701TRAFFIC STRIPE

AL · 2022 Standard SpecificationsBook pages 587595View official source ↗

701.01 Description .

Division 700

TRAFFIC CONTROL DEVICES AND HIGHWAY LIGHTING TRAFFIC STRIPE

701.01 Description.

This Section shall cover the work of placing a permanent or temporary traffic stripe at the locations shown on the plans or where directed by the Engineer. This Section shall also cover the removal of existing or temporary traffic stripe.

701.02 Materials.

Materials shall be furnished in accordance with the requir ements given in Sections 856 and 857. The required dimensions, color, class, retroreflectivity and type of stripe will be shown on the plans. The required type of material will be designated by "Class" in accordance with the following. CLASS OF TRAFFIC STRIPE CLASS MATERIAL 1 Paint 1H High Build Paint 2 Standard Thermoplastic Material 2T Thin Film Spray Applied Thermoplastic Material 3 Tape W Warranted Traffic Marking Material The required reflectivity will be designated by "Type" in accordance with the following. TYPE OF TRAFFIC STRIPE TYPE REFLECTIVITY A Reflective B Non-reflective Class 1H, Class 2, and Class 2T materials shall be in compliance with the formulations given in the tables in Section 856 for each class. Class 1, Class 3, Class W, and Drop On Glass Beads shall be one of the materials shown on List V -3, Temporary Traffic Marking Materials, and List V -4, Permanent Traffic Marking Materials. These lists are in the Department’s Manual, “Materials, Sources, and Devices with Special Acceptance Requirements”. Information concerning these lists is given in Subarticle 106.01(f) and ALDOT -355.

701.03 C onstruction Requirements.

a.Acceptance Program for Traffic Marking Materials . The guidelines for the evaluation and acceptance of traffic marking materials are given in the procedure ALDOT -420 "Acceptance Program for Traffic Marking Materials". These guidelines shall be followed in the furnishing and placement of stripe.
b.Temporary Traffic Stripe .
1.Requirement for Use . A roadway shall not be opened to traffic without a traffic stripe u nless approved otherwise by the Engineer. Lane lines shall be maintained at all times when traffic is required to pass through the areas of construction. Existing lane lines covered by paving operations shall be replaced with temporary stripe. Temporary edge lines will not be required unless shown to be required on the plans or required by the Engineer.
2.Allowable Material . Temporary traffic stripe shall be reflective and shall be: • Permanent Traffic Marking Materials (Class 1, LIST V -4) or;

701.03 Construction Requirements.

• Removable Ta pe (List V -3).

3.Weather Co nditions for Application . Temporary striping may be placed without regard to the weather conditions if allowed by the Engineer.
4.Configuration . A broken line of temporary stripe shall consist of 4 inch {100 mm} wide by 8 foot {2.4 m} long markings placed on 40 foot {12 m} centers. A solid line of temporary stripe shall be a continuous 4 inch {100 mm} wide stripe. Other width stripes may be required as shown on the plans.
5.Temporary Traffic Marking Tape . Temporary traffic marking tape shall be applied as recommended by the tape manufacturer or as directed by the Engineer. Any failure of traffic marking tape shall be repaired immediately.
6.Removal . A temporary solid line stripe of marking tape used on an underlying pavement layer, or any type temporary stripe of marking tape used on a wearing surface shall be removed. A temporary solid or broken line stripe of paint used on a wearing surface shall be removed if it is not to be completely covered with a Class 1H or 2 permanent stripe. Other types of temporary stripe may remain in place if the temporary stripe will be covered by the placement of paving layers or permanent stripe.
c.Class 1 Paint .
1.Usage . Class 1 paint shall be used for temporary striping unless shown otherwise on the plans. Class 1 paint shall not be applied to concrete surfaces.
2.Surface Preparation . Areas to be striped shall be thoroughly cleaned of all dirt, oil and other debris in a way that will not damage the pavement surface. Striping shall not begin until the Engineer has inspected the pavement surface and has informed the Contractor that striping may begin.
3.Weather Conditions for Application . Class 1 paint may be placed without regard to the weather conditions if allowed by the Engineer.
4.Equipment for Application . Equipment for the application of Class 1 paint shall be designed to place the paint and reflective beads when required. The equipment shall be capable of placing the materials at the required rates of placement and within the allowable placement tolerances.
5.Rate of Placement. Class 1 paint for temporary applications shall be placed at the rate of 10 gallons per mile for a 4 inch wide solid stripe {24 L/km for a 100 mm wide solid stripe} except for the following ci rcumstances. The rate of placement for temporary applications shall be 18 gallons per mile for a 4 inch wide solid stripe {43 L/km for a 100 mm wide solid stripe} on rough pavement surfaces such as Open Graded Friction Course (OGFC), milled surfaces, or wh en used as a temporary stripe that will not be covered within 60 calendar days. Class 1 paint for permanent applications shall be placed at the rate of 22.5 gallons per mile for a 5 inch wide solid stripe {53.8 L/km for a 125 mm wide solid stripe} except f or the following circumstances. The rate of placement for permanent applications shall be 27.5 gallons per mile for a 5 inch wide solid stripe {65.0 L/km for a 125 mm wide solid stripe} on rough pavement surfaces such as Open Graded Friction Course (OGFC) and milled surfaces. The rates of placement for other widths of stripe and for broken stripe shall be the prorated rates of placement determined from the placement rates given for 5 inch {125 mm} solid stripe. Paint stripe that is placed at a rate that is not greater than 95 % of the required rate shall be replaced if the stripe is not accepted by the Engineer with an approved price reduction.
6.Placement of Reflective Beads. Type 1 glass beads shall be placed at a rate of 146.3 pounds per mile for a soli d 5 inch wide stripe {41.3 kg/km for 125 mm wide solid stripe}. Prorated rates of application shall be made other widths of stripe and for broken stripe. Beads shall be applied before the final set of the paint has occurred to insure that the beads will ad here to the paint.

