M 41-10 Page 6-1376-03 Steel Structures
6-03.1 Description
This Work consists of furnishing, fabricating, erecting, cleaning, and painting steel Structures and the structural steel parts of nonsteel Structures
6-03.2 Materials
Materials shall meet the requirements of the following sections: Structural Steel and Related Materials 9-06 Paints and Related Materials 9-08 Grout 9-20.3 Structural steel shall be classified as:
6-03.3 Construction Requirements
Structural steel fabricators of plate and box girders, floorbeams, truss members, stringers, cross frames, diaphragms, and laterals shall be certified under the AISC Certification Program for Steel Bridge Fabricators, Advanced Bridges Category unless otherwise specified in the Special Provisions. When fracture critical members are specified in the Contract, structural steel fabricators shall also meet the supplemental requirements F, Fracture Critical, under the AISC Quality Certification Program for Steel Bridge Fabricators.
6-03.3(1) Vacant
6-03.3(2) Facilities for Inspection
The Contractor shall provide all facilities the Inspector requires to inspect material and Work. Inspectors shall be given safe and free access to all areas in the mill and shop. Steel Structures 6-03 Page 6-138 M 41-106-03.3(3) Inspector’s Authority The Inspector may reject materials or Work that does not comply with these Specifications. In any dispute, the Contractor may appeal to the Engineer whose decision shall be final. By its inspection at the mill and shop, the Contracting Agency intends only to facilitate the Work and prevent errors. This inspection shall not relieve the Contractor of any responsibility for identifying and replacing defective material or Work.
6-03.3(4) Rejections
Even if the Inspector accepts materials or finished members, the Contracting Agency may later reject them if defective. The Contractor shall promptly replace or make good any rejected materials or Work.
6-03.3(5) Mill Orders and Shipping Statements
The Contractor shall furnish as many copies of mill orders and shipping statements as the Engineer requires.
6-03.3(6) Weighing
Structural steel need not be weighed unless the Plans or Special Provisions require it. When a weight is required, it may either be calculated or obtained by scales. The Contractor shall furnish as many copies of the calculations or weight slips as the Engineer requires. If scale weights are used, the Contractor shall record separately the weights of all tools, erection material, and dunnage.
6-03.3(7) Shop Plans
The Contractor shall submit all shop detail plans for fabricating the steel as Type 2 Working Drawings. If these plans will be submitted directly from the fabricator, the Contractor shall so notify the Engineer in writing. No material shall be fabricated until: (1) the Working Drawing review is complete, and (2) the Engineer has accepted the materials source. Before physical completion of the project, the Contractor shall furnish the Engineer one set of reproducible copies of the as built shop plans. The reproducible copies shall be clear, suitable for microfilming, and on permanent sheets that measure no smaller than 11 by 17 inches. Alternatively, the shop drawings may be provided in an electronic format with the approval of the Engineer.
6-03.3(7)A Erection Methods
Before beginning to erect any steel Structure, the Contractor shall submit Type 2E Working Drawings consisting of the erection plan and procedure describing the methods the Contractor intends to use. The erection plan and procedure shall provide complete details of the erection process including, at a minimum, the following:
6-03 Steel Structures
M 41-10 Page 6-1396. Girder launcher or trolley details and capacity (if intended for use); and
6-03.3(8) Substitutions
The Contractor shall not substitute sections that differ from Plan dimensions unless the Engineer approves in writing. If the Contractor requests and receives approval to substitute heavier members, the Contracting Agency shall not pay any added cost.
6-03.3(9) Handling, Storing, and Shipping of Materials
Markings applied at the mill shall distinguish structural low alloy steel from structural carbon steel. The fabricator shall keep the two classes of steel carefully separated. Before fabrication, all material stored at the fabricating plant shall be protected from rust, dirt, oil, and other foreign matter. The Contracting Agency will accept no rust-pitted material. After fabrication, all material awaiting shipment shall be subject to the same storage requirements as unfabricated material. All structural steel shall arrive at the job in good condition. As the Engineer requires, steel damaged by salt water shipment shall be thoroughly cleaned by high pressure water flushing, chemical cleaning, or sandblasting, and repainted with the specified shop coat. All material shall be stored so as to prevent rust and loss of small parts. Piled material shall not rest on the ground or in water but on skids or platforms. The loading, transporting, unloading, and piling of the structural steel material shall be so conducted that the metal will be kept clean and free from injury from rough handling. In field assembly of structural parts, the Contractor shall use methods and equipment not likely to twist, bend, deform, or otherwise injure the metal. Any member slightly bent or twisted shall be corrected before it is placed. The Contracting Agency will reject any member with serious handling damage. Steel Structures 6-03 Page 6-140 M 41-10Girder sections shall be handled so as to prevent damage to the girders. If necessary, the Contractor shall provide temporary stiffeners to prevent buckling during erection.
