B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Site Construction & Earthwork (02000-02999)

02982Bridge Concrete Grinding

UT · 2026 Standard Specifications✓ Full text on BuildSpecRev. November 18, 2021Book pages 875–877 Save this section

Ask about Section 02982

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

BRIDGE CONCRETE GRINDING

PART 1 GENERAL

1.1SECTION INCLUDES

A.Grinding of concrete bridge decks, approach slabs, and sleeper slabs for

precast concrete deck panel systems

B.Grinding of existing concrete bridge decks, approach slabs, and sleeper

slabs for rehabilitation work

1.2RELATED SECTIONS Not Used

1.3REFERENCES Not Used

1.4DEFINITIONS

A.Critical Areas – Areas of the deck where concrete cover will be or is

anticipated to be less than 2 inch after grinding.

1.5SUBMITTALS

A.Request for alternative to ferroscanning for review. Include at least the

following:

1.Model name and technical data sheet for proposed equipment
2.Manufacturer’s guidelines for proper usage of the equipment
B.Map of rebar depths for review.
1.State on the submittal that the record of measurements are

representative of the deck before grinding was performed.

2.Indicate the critical areas and include a description of the resolution

if low measurements caused a stop in work.

Bridge Concrete Grinding

PART 2 PRODUCTS

2.1EQUIPMENT

A.Provide and operate equipment utilizing diamond blades mounted on a

self-propelled machine designed for grinding and texturing pavement.

1.Do not use equipment that causes damage to the transverse or

longitudinal joints.

B.Provide vacuuming equipment for the removal of residue and excess

water.

PART 3 EXECUTION

3.1GENERAL REQUIREMENTS

A.Provide a uniform finished texture.
B.Limit deviations to an ⅛ inch from the lower edge of a 10 ft

straightedge after grinding.

C.Perform grinding in a longitudinal direction.
1.Begin and end grinding at lines normal to the bridge centerline.
D.Protect expansion joints during grinding operations.
E.Create a surface in a parallel, corduroy-type texture consisting of grooves

between 1/16 and ¼ inch wide.

1.Use a distance between the grooves of between 1/16 and ¼ inch.
2.Limit height of ridges to 1/16 inch.
F.Maintain drainage.
G.Use vacuuming equipment after grinding to remove residue and excess

water.

H.Tailings from the grinding process become the property and responsibility

of the Contractor.

Bridge Concrete Grinding

3.2GRINDING PRECAST DECKS AND APPROACH SLABS

A.Grind surfaces of concrete bridge decks and approach slabs until both

sides of panel joints are in the same plane and the entire surface, including the sleeper slab to roadway interface, meets the requirement of this Section, 3.1B.

1.Do not perform grinding operations until the concrete in the

blockouts and closure pours has cured for at least 24 hours.

2.Limit grinding to a depth of no more than ¼ inch.

3.3GRINDING EXISTING DECK SURFACES

A.Grind surfaces as shown.
B.Verify concrete cover to reinforcing steel by ferroscanning or an

authorized equivalent method before grinding.

1.Do not grind the concrete if the final concrete cover after grinding is

anticipated to be less than the cover shown, or less than 2 inch if cover is not shown.

C.Do not damage existing reinforcing steel.

END OF SECTION

Bridge Concrete Grinding

Get an email when 02982 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 875–877 of 1,331. View official source ↗

Ask about this section

Scoped to Utah Standard Specifications, Section 02982 — Bridge Concrete Grinding. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.