701.03 Construction Requirements.

d.Class 1H, High Build Paint.
1.Usage . Class 1H paint shall be used for State maintenance operations only. Class 1H paint may be applied to asphalt and concrete surfaces. Asphalt pavement shall be allowed to cure for a period of 14 ca lendar days before the application of the Class 1 H paint. Concrete pavement shall be allowed to cure for a period of 30 calendar days before the application of the Class 1 H paint.
2.Surface Preparation . Areas to be striped shall be thoroughly cleaned of all dirt, oil and other debris in a way that will not damage the pavement surface. Striping shall not begin until the Engineer has inspected the pavement surface and has informed the Contractor that striping may begin. Curing compound on concrete surfac es shall be removed by grinding, wire brushing, sand blasting or other effective means.
3.Weather Conditions for Application . Permanent Class 1H paint shall not be placed during rain or mist or if the pavement surface is wet. Class 1H paint shall only be placed when the pavement temperature is 45 ºF {7 ºC} and rising.
4.Equipment for Application . Equipment for the application of Class 1H paint shall be designed to place the paint, and reflective beads when required, at the required rates of placemen t and within the allowable placement tolerances.
5.Rate of Placement . Class 1H paint shall be placed at the rate given in the following table. Rough pavement surfaces are such surfaces as Open Graded Friction Course (OGFC) and milled surfaces. Class 1H paint shall be placed at the rate of 34.3 gallons per mile for a 5 inch wide solid stripe {81.8 L/km for a 125 mm wide solid stripe} except for the following circumstances. The rate of placement for permanent applications shall be 40.5 gallons per mile for a 5 inch wide solid stripe {96.8 L/km for a 125 mm wide solid stripe} on rough pavement surfaces such as Open Graded Friction Course (OGFC) and milled surfaces. The rates of placement for other widths of stripe and for broken stripe shall be prorated rates determined from the placement rates given for 5 inch {125 mm} solid stripe. Class 1H paint stripe that is placed at a rate that is not greater than 95 % of the required rate shall be replaced if the stripe is not accepted by the Engineer with an ap proved price reduction. The required width of the stripe will be shown on the plans.
6.Placement of Reflective Beads . Type 3 glass beads shall be placed on the Class 1H paint at a rate of 220 pounds per mile for a 5 inch solid wide stripe {93.7 kg/km for 125 mm wide solid stripe}. The rates of placement for other widths of stripe and for broken stripe shall be prorated ra tes determined from the placement rates given for 5 inch {125 mm} solid stripe.
7.Retroreflectivity . The target retroreflectivity shall be 300 mcd/lux/sq m for white stripe and 200 mcd/lux/sq m for yellow stripe. The Engineer will measure the retroref lectivity of edge lines for each color at 5 random locations throughout the project selected in accordance with the requirements given in ALDOT Procedure 210, "Selecting Samples by the Random Numbers Method" . If the average of the 5 retroreflectivity measu rements is 85 % of the target retroreflectivity, or greater, the stripe will be accepted without a price adjustment for retroreflectivity. If the average of the 5 retroreflectivity measurements is less than 85 % and greater than 50 % of the target retroref lectivity, the stripe will be paid for at a percentage equal to the percentage determined from the measurements. For example, if the average of the measurements is 65 % of the target retroreflectivity, payment for the stripe will be 65 % of the contract un it price. If the average of the 5 retroreflectivity measurements is 50 % of the target retroreflectivity, or less, the stripe shall be removed and replaced without extra compensation. Any portion of the stripe that is determined by the Engineer to be not iceably inconsistent with the overall striping and measures less than 50 % of the target retroreflectivity shall be removed and replaced without extra compensation.