6-03.3(10) Straightening Bent Material
If the Engineer permits in writing, plates, angles, other shapes, and built-up members may be straightened. Straightening methods shall not fracture or injure the metal. Distorted members shall be straightened mechanically. A limited amount of localized heat may be applied only if carefully planned and supervised, and only in accordance with the heat-straightening procedure Working Drawing submittal. Parts to be heat-straightened shall be nearly free from all stress and external forces except those that result from the mechanical pressure used with the heat. After straightening, the Contractor shall inspect the member for fractures using a method proposed by the Contractor and accepted by the Contracting Agency. The Contracting Agency will reject metal showing sharp kinks and bends. The procedure for heat straightening of universal mill (UM) plates by the mill or the fabricator shall be submitted as a Type 2 Working Drawing.
6-03.3(11) Quality of Construction and Finish
Work and finish shall be first-class, equaling the best practice in modern bridge fabrication shops. Welding, shearing, burning, chipping, and grinding shall be done neatly and accurately. All parts of the Work exposed to view shall be neatly finished. Wherever the Plans show a surface finish symbol, the surface shall be machined.
6-03.3(12) Falsework
All falsework shall meet the requirements of Section 6-02 .
6-03.3(13) Fabricating Tension Members
Plates for main load-carrying tension members or tension components of flexural members shall be:
6-03.3(14) Edge Finishing
All rolled, sheared, and thermal cut edges shall be true to line and free of rough corners and projections. Corners along exposed sheared or cut edges shall be broken by light grinding or another method acceptable to the Engineer to achieve an approximate 1⁄16-inch chamfer or rounding. Sheared edges on plates more than ⅝ inch thick shall be planed, milled, ground, or thermal cut to a depth of at least ⅛ inch. Re-entrant corners or cuts shall be filleted to a minimum radius of 1 inch. Exposed edges of main load-carrying tension members or tension components of flexural members shall have a surface roughness no greater than 250-micro inches as defined by the American National Standards Institute, ANSI B46.1, Surface Texture. Exposed edges of other members shall have surface roughness no greater than 1,000-micro inches. The Rockwell hardness of thermal-cut edges of structural low alloy or high-strength steel flanges, as specified in Sections 9-06.2 and 9-06.3 , for main load-carrying tension members or tension components of flexural members shall not exceed RHC 30. The fabricator shall prevent excessive hardening of flange edges through preheating or post heating.
6-03 Steel Structures
M 41-10 Page 6-141Hardness testing shall consist of testing thermal-cut edges with a portable hardness tester. The hardness tester, and its operating test procedures, shall be submitted as a Type 1 Working Drawing. The hardness tester shall be convertible to Rockwell C scale values. At two locations, two tests shall be performed on each thermal-cut edge, one each within ¼ inch of the top and bottom surfaces. The tests shall be located ¼ the length of each thermal-cut edge from each end of the cut. If one or more readings are greater than RHC 30, the entire length of the edge shall be ground or machined to a depth sufficient to provide acceptable readings upon further retests. If thermal-cutting operations conform to procedures established by the steel manufacturer, and hardness testing results are consistently within acceptable limits, the Engineer may authorize a reduction in the testing frequency.
6-03.3(15) Planing of Bearing Surfaces
Ends of columns that bear on base and cap plates shall be milled to true surfaces and accurate bevels. When assembled, caps and base plates of columns and the sole plates of girders and trusses shall have a fit tolerance within 1⁄32 inch for 75 percent of the contact area. For sole plates, contact area shall be 75 perfcent of the projected area of the web and bearing stiffeners. If warped or deformed, the plates shall be heat straightened, planed, or corrected in some other way to produce accurate, even contact. If necessary for proper contact, bearing surfaces that will contact other metal surfaces shall be planed or milled. Surfaces of warped or deformed base and sole plates that will contact masonry shall be rough finished. On the surface of expansion bearings, the cut of the planer shall be in the direction of expansion. Where finish to bear is specified in the Plans, the bearing end of the stiffener shall be flush and square with the flange and shall have at least 75 percent of this area in contact with the flange.
6-03.3(16) Abutting Joints
Abutting ends of compression members shall be faced accurately so that they bear evenly when in the Structure. On built-up members, the ends shall be faced or milled after fabrication. Ends of tension members at splices shall be rough finished to produce neat, close joints. A contact fit is not required.
6-03.3(17) End Connection Angles
On floorbeams and stringers, end connection angles shall be flush with each other and set accurately in relationship to the position and length of the member. Unless the Plans require it, end connection angles shall not be finished. If, however, faulty assembly requires them to be milled, milling shall not reduce thickness by more than ¹/ 16 inch.
6-03.3(18) Built Members
The various pieces forming one built member shall be straight and close fitting, true to detailed dimensions, and free from twists, bends, open joints, or other defects. When fabricating curved girders, localized heat or the use of mechanical force shall not be used to bend the girder flanges about an axis parallel to girder webs.
6-03.3(19) Hand Holes
Hand holes, whether punched or cut with burning torches, shall be true to sizes and shapes shown in the Plans. Edges shall be true to line and ground smooth. Steel Structures 6-03 Page 6-142 M 41-106-03.3(20) Lacing Bars Unless the Plans state otherwise, ends of lacing bars shall be neatly rounded.
