Division 500 — Section 503

500-35 Section 503 — Grinding and Texturing Concrete Pavement

503.1 Description

1 Grind and texture Portland cement concrete pavement longitudinally.

503.2 Materials

1 Conform to SC-M-502.

503.3 Construction

1 Conform to the construction and equipment requirements pertaining to grinding and texturing concrete pavement in SC -M-502.

503.4 Measurement

1 The quantity for the pay item grinding and texturing existing concrete pavement is the surface area of grinding and texturing Portland cement concrete pavement and is measured by the square yard (SY), complete and accepted. Grinding and texturing performe d outside the areas designated is disregarded in computing the quantity for payment.

503.5 Payment

1 Payment for the accepted quantity for Grinding and Texturing Existing Concrete Pavement at the Unit Price is full compensation for furnishing all materials, labor, equipment, tools, supplies, transportation, and incidentals necessary to complete the work as specified . 2 Pay items under this Section include the following: Item No. Pay Item Unit 5031000 Grinding and Texturing Existing Concrete Pavement SY

Get an email when 503 changes

South Carolina revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: South Carolina Standard Specifications for Highway Construction, 2025 Edition. Pages 318–318 of 908. View official source ↗

Ask about this section

Scoped to South Carolina Standard Specifications for Highway Construction, Section 503 — — Grinding and Texturing Concrete Pavement. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.