701.03 Construction Requirements.

Retroreflectivity measurements will be made in accordance with the requirements given in ALDOT -422 "Method of Retroreflectivity Measurement of Traffic Marking Materials" with the exception of the sampling frequency. Measurements will be made between 7 and 30 calendar days after the completion of the placement of all stripe.

8.Color and Lumina nce Factors . The color and luminance factors shall meet the requirements given in Section 856.
e.Class 2, Standard Thermoplastic .
1.Usage . Class 2 thermoplastic shall be used for permanent striping, and for other circumstances designated by the Engineer. Class 2 thermoplastic may be applied to asphalt and concrete surfaces. Asphalt pavement shall be allowed to cure for a period of 14 calendar days before the application of the thermoplastic. Concrete pavement shall be allowed to cure for a period of 30 calendar days before the application of the thermoplastic.
2.Surface Preparation . Areas to be striped shall be thoroughly cleaned of all dir t, oil and other debris in a way that will not damage the pavement surface. Curing compound on concrete surfaces shall be removed by grinding, wire brushing, sand blasting or other effective means. A primer, sealer or surface preparation adhesive of the t ype recommended by the manufacturer of the Class 2 thermoplastic shall be applied to concrete surfaces (concrete pavement and bridge decks) before the application of the thermoplastic. Longitudinal stripes shall be offset at least 2 inches {50 mm} from lon gitudinal joints in concrete surfaces. Striping shall not begin until the Engineer has inspected the pavement surface and has informed the Contractor that striping may begin.
3.Weather Conditions for Application . Class 2 thermoplastic shall not be placed during rain or mist or if the pavement surface is wet. The pavement surface temperature shall be at least 50 °F {10 °C} and rising before application will be allowed to asphalt pavement surfaces. The pavement surface temperature shall be at least 60 °F {16 °C} and rising before application will be allowed to concrete pavement surfaces.
4.Equipment for Application . The equipment shall be capable of placing thermoplastic and beads at the required rates of placement and within the allowable placement to lerances. The equipment shall have the capacity to maintain the thermoplastic at temperatures greater than 390 °F {200 °C}. The temperature of the thermoplastic shall be greater than 390 °F {200 °C} at the point of application. The equipment shall be capa ble of applying glass beads to the surface of the stripe by a double drop application. The bead dispenser for the first bead drop shall be attached to the striping machine so that the beads are dispensed closely behind the thermoplastic material. The secon d bead dispenser shall be attached to the striping machine so that the beads are dispensed immediately after the first bead drop application. The bead dispensers shall be equipped with an automatic cut -off control that is synchronized with the cut -off of t he thermoplastic material. The dispensers shall apply the glass beads to produce a uniform appearance on the entire surface of the stripe and 50 % embedment of the beads. The Engineer will make the determination of the acceptability of the bead embedment by visual inspection.
5.Required Thickness. Class 2 thermoplastic shall be placed to a target uniform thickness of 0.100 inches {2.5 mm. The required width of the stripe will be shown on the plans. The Engineer will measure the thickness of the edge lin es for each color at 5 random locations throughout the project selected in accordance with the requirements given in ALDOT Procedure 210. If the average of the 5 thickness measurements is 85 % of the target thickness, or greater, the stripe will be accepted without a price adjustment for thickness. If the average of the 5 thickness measurements is less than 85 % and greater than 50 % of the target thickness, the stripe will be paid for at a percentage equal to the percentage determined from the measu rements. For example, if the average of the measurements is 65 % of the target thickness, payment for the stripe will be 65 % of the contract unit price.

