Effective with the December 2018 Letting 468 2019 Standard Spec ifications Section 651 General Requirements for Electrical Work
651.1Description
requirements used to perform ele ctrical work required in the co ntract under 652 through 678.
651.2Materials
under the provisions of the SPS 316 component of the WSEC.
department's QPL.
drawings to the engineer. Include bid items, names and addresses of manufacturers, catalog cut sheets with catalog numbers, and manufacturer's specifications in the materials list. Do not deliver materials or begin the work wit hout the engineer's written approval. The engineer may reject all or part of the materials list. Resubmit a lternatives for rejected mater ials within 15 business days of receipt of the engineer's written rejection . Do not substitute or change materials without the engineer’s written approval.
not have a UL or NRTL standard.
will compensate the contractor if material is destroyed.
following terms: - Ensure that return materials ar e new and in original packagin g. - Return materials to the electr ical unit within 6 months of the date that they w ere picked up. - Region electrical personnel w ill not release loaned materials for contractor pick up until the region traffic engineer has a copy of the contractor's order forms for exact r eplacement materials. - Ensure that contractor-ordered replacement materials conform to the latest specific ations and drawings used for new state replacement orders. - The department will not accept monetary reimbursement.
651.3Construction
651.3.1 General
or other material during excavation, remove and dispose of that material. Place trench backfill in 12- inch or shallower thoroughly-compact layers. Dispose of excess material as specified for disposing of surplus unsuitable material in 205.3.12 . Restore areas damaged or disturbed by the contractor's operations.
connections exposed to the weathe r. Do not use spray-on products. Do not apply anti-seize compound to the following: - Electrical Connections. - Anchor rods and anchor assemb lies associated with type 9, 10, 12, & 13 poles under 657, high mast light poles under 660, and camera poles under 677. - Friction connections using ASTM F3125 high-strength A325 steel bolts.
with 2 coats of synthetic resin enamel or with 2 coats of engin eer-approved zinc- rich paint. Repair damage to galvanized coatings wit h 2 coats of zinc dust/zinc ox ide paint conforming to 614.2 . These requirements apply to both contra ctor-furnished and state-furni shed equipment.
electrodes.
- Remove unused signal heads or cover them from traffic's view. - Energize and turn on availabl e intersection lighting if signalization is not operational unless the engineer approves otherwise.
Effective with the December 2018 Letting 469 2019 Standard Spec ifications (7) Provide as-built drawings detailing the final placement of con duit, cabling, equipment, and geometric modifications under the contract. Provide a PDF copy conforming to CMM 1-65.14 . The engineer will reject as-builts with incomplet e or incorrect content or not co nforming to CMM standards. 651.3.2 Personnel Qualifications
supervision of a journey worker el ectrician. Before performing electrical work, provide the documentation specified in 651.3.2(3) to the engineer proving that the el ectricians performing the w ork have attained status as journey worker and apprentice electrici ans.
contract, performed as specified in the standards pecifications , contract special provisions, standard detail drawings, and plan details applicable to electrical cons truction.
Wisconsin department of safety and professional services to pro ve electricians are qualified. 651.3.3 Testing
conductors, equipment grounding conductors, ungrounded conducto rs, and shielding contained in the cable with a megger. Submit the megger test results to the engineer. Ensure that the megger reads greater than 500 mega ohms during each of the following tests: - To ground. - Between each conductor. - Between each shield.
engineer's satisfaction that the following conditions exist:
requested inspection. In the ev ent of deficiencies, request a r einspection when the work is corrected. The engineer will not authorize turn -on until the contractor corrects deficiencies.
sequence and all special functions, such as preemption, as the plans show, or as the engineer approves.
work properly.
that fails shall be repaired or r eplaced and that component sha ll again be subject to the twenty-night proper working order test.
and electrical systems work properly. 651.4 (Vacant)
651.5Payment
lighting, and ITS contract bid items.
Effective with the December 2018 Letting 470 2019 Standard Spec ifications Section 652 Electrical Conduit
652.1Description
and other electrical work, and rigid nonmetallic conduit for tr affic signal detectors.
652.2Materials
652.2.1 General
652.2.2 Rigid Metallic Conduit
652.2.3 Rigid Nonmetallic Conduit
locations. Use schedule 80 ext ra-heavy wall type for locations exposed to the elements. 652.2.4 Reinforced Therm osetting Resin Conduit
to UL 2515. Ensure that wall th ickness, coupling type or method , fittings, and hanger system conform to manufacturer recommendations for installation on the outside of structures. 652.2.5 Loop Detector Conduit
attachments designed specifica lly for the conduit furnished to join and terminate PVC conduit. Use engineer-approved PVC terminal adaptor fittings to connect cast iron T-condulets to PVC conduit.
wedge-nut style covers with neoprene gaskets on cast iron condu lets.
652.3Construction 652.3.1 Installation of Conduit
652.3.1.1 General
conduit.
plans show or as the engineer directs. Inst all each run of cond uit between adjacent access points using one size for its entire length. A run is the conduit from pull box to pull box, junction box to junction box, or pull box to j unction box. If the engineer appr oves, the contractor may substitute a larger size of conduit than the contract shows for that run. Delete 652.3.1.1(3), the department no longer allows drilled and open drain hole conduit installations.
the contract specifies wire or cable, install a 12 AWG. XLP insulated, stranded, copper, 600-volt AC, wire. Provide wire 4 feet longer than the conduit run and doubl e it back at least 2 feet at each raceway access point. Anchor the tracer wire at each access point.
wire or cable, install engineer- approved threaded caps with ant i-seize compound applied to the threads.
pull box, and keep capped or plugged until installing the wire or cable. Install end bells on rigid nonmetallic conduit raceway access points before installing wir e or cable. Ream non-metallic conduits to eliminate internal sharp edges before installing end bells. Use only UL or NRTL listed adapter fittings to connect rigid nonme tallic conduit to rigid metallic conduit. 652.3.1.2 Installing Underground
depth and width sufficient to acc ommodate the outside diameter of the conduit couplings. Lay the conduit at the depth below grade t he plans show. Backfill the trench with select material passing a one-inch sieve.
Do not backfill the trench befo re inspecting the conduit. Caref ully tamp the backfill in place as specified for placing backfill in layers in 651.3 . Place at least 0.7 cubic feet of size No. 2 coarse aggregate, as specified in 501.2.5.4.5 , directly under each drainage hole.