Effective with the December 2018 Letting 376 2019 Standard Spec ifications Section 625 Topsoil and Salvaged Topsoil
625.1Description
sustain plant life, commonly known as topsoil, from locations t he contractor furnishes beyond the limits of the right-of-way.
embankments in quantities and depths available and necessary to cover the work slopes. This work also includes reclamation, placing, spreading, and finishing of this topsoil.
625.2Materials
adapted to sustain plant life, and ensure this topsoil is in a pH range of 6.0 to 7.0.
bearing soils available from overlying portions of areas to be occupied by the completed roadway.
625.3Construction
625.3.1 Preparing the Roadway for Topsoil
depth with topsoil the finished work conforms to the required l ines, grades, slopes and cross-sections the plans and drawings show. 625.3.2 Processing Topsoil or Salvaged Topsoil
rock, and other materials that will interfere with subsequent vegetation establishment.
stockpile the topsoil on the right-of-way or place it directly on the designated areas.
foundation up to the quantity neces sary to cover the slopes for the bid items of Salvaged Topsoil and Topsoil. Salvage topsoil from e mbankment areas outside the road way foundation only if that additional material is required to cover the slopes.
excess topsoil on the project or dispose of as specified in 205.3.12 . 625.3.3 Placing
cross-section, place and spread the topsoil to a uniform depth as the plans show or the contract requires. If no depth is shown, place and spread the topsoil to a minimum depth of 4 inches in rural areas and a minimum depth of 6 inches in urban areas, or as the engineer designates.
material passes a one-inch sie ve and at least 90 percent passes the No. 10 sieve.
to present a uniform appearance. The engineer will not require rolling.
soils to a more or less homogen eous mixture by using the approp riate equipment.
625.4Measurement 625.4.1 Topsoil
whichever the contract specifies.
of square yards of topsoiled ar ea to the depth specified within the limits of construction designated on the plans, or in the contract , or as the engineer directs.
transports the material in vehi cles not adapted for measurement , then the departmen t will measure the material in cubic yards of volume in its original position computed by the method of average end areas with no correction for curvature; or if the engineer elects, by the method of truncated prisms.
Effective with the December 2018 Letting 377 2019 Standard Spec ifications 625.4.2 Salvaged Topsoil
quantity measured for payment sha ll equal the actual number of square yards of area topsoiled to the depth specified within the limits of construction designated on the plans or in the contract, or as the engineer directs.
625.5Payment
items: ITEM NUMBER DESCRIPTION UNIT
625.0100 Topsoil SY
05 Topsoil CY
625.0500 Salvaged Topsoil SY
625.5.1 Topsoil
material; and for undercutting excavations, or underfilling emb ankments necessary to receive this material. The department will make no allowance, adjustment, or measurement for payment under the Excavation bid items for undercutting cut sections, or underfil ling embankments. 625.5.2 Salvaged Topsoil
placing this material; and for undercutting excavations, or und erfilling embankmen ts necessary to receive this material. The department will make no deductions f rom the Excavation bid items for the quantities of Salvaged Topsoil material obtained from areas of cut sections. Additionally, the department will not measure or pay for the volumes of Salvaged Topsoil removed from sites of proposed embankments under the Exca vation bid items, or make any allowance, adjustment, or measurement for payment under the Excavation bid items for undercutting cut sections, or underfilling embankments.
in these areas at a unit price determined by multiplying the co ntract unit price bid for Salvaged Topsoil by 3, or absent that bid item in the contract, as the contract unit price bid for Tops oil multiplied by 3, The department will pay for restor ation under the Restoration Post Acceptance Topsoil administrative item.
areas unless that material is n ecessary to cover the slopes.
Effective with the December 2018 Letting 378 2019 Standard Spec ifications Section 626 Peat Humus
626.1Description
under the contract, or stored under a previous contract, and in corporating it into the surfaces of portions of the roadway.
626.2Materials
626.2.1 If Marsh Excavation is an Item in the Contract
more fibrous material consisting of decomposed vegetable matter , moss, etc. from the muck-like substances. Take this material from marshes the plans or the co ntract indicates as having suitable material, to the extent that it is available or necessary for t he work intended. Place the selected material into piles separate and apart from the waste materials encountered. Locate and size these piles of selected material to ensure proper drainage, and ready and convenient handling when incorporating into the work. 626.2.2 If Marsh Excavation is N ot an Item in the Contract
material stored and made available to the contractor under the contract.
626.3Construction
626.3.1 General
previously designated. Cover the selected areas with a layer of marsh excavation material approximately 3 to 4 inches dee p, dependent upon its consistenc y and moisture content, and incorporate it into the native soil by the appropriate equipmen t to accomplish the above-required results. After completing mixing operations, smooth and dress the surfaces to restore them to the required lines, grades, slopes, and cross-section. 626.3.2 Disposing of Surplus Material
disposal. 626.4 Measurement
measured shall equal the actual num ber of square yards of area this material was placed on, and incorporated into, according to the contract, within the limits of the construction the plans show, or in the contract, or as the engineer directed. 626.5 Payment
items: ITEM NUMBER DESCRIPTION UNIT
626.0200 Peat Humus SY
placing, and incorporating in t he soil; for subsequent restoring of the surface, and disposing of surplus material; provided, that the department makes no deductions from the Excavation Marsh bid item for the quantities of materials salva ged or reclaimed from for the bid item of Peat Humus.