701.03 Construction Requirements.

If the average of the 5 thickness measurements is 50 % of the target thickness, or less, the stripe shall be removed and replaced without extra compensation. Any portion of the stripe that is determined by the Engineer to be noticeably inconsistent with the overall striping and measures less than 50 % of the target thickness shall be removed and replaced without extra compensation. Thickness and width measurements will be made in accordance with the requirements given in ALDOT -423 "Method of Measuring Traffic Stripe and Traffic Control Legends and Markings" with the exception of the sampling frequency. M easurements will be made between 7 and 30 calendar days after the completion of the placement of all stripe. The removal and replacement shall be done without additional compensation.

6.Placement of Reflective Beads . The Contractor shall use either one of the optional double drop bead systems shown in the following tables. OPTION 1 > AASHTO TYPE 4 BEADS AND AASHTO TYPE 1 BEADS Type of Reflective Beads AASHTO Type 4 AASHTO Type 1 Order of Placement First Second Minimum Rate of Placement 6 pounds per 100 square feet {2.7 kg per 9.3 m2} 8 pounds per 100 square feet {3.6 kg per 9.3 m2} OPTION 2 > 3M "REFLECTIVE ELEMENTS" AND AASHTO TYPE 3 BEADS Type of Reflective Beads 3M "Reflective Elements" AASHTO Type 3 Order of Placement First Second Minimum Rate of Placement 6.6 pounds per 100 square feet {3.0 kg per 9.3 m2} 10 pounds per 100 square feet {4.5 kg per 9.3 m2}
7.Retroreflectivity . The target retroreflectivity shall be 450 mcd/lux/sq m for white stripe and 300 mcd/lux/sq m for yellow stripe. The Engineer will measure the retroreflectivity of edge lines for each color at 5 random locations throughout the project selected in accordance with the requirements given in ALDOT Procedure 210 . If the average of the 5 retroreflectivity measurements is 85 % of the target retroreflectivity, or greater, the stripe will be accepted without a price adjustment for retroreflectivity. If the average of the 5 retroreflectivity measurements is less than 85 % and greater than 50 % of the target retroreflectivity, the stripe will be paid for at a percentage equal to the percentage determined from the measurements. For example, if the average of the measurements is 65 % of the target retroreflectivity, payme nt for the stripe will be 65 % of the contract unit price. If the average of the 5 retroreflectivity measurements is 50 % of the target retroreflectivity, or less, the stripe shall be removed and replaced without extra compensation. Any portion of the st ripe that is determined by the Engineer to be noticeably inconsistent with the overall striping and measures less than 50 % of the target retroreflectivity shall be removed and replaced without extra compensation. Retroreflectivity measurements will be ma de in accordance with the requirements given in ALDOT -422 with the exception of the sampling frequency. Measurements will be made between 7 and 30 calendar days after the completion of the placement of all stripe.
8.Color and Luminance Factors . The color and luminance factors shall meet the requirements given in Section 856.

