105.09AUTHORITY AND DUTIES OF RESIDENT ENGINEER . As the representative of the

RI · 2024 Standard SpecificationsBook pages 5152View official source ↗

1−37 The contractor will maintain construction lines, points and grade staking to assure accurate and proper control of the work and to verify final grades and construction lines. The Contractor shall be held responsible for preserving all stakes and marks, and if the stakes or marks are destroyed or disturbed by the Contractor , the responsibility of replacing them will be borne by the Contractor at his own expense. The Contractor will be responsible for the accuracy of lines, slopes, grades, and other engineering work set forth under the contract documents and the provisions of SECTION 934; FIELD CONTROL AND CONSTRUCTION LAYOUT.

105.09 AUTHORITY AND DUTIES OF RESIDENT ENGINEER . As the representative of the

Engineer, the Resident Engineer has immediate charge of the engineering details of each construction project, and is responsible for the administration and satisfactory completion of the project. The Resident Engineer is delegated commensurate authority by the Department and is, thereby, authorized to reject defective material and to suspend any work that is being improperly performed. The Resident Engineer is authorized to make changes that involve increases or decreases in quantities not greater than ten-percent of the corresponding values that appear in the Proposal. The Resident Engineer is not authorized to make changes in any design element or project specification; or to make increases or decreases in quantities greater than ten-percent of the corresponding values that appear in the Proposal. 105.10 INSPECTION OF WORK . All materials and each part or detail of the work shall be subject to inspection by the Engineer. The Engineer shall be allowed access to all parts of the work and shall be furnished with such information and assistance by the Contractor as is required to make a complete and detailed inspection. If requested by the Engineer, the Contractor, before acceptance of the work, shall remove or uncover such portions of the finished work as may be directed. After examination, the Contractor shall restore said portions of the work to the standard required by the Contract. Should the work thus exposed or examined prove acceptable, the uncovering, removing, and replacing the covering, or making good of the parts removed will be paid for as Extra Work. Should the work so exposed or examined prove unacceptable, the uncovering, removing, and replacing of the covering, or making good of the parts removed, shall be at the Contractor's expense. Work performed or materials used without supervision or inspection by an authorized Department representative as a result of failure of the Contractor to notify the Engineer may be ordered removed and/or replaced at the Contractor's expense. When any unit of government or political subdivision, utility or railroad corporation is required to accept and/or pay a portion of the cost of the work covered by this Contract, its representatives shall have the right to inspect the work. Such inspection shall not make any unit of government or political subdivision, utility, or railroad corporation a party to this Contract, and shall in no way interfere with the rights of either such party. 1−38

105.11 REMOVAL OF UNACCEPT ABLE AND UNAUTHORIZED WORK . Work which does

not reasonably conform to the requirements of the Contract will be considered unacceptable, unless otherwise determined acceptable under the provisions of Subsection 105.03; Conformity with Plans and Specifications . Unacceptable work, whether the result of poor workmanship, use of defective materials, or damage through carelessness, found to exist prior to the final acceptance of the work, shall be removed immediately and replaced in an acceptable manner at the Contractor's expense. Work performed contrary to the instructions of the Engineer; work performed beyond the lines and grades shown on the Plans, or as otherwise provided; or any extra work performed without authority, will be considered as unauthorized work and will not be paid for under the provisions of the Contract. Work so performed may be ordered removed and/or replaced at the Contractor's expense. If the Contractor fails to promptly comply with any order of the Engineer made under the provisions of this Subsection, the Engineer is authorized to require unacceptable work to be remedied or removed and replaced, and unauthorized work to be removed, and to deduct the costs incurred thereby from any monies due or to become due the Contractor.

105.12 LOAD RESTRICTIONS . The Contractor shall comply with all legal load restrictions in

the hauling of equipment or materials on public roads beyond the limits of the project. A special permit will not relieve the Contractor of liability for damage which may result from the moving of such equipment or materials. The operation of equipment on hauling loads which cause damage to structures or the roadway, or to any other type of construction, will not be permitted. Handling or hauling of materials over the base course or surface course under construction shall be limited as directed by the Engineer to prevent damage to the pavement structure. No loads will be permitted on a concrete pavement, base or structure before the concrete has attained its required strength unless otherwise authorized in writing by the Engineer.

105.13 MAINTENANCE DURING CONSTRUCTION . The Contractor shall maintain the work

during construction and until the project is substantially complete. This maintenance shall constitute continuous and effective work pr osecuted day by day, with adequate equipment and forces to the end that the roadway or structures are kept in satisfactory condition. If the Contract requires the placing of a course upon a course or subgrade previously constructed, the Contractor shall maintain the previous course or subgrade during all construction operations. Cost of maintenance work during construction and before the project is substantially completed is contained within the Contract unit prices of the various pay items and the Contractor will not be paid an additional amount.

Source: Rhode Island Standard Specifications (Bluebook), 2024 Edition. Pages 5152 of 826.