6-03.3(21) Plate Girders
6-03.3(21)A Web Plates
If web plates are spliced, gaps between plate ends shall be set at shop assembly to measure ¼ inch, and shall not exceed ⅜ inch.
6-03.3(21)B Vacant
6-03.3(21)C Web Splices and Fillers
Web splice plates and fillers under stiffeners shall fit within ⅛ inch at each end. In lieu of the steel material specified in the Plans or Special Provisions, the Contractor may substitute ASTM A1008 or ASTM A1011 steel for all filler plates less than ¼ inch thickness, provided that the grade of filler plate steel meets or exceeds that of the splice plates.
6-03.3(22) Eyebars
Eyebars shall be straight, true to size, and free from twists or folds in the neck or head and from any other defect that would reduce their strength. Heads shall be formed by upsetting, rolling, or forging. Dies in use by the manufacturer may determine the shape of bar heads if the Engineer approves. Head and neck thickness shall not overrun by more than ¹/ 16 inch. Welds shall not be made in the body or head of any bar. Each eyebar shall be properly annealed and carefully straightened before it is bored. Pinholes shall be located on the centerline of each bar and in the center of its head. Holes in bar ends shall be so precisely located that in a pile of bars for the same truss panel the pins may be inserted completely without driving. All eyebars made for the same locations in trusses shall be interchangeable.
6-03.3(23) Annealing
All eyebars shall be annealed by being heated uniformly to the proper temperature, then cooled slowly and evenly in the furnace. At all stages, the temperature of the bars shall be under full control. Slight bends on secondary steel members may be made without heat. Crimped web stiffeners need no annealing.
6-03.3(24) Pins and Rollers
Pins and rollers shall be made of the class of forged steel the Plans specify. They shall be turned accurately to detailed dimensions, smooth, straight, and flawless. The final surface shall be produced by a finishing cut. Pins and rollers 9 inches or less in diameter may either be forged and annealed or made of cold-finished carbon steel shafting. Pins more than 9 inches in diameter shall have holes at least 2 inches in diameter bored longitudinally through their centers. Pins with inner defects will be rejected. The Contractor shall provide pilot and driving nuts for each size of pin unless the Plans state otherwise.
6-03.3(24)A Boring Pin Holes
Pin holes shall be bored true to detailed dimensions, smooth and straight, and at right angles to the axis of the member. Holes shall be parallel with each other unless the Plans state otherwise. A finishing cut shall always be made.
6-03 Steel Structures
M 41-10 Page 6-143The distance between holes shall not vary from detailed dimensions by more than ¹⁄32 inch. In tension members, this distance shall be measured from outside to outside of holes; in compression members, inside to inside.
6-03.3(24)B Pin Clearances
Each pin shall be ¹⁄50 inch smaller in diameter than its hole. All pins shall be numbered after being fitted into their holes in the assembled member.
6-03.3(25) Welding and Repair Welding
Welding and repair welding of all steel bridges, including pedestrian Structures, shall comply with the AASHTO/AWS D1.5M/D1.5, latest edition, Bridge Welding Code. Welding and repair welding for all other steel fabrication shall comply with the AWS D1.1/D1.1M, latest edition, Structural Welding Code. The requirements described in the remainder of this section shall prevail whenever they differ from either of the above welding codes. The Contractor shall weld structural steel only to the extent shown in the Plans. No welding, including tack and temporary welds shall be done in the shop or field unless the location of the welds is shown on the approved shop drawings reviewed and accepted by the Engineer. Welding procedures shall accompany the shop drawing Working Drawing submittal. The procedures shall specify the type of equipment to be used, electrode selection, preheat requirements, base materials, and joint details. When the procedures are not prequalified by AWS or AASHTO, evidence of qualification tests shall be submitted. Steel bridge elements not subject to live load tensile stress and not welded to main members in tension areas, such as steel expansion dams, bearings, handrail, drainage components, and curb plates, may follow the requirements of AASHTO/AWS D1.5M/D1.5, latest edition, Bridge Welding Code for Welding of Ancillary Products whereby qualification of welding procedures is not required. Welding shall not begin until completion of the shop plan Working Drawing review as required in Section 6-03.3(7) . These plans shall include procedures for welding, assembly, and any heat-straightening or heat-curving. Any welded shear connector longer than 8 inches may be made of two shorter shear connectors joined with full-penetration welds. In shielded metal-arc welding, the Contractor shall use low-hydrogen electrodes. In submerged-arc welding of main load-carrying tension members and tension components of flexural members, flux shall be oven-dried at 550ºF for at least 2 hours, then stored in ovens held at 250ºF or more. If not used within 4 hours after removal from a drying or storage oven, flux shall be redried before use. Preheat and interpass temperatures shall conform to the applicable welding code as specified in this section. When welding main members of steel bridges, the minimum preheat shall not be less than 100ºF. If groove welds (web-to-web or flange-to-flange) have been rejected, they may be repaired no more than twice. If a third failure occurs, the Contractor shall:
6-03.3(25)A Welding Inspection
The Contractor’s inspection procedures, techniques, methods, acceptance criteria, and inspector qualifications for welding of steel bridges, including pedestrian Structures, shall be in accordance with the AASHTO/AWS D1.5M/D1.5, latest edition, Bridge Welding Code. The Contractor’s inspection procedures, techniques, methods, acceptance criteria, and inspector qualifications for welding of steel Structures other than steel bridges, including pedestrian Structures, shall be in accordance with AWS D1.1/D1.1M, latest edition, Structural Welding Code. The requirements described in the remainder of this section shall prevail whenever they differ from either of the above welding codes. Nondestructive testing in addition to visual inspection shall be performed by the Contractor. Unless otherwise shown in the Plans or specified in the Special Provisions, the extent of inspection shall be as specified in this section. Testing and inspection shall apply to welding performed in the shop and in the field. After the Contractor’s welding inspection is complete, the Contractor shall allow the Engineer sufficient time to perform quality assurance ultrasonic welding inspection.
