105.08CONSTRUCTION STAKES, LINES, AND GRADES . The Contractor will set

RI · 2024 Standard SpecificationsBook pages 5051View official source ↗

1−36 If the Engineer determines that adjustment of utility facilities is necessary to accommodate construction, and the adjustment work is not provided for in the Contract, the Contractor will be paid for the work in accordance with Subsection 109.04; Differing Site Conditions, Changes, Extra Work, and Force Account Work .

a.Contractor Coordination with U.S. Postal Service . The Contractor shall notify and coordinate with the U.S. Postal Service in situations where existing U.S. Postal Boxes (mail drop/collection boxes) within the limits of the Contract are to be removed and reset to allow for sidewalk/curbing construction. This requirement applies only in the case of standard U.S. Postal Service main drop boxes; it is not applicable for the removal and resetting or replacement of private mailboxes. The removal and resetting of U.S. Postal Service mail drop boxes must be conducted only by the U.S. Postal Service, and therefore, a reasonable time allowance must be provided by the Contractor to allow the Postal Service to complete the removal prior to start of construction. Finally, the Contractor shall coor dinate with the Post Office when construction is complete and acceptable such that the boxes may be reset.
b.Contractor Coordination with Narragansett Bay Commission . The Contractor must obtain a sewer facility alteration permit from the Narragansett Bay Commission prior to undertaking any work that affects sanitary sewer facilities that fall within NBC jurisdiction. The permit will be issued through the NBC and can be obtained at the location indicated in Special Provision Code 105.1000 of the Contract.

105.07 COOPERATION BETWEEN CONTRACTORS . The Department reserves the right to

contract for, and perform other or additional work on or near the work covered by the Contract. When separate contracts are let within the limits of any one project, each Contractor shall conduct its work without interfering or hindering the progress or completion of the work being performed by other contractors. Contractors working on the same project shall cooperate with each other as directed by the Engineer. Each Contractor involved shall assume all liability, financial or otherwise, in connection with its contract and shall protect and save harmless the Department from any and all damages or claims that may arise because of inconvenienc e, delay, or loss experienced because of the presence and operations of other contractors working within the limits of the same project unless otherwise provided for under Subsection 104.03; Differing Site Conditions . The Contractor shall arrange the work and shall place and dispose of the materials being used without interfering with the operations of the other contractors within the limits of the same project. The work shall be coordinated with that of the others in an acceptable manner and shall be performed in proper sequence with that of the other contractors.

105.08 CONSTRUCTION STAKES, LINES, AND GRADES . The Contractor will set

construction stakes establishing lines, slopes , profile grades, centerline and benchmarks for roadwork, bridge work, culvert work, protective and accessory structures, and appurtenances. These stakes and marks shall constitute the field control by which the Contractor shall establish other necessary controls and perform the work. 1−37 The contractor will maintain construction lines, points and grade staking to assure accurate and proper control of the work and to verify final grades and construction lines. The Contractor shall be held responsible for preserving all stakes and marks, and if the stakes or marks are destroyed or disturbed by the Contractor , the responsibility of replacing them will be borne by the Contractor at his own expense. The Contractor will be responsible for the accuracy of lines, slopes, grades, and other engineering work set forth under the contract documents and the provisions of SECTION 934; FIELD CONTROL AND CONSTRUCTION LAYOUT.

105.09 AUTHORITY AND DUTIES OF RESIDENT ENGINEER . As the representative of the

Engineer, the Resident Engineer has immediate charge of the engineering details of each construction project, and is responsible for the administration and satisfactory completion of the project. The Resident Engineer is delegated commensurate authority by the Department and is, thereby, authorized to reject defective material and to suspend any work that is being improperly performed. The Resident Engineer is authorized to make changes that involve increases or decreases in quantities not greater than ten-percent of the corresponding values that appear in the Proposal. The Resident Engineer is not authorized to make changes in any design element or project specification; or to make increases or decreases in quantities greater than ten-percent of the corresponding values that appear in the Proposal. 105.10 INSPECTION OF WORK . All materials and each part or detail of the work shall be subject to inspection by the Engineer. The Engineer shall be allowed access to all parts of the work and shall be furnished with such information and assistance by the Contractor as is required to make a complete and detailed inspection. If requested by the Engineer, the Contractor, before acceptance of the work, shall remove or uncover such portions of the finished work as may be directed. After examination, the Contractor shall restore said portions of the work to the standard required by the Contract. Should the work thus exposed or examined prove acceptable, the uncovering, removing, and replacing the covering, or making good of the parts removed will be paid for as Extra Work. Should the work so exposed or examined prove unacceptable, the uncovering, removing, and replacing of the covering, or making good of the parts removed, shall be at the Contractor's expense. Work performed or materials used without supervision or inspection by an authorized Department representative as a result of failure of the Contractor to notify the Engineer may be ordered removed and/or replaced at the Contractor's expense. When any unit of government or political subdivision, utility or railroad corporation is required to accept and/or pay a portion of the cost of the work covered by this Contract, its representatives shall have the right to inspect the work. Such inspection shall not make any unit of government or political subdivision, utility, or railroad corporation a party to this Contract, and shall in no way interfere with the rights of either such party.