EROSION, SEDIMENT, AND STORMWATER MANAGEMENT SECTION 901
573 DIVISION 900 — EROSION, SEDIMENT, AND STORMWATER MEASURES
901.1Description.
This work consists of implementing erosion and sediment control and stormwater management practices and techniques. 901.1.1 Definitions.
disturbing activities.
and that may result in accelerated stormwater runoff and soil erosion.
the project site.
controls certified by the Department of Natural Resources and Environmental Control (DNREC) and as appointed by the engineer.
disturbing activities and for sediment and stormwater control.
control of soil erosion, sedimentation, stormwater quantity, and water quality impacts resulting from land disturbing activities on the project.
contained in the Sediment and Stormwater Management Plan.
901.2Materials.
Not applicable.
901.3Construction.
901.3.1 Legal Authority.
Regulations Governing Control of Water Pollution, Section 9;
Sediment and Stormwater Regulations; and
Activities.
EROSION, SEDIMENT, AND STORMWATER MANAGEMENT SECTION 901
574 901.3.2 Contractor Responsibility.
Management systems in accordance with the Sediment and Stormwater Management Plan.
Construction General Permit.
successfully completed the DNREC Contractor Training Program (Blue Card) before beginning land disturbing activities.
Management Plan and provides daily oversight and guidance to construction personnel during land disturbing activities.
offsite stockpiling.
of site conditions.
as a Co -Permittee on the original Notice of Intent under DNREC ’'s Construction General Permit for the project. File as a Co -Permittee after receipt of the contract award notice as a condition of contract execution. Upon contract execution, assume responsibility for implementing and complying with the approved Sediment an d Stormwater Management Plan.
directed by the engineer. The notice will be legible, publicly accessible, and protected from the weather. Posting of permit coverage and maintenance is incidental to the contract.
by the Department and the Division of Maintenance and Operations has issued the final project acceptance letter. Permit fees are annual, charged on July 1.
Stormwater Management Plan, corrects deficiencies, and coordinates deviations from the approved plan for redline plan preparation and approval;
information with the ES2M CCR;
project duration; and EROSION, SEDIMENT, AND STORMWATER MANAGEMENT SECTION 901
575 8. contacts the ES2M CCR a minimum of 48 hours before land disturbing activities begin to schedule an initial inspection of perimeter controls for the next phase. 901.3.3 Maintain Erosion and Sediment Control Measures. Maintain erosion and sediment control items continuously throughout the project duration, including periods when the project is inactive or suspended. Repair, replace, or maintain erosion and sediment control devices promptly as noted during the ES2M Inspe ction or as directed by the engineer. Maintain erosion and sediment control devices until construction phasing or stabilization allow the removal of those controls as determined by the engineer. 901.3.4 Failure to Implement or Maintain Erosion and Sediment Control Measures. If the contractor fails to perform the work as described in the approved Sediment and Stormwater Management Plan, the ES2M Report, or in writing from the engineer, the engineer may take any or all of the actions described in Sections 105.1 and 105.13, incl uding suspending all or part of the work, withholding progress payments, or performing maintenance with DelDOT forces, or third party forces, and deducting the costs from monies due or to become due to the contractor. 901.3.5 Fines Resulting from Non -Compliance. If the DNREC, the Army Corps of Engineers, or the EPA fine the Department as a result of the contractor's failure to implement and maintain the Sediment and Stormwater Management Plan and SWPPP, the Department will require the contractor to pay the fines d irectly or the Department will deduct the fines from monies due the contractor.
901.4Method of Measurement.
The Department will not measure this item.
901.5Basis of Payment.
The Department will consider costs associated with the provisions in this Section 901 as incidental to the contract.
PUMPING OR DEWATERING OPERATIONS SECTION 902 576 SECTION 902 — PUMPING OR DEWATERING OPERATIONS
902.1Description.
interagency Memorandum of Agreement. Covered work includes the following activities:
per day.
pass pumping at rates exceeding 50,000 gallons per day are permitted provided no water is withdrawn for consumptive use and all water is returned to its natural course immediately downstream of the work area.
withdrawal rates in excess of 50,000 gallons per day are necessary.
construct and complete the Work from DNREC, Division of Water, Water Supply Section, unless covered in the Statewide General Permit for Minor Dewatering Activities.
possibly a public hearing before DNREC will issue a permit. Ensure that sufficient permit acquisition time is included in the project schedule to obtain the permit. Time extensions will not be granted for failure to account for this time in the Project Schedule.
Environmental requirements are more fully described in the Project Environmental Statement. ii. The Statewide General Permit for Minor Dewatering Activities does not constitute approval, exemption, or waiver from any other law, rule, or regulation that may apply to the work shown in the plans or the activities necessary to complete the work. See Specification Section 107.2.
dewatering equipment, or employ the services of properly licensed subcontractors such as a well driller when an individual dewatering permit is required. PUMPING OR DEWATERING OPERATIONS SECTION 902 577 902.2 Material. Provide materials as necessary and required.
