B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Miscellaneous Construction

8-08Rumble Strips

WA · 2024 Standard Specifications✓ Full text on BuildSpecBook pages 809–809 Save this section

Ask about Section 8-08

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

M 41-10 Page 8-59 Rumble Strips 8-088-08 Rumble Strips

8-08.1 Description

This Work consists of constructing centerline and shoulder rumble strips by grinding hot mix asphalt. The Work shall include cleanup and disposal of cuttings and other resultant debris. The Standard Plans show the patterns and construction details for the centerline rumble strip and the four types of shoulder rumble strips.

8-08.2 Vacant

8-08.3 Construction Requirements

The equipment shall have a rotary type cutting head or series of cutting heads capable of grinding one or more recesses in the hot mix asphalt as detailed in the Standard Plans . The difference in the surface texture between the high and low surfaces from the grinding shall not exceed ⅛ inch. Rumble strips shall not be constructed on bridge decks, bridge approach slabs, or cement concrete surfaces. In areas where monuments, drainage structures, induction loop lead-ins, pavement markings or other features will not allow the rumble strips to be constructed as detailed, the rumble strips shall be eliminated or relocated as approved by the Project Engineer. The traveled lanes shall be kept free of cuttings and other construction debris at all times. All cuttings, grinding debris, dust, and other loose materials shall become the property of the Contractor and, upon completion of rumble strip grinding, shall be immediately removed and disposed of outside the project limits. Cuttings and other debris shall not be allowed to enter waterways. When shown in the Plans, the rumble strips shall be fog sealed in accordance with the requirements of Section 5-02 , following the completion of the rumble strips. All pavement markings, junction boxes, drainage structures, and similar objects shall not be fog sealed. The accumulative error in the longitudinal spacing of the rumble strips and the gaps, when required, shall not exceed plus or minus 5 percent.

8-08.4 Measurement

Centerline and shoulder rumble strips will be measured to the nearest 0.01 mile along the mainline roadway for centerline or each shoulder. No deductions will be made for required gaps shown on the Standard Plans or for the elimination of rumble strips across bridge decks, bridge approach slabs, cement concrete areas, or other areas approved by the Engineer. Fog sealing, when shown in the Plans, will be measured as asphalt for fog seal in accordance with Section 5-02.4 .

8-08.5 Payment

“Shoulder Rumble Strip Type __”, per mile. “Centerline Rumble Strip”, per mile. Layout of the rumble strip pattern on the centerline or shoulders for grinding purposes is the responsibility of the Contractor. All costs involved in this Work shall be included in the appropriate Bid item. Payment for fog sealing the rumble strip on the centerline or shoulder, when shown in the Plans, shall be paid as asphalt for fog seal in accordance with Section 5-02.5 .

Get an email when 8-08 changes

Washington revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Washington Standard Specifications for Road, Bridge, and Municipal Construction, 2024 Edition. Pages 809–809 of 1,151. View official source ↗

Ask about this section

Scoped to Washington Standard Specifications for Road, Bridge, and Municipal Construction (M 41-10), Section 8-08 — Rumble Strips. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.