903.1Description.
This work consists of implementing and maintaining the pollution prevention plan outlined in the contract.
903.2Materials.
Not applicable.
903.3Construction.
903.3.1 Application Law and Regulations. Follow the Delaware Erosion and Sediment Control Handbook. https://dnrec.alpha.delaware.gov/watershed-stewardship/sediment-stormwater 903.3.2 Prohibited Discharges.
construction materials, unless managed by an appropriate control;
903.3.3 Maintenance.
903.4Method of Measurement.
Not applicable.
903.5Basis of Payment.
The Department will consider the cost of pollution prevention as incidental to the associated work items. The Department will make no separate payment for pollution prevention activities.
Get an email when 903 changes