6-03.3(25)A1 Visual Inspection
All welds shall be 100 percent visually inspected. Visual inspection shall be performed before, during, and after the completion of welding.
6-03.3(25)A2 Radiographic Inspection
Complete penetration tension groove welds in Highway bridges and pedestrian Structures shall be 100 percent radiographically inspected. These welds include those in the tension area of webs, where inspection shall cover the greater of these two distances:
6-03.3(25)A3 Ultrasonic Inspection
Complete penetration groove welds on plates 5/16 inch and thicker in the following welded assemblies or Structures shall be 100 percent ultrasonically inspected:
6-03 Steel Structures
M 41-10 Page 6-145A minimum of 30 percent of complete penetration vertical welds on steel column jackets 5/16-inch and thicker, within 1.50 column jacket diameters of the top and bottom of each column, shall be inspected. If any rejectable flaws are found, 100 percent of the weld within the specified limits shall be inspected. The largest column cross section diameter for tapered column jackets shall constitute one column jacket diameter. The testing procedure and acceptance criteria for tubular members shall conform to the requirements of the AWS D1.1/D1.1M latest edition, Structural Welding Code.
6-03.3(25)A4 Magnetic Particle Inspection
6-03.3(26) Screw Threads
Screw threads shall be U.S. Standard and shall fit closely in the nuts. Steel Structures 6-03 Page 6-146 M 41-106-03.3(27) High-Strength Bolt Holes At the Contractor’s option under the conditions described in this section, holes may be punched or subpunched and reamed, drilled or subdrilled and reamed, or formed by numerically controlled drilling operations. The hole for each high-strength bolt shall be ¹/ 16 inch larger than the nominal diameter of the bolt. In fabricating any connection, the Contractor may subdrill or subpunch the holes then ream full size after assembly or drill holes full size from the solid with all thicknesses of material shop assembled in the proper position. If the Contractor chooses not to use either of these methods, then the following shall apply:
6-03.3(27)A Punched Holes
For punched holes, die diameter shall not exceed punch diameter by more than ¹/ 16 inch. Any hole requiring enlargement to admit the bolt shall be reamed. All holes shall be cut clean with no torn or ragged edges. The Contracting Agency will reject components having poorly matched holes.
6-03.3(27)B Reamed and Drilled Holes
Reaming and drilling shall be done with short taper reamers or twist drills, producing cylindrical holes perpendicular to the member. Reamers and drills shall be directed mechanically, not hand-held , except hand-held reamers may be used under the following conditions:
6-03 Steel Structures
M 41-10 Page 6-147If templates are used to ream or drill full-size connection holes, the templates shall be positioned and angled with extreme care and bolted firmly in place. Templates for reaming or drilling matching members or the opposite faces of one member shall be duplicates. All splice components shall be match-marked unless otherwise approved by the Engineer.
6-03.3(27)C Numerically Controlled Drilled Connections
In forming any hole described in Section 6-03.3(27) , the fabricator may use numerically controlled (N/C) drilling or punching equipment if it meets the requirements in this Subsection. The Contractor shall submit Type 1 Working Drawings consisting of a detailed outline of proposed N/C procedures. This outline shall:
6-03.3(27)D Accuracy of Punched, Subpunched, and Subdrilled Holes
After shop assembly and before reaming, all punched, subpunched, and subdrilled holes shall meet the following standard of accuracy. At least 75 percent of the holes in each connection shall permit the passage of a cylindrical pin ⅛ inch smaller in diameter than nominal hole size. This pin shall pass through at right angles to the face of the member without drifting. All holes shall permit passage of a pin ³/ 16 inch smaller in diameter than nominal hole size. The Contracting Agency will reject any pieces that fail to meet these standards.
