Effective with the December 2018 Letting 378 2019 Standard Spec ifications Section 626 Peat Humus
626.1Description
under the contract, or stored under a previous contract, and in corporating it into the surfaces of portions of the roadway.
626.2Materials
626.2.1 If Marsh Excavation is an Item in the Contract
more fibrous material consisting of decomposed vegetable matter , moss, etc. from the muck-like substances. Take this material from marshes the plans or the co ntract indicates as having suitable material, to the extent that it is available or necessary for t he work intended. Place the selected material into piles separate and apart from the waste materials encountered. Locate and size these piles of selected material to ensure proper drainage, and ready and convenient handling when incorporating into the work. 626.2.2 If Marsh Excavation is N ot an Item in the Contract
material stored and made available to the contractor under the contract.
626.3Construction
626.3.1 General
previously designated. Cover the selected areas with a layer of marsh excavation material approximately 3 to 4 inches dee p, dependent upon its consistenc y and moisture content, and incorporate it into the native soil by the appropriate equipmen t to accomplish the above-required results. After completing mixing operations, smooth and dress the surfaces to restore them to the required lines, grades, slopes, and cross-section. 626.3.2 Disposing of Surplus Material
disposal. 626.4 Measurement
measured shall equal the actual num ber of square yards of area this material was placed on, and incorporated into, according to the contract, within the limits of the construction the plans show, or in the contract, or as the engineer directed. 626.5 Payment
items: ITEM NUMBER DESCRIPTION UNIT
626.0200 Peat Humus SY
placing, and incorporating in t he soil; for subsequent restoring of the surface, and disposing of surplus material; provided, that the department makes no deductions from the Excavation Marsh bid item for the quantities of materials salva ged or reclaimed from for the bid item of Peat Humus.
Effective with the December 2018 Letting 379 2019 Standard Spec ifications Section 627 Mulching
627.1Description
seeding the surfaces of the roadway.
627.2Materials
other suitable material of a similar nature that the engineer a pproves, and is substantially free of noxious weed seeds and objectionable foreign matter.
erosion control prod uct acceptability list ( PAL). The contractor may obtai n a copy of the department's PAL and the prequalification procedur e for products not on the dep artment's PAL.
627.3Construction
627.3.1 General
seeding.
proper mulch placement.
but thick enough to shade the gr ound, conserve soil moisture, a nd prevent or reduce erosion.
causes. 627.3.2 Placing
or Method C, or a combination o f the 3, unless a specific metho d is specified in the contract. 627.3.2.1 Method A, Netting
inches. Use a specific rate o f application; dependent on the character of the material, that results in a cover conforming to the requi rements specified above in 627.3.1 . Loosen or make fluffy the mulch material from compacted bales before spreading in place. Unless directed otherwise, begin mulching at the top of the slopes a nd proceed downward.
pegs or staples to prevent it fr om floating as the vegetation g rows. Instead of this anchorage, the contractor may secure mulch by heavy biodegradable twine fastened by pegs or staples to form a grid with 6 to 10 feet spacing.
instead of separately applying mulch and netting. 627.3.2.2 Method B, Tackifier
in one operation. Place straw o r hay uniformly over the area 1/2 to 1 inch deep, using 1/2 to 3 tons of mulch per acre. Mix and place tackifier according to the department's PAL. Within the above limits, the engineer will determine, on the job, the application rate of the mulch and the tackifier, and the engineer may vary the rates during mulching to produce the desi red results. Use an engineer- approved machine to place the mulc h that blows or ejects by con stant air stream a controlled quantity of mulch and applies a spray of tackifier to partially coat the straw or hay, sufficient to hold together and keep in place the deposited straw or hay. The contractor ma y apply the tackifier as an overspray in a separate operation after placing the straw or hay.
engineer-approved methods, that p lace a controlled quantity of mulch uniformly over the area 1/2 to 1 1/2 inches deep. Treat areas receiving wood chip mulch, with one pound of available nitrogen per 1000 square feet before or after applying the chips.
uniform ejection from the disc harge spout, and operate in a pos ition to produce mulch of uniform depth and coverage.