701.03 Construction Requirements.

f.Class 2T, Thin Film Spray Applied Thermoplastic .
1.Usage . Class 2T thermoplastic shall be used for permanent striping, and for other circumstances designated by the Engineer. Class 2T thermoplastic may be applied to asphalt and concrete surfaces. Asphalt pavement shall be allowed to cure for a period of 14 calendar days before the application of the thermoplastic. Concrete pavement shall be allowed to cure for a period of 30 calendar days before the application of the thermoplastic.
2.Surface Preparation . Areas to be striped shall be thoroughly cleaned of all dirt, oil and other debris in a way that will not damage the pavement surface. Curing compound on concrete surfaces shall be removed by grinding, wire brushing, sand blasting or other effective means. A primer, sealer or surface preparation adhesive of the type recommended by the manufacturer of the Class 2T thermoplastic shall be applied to concrete surfaces (concrete pavement and bridge decks) before the application of the thermoplastic. Longitudinal stripes shall be offset at least 2 inches {50 mm} from longitudinal joints in concrete surfaces. Striping shall not begin until the Engineer has inspected the pavement surface and has informed the Contractor that striping may begin.
3.Weather Conditions for Application . Class 2T thermoplastic shall not be pl aced during rain or mist or if the pavement surface is wet. The pavement surface temperature shall be at least 50 °F {10 °C} and rising before application will be allowed to asphalt pavement surfaces. The pavement surface temperature shall be at least 60 °F {16 °C} and rising before application will be allowed to concrete pavement surfaces.
4.Equipment for Application . Equipment for the application of Class 2T thermoplastic shall be designed to place the thermoplastic and beads at the required rates of placement and within the allowable placement tolerances. The equipment shall have the capacity to maintain the thermoplastic at temperatures greater than 390 °F {200 °C}. The temperature of the thermoplastic shall be greater than 390 °F {200 °C} at the poi nt of application.
5.Required Thickness . Class 2T thermoplastic shall be placed to a target uniform thickness of 0.060 inches {1.5 mm}. The required width of the stripe will be shown on the plans. The Engineer will measure the thickness of the edge lines for each color at 5 random locations throughout the project selected in accordance with the requirements given in ALDOT Procedure 210. If the average of the 5 thickness measurements is 85 % of the target thickness, or greater, the stripe will be accepted without a price adjustment for thickness. If the average of the 5 thickness measurements is less than 85 % and greater than 50 % of the target thickness, the stripe will be paid for at a percentage equal to the percentage determined from the measurements. For example, if the average of the measurements is 65 % of the target thickness, payment for the stripe will be 65 % of the contract unit price. If the average of the 5 thickness measurements is 50 % of the target thickness, or less, the stripe shall be removed and replaced without extra compensation. Any portion of the stripe of the stripe that is determined by the Engineer to be noticeably inconsistent with the overall striping and measures less than 50 % of the target thickness shall be removed and re placed without extra compensation. Thickness and width measurements will be made in accordance with the requirements given in ALDOT -423 with the exception of the sampling frequency. Measurements will be made between 7 and 30 calendar days after the completion of the placement of all stripe. The removal and replacement shall be done without additional compensation.
6.Placement of Reflective Beads . Type 1 glass beads shall be placed on the Class 2T thermoplastic at a rate of 220 pounds per mile for a 5 inch solid wide stripe {93.8 kg/km for 125 mm wide solid stripe}. The rates of placement for other widths of stripe and for broken stripe shall be prorated rates determined from the placement rates given for 5 inch {125 mm} solid stripe.

