MATERIALS FOR PORTLAND CEMENT CONCRETE (STRUCTURAL, PAVEMENT, AND MISCELLANEOUS)
921-1 General.
Cement shall conform to the requirements of AASHTO M 85 or AASHTO M 240, as applicable, except as provided in this Section.
921-1.1 Type of Cement: Cement may be Types I, II, III, V (as defined by
AASHTO M 85), or IL, IP, IS, IT (as defined by AASHTO M 240). Cement type shall be selected based on component and environmental conditions in accordance wi th Section 346. Different brands of cement, cement of the same brand from different facilities, or different types of cement shall be stored separately , identified, and shall not be mixed.
921-1.2 Heat of Hydration: The cement heat of hydration for Type II, Type IT, Type IL,
Type IP, and Type IS shall be tested in accordance with ASTM C1702 and reported at three days.
921-2 Definitions.
The following definitions are applicable to the production and Quality Control (QC) of cement:
921-3 Quality Control Program.
921-3.1 General : Develop a Producer QC Program as specified in Section 105.
Producers shall submit a proposed QC Plan to the SMO for acceptance. Complete the Cementitious Materials Producer QC Plan Checklist (Appendix B02) and submit it along with the QC Plan, in a separate file. The checklist can be found on the SMO website: https://www.fdot.gov/materials/quality/programs/qualitycontrol/checklists/index.shtm . In addition to the QC Plan, the Producer must submit monthly test reports from a n approved laboratory which certifies that the cement in current production or supply conforms to the requirements of this Section. Producers with an accepted QC Plan will appear on the Cementitious Materials Production Facility Listing. QC test data that does not comply with this Section will not be a reason for rejection of the material if the Producer’s QC Plan indicated that material will be diverted and not used for Department work.
921-3.2 Sampling and Testing: An approved laboratory shall perform one QC test per
day. Test reports representing no more than one month’s production shall be submitted to the SMO on a monthly basis, for foreign cement, refer to 921 -5. Representatives from the Department may take verification samples at the Producer’s plant, terminal, distribution facility, or the concrete production facility. Samples shall be obtained by one of the methods described in FM 5-503. Sample size shall be a minimum of one gallon. At the concrete production facility, cement samples shall be jointly obtained by the Department inspector and the concrete producer’s representative. Upon request of the Department, the Producer shall provide split samples of the cement collected for QC testing. Split samples shall be delivered to the SMO and shall be identified as representing a designated LOT of cement. Notification of failing verification sample test results will be distributed to the Producer and concrete producer, if applicable. Split samples of the initial sample may be provided to the Producer an d concrete producer upon request, as available.
921-3.3 Limestone and Inorganic Processing Additions: Producers intending to use
limestone and/or inorganic processing additions as component materials in the production of cement shall describe the type, source, and the target amount, expressed as a percentage of cement mass. In addition, the Producer shall display the information req uired in 921 -2 on the test report. Samples of any pulverized limestone and /or inorganic processing additions shall be provided to the S MO for evaluation upon request.
921-4 Shipping and Storage .
Cement shall be delivered in bags or in bulk. Portland cemen t from a Producer on the Cementitious Materials Production Facility Listing shall be shipped on the basis of test reports meeting the requirements of this S ection. Ensure that e ach shipment is accompanied by a delivery ticket that is traceable to the test report and includes, at a minimum, the following information: FY 2023-24 Return to Table of Contents
921-5 Foreign Cement Acceptance .
Cement being imported from a foreign source shall conform to all requirements of this Section and will be subject the following process:
921-6 Rejection of Material:
Reject the entire container of cement if it does not meet the requirements of this Section , including cement that has been damaged, is partially set, lumpy or caked. Reject bagged cement if it varies more than 5% from the designated weight, or if the average weight of 50 randomly selected sacks is less than the designated weight. FY 2023-24 Return to Table of Contents SECTION 923 WATER FOR CONCRETE
923-1 General Requirements.
Water for use with cement shall be clear and free from oil, and injurious amounts of acid, alkali, chlorides, organic matter, and other deleterious substances. It shall not be salty or brackish. Water that contains quantities of substances which makes it discolored or smell unusual or objectionable, shall not be used unless approved by the Department. Water sources permitted include potable water supplies that a re approved by a public health department, open bodies of water, well water, reclaimed water, and recycled water. Reclaimed water shall be as defined in Chapter 62 -610, F.A.C. Open bodies of water are defined as naturally occurring rivers, lakes, and ponds. Recycled water includes wash water from mixer washout operations and stored in a lined settling pond. Water sources that meet the requirements of Table 923-1, Table 923-2 or from a public health department may be used alone or blended in a storage tank f or use in batching structural or non -structural concrete. All other sources of water not listed above shall be considered recycled and reclaimed water.
923-2 Evaluation of Water for Concrete.
923-2.1 General: Water from potable water supplies approved by a public health
department may be used without additional testing. The concrete producer shall submit test data of water samples from other sources. To determine chemical properties, the concrete producer shall use a laboratory accredited by the Constructi on Materials Engineering Council Accreditation Program including accreditation on referred chemical tests on Table 923-1 and 923-2.
923-2.2 Initial Sampling and Testing Frequency: Open bodies of water and well water
shall be initially sampled once prior to use. Recycled and reclaimed water shall be tested once per week for four weeks initially, and thereafter once per month for four months prior to its use, provided that the results of the test samples comply with all the applicable limits. Failing test results will result in restarting initial sampling and testing.
923-2.3 Production Sampling and Testing Frequency : Open bodies of water and
recycled water shall be tested monthly. Well water and reclaimed water shall be tested once every three months. If th e last eight consecutive well water and reclaimed water samples meet the requirements, then the sample frequency may be reduced to one sample every six months, as approved by the Department. If a well water or reclaimed water sample fails once the frequenc y has been reduced, then the sampling frequency shall revert to once every three months.
923-3 Chemical Requirements.
923-3.1 Testing: All chemical analysis shall be performed in accordance with the test
methods listed in Tables 923-1 and 923 -2 or equivalent Standard Methods for the Examination of Water and Wastewater (SM). Inorganic Anions (Chlorides and Sulfates) shall be determined simultaneously using SM 4110B Ion Chromatography or separately using SM 4500 Cl- B and SM 4500 SO 42- E. ASTM D516 may be used as an alternative method for sulfates. The test method used shall be included in the concrete producer report.
923-3.2 Recycled and Reclaimed Water : Recycled and reclaimed water shall be tested
before use and shall not exceed the limits in Table 923-1: FY 2023-24 Return to Table of Contents