2-56 SECTION 206 – ROCK SLOPE SCALING
206.01 DESCRIPTION . This work shall consist of excavating loose and dilated rock on slopes. This work
includes high -angle construction to be completed via hand scaling using industrial rope access methods or machine scaling.
206.02 SUBMITTALS . The Contractor shall submit to the Engineer the following information for
completing the work. Work shall not begin until the submittals have been approved in writing by the Engineer.
206.03 GENERAL REQUIREMENTS . Prior to the beginning of ledge removal, all necessary clearing
and grubbing in the project area shall be completed in accordance with Section 201 . Vegetation removal performe d as part of hand scaling or machine scaling operations shall meet the applicable requirements of Section 201 . All material from previous activities shall be removed from the ditch line prior to beginning ledge removal. Work shall proceed according to the approved work plan and schedule submitted by the Contractor. Under no circumstances shall any material be pushed towards or over the crest of the rock slope, unless otherwise approved by the Engineer. Devices for protecting the roadway and adjacent facilities shall be provided by the Contractor and installed prior to the beginning of scaling.
206.04 HAND SCALING WITH VEGETATION REMOVAL . Hand scaling with vegetation removal
shall consist of removing lo ose, dilated or potentially dangerous rocks; cleaning out soil and weathered rock exposed during removal; and removing trees, root structures, and shrubs from the slope face using hand removal techniques requiring the use of rope access. Methods may includ e, but are not limited to, the use of standard steel miner pry bars and pneumatic or hydraulic devices. Slopes identified on the Plans shall be scaled at such frequency as required to remove all hazardous loose rock or overhangs. Slopes shall be scaled us ing a suitable standard steel mine scaling rod, bar, hand placed jacks, and inflatable air bags, as approved by the Engineer. Other methods such as hydraulic splitters or expansive grout may be used in lieu of, or to supplement, hand scaling upon approval of the Engineer. Scaling shall start at the top of the slope and work shall proceed downward, removing all loose rock blocks and vegetation as the work progresses. The rock face will be inspected by the Engineer and Geologist to determine whether the rock slope scaling has been completed. If other rocks, soil, or vegetation are identified that require removal, the Contractor shall continue to scale the slope until the scaling has been completed to the satisfaction of the Engineer. 2-58 206.05 MACHINE SCALING WITH VEGETATION REMOVAL . Machine scaling with vegetation removal shall consist of removing loose and dilated or potentially dangerous rocks; cleaning out soil and weathered rock exposed during removal; and removing trees, root structures, and shrub s from the slope face using heavy equipment such as excavators or specialized high -reach excavators. Attachments may include a hydraulic hammer, a bucket, or other attachments as necessary to complete the work. The work may be performed from the base of th e slope, top of the slope, or from work pads. Slopes identified on the Plans shall be machine scaled at such frequency as required to remove all hazardous loose rock or overhangs. Equipment used for machine scaling shall be as specified in the approved wor k plan.
206.06 REMOVAL OF LEDGE MATERIAL . When the scaling work is complete, all material from
inside the excavation line, as shown on the Plans, and all loose material from the rock slopes outside the excavation line shall be removed from the work area. Portable scales sufficient to weigh trucks with up to 12 wheels (i.e. tri -axle dump trucks) shall be provided by the Contractor. Trucks having more than 12 wheels will not be permitted. All trucks will be single -unit type. The scales shall be certified and sealed. Calibration shall be performed according to the manufacturer’s recommendations. Storage, placement, and handling of the truck scales shall be the responsibility of the Contractor. Any damage done to the truck scales by the Contractor’s operation s hall be the Contractor’s responsibility. Damaged scales shall be replaced or repaired to the satisfaction of the Engineer at no cost to the Agency. When scales are no longer needed, as determined by the Engineer, they shall remain the property of the Contractor. In lieu of providing portable scales, the Contractor may utilize local permanent truck scales for weighing trucks. Use of local scales shall be approved by the Engineer prior to beginning work. A printed load ticket, which indicates the truck i dentification, date, and time, shall be furnished to the Engineer for each load removed from the site.
206.05 BASIS OF PAYMENT . The accepted quantity of Hand Scaling with Vegetation Removal will be
paid for at the Contract unit price per hour. Payment will be full compensation for hours of scaling operations accrued on the project; for furnishing all materials required; and for furnishing all labor, tools, equipment, and incidentals necessary to complete the work. The accepted quantity of Machin e Scaling with Vegetation Removal will be paid for at the Contract unit price per hour. Payment will be full compensation for performing the work specified; for furnishing, operation, and supervising the use of this equipment, including fuel, repairs, and attachments; and for furnishing all labor, tools, other equipment, and incidentals necessary to complete the work. The accepted quantities of Ledge Salvage Material and Ledge Waste Material will be paid for at the Contract unit price per ton. Payment will be full compensation for performing the work specified; including refining, handling, loading, transporting, and placing the specified materials; for breaking down large blocks of rock prior to removal from the site; and for furnishing all labor, tools, eq uipment, and incidentals necessary to complete the work. 2-60 Payment for preparing and making required submittals and for furnishing truck scales will not be made separately but will be considered incidental to the work under this section. Payment will be made under: Pay Item Pay Unit 206.1000 Hand Scaling with Vegetation Removal ................................ ................... Hour 206.1500 Machine Scaling with Vegetation Removal ................................ ............. Hour 206.3000 Ledge Salvage Material ................................ ................................ ............ Ton 206.3500 Ledge Waste Material ................................ ................................ ............... Ton 2-61 SECTIO N 208 – COFFERDAMS 208.0 1 DESCRIPTION . This work shall consist of the construction, material excavation within, dewatering, maintenance , and removal of cofferdams in accordance with the Contract. The work will be classified as follows: