer will evaluate the Contractor's request. If the Engineer agrees that the cost and/or time required for the performance of the Contract has increased as a result of such suspension and the suspension was caused by conditions beyond the control of and not the fault of the Contractor, its suppliers, or subcontractors at any approved tier, and not caused by weather, the Engineer will make an adjustment (excluding profit) and modify the Contract in writing accordingly. The Contractor will be notified of the Engineer's determination whether or not an adjustment of the Contract is warranted. No Contract adjustment will be allowed unless the Contractor has submitted the request for adjustment within the time prescribed. No Contract adjustment will be allowed under this clause to the extent that performance would have been suspended or delayed by any other cause, or for which an adjustment is provided for or excluded under any other te rm or condition of this Contract.
104.07 SIGNIFICANT CHANGES IN THE CHARACTER OF THE WORK . The Engineer
reserves the right to make in writing at any time during the work, such changes in quantities and such alterations in the work as are necessary to satisfactorily complete the project. Such changes in quantities and alterations shall not invalidate the Contract nor release the surety, and the Contractor agrees to perform the work as altered. If the alterations or changes in quantities significantly change the character of the work under the Contract, whether such alterations or changes are in themselves significant changes to the character of the work or by affecting other work cause such other work to become significantly different in character, an adjustm ent, excluding anticipated profits, will be made to the Contract. The basis for the adjustment shall be agreed upon prior to the performance of the work. If a basis cannot be agreed upon, then an adjustment will be made either for or against the Contractor in such amount as the Engineer may determine to be fair and equitable. If the alterations or changes in quantities do not significantly change the character of the work to be performed under the Contract, the altered work will be paid for as provided elsewhere in the Contract.
104.08 MAINTENANCE OF TRAFFIC. Unless otherwise provided, the Contractor shall maintain
the road undergoing improvement open to all traffic during the work of the Contract. Where so provided on the Plans, the Contractor may bypass traffic over an approved detour route. Additional detours not shown on the Plans may be employed only if plans for the detours are designed, submitted, reviewed, approved, and implemented in accordance with the requirements indicated in the Transportation Management Plan and such plans receive the written approval of the local City/Town Public Works Director. Detours of a short-term nature, which may be implemented only during the Contractor’s scheduled hours of operation, and which must be removed at the close of the day’s operations, shall require a 24-hour advance notice and approval of the Engineer. The Contractor shall keep the portion of the project being used by public traffic, whether it be through or loca l traffic, in a condition that shall safely and adequately accommodate such traffic. The Contractor shall furnish, erect and maintain all temporary traffic control devices in accordance with the Manual on Uniform Traffic Control Devices for Streets and Highways, latest Edition. The Contractor shall bear all expense of maintaining traffic over the section of road undergoing improvement without direct com pensation, except as provided below: