105.05 COOPERATION BY CONTRACTOR . The Department will supply the Contractor with a
Contract Award Booklet containing a Contract Aw ard compact disk (CD), from which the plans, specifications, contract addenda and other contract documents may be printed. The Contractor will be required to keep one set of printed copies of the Contract Documents available on the project site at all times. The Contractor shall give the work the constant attention necessary to facilitate progress and shall cooperate fully with the Engineer, the Department's Resident Engineer and inspectors, and other Contractors. The Contractor shall have on the project site as its agent, a competent superintendent capable of reading and thoroughly understanding the Contract Documents and experienced in the type of work being performed. The superintendent shall receive orders or instructions from the Engineer, shall be authorized to act for the Contractor on the work, and shall have full authority to execute orders or directions of the Engineer without delay. The Contractor shall promptly supply, irrespective of the amount of work sublet, the necessary materials, equipment, tools, labor, and other incidentals to complete the Contract.
105.06 COOPERATION WITH UTILITIES . The Department will notify all utility companies, all
pipe line owners, or other parties affected, and endeavor to have all necessary adjustments of public or private utility fixtures, pipe lines, and other appurtenances within or adjacent to the limits of construction, made as soon as practicable. Water lines, gas lines, wire lines, service connections, water and gas meter boxes, water and gas valve boxes, light standards, cableways, signals, and all other utility appurtenances within the limits of the proposed construction in which the respective owners hold no private easements are to be relocated or adjusted by said owners in accordance with executed Construction and Maintenance Agreements/Utilities. It is understood that the Contractor has considered in its Proposal all of the permanent and temporary utility facilities in their present or relocated positions as specified in the Contract and as revealed by site investigation. No additional compensation will be allowed the Contractor for any delays, inconvenience, or damage sustained by it due to any interference caused by such facilities or the operation of relocating them, unless otherwise provided for in Subsection 104.03; Differing Site Conditions . In general, the Contract will indicate those various utility items which are to be relocated or adjusted by the utility owner in accordanc e with Construction and Maintenance Agreements, and those which are to be relocated or adjusted by the Contractor. In this latter case, all 1−35 underground construction required under the Contract for new or existing electric and/or telephone related facilities shall be performed by a contractor approved by the respective utility company. The Contractor may perform this work if it has been so-approved; otherwise, the Contractor shall retain a firm that has been approved for such work. The work involved would include all adjustments to utility manholes, frames and grates, as well as the utility lines themselves. Prior to the preconstruction conference, the Contractor shall submit to the Engineer written statements from the respective ut ility companies that the firm or firms selected by the Contractor are approved for such work. See Special Provision Code 105.2000. Prior to commencing work, the Contractor shall make arrangements to protect the properties of railway, telegraph, telephone, water, gas, and power companies, or other property, from damage that could result in considerable expense, loss, or inconvenience. In addition, the Contractor shall notify each utility owner and/or municipality whose facilities might be affected by its work 24 hours in advance of the commencement of such work. This notification shall also request the respective utility owner and/or municipality to assign a representative to be present at the site of the work during the period of the Contractor's operations. The locations and depths of existing utilities as shown on the Plans are approximate and should not be relied upon by the Contractor. The Contractor shall check and verify the location of all existing utilities, both underground and overhead, before proceeding to commence the work or order materials. Excavation shall be in accordance with all statutes, ordinances, and regulations of the Municipality, State or Federal Government that may be applicable. The Contractor is specifically required to follow the Dig Safe process. Damage to existing utilities which are shown on the Plans or located by the respective utilities in accordance with the Dig Safe process shall be the sole responsibility of the Contractor. The Contractor shall cooperate with the utility owners in the removal and rearrangement of any underground or overhead utilities in order that these operations may progress in a reasonable manner; that duplication of rearrangement work may be reduced to a minimum; and that services rendered by the utility owners will not be unnecessarily interrupted. In the event of interruption to water or utility services as a result of accidental breakage or of being exposed or unsupported, the Contractor shall promptly notify the proper authority and shall cooperate fully in the restoration of such services. If water service is interrupted, repair work shall be continuous until the service is restored. No work shall be undertaken around fire hydrants until provisions for continued service have been approved by the local fire authority. The Contractor shall prevent damage to pipes, cables, and other utilities. Repairs to damaged utilities caused by carelessness or omissions on the Contractor's part will be corrected at the Contractor's expense. The damaged facilit ies shall be restored to a condition similar or equal to that existing before the damage occurred. If the Engineer determines that adjustment or relocation of utilities is necessary to accommodate construction, the Engineer will make necessary arrangements with the owner if the work is not otherwise provided for in the Contract. 1−36 If the Engineer determines that adjustment of utility facilities is necessary to accommodate construction, and the adjustment work is not provided for in the Contract, the Contractor will be paid for the work in accordance with Subsection 109.04; Differing Site Conditions, Changes, Extra Work, and Force Account Work .
105.07 COOPERATION BETWEEN CONTRACTORS . The Department reserves the right to
contract for, and perform other or additional work on or near the work covered by the Contract. When separate contracts are let within the limits of any one project, each Contractor shall conduct its work without interfering or hindering the progress or completion of the work being performed by other contractors. Contractors working on the same project shall cooperate with each other as directed by the Engineer. Each Contractor involved shall assume all liability, financial or otherwise, in connection with its contract and shall protect and save harmless the Department from any and all damages or claims that may arise because of inconvenienc e, delay, or loss experienced because of the presence and operations of other contractors working within the limits of the same project unless otherwise provided for under Subsection 104.03; Differing Site Conditions . The Contractor shall arrange the work and shall place and dispose of the materials being used without interfering with the operations of the other contractors within the limits of the same project. The work shall be coordinated with that of the others in an acceptable manner and shall be performed in proper sequence with that of the other contractors.
105.08 CONSTRUCTION STAKES, LINES, AND GRADES . The Contractor will set
construction stakes establishing lines, slopes , profile grades, centerline and benchmarks for roadwork, bridge work, culvert work, protective and accessory structures, and appurtenances. These stakes and marks shall constitute the field control by which the Contractor shall establish other necessary controls and perform the work.