701.03 Construction Requirements.

7.Retroreflectivity . The target retroreflectivity shall be 250 mcd/lux/sq m for white stripe and 175 mcd/lux/sq m for yellow stripe. The Engineer will measure the retroreflectivity of edge lines for each color at 5 random locations throughout the project selected in accorda nce with the requirements given in ALDOT Procedure 210. If the average of the 5 retroreflectivity measurements is 85 % of the target retroreflectivity, or greater, the stripe will be accepted without a price adjustment for retroreflectivity. If the averag e of the 5 retroreflectivity measurements is less than 85 % and greater than 50 % of the target retroreflectivity, the stripe will be paid for at a percentage equal to the percentage determined from the measurements. For example, if the average of the meas urements is 65 % of the target retroreflectivity, payment for the stripe will be 65 % of the contract unit price. If the average of the 5 retroreflectivity measurements is 50 % of the target retroreflectivity, or less, the stripe shall be removed and replaced without extra compensation. Any portion of the stripe of the stripe that is determined by the Engineer to be noticeably inconsistent with the overall striping and measures less than 50 % of the target retroreflectivity shall be removed and replaced without extra compensation. Retroreflectivity measurements will be made in accordance with the requirements given i n ALDOT -422 with the exception of the sampling frequency. Measurements will be made between 7 and 30 calendar days after the completion of the placement of all stripe.
8.Color and Luminance Factors . The color and luminance factors shall meet the requir ements given in Section 856.
g.Class 3, Tape . Class 3 Tape shall be used for permanent striping, and for other circumstances designated by the Engineer. Class 3 tape shall be applied in accordance with the procedures recommended by the manufacture r. Tape stripe shall not be placed when the pavement temperature is below 60 °F {16 °C}. Tape may be placed at lower temperatures if shown in the manufacturer's recommendations for placement and allowed by the Engineer. The target retroreflectivity of the Class 3 tape shall be 450 mcd/lux/sq m for white tape and 350 mcd/lux/sq m for yellow tape. The Engineer will measure the retroreflectivity of edge lines for each color at 5 random locations throughout the project selected in accordance with the requi rements given in ALDOT Procedure 210. If the average of the 5 retroreflectivity measurements is 85 % of the target retroreflectivity, or greater, the tape will be accepted without a price adjustment for retroreflectivity. If the average of the 5 retrorefl ectivity measurements is less than 85 % and greater than 50 % of the target retroreflectivity, the tape will be paid for at a percentage equal to the percentage determined from the measurements. For example, if the average of the measurements is 65 % of th e target retroreflectivity, payment for the tape will be 65 % of the contract unit price. If the average of the 5 retroreflectivity measurements is 50 % of the target retroreflectivity, or less, the tape shall be removed and replaced without extra compens ation. Any portion of the tape that is determined by the Engineer to be noticeably inconsistent with the overall striping and measures less than 50 % of the target retroreflectivity shall be removed and replaced without extra compensation. Retroreflectiv ity measurements will be made in accordance with the requirements given in ALDOT - 422 with the exception of the sampling frequency. Measurements will be made between 7 and 30 calendar days after the completion of the placement of all stripe.
h.Warranted Traffic Marking Materials . Class W traffic marking materials shall be used for permanent striping, and for other circumstances designated by the Engineer. Class W traffic marking materials shall be applied in accordance with the procedures recommended by the manufacturer.
i.Removing Stripe and Markers . Existing traffic stripe (permanent or temporary), markers and adhesive shall be removed by a method that will not damage or disfigure the appearance of pavement surfaces that will be visible at the comp letion of construction. Burning the old stripe will not be permitted.

701.03 Construction Requirements.

Hiding the old stripe by covering it with a striping material that is colored to match the appearance of the pavement surface will only be allowed if approved in writing by the Engineer. Covering the old stripe will only be considered for hiding what may remain of the stripe on rough pavement surfaces like Open Graded Friction Course after other methods of removal have failed to adequately remove the old stripe. The Contractor shall propo se the type, color and application rate the striping material for review and approval by the Engineer. There will be no extra compensation given for furnishing and applying striping material to hide an existing stripe. Removal of traffic stripe, existing o r temporary, will be paid for as a separate item of work.

j.Placement Location . The Engineer will set the limits of no -passing zones. The Contractor shall provide all other controls required to place the stripe in accordance with the details shown on th e plans or as directed by the Engineer. The Contractor shall mark the surfaces prior to the placement of the stripe to insure that the stripe will be installed in the required location. The Contractor may be required to adjust the operation of the stripin g equipment to cover the width and length of existing stripe.
k.Width and Length Placement Tolerances .
1.Permanent Striping . A tolerance of 1/2 of an inch {13 mm} over or 1/8 of an inch {3 mm} under the required width will be allowed, provided the variation is gradual and does not detract from the general appearance. Segments of broken line may vary up to 1 foot {0.3 m} from the required length. Segments shall have neat edges without mist or drip. Variations fro m the control guide up to 1 inch {25 mm} will be allowed provided the variation does not increase or decrease at a rate of more than 1/2 of an inch {13 mm} in 20 feet {7.5 m}. Lines that do not meet these tolerances shall be removed and replaced, without additional compensation. Establishment of tolerances does not relieve the Contractor of responsibility to construct as closely as practicable to exact plan dimensions.
2.Temporary Stripe. The width of the temporary stripe shall not exceed 4 inches {100 mm }, but shall have a 1/2 inch {13 mm} under tolerance. Traffic marking tape shall have a nominal 4 inch {100 mm} width. The tolerance for the lengths of the temporary broken stripe sections shall be 1 foot {0.3 m} under and 1 foot {0.3 m} over the length sp ecified in Subitem 701.03(e)5.a. Strict compliance to alignment on underlying surfaces will not be required provided a reasonable straight line of markings is obtained. The tolerances for placement on a wearing surface shall be the same as those for perman ent striping.
3.Failure to Meet Width and Length Placement Tolerances . Permanent or temporary striping placed on a final wearing surface that does not meet the tolerances specified shall be removed and replaced without compensation. This includes areas where the permanent striping does not match the alignment, spacing, etc. of the temporary stripe, leaving the temporary stripe exposed. Portions, or as much as the entire pavement surface, shall be overlaid with a bituminous plant mix layer in extreme cases of disfigurement of the pavement due to stripe removal. The Engineer will make the final determination of the severity of the disfigurement, the requirement for the extent of the overlay, and the material and placement requirements for the plant mix requ ired for the overlay. The Contractor shall place the overlay without compensation.
l.Protection Of Traffic Stripe . Traffic shall be prevented from crossing traffic stripe that is not dried, cured or taken a set to bear the traffic. The Contractor shall use a sufficient number of flagmen or other protection for the stripe to prevent traffic from damaging the newly applied stripe. Sections of traffic stripe that have been marred or picked up by traffic shall be repaired and the pavement shall be cleaned outside the limits of the stripe. Repair and cleaning shall be done by the Contractor without extra compensation.
m.Protection Of Traffic . The Contractor shall furnish and place without extra compensation all warning and directional signs required to direct, control and protect the traveling public while marking and striping operations are in progress. Temporary barricades and signs of the design shown on the plans or directed by the Engineer shall be placed as shown on the plans at the beginning and end of the section that the Contractor proposes to stripe in one operation. As soon as the striping material has dried or cured