6-03.3(27)E Accuracy of Reamed and Drilled Holes
At least 85 percent of all holes in a connection of reamed or drilled holes shall show no offset greater than ¹/ 32 inch between adjacent thicknesses of metal. No hole shall have an offset greater than ¹/ 16 inch. Centerlines from the connection shall be inscribed on the template and holes shall be located from these centerlines. Centerlines shall also be used for accurately locating the template relative to the milled or scribed ends of the members. Templates shall have hardened steel bushing inserted into each hole. These bushings may be omitted, however, if the fabricator satisfies the Engineer (1) that the template will be used no more than five times, and (2) that use will produce no template wear. Each template shall be at least ½ inch thick. If necessary, thicker templates shall be used to prevent buckling and misalignment as holes are formed.
6-03.3(27)F Fitting for Bolting
Before drilling, reaming, and bolting begins, all parts of a member shall be assembled, well pinned, and drawn firmly together. If necessary, assembled pieces shall be taken apart to permit removal of any burrs or shavings produced as the holes are formed. The member shall be free from twists, bends, and other deformation. In shop-bolted connections, contacting metal surfaces shall be sandblasted clean before assembly. Sandblasting shall meet the requirements of the SSPC Specifications for Commercial Blast Cleaning (SSPC-SP 6). Steel Structures 6-03 Page 6-148 M 41-10Any drifting done during assembly shall be no more than enough to bring the parts into place. Drifting shall not enlarge the holes or distort the metal.
6-03.3(28) Shop Assembly
6-03.3(28)A Method of Shop Assembly
Unless the Contract states otherwise, the Contractor shall choose one of the five shop assembly methods described below that will best fit the proposed erection method. The Contractor shall obtain the Engineer’s approval of both the shop assembly and the erection methods before Work begins.
6-03 Steel Structures
M 41-10 Page 6-1496-03.3(28)B Check of Shop Assembly The Contractor shall check each assembly for alignment, accuracy of holes, fit of milled joints, and other assembly techniques. Drilling or reaming shall not begin until the Engineer has given approval. If the Contractor uses N/C drilling, this approval must be obtained before the assembly or stage is dismantled.
6-03.3(29) Welded Shear Connectors
Installation, production control, and inspection of welded shear connectors shall conform to Chapter 9 of the AASHTO/AWS D1.5M/D1.5, latest edition, Bridge Welding Code. If welded shear connectors are installed in the shop, installation shall be completed prior to applying the shop primer coat in accordance with Section 6-07.3(9)G . If welded shear connectors are installed in the field, the steel surface to be welded shall be prepared to SSPC-SP 11, power tool cleaning, just prior to welding.
6-03.3(30) Painting
All painting shall be in accordance with Section 6-07 .
6-03.3(30)A Vacant
6-03.3(30)B Vacant
6-03.3(30)C Erection Marks
Erection marks to permit identification of members in the field shall be painted on previously painted surfaces.
6-03.3(30)D Machine Finished Surfaces
As soon as possible and before they leave the shop, machine-finished surfaces on abutting chord splices, column splices, and column bases shall be covered with grease. After erection, the steel shall be cleaned and painted as specified. All surfaces of iron and steel castings milled to smooth the surface shall be painted with the primer called for in the specified paint system. While still in the shop, machine-finished surfaces and inaccessible surfaces of rocker or pin-type bearings shall receive the full paint system. Surfaces of pins and holes machine- finished to specific tolerances shall not be painted. But as soon as possible and before they leave the shop, they shall be coated with grease.
6-03.3(31) Alignment and Camber
Before beginning field bolting, the Contractor shall:
6-03.3(31)A Measuring Camber
The Contractor shall provide the Engineer with a diagram for each truss that shows camber at each panel point. This diagram shall display actual measurements taken as the truss is being assembled. Steel Structures 6-03 Page 6-150 M 41-106-03.3(32) Assembling and Bolting To begin bolting any field connection or splice, the Contractor shall install and tighten to snug tight enough bolts to bring all parts into full contact with each other prior to tightening these bolts to the specified minimum tension. “Snug tight” means either the tightness reached by (l) a few blows from an impact wrench or (2) the full effort of a person using a spud wrench. As erection proceeds, all field connections and splices for each member shall be securely drift pinned and bolted in accordance with 1 or 2 below before the weight of the member can be released or the next member is added. Field erection drawings shall specify pinning and bolting requirements that meet or exceed the following minimums:
6-03 Steel Structures
M 41-10 Page 6-151Assemblies removed for the purpose of rotational capacity testing, determination of the inspection torques, or verification of tension controlled bolt performance shall be replaced with new bolts at no additional expense to the Contracting Agency. To minimize the number of removed assemblies, the Contractor may combine rotational capacity testing and inspection torque determination as approved by the Engineer. The Contractor may complete a field bolted connection or splice in a continuous operation before releasing the mass of the member or adding the next member. The Contractor shall utilize drift pins to align the connection. The alignment drift pins shall fill between 15 and 30 percent of the holes in a single field connection and between 15 and 30 percent of the holes on each side of a single joint in a splice plate. Once the alignment drift pins are in place, all remaining holes shall be filled with bolts and tightened to snug tight starting from near the middle and proceeding toward the outer gage lines. Once all of these bolts are snug tight, the Contractor shall systematically tighten all these bolts to the specified minimum tension. The Contractor shall then replace the drift pins with bolts. Each of these bolts shall be tightened to the specified minimum tension. All bolts shall be placed with heads toward the outside and underside of the bridge. All high-strength bolts shall be installed and tightened before the falsework is removed. The Contractor may erect metal railings as erection proceeds. But railings shall not be bolted or adjusted permanently until the falsework is released and the deck placed. The Contractor shall not begin painting until the Engineer has inspected and accepted field bolting.
