for Highway Construction Page 173 of 71 5 SECTION 213 – TOPSOIL
213.01 Description.
Excavate suitable topsoil from stockpiles, sources outside the roadway, or from its natural position within the right of way that will be occupied by the roadway. Place and key in the topsoil on designated constructed cut and fill slopes and other designated areas after grading operations are complete.
213.02 Materials.
Obtain topsoil from approved sources from the soil profile A horizon layer that has a friable, loamy character and contains an organic matter amount normal to the region. Obtain topsoil from well -drained arable land that d oes not contain subsoil (from the soil profile B horizon layer), refuse, roots, heavy or stiff clay, stones larger than 1 inch, coarse sand, sticks, brush, litter, pesti cides, contaminated soil, noxious weeds, or other material detrimental to vegetative growth and establishment. Ensure the county weed authority has visually inspected approved sources for presence of noxious weeds before delivery or placement . Test sources if noxious weeds are located within or adjacent to the source site, and obtain approval from the county weed authority or authorized personnel from the Department or Idaho State Department of Agriculture that the source is acceptable to use on the project site. Incorporate vegetative matter into topsoil, except brush, trees, or noxious weeds. Other deleterious material (e.g., plastic, glass, metal, rocks) will not exceed 0.1 percent by weight or volume. Provide microorganism inoculants that contain a diverse mix of regional specific mycorrhizal species for specific condition, provide macronutrients and micro- nutrients that are tolerant of chemical imbalances in the soil, produce humic compounds and binding compounds, and improve soil structure. Soil Amendments .................................................................................................................... 711.18 Remove and di spose of vegetation at topsoil sources before taking materials from the source. Provide topsoil as specified below in Table 213.02- 1 and Table 213.02-2 . Table 213.02-1 – Topsoil Gradation Sieve Size Percent age by Weight Required to Pass a Square Mesh Sieve 1 in 98 - 100 No. 4 95 - 100 No. 8 80 - 100 No. 200 15 - 80 for Highway Construction Page 174 of 71 5 Table 213.02-2 – Topsoil Chemistry Property Minimum Maximum pH (a) 5.5 7.8 ESP (b) — 10.0 EC (c) — 8.0 Organic Material 0.5 15.0
213.03 Construction Requirements.
Remove, treat, and process all areas containing noxious weed seeds and/or plants with herbicide applications or by specific heat treatments and material rotation for composted material. Process composted material (heat and rotation) for at least 90 calendar days to kill all viable weed seed and plant material. Test topsoil to verify the topsoil is free of viable noxious weed seed or plant parts, herbicides, fungicides or other chemical residues harmful to plant or animal life. Obtain a representative composite topsoil sample 2 months before final placement and seeding applications to determine soil pH, nutrients, and organic materials present. Provide a soil analysis by an North American Proficiency Testing -Performance Assessment Program (NAPT -PAP) accredited laboratory to determine if extra nutrients (fertilizer ingredients) and organic materials (mulch or compost) are needed to amend the soil, and verify the soil does not contain noxious weeds. The following labs are accredited to perform the required tests:
213.04 Method of Measurement.
The Engineer will measure acceptably completed work as follows:
213.05 Basis of Payment .
The Department will pay for accepted quantities at contract unit price as follows: Pay Item Pay Unit Topsoil .................................................................................................... CY or SY The Department will pay for topsoil excav ated from the roadway at the excavation contract unit price as specified in 205. The Department will pay for topsoil in its final p osition, which includes the cost to stockpile if necessary, and to haul to the project site where it is to be placed and finished on the slope. for Highway Construction Page 176 of 715 The cost to provide and incorporate soil amendments, including fertilizer and/or organic mater ials is incidental . for Highway Construction Page 177 of 715 SECTION 214 – ROADSIDE CLEANUP
214.01 Description.
Remove and dispose of stumps, foundations, debris, and boulders and perform minor leveling and drifting of material between the limits of clearing and right of way only as specified or as directed. The Department will not pay for neces sary cleanup resulting from the Contractor’s operations.
214.02 Materials.
Not specified.
214.03 Construction Requirements.
Not specified.
214.04 Method of Measurement.
The Engineer will measure acceptably completed work as specified in 109.03.
214.05 Basis of Payment .
The Department will pay for acceptable quantities as follows: Pay Item Pay Unit Roadside Cleanup (Contingency Item) ................................................... CA