650.02 Materials.
Installation of the pipe shall meet the requirements of ASTM F 714. Joining of the HDPE pipe shall be performed by thermal butt -fusion in accordance with the pipe ma nufacturer’s recommendations. The piping shall be assembled in a manner that does not obstruct adjacent roadways or public activities. The pipe installed by the directional drill method shall be to the alignment and grade shown on the project plans. The Co ntractor shall provide a record drawing showing the constructed horizontal and vertical alignment shown for intervals not exceeding 30 feet {9.0 m}. The Contractor shall perform the construction in a manner so that the drilling fluids and cuttings are cont ained and not released into waterways or their tributaries. The Contractor shall handle the HDPE and steel pipe in a manner that will not over stress the pipe at any time before, during, and after construction. A sizing pig shall be used to determine the presence of buckles, dents, out of roundness, and any other deformations. Anomalies shall not exceed 2% of the nominal pipe diameter or excessive ovality greater than 5% of the nominal pipe diameter.
649.04 Method of Measurement.
Encasement pipe will be mea sured by the linear foot {meter}.
649.05 Basis of Payment.
650.01 Description.
This Section shall cover the work of furnishing and placing topsoil and the placement of State furnished topsoil from stockpiles.
650.02 Materials.
650.03 Construction Requirements.
650.03 Construction Requirements.
650.04 Method of Measurement.
650.05 Basis of Payment.
652.03 Construction Requirement s.
SECTION 652 GROUND PREPARATION, VEGETATION ESTABLISHMENT AND MOWING
652.01 Description.
This Section shall cover ground preparation work and the work of establishing an acceptable permanent stand of vegetation of the species designated for establishment. This section also covers mowing of vegetated areas.
652.02 Materials.
Materials (seed mixes, mulch, fertilizer, etc.) shall be furnished in compliance with the requirements given in Section 860.