6-03.3(33) Bolted Connections
Fastener components shall consist of bolts, nuts, washers, tension control bolt assemblies, and direct tension indicators. Fastener components shall meet the requirements of Section 9-06.5(3) . After final tightening of the fastener components, the threads of the bolts shall at a minimum be flush with the end of the nut. The Contractor shall submit Type 1 Working Drawings providing documentation of the bolt tension calibrator, including brand, capacity, model, date of last calibration, and manufacturer’s instructions for use. The Contractor shall supply the bolt tension calibrator and all accompanying hardware and calibrated torque wrenches to conduct all testing and inspections described herein. Use of the bolt tension calibrator shall comply with manufacturer’s recommendations. Fastener components shall be protected from dirt and moisture in closed containers at the site of installation. Only as many fastener components as are anticipated to be installed during the Work shift shall be taken from protected storage. Fastener components that are not incorporated into the Work shall be returned to protected storage at the end of the Work shift. Fastener components shall not be cleaned or modified from the as-delivered condition. Fastener components that accumulate rust or dirt shall not be incorporated into the Work. Tension control bolt assemblies shall not be relubricated, except by the manufacturer. All bolted connections are slip critical unless otherwise noted in the Plans. Bolts installed in the field for painted structures require either Type 1 or Type 3 bolts and shall be galvanized in accordance with ASTM F2329 or ASTM B695 Class 55. All components of the fastener assembly including bolt, nut and washer, shall be galvanized using the same method. When galvanized bolts are specified, tension-control galvanized bolts are not permitted. Unpainted structures require Type 3 bolts. ASTM F3125 Grade A490 bolts shall not be galvanized and shall not be used in contact with galvanized metal. Steel Structures 6-03 Page 6-152 M 41-10Washers are required under turned elements for bolted connections and as required in the following:
6-03 Steel Structures
M 41-10 Page 6-153Table 2 Turn-of-Nut Tightening Method Nut Rotational From Snug Tight Condition Bolt LengthDisposition of Outer Faces of Bolted Parts Condition 1 Condition 2 Condition 3 L <= 4D ⅓-turn ½-turn ⅔-turn 4D < L<= 8D ½-turn (*) ⅔-turn 5/6-turn 8D < L<= 12D ⅔-turn (*) 5/6-turn 1-turn (*) When performing rotational capacity testing in accordance with Section 6-03.3(33) A, the total of two times the turns specified in Table 2 may be reduced by 15% for ASTM F3125 GR A490 bolts when allowed by the Engineer. Bolt length measured from underside of head to top of nut. Condition 1 – Both faces at right angles to bolt axis. Condition 2 – One face at right angle to bolt axis, one face sloped no more than 1:20, without bevel washer. Condition 3 – Both faces sloped no more than 1:20 from right angle to bolt axis, without bevel washer. Nut rotation is relative to the bolt regardless of which element (nut or bolt) is being turned. Tolerances permitted plus or minus 30 degrees ( 1⁄12-turn) for final turns of ½-turn or less; plus or minus 45 degrees (⅛-turn) for final turns of ⅔-turn or more. D = nominal bolt diameter of bolt being tightened. When bolt length exceeds 12D, the rotation shall be determined by actual tests in which a suitable tension device simulates actual conditions.
6-03 Steel Structures
M 41-10 Page 6-155bolt and turning the nut for the full length of the bolt threads by hand. Bolts to be reused shall be relubricated in accordance with the manufacturer’s recommendation. Used bolts shall be subject to a rotational capacity test as specified in Section 6-03.3(33)A Pre- Erection Testing. Touching up or retightening bolts previously tightened by the Turn-of- Nut Method, which may have been loosened by the tightening of adjacent bolts shall not be considered as reuse, provided the snugging up continues from the initial position and does not require greater rotation, including the tolerance, than that required by Table 2 .
