Division 200 — Section 211

200-44 Section 211 — Proof Rolling

211.1 Description

1 Furnish and operate, at the direction of the RCE, heavy, pneumatic -tire equipment for testing the roadway embankment and subgrade for stability and uniformity of compaction.

211.2 Materials

1 None specified.

211.3 Construction

211.3.1 Equipment

1 Use equipment for proof rolling that inc ludes a fully loaded tandem axle dump truck or an equivalent accepted by the RCE. Use only equipment with air -filled pneumatic tires. Ensure that the tires have a pressure between 70 and 90 psi while proof rolling . Use equipment with tires mounted on articulated axles so that all wheels on the same axle carry approximately equal loads when operated over uneven surfaces.

211.3.2 Operation

1 Proof roll each lift of embankment and subgrade that has an elevation of 5 ft or less below the finished subgrade elevation before placement of subsequent lifts, or as directed by the RCE. Perform proof rolling in t he presence of the RCE or the RCE’s certified earthwork, drainage, and base inspector. Operate proof rolling equi pment at a speed between 200 and 300 ft per minute. Make a minimum of five passes over each area proof rolled. Correct areas that are unstable or non- uniform. After correction of these deficient areas, repeat the proof rolling operation.

211.4 Measurement

1 No specific measurement is made for the work involved in proof rolli ng.

211.5 Payment

1 This work includes furnishing all labor, equipment, fuel, and ballast for loading; loading and unloading ballast as directed; and increasing and decreasing tire pressure as directed. This work is considered incidental to embankment and subgrade compaction and no direct payment is made for this work.

Get an email when 211 changes

South Carolina revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: South Carolina Standard Specifications for Highway Construction, 2025 Edition. Pages 198–198 of 908. View official source ↗

Ask about this section

Scoped to South Carolina Standard Specifications for Highway Construction, Section 211 — — Proof Rolling. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.