02963Profile Rotomilling

UT · 2026 Standard Specifications✓ Full text on BuildSpecRev. January 1, 2017Book pages 870–871 Save this section

Ask about Section 02963

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

PROFILE ROTOMILLING

PART 1 GENERAL

1.1SECTION INCLUDES

A.Rotomilling of the existing bituminous surface at the location and to the

profile and cross-slope shown.

1.2RELATED SECTIONS

A.Section 02741: Asphalt Mix

1.3REFERENCES Not Used

1.4DEFINITIONS Not Used

1.5SUBMITTALS

A.Submit for information the record of profile grades.

PART 2 PRODUCTS

2.1MATERIALS

A.Use the milled material obtained from the rotomill process passing a 2

inch sieve as optional use of Reclaimed Asphalt Pavement (RAP). Refer to Section 02741.

2.2EQUIPMENT

A.Use power-operated track propelled planing machine or grinder:
1.Capable of milling to the plan cross slope.
2.Self-propelled with sufficient power, traction, and stability to

maintain accurate depth of cut.

3.Maximum of ⅝ inch between the cutting teeth on the mandrel.
B.Use appropriate cleaning equipment capable of sweeping, picking up

millings, and cleaning the vertical edge to clean up after milling operation.

Profile Rotomilling

PART 3 EXECUTION

3.1PREPARATION

A.Measure and record profile grades during rotomilling operation:
1.Use a means that provides the required accuracy.
B.Achieve a rotomilled depth in the field of plan depth not to exceed an

additional ¼ inch, measured from original surface to the top of the ridge.

C.Rotomill existing bituminous pavement surface to a depth below final

profile and cross slope grade as shown.

D.Clean rotomilled surface after milling operation and before opening to

traffic.

E.Remove and replace or repair damage by the Contractor’s operation

outside the widths and depths as shown.

1.Repair damage to traffic due to loose material on milled surface.
F.Use a wire guide or other approved grade control methods to control the

profile grade and cross slope of the rotomill.

G.Load the reclaimed material from milling operation into a truck in one

operation.

1.Remove and clean all millings from the surface daily.
2.Control dust created by the cutting action.
H.Milled material is the property of the Contractor unless specified

otherwise.

I.Dispose of the milled material

3.2CLEAN AND REPAIR

A.Remove and clean all millings from the surface daily.
1.Control dust created by the cutting action.
2.Clean rotomilled surface after milling operation and before opening

to traffic.

B Verify all milled surfaces are sturdy and sound.

1.Remove any material that is loose or not well bonded.
C.Dispose of the milled material.

END OF SECTION Profile Rotomilling

Get an email when 02963 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 870–871 of 1,331. View official source ↗

Ask about this section

Scoped to Utah Standard Specifications, Section 02963 — Profile Rotomilling. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.