6-03.3(33)A Pre-Erection Testing
High-strength bolt assemblies (bolt, nut, direct tension indicator, and washer), both black and galvanized, shall be subjected to a field rotational capacity test, as outlined below, prior to any permanent fastener installation. For field installations, the rotational capacity test shall be conducted at the jobsite. Each combination of bolt production lot, nut production lot, washer production lot, and direct tension indicator production lot shall be tested as an assembly, except tension control bolt assemblies, which shall be tested as supplied by the manufacturer. Each rotational capacity test shall include three assemblies. Once an assembly passes the rotational capacity test, it is accepted for use for the remainder of the project unless the Engineer deems further testing is necessary. All tests shall be performed in a bolt tension calibrator by the Contractor in the presence of the Engineer. High-strength bolt assemblies used in this test shall not be reused. The bolt assemblies shall meet the following requirements after being pretensioned to 15 percent of the minimum bolt tension in Table 1 . The assembly shall be considered as nonconforming if the assembly fails to pass any one of the following specified requirements:
6-03.3(33)B Bolting Inspection
The Contractor, in the presence of the Engineer, shall inspect the tightened bolt using a calibrated inspection torque wrench, regardless of bolting method. The Contractor shall supply the inspection torque wrench. Inspection shall be performed within seven calendar days from the completion of each bolted connection or as specified by the Engineer. If the bolts to be installed are not long enough to fit in the bolt tension calibrator, five bolts of the same grade, size, and condition as those under inspection shall be tested using Direct-Tension-Indicators (DTIs) to measure bolt tension. This tension measurement test shall be done at least once each inspection day. The Contractor shall supply the necessary DTIs. The DTI shall be placed under the bolt head. A washer shall be placed under the nut, which shall be the element turned during the performance of this tension measurement test. Each bolt shall be tightened by any convenient means to the specified minimum tension as indicated by the DTI. The inspecting wrench shall then be applied to the tightened bolt to determine the torque required to turn the nut 5 degrees (approximately 1 inch at a 12-inch radius) in the tightening direction. The job inspection torque shall be taken as the average of three values thus determined after rejecting the high and low values. Five representative bolts/nuts/washers and DTIs if used (provided by the Contractor) of the same grade, size, and condition as those under inspection shall be placed individually in a bolt tension calibrator to measure bolt tension. This calibration operation shall be
6-03 Steel Structures
M 41-10 Page 6-157done at least once each inspection day. There shall be a washer under the part turned in tightening each bolt if washers are used on the Structure. In the bolt tension calibrator, each bolt shall be tightened by any convenient means to the specified tension. The inspection torque wrench shall then be applied to the tightened bolt to determine the torque required to turn the nut or head 5 degrees (approximately 1 inch at a 12-inch radius) in the tightening direction. The job-inspection torque shall be taken as the average of three values thus determined after rejecting the high and low values. Ten percent (at least two), or as specified by the Engineer, of the tightened bolts on the Structure represented by the test bolts shall be selected at random in each connection. The job-inspection torque shall then be applied to each with the inspecting wrench turned in the tightening direction, with no restraint applied to the opposite end of the bolt. If this torque turns no bolt head or nut, the Contracting Agency will accept the connection as being properly tightened. If the torque turns one or more bolt heads or nuts, the job- inspection torque shall then be applied to all bolts in the connection. Except for tension control bolt assemblies and DTIs with zero gap at all protrusion spaces, any bolt whose head or nut turns at this stage shall be tightened and reinspected. Any tension control bolt assemblies or DTIs that have zero gap at all protrusion spaces shall be replaced if the head or nut turns at this stage. The Contractor shall submit Type 1 Working Drawings consisting of the manufacturer’s detailed procedure for routine observation to ensure proper use of the tension control bolt assemblies.
6-03.3(34) Adjusting Pin Nuts
All pin nuts shall be tightened thoroughly. The pins shall be placed so that members bear fully and evenly on the nuts. The pins shall have enough thread to allow burring after the nuts are tightened.
6-03.3(35) Setting Anchor Bolts
Anchor bolts shall be set in masonry as required in Section 6-02.3(18) . Anchor bolts shall be grouted in after the shoes, masonry plates, and keeper plates have been set and the span or series of continuous spans are completely erected and adjusted to line and camber.
6-03.3(36) Setting and Grouting Masonry Plates
The following procedure applies to masonry plates for all steel spans, including shoes, keeper plates, and turning racks on movable bridges. To set masonry plates, the Contractor shall:
6-03.3(38) Placing Superstructure
The concrete in piers and crossbeams shall reach at least 80 percent of design strength before girders are placed on them.
6-03.3(39) Swinging the Span
Forms weighing less than 5 pounds per square foot of bridge deck area and uniformly distributed along the steel spans may be placed before the spans swing free on their supports. Steel reinforcing bars or concrete bridge deck shall not be placed on steel spans until the spans swing free on their supports and elevations are recorded. No simple span or any series of continuous spans will be considered as swinging free until all temporary supports have been released. Reinforcing steel or concrete bridge decks shall not be placed on any simple or continuous span steel girder bridge until all its spans are adjusted and its masonry plates, shoes, and keeper plates grouted. For this specification, the structure shall be considered as continuous across hinged joints. After the falsework is released (spans swung free), the masonry plates, shoes, and keeper plates are grouted, and before any load is applied, the Contractor (or the Engineer if the Contracting Agency is responsible for surveying) shall survey elevations at the tenth points along the centerline on top of all girders and floorbeams. The Contractor shall calculate the theoretical top of girder or floorbeam flange elevations and compare the calculated elevations to the surveyed elevations. The theoretical pad or haunch depth shown in the Plans shall be increased or decreased by the difference between the theoretical and surveyed top of girder or floorbeam elevations. The soffit (deck formwork) shall be set based on the Plan bridge deck thickness and the adjusted pad or haunch depth. The Contractor shall submit all survey data and calculations to the Engineer for review ten working days prior to placing any load, beyond the maximum five pounds per square foot of form weight allowed, on the Structure.