902.3Construction.
the necessary dewatering permit is submitted to the engineer.
continuous dewatering of the work area. Instantaneous and totalizing flow meters, accurate to within +/ - 5 percent, are required on all dewatering equipment.
dewatering operations.
starting any dewatering adjacent to wetlands or if discharge water is proposed to be directed to any wetlands.
until the work has been brought to finished lines and grades and accepted by the engineer. None of the proposed work shown on the plans will be laid in water, unless otherwise indicated on the plans or directed by the engineer.
undisturbed areas into open excavations using any combination of berms, pipes, dikes, pumps, etc. in order to establish a clean water diversion. Comply with applicable sediment control measures.
adjacent property, buildings, structures, utilities, and other work. Protect adjacent structures and property from any damage that may occur as a result of settlement o r other effects related to the removal of ground water and lowering of the water table. Do not drain dewatering discharge into work completed or under construction without prior consent of the engineer. Dispose of water in such a manner as not to be a m enace to the public health. Discharging to the sanitary sewer system is not permitted.
water system is prohibited. Dewatering operations for the project cannot cause the inadvertent drawdown or dewatering of wetlands or other surface water bodies.
PUMPING OR DEWATERING OPERATIONS SECTION 902 578 1. Ensure all discharges are directed to sediment trapping or filtering devices such as a dewatering bag, dewatering basin, portable sediment tank, sediment trap, or sediment basin prior to release into ditches, storm drain systems, streams, or surface water bodies of any type.
temporary dike to create a temporary cofferdam, leave the sediment -laden water within the cofferdam undisturbed for a minimum of 12 -hours to allow settling of suspended soil particles. Remove water from temporary cofferdams by skimming it off the surface. Immerse intake no more than 6 inches below the water surface. Once the water level has bee n pumped down, accomplish additional dewatering using a sump pit constructed in conformance with DelDOT Standard Construction Details. Any deviation from Standard Construction Details requires prior approval and may require an individual dewatering permit from DNREC.
continuous uninterrupted water service to any affected public or private potable water supplies or wells within the project area if adversely affected by the dewa tering operations associated with this project.
902.4Method of Measurement.
Pumping or Dewatering operations will not be separately measured.
902.5Basis of Payment.
associated work i tems .
DNREC.
POLLUTION PREVENTION SECTION 903 579 SECTION 903 — POLLUTION PREVENTION
903.1Description.
This work consists of implementing and maintaining the pollution prevention plan outlined in the contract.
903.2Materials.
Not applicable.
903.3Construction.
903.3.1 Application Law and Regulations. Follow the Delaware Erosion and Sediment Control Handbook. https://dnrec.alpha.delaware.gov/watershed -stewardship/sediment -stormwater 903.3.2 Prohibited Discharges.
construction materials, unless managed by an appropriate control;
903.3.3 Maintenance.
903.4Method of Measurement.
Not applicable.
903.5Basis of Payment.
The Department will consider the cost of pollution prevention as incidental to the associated work items. The Department will make no separate payment for pollution prevention activities. SEDIMENT TRAPPING DEVICES SECTION 905 580 SECTION 905 — SEDIMENT TRAPPING DEVICES
905.1Description.
This work consists of constructing facilities to trap sediment before it leaves the job site.
905.2Materials.
SEDIMENT TRAPPING DEVICES SECTION 905 581 3. Fence Section 1061
905.3Construction.
releasing the runoff from the project limits. Inspect weekly and immediately after every rainfall to maintain and make repairs as needed. Use the following sediment trapping devices.
ends of the silt fence.
flow.
Place fence in accordance with the Standard Construction Details and Section 905.3.A. Fasten wire mesh to the posts between the geotextile and the posts.
Place fence in accordance with the Standard Construction Details and Section 905.3.A. Fasten geotextile to chain link fence with ties spaced every 24 -inches at the top and midsection.
by the engineer.
the geotextile.
engineer determines that the fence is no longer required.
contract and the Standard Construction Details.
SEDIMENT TRAPPING DEVICES SECTION 905 582 3. Notify the engineer of conflicts between sediment traps and permanent features to obtain an alternate design for sediment trap locations.
bottom elevations greater than 4 -feet below the original grade in stages concurrent with the roadway excavation.
percent as determined by the engineer.
(https://deldot.gov/Business/drc/index.shtml?dc=stormwater). Construct inlet sediment control according to the type required and follow the applicable Standard Construction Details or the manufacturer's recommendations, whichever is more stringent.
requirements or when sediments interfere with the flow of water through the material.
state, federal, or privately owned.
required.
905.4Method of Measurement.
placed and accepted. The Department will not include overlap in the measurement. SEDIMENT TRAPPING DEVICES SECTION 905 583 2. Sediment traps as the number of cubic yards of material excavated to construct the sediment traps. The Department will compute the volume of excavated material using the actual dimensions and elevations of the sediment traps constructed as shown in the contract.
905.5Basis of Payment.
contract unit price per linear foot. Price and payment constitute full compensation for:
Price and payment constitute full compensation for:
Price and payment constitute full compensation for:
SEDIMENT TRAPPING DEVICES SECTION 905 584 D. The Department will consider maintenance of the devices, including sediment removal, as incidental to the initial installation of the device. ITEM DESCRIPTION UNIT 905001 SILT FENCE LF 905002 REINFORCED SILT FENCE LF 90500 3 SEDIMENT TRAP CY 90500 4 INLET SEDIMENT CONTROL, DRAINAGE INLET EACH 90500 5 INLET SEDIMENT CONTROL, CURB INLET EACH 90500 6 INLET SEDIMENT CONTROL, CULVERT INLET EACH 90500 7 SUPER SILT FENCE LF
DEWATERING PRACTICES SECTION 906 585 SECTION 906 — DEWATERING PRACTICES
906.1Description.
This work consists of dewatering work sites.
906.2Materials.
inch by 1/4 -inch.
Use in accordance with the manufacture’s recommendations with a performance requirement retaining soil particles on a #80 sieve, 177 microns.
1/4-inch.