701.04 Method of Measure ment.

sufficiently in any one section to permit traffic to cross the traffic line, the temporary barricades and signs shall be moved ahead to the next section. Barricades and signs shall not be left in place overnight. The striping equipment shall be operated in a manner to cause the least disruption to the normal flow of traffic.

701.04 Method of Measurement.

a.Items 701-A, 701 -B, 701 -C, 701 -E, 701 -F, and 701-G. Solid or broken traffic stripe (Items 701 -A, and 701- C ) will be measured in miles {kilometers} along the centerline of each stripe either by direct measurement and computation to the nearest 0.001 mile {0.001 kilometer} or by odometer to the nearest 0.001 mile {0.001 kilometer}. Solid, broken, or dotted traffic stripe (Items 701 -B, 701- E, 701- F and 701 -G) will be measured in linear feet {meters} along the centerline of the stripe to the nearest linear foot { meter}. The length of broken traffic stripe and dotted traffic stripe complete in place and accepted will include the gaps shown on the plans as a part of the traffic line design but will not include the length of any other gap or section omitted by the En gineer. Each width of traffic stripe will be measured separately for payment.
b.Items 701-D and 701-H. Any traffic stripe, existing or temporary, removed as directed (Items 701 -D and 701- H) will be measured in the same manner noted for placement of the t ype stripe involved. Removal of markings or legends will be measured and paid for under the appropriate item provided in Section 703.

701.05 Basis of Payment.

a.Unit Price Coverage . The length of Solid or Broken Traffic Stripe, Item 701 -A, and the length of Solid or Broken Traffic Stripe, Item 701 -G, measured as noted above, will be paid for at the respective contract unit prices and shall be full compensation for the stripe including the cleaning of the pavement, the furnishing and applying of the stripi ng material, and for all equipment, tools, labor and incidentals necessary to complete the item of work. The length of Dotted Traffic Stripe, Item 701 -B, measured as noted above, will be paid for at the contract unit price which shall be full compensation for furnishing all materials of the appropriate color consistent with the use of the stripe in accordance with the plan details, the preparation of the pavement, the application of the striping material, and for all equipment, tools, labor and incidentals necessary to complete this item of work. The length of Solid or Broken Temporary Traffic Stripe, Item 701 -C, and the length of Solid or Broken Temporary Traffic Stripe, Item 701 -E, and Dotted Temporary Traffic Stripe, Item 701 -F, measured as noted above, will be paid for at the respective contract unit prices which shall be full compensation for the furnishing of all materials, of the appropriate color consistent with the use of the stripe in accordance with the requirements of the plan details and the MUTCD, the preparation of the surface, the placing of the material, the maintenance of the traffic stripe, and for all equipment, miscellaneous materials, tools, labor and incidentals necessary to complete the item of work. The length of existing or temporary Solid or Broken Traffic Stripe Removed, Item 701 -D, and the length of Solid, Broken, or Dotted Traffic Stripe Removed, Item 701 -H, measured as provided above, will be paid for at the contract unit price which shall be payment in full for all materials, equipment, tools, and labor necessary to complete the work. When the traffic stripe to be removed consists of pavement markers used as traffic stripes the cost of removing markers, marker adhesive, and existing paint, plastic or tape located between the markers shall also be included in the price.
b.Payment will be made under Item No .: 701-A Solid/Broken Color , Class * Type ** Traffic Stripe - per mile {kilometer} 701-B Dotted Class * Type ** Traffic Stripe - per linear foot {meter} 701-C Solid/Broken Temporary Traffic Stripe ( ***) - per mile {kilometer} 701-D Solid/Broken Traffic Stripe Removed ( ***) - per mile {kilometer} 701-E Solid/Broken Temporary Traffic Stripe ( ***) - per linear foot {meter} 701-F Dotted Temporary Traffic Stripe ( ***) - per linear foot {meter} 701-G Solid/Broken Color , Class * Type ** Traffic Stripe - per linear foot {meter} 701-H Solid/Broken/Dotted Traffic Stripe Removed ( ***) - per linear foot {meter} * Specify "1", "1H", "2", "2T", "3", or “W”.

