Retaining wall permit checklist — Seattle, Washington

Assembled from Seattle’s own published permit rules. Every line below is quoted from a city document and linked to it. Nothing here is generated, estimated, or inferred from another jurisdiction.

Do you need a permit?

Seattle requires a permit for a retaining wall.

When a permit is not required

A construction permit is not required when all three of the following are met: the rockery or retaining wall stands 4 feet or lower, sized from the footing base — even where that base sits below grade — up to the wall's highest point; the wall is not located on a parcel with an environmentally critical area; and no damage will occur to adjoining properties or structures during or after construction. Building a wall at the property line creates potential for damage and requires a construction permit.

What Seattle publishes for this permit

  • 2 submittal documents to include with the application
  • 1 process step from application to final
  • 1 published fee line from the city's fee schedule
  • Checked against Seattle's documents on September 18, 2026

Loading the full checklist…

Sources

Other permits Seattle publishes rules for

Listed because the city publishes a separate rule for each type — not because this project necessarily triggers one. Whether it does depends on your scope of work.

All Seattle permit requirementsSeattle permit costsApply with the city ↗

BuildSpec is a reference, not the authority having jurisdiction. Confirm requirements with Seattle before you build.