Division 500 — Section 502
500-29 Section 502 — Full Depth Concrete Pavement Patching
502.1 Description 1 Construct full depth patches of Portland cement concrete pavement. 502.2 Materials 502.2.1 General 1 Use materials that meet the requirements of Sections 305, 501, 701, and 703. 502.2.2 Portland Cement Concrete 1 Use Portland cement Type I , Type III, or Type 1L from an approved source listed on Qualified Products List 6. Ensure that the minimum cement content for patching concrete is 800 lb/cu yd or more. Use a water -cementitious material ratio less than or equal to 0.38. Maintain the water -cementitious material ratio using normal or high range water reducing materials Type F or G from an approved source listed on Qualified Products List 5. Use non- chloride accelerators to achieve compressive strength and time of set desired. Use coarse aggregates meeting the gradation of Aggregate No. 56, 57, or 67. Provide an air content of 3.0 % to 6.0 % when tested according to AASHTO T 152. 2 Submit mix designs to the SME according to Subsection 701.2.12 , except as modified by the mix requirements of this Section. Review of the mix design by the Department in no way relieves the Contractor of this responsibility. 3 Provide concrete for patching that develops sufficient strength, as determined by the Contractor, so that the patch may be opened to traffic within 6 hours of placement. Replace any patch that develops cracking or deformation within 45 days after opening to traffic at no additional cost to the Department . 502.2.3 Reinforcing Steel 1 Provide tie bars and dowel bars as specified in the patching detail that conform to Subsection 501.2.1.2. 502.2.4 Epoxy System 1 When an epoxy system is required to anchor dowel bars and tie bars, use a product that meets ASTM C881, Type 4, Grade 3, Class B or Class C. Provide the RCE with a certification from the manufacturer for each lot number received at the job site. If requested by the RCE , verify that the proposed epoxy system provides adequate pullout resistance by demonstrating the epoxy with a No. 4 tie bar in a scrap section of pavement slab. Provide the equipment to test the
Get an email when 502 changes
South Carolina revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.