6-03.3(40) Draining Pockets
The Contractor shall provide enough holes to drain all water from pockets in trusses, girders, and other members. Unless shown on approved shop plans, drain holes shall not be drilled without the written approval of the Engineer. All costs related to providing drain holes shall be included in the unit Contract prices for structural or cast steel.
6-03.3(41) Vacant
6-03.3(42) Surface Condition
As the Structure is erected, the Contractor shall keep all steel surfaces clean and free from dirt, concrete, mortar, oil, paint, grease, and other stain-producing foreign matter. Any surfaces that become stained shall be cleaned as follows: Painted steel surfaces shall be cleaned by methods required for the type of staining. The Contract shall submit a Type 1 Working Drawing of the cleaning method. Unpainted steel surfaces shall be cleaned by sandblasting. Sandblasting to remove stains on publicly visible surfaces shall be done to the extent that, in the Engineers opinion, the uniform weathering characteristics of the Structure are preserved.
6-03 Steel Structures
M 41-10 Page 6-1596-03.3(43) Castings, Steel Forgings, and Miscellaneous Metals Castings, steel forgings, and miscellaneous metals shall be built to comply with Section 9-06 .
6-03.3(43)A Shop Construction, Castings, Steel Forgings, and Miscellaneous Metals
This section’s requirements for structural steel (including painting requirements) shall also apply to castings, steel forgings, and miscellaneous metals. Castings shall be:
6-03.4 Measurement
Cast or forged metal (kind) shown in the Plans will be measured by the pound or will be paid for on a lump sum basis, whichever is shown on the Proposal.
6-03.5 Payment
Payment will be made for each of the following Bid items that are included in the Proposal: “Structural Carbon Steel”, lump sum. The lump sum Contract price for “Structural Carbon Steel” shall be full pay for all costs in connection with furnishing all materials, labor, tools, and equipment necessary for the manufacture, fabrication, transportation, erection, and painting of all structural carbon steel used in the completed Structure, including the providing of such other protective coatings or treatment as may be shown in the Plans or specified in the Special Provisions. For steel Structures, the estimated weight of the structural carbon steel in the project will be shown in the Plans or in the Special Provisions. In the event any change in the Plans is made which will affect the weight of materials to be furnished, payment for the additional structural carbon steel required as a result of the change in the Plans will be made at a unit price per pound obtained by dividing the Contractor’s lump sum Bid for structural carbon steel by the total estimated weight of structural carbon steel shown in the Plans or in the Special Provisions. Reductions in weight due to a change in the Plans will be made at the same rate as determined above and will be deducted from payments due the Contractor. Prospective Bidders shall verify the estimated weight of structural carbon steel before submitting a Bid. No adjustment other than for approved changes shall be made in the lump sum Bid even though the actual weight may deviate from the stated estimated weight. For concrete and timber Structures, where the structural carbon steel is a minor item, no estimated weight will be given for the structural carbon steel. In the event any change in the Plans is necessary which will affect the weight of material to be furnished for this type of Structure, the payment or reduction for the revision in quantity will be made at a unit price per pound obtained by dividing the Contractor’s Steel Structures 6-03 Page 6-160 M 41-10lump sum Bid for the structural carbon steel by the calculated weight of the original material. The calculated weight will be established by the Engineer and will be based on an estimated weight of 490 pounds per cubic foot for steel. Any change in the Plans which affects the weight of material to be furnished as provided herein will be subject to the provisions of Section 1-04.4 . “Structural Low Alloy Steel”, lump sum. “Structural High Strength Steel”, lump sum. Payment for “Structural Low Alloy Steel” and “Structural High Strength Steel” shall be made on the same lump sum basis as specified for structural carbon steel. “(Cast or Forged) Steel”, lump sum or per pound. “(Cast, Malleable, or Ductile) Iron”, lump sum or per pound. “Cast Bronze”, lump sum or per pound. Payment for “(Cast or Forged) Steel”, “(Cast, Malleable or Ductile) Iron”, and “Cast Bronze” will be made at the lump sum or per pound Contract prices as included in the Proposal. For the purpose of payment, such minor items as bearing plates, pedestals, forged steel pins, anchor bolts, field bolts, shear connectors, etc., unless otherwise provided, shall be considered as structural carbon steel even though made of other materials. When no Bid item is included in the Proposal and payment is not otherwise provided, the castings, forgings, miscellaneous metal, and painting shall be considered as incidental to the construction, and all costs therefore shall be included in the unit Contract prices for the payment items involved and shown.