703.03 Construction Requirements.

** Specify "A" or "B". *** Specify "Paint", "Plastic", "Tape", etc., only if required. SECTION 703 TRAFFIC CONTROL MARKINGS AND LEGENDS

703.01 Description.

This Sec tion shall cover the work of placing permanent or temporary traffic control markings and legends at the locations shown on the plans or where directed by the Engineer. Preformed thermoplastic markings may be used for permanent striping, and for other circu mstances as designated by the Engineer. This Section shall also cover the removal of existing or temporary traffic control markings and legends.

703.02 Materials.

a.General. Materials shall be furnished in accordance with the requirements given in Sectio ns 856 and 857. The required dimensions, color, type of material and reflectivity will be shown on the plans. The required type of material will be designated by "Class" and "Type" in accordance with the requirements given Section 701 Class 1H, Class 2, an d Class 2T materials shall be in compliance with the formulations given in the tables in Section 856 for each class. Class 1, Class 3, Class W , Preformed Traffic Markings, and Drop On Glass Beads shall be one of the materials shown on List V -3, Temporary T raffic Marking Materials, and List V -4, Permanent Traffic Marking Materials. These lists are in the Department’s Manual, “Materials, Sources, and Devices with Special Acceptance Requirements”. Information concerning these lists is given in Subarticle 106.0 1(f) and ALDOT -355. Preformed traffic markings and legends shall also meet the requirements given in Article 856. 09. All preformed traffic markings and legends shall meet the dimensions as shown in the plans and shall meet the tolerance requirements given in Item 703.03(c)1.

703.03 Construction Requirements.

a.Acceptance Program for Traffic Marking Materials . The guidelines for the evaluation and acceptance of traffic marking materials are given in the procedure ALDOT -420 "Acceptance Program for Traffic Marking Materials". These guidelines shall be followed in the furnishing and placement of traffic markings and legends.
b.Temporary Traffic Markings and Legends . Temporary traffic control markings and legends shall be furnished and placed in accordance with all of the requirements given in Section 701 for Temporary Traffic Stripe except for the placement tolerances for length and width. The length of the markings and legends shall be no greater than 2 inches {50 mm} over or 1 inch {25 mm} under the required length. The width of the markings and legends shall be no greater than 1/2 of an inch {12 mm} over or 1/2 of an inch {12 mm} under the required width.
c.Permanent Traffic Markings and Legends .
1.Applicator Appl ied Traffic Markings and Legends. Permanent traffic control markings and legends shall be furnished and placed in accordance with all of the requirements given in Section 701 for permanent traffic stripe except for the following: • Any type of equipment may be used that produces acceptable results; • Class 2 thermoplastic shall be placed to produce a minimum uniform thickness of 0.125 inches {3.0 mm}. • The length of the markings and legends shall be no greater t han 2 inches {50 mm} over or 1 inch {25 mm} under t he required length. • The width of the markings and legends shall be no greater than 1/2 of an inch {12 mm} over or 1/2 of an inch {12 mm} under the required width • Beads may be hand placed.
Source: Alabama Standard Specifications for Highway Construction, 2022 Edition. Pages 587595 of 934.