207— Overhaul

SC · 2025 Standard SpecificationsBook pages 187186View official source ↗

Division 200 — Section 207

200-33 Section 207 — Overhaul

207.1 Description 1 Perform overhaul, which is the hauling of locally excavated material more than 3000 ft in performance of the work in the Contract. 207.2 Materials 1 None specified. 207.3 Construction 1 None specified. 207.4 Measurement 1 If the item Overhaul is not included in the Contract, the cost is included in other items of work. The quantity for the pay item Overhaul is the product of the volume of material, in cubic yards, multiplied by the distance, in half -mile units, that the material was moved as determined below and is measured by cubic yard half -mile (CYHM), complete and ac cepted. 2 There is a free haul distance of 3000 ft in which no o verhaul is measured or paid. The distance measured for payment is the distance between the centers of the material volume moved from its original location to its final location minus the free haul limit of 3000 ft. In other words, the first half -mile unit of overhaul applies to material hauled more than 3000 ft but less than 5640 ft. The second half -mile unit of overhaul ap plies to material hauled more than 5640 ft but less than 8280 ft, etc. The overhaul distance is based on the shortest feasible route. Any part of the overhaul distance not determined by the RCE as reasonably necessary is disregarded in computing the overhaul quantity. 3 The measurement of the volume of material in the Overhaul quantity is calculated by the same method prescribed for measuring the volume of earthwork material for payment. 4 When the Plan quantity for Overhaul of roadway excavation has been computed and is shown on the Plans, the final pay quantity for the roadway overhaul is an adjusted amount based on the original Plan quantity. The adjusted quantity is computed by multiplying the original Plan quantity of roadway Overhaul by the final roadway excavation, and then dividing this result by the original roadway excavation. When the Contract contains more than one roadway, each is considered separately. according to the followi ng formula:

Source: South Carolina Standard Specifications for Highway Construction, 2025 Edition. Pages 187186 of 908.