568
individual components but will be measured along the top of the barrier in linear feet {meters} to the nearest foot {0.1 m}.
Brush Barriers (Item 665-S) will be measured in linear feet {meters} to the nearest foot {0.1 meter} with measurements taken along the top of the barrier. Geotextile installed both as underlayment and as a choker will be measured separately and payment made in accordance with the requirements given in Section 610.
Materials used to construct Stage 1 and 2 Inlet Protection will be measured for payment as appropriate for items such as silt fence, wattles, hay bales, etc. This also applies to curb inlet protection necessary beyond Stage 2. Stages 3 and 4 Inlet Protection (Item 665-P) for drop inlets will be measured per each stage of each inlet protected if protected in accordance with the details shown on the plans.
Drainage Sump Excavation (Item 665-K) will be measured in cubic yards {cubic meters} computed from dimensions of the sump size and depth approved by the Engineer. Material removed during sump maintenance operations will be measured for payment as Drainage Sump Excavation to the nearest cubic yard {0.1 cubic meter}. No measurement will be made for material used as backfill when the sump is closed. Removal of sediment collected by sedimentation basins, sediment retention barriers, ditch checks and inlet protection will be measured as drainage sump excavation if soil erosion is being prevented to the maximum extent practicable. If the proposal does not contain this item, measurement and payment will be made under the Item of Unclassified Excavation. Material removed will not be paid as muck excavation regardless of the consistency.
Each component and work item required for the construction of a Sedimentation Basin will be measured individually for payment. Excavation and embankment will be measured as Unclassified Excavation. Removal of captured sediment will be measured as Drainage Sump Excavation. Typical items required to construct the sedimentation basin may include unclassified excavation, aggregates, riprap, filter fabric, polyethylene, flow baffles, rolled erosion control products, seeding, basin dewatering device, temporary pipe, etc. Access roads to sedimentation basins, as shown in the plans or as directed by the Engineer, will be measured separately and payment made as Temporary Coarse Aggregate (Item 665-N) and geotextile in accordance with the requirements given in Section 610, unless otherwise specified in the plans. No measurement will be made for access roads installed without the approval of the Engineer.
Flow Baffles (Item 665-H) will be measured along the top of the baffle material in linear feet {meters} to the nearest foot {0.1 m}.
Basin Dewatering Devices (Item 665-X) will be measured per each. Elevated device rest, outlet pipes, valves, and end treatments serving the basin dewatering device are considered to be a part of the device and will not be measured separately for payment.
Temporary Pipe End Treatments (Item 665-D) will be measured per each.
Floating Basin Booms (Item 665-L) will be measured in linear feet {meters} to the nearest 0.1 foot {0.01 meter} with measurements taken along the top line of the boom.
665.05Basis of Payment
The unit price for all temporary erosion and sediment control items, except drainage sumps and silt fence, shall be full compensation for furnishing all materials unless otherwise noted, the construction and installation of the materials into complete erosion or sediment control measures, and PEST CONTROL 569
shall include all equipment, tools, labor and incidentals necessary to complete the work, to perform maintenance to keep work in an acceptable condition, and to remove the items when no longer needed as directed by the Engineer. The excavation of sediment collected by drainage sumps, ditch checks, sediment barriers, sediment retention barriers, and other sediment control BMPs will be considered for payment as Drainage Sump Excavation as long as erosion is being controlled to the maximum extent practicable. Direct payment will be made for the removal of silt fence. Payment for Stage 3 and Stage 4 Inlet Protection shall include the installation and maintenance of all items at quantities shown on the plans as being required or permitted. Payment for sedimentation basins will be made for individual components and work items required for construction and shall be full compensation for the installation, maintenance and removal of all components of the sedimentation basin as constructed in accordance with requirements shown on the plans. Payment for access roads to sedimentation basins will be made for individual components required for the construction and shall be full compensation for the installation, maintenance and removal when no longer needed as directed by the Engineer. In the event that additional temporary or permanent erosion and sediment control measures become necessary due to the negligence or actions of the Contractor, or for the contractor’s convenience the temporary work shall be performed at the Contractor's expense. Temporary or permanent erosion control measures installed in previously stabilized areas that are necessary due to required work sequencing will be paid as outlined in this section. Payment will not be made for any temporary erosion or sediment control measures installed due to the methods chosen by the Contractor to perform the required work. Measures include those utilized for convenience, for access to the work (work bridges or platforms, stream crossings, access roads, haul roads), those utilized for treating or handling water in order to assist the Contractor in the execution of the work (diversions, dewatering, conveyances) or those utilized for protecting the Contractor's work or staging areas. Payment will also not be made for measures installed outside of the right of way or easements such as material pits, haul or access roads, plant sites, and staging areas.
665-A Temporary Seeding - per acre {hectare} 665-B Temporary Mulching - per ton {metric ton} 665-C Temporary Pipe - per linear foot {meter} 665-D Temporary Pipe End Treatment – per each 665-E Polyethylene - per square yard {square meter} 665-F Hay Bales - per each 665-G Sand Bags - per each 665-H Flow Baffle – per linear foot {meter} 665-I Temporary Riprap, Class ____ - per ton {metric ton} 665-J Silt Fence - per linear foot {meter} 665-K Drainage Sump Excavation - per cubic yard {cubic meter} 665-L Floating Basin Boom - per linear foot {meter} 665-M Sediment Retention Barrier – per linear foot {meter} 665-N Temporary Coarse Aggregate, ALDOT Number ____ - per ton {metric ton} 665-O Silt Fence Removal - per linear foot {meter} 665-P Inlet Protection, Stage 3 or 4 – per each 665-Q Wattle (size) - per linear foot {meter} 665-S Brush Barrier - per linear foot {meter} 665-T Temporary Earth Berm - per linear foot {meter} 665-X Basin Dewatering Device – per each PEST CONTROL
666.01Description
The work covered by this Section shall consist of furnishing and applying designated chemicals to control certain destructive pests, namely, Armyworm, Fall Armyworm, Cutworm, Spittlebug, White Grubs and Pine Bark Beetles. PEST CONTROL 570
Because of the destructive nature of the action of these pests to trees and ground cover with the possible result of erosion and ultimate siltation of areas, control of these pests is a necessity. Both the Engineer and the Contractor have the responsibility of continually observing the planted areas for possible pest damage. The Contractor should, upon observing any of these pests, report such to the Engineer, both verbally and in writing. The Engineer will verify any reports of this type of pest and direct appropriate treatment to be taken. The following brief descriptions are provided for ease in recognizing these pests: Armyworm: A medium size caterpillar of dark green color with white stripes on sides and down the middle of the back, Size, approximately 1 inch {25 mm} in length. This worm usually feeds only at night destroying foliage. Fall Armyworm: A medium size caterpillar of dark green color with white stripes on sides and down the middle of the back with a distinctive yellow inverted "Y" on the head capsule. Size, approximately 1 inch {25 mm}. This worm will feed both day and night destroying foliage. Cutworm: A fat bodied caterpillar with a greasy appearance, color mostly greybrown or mottled on top and lighter color underneath. Size, approximately 1 to 2 inches {25 to 50 mm} in length when full grown. This worm hides during the day and feeds at night, destroying foliage. Spittlebug: Most easily identified by a frothy mass of plant juice at the forks of plant stems resembling spittle. This pest lives inside the spittle mass. White Grubs: The immature (larval) stage of June or May beetles. Length, 0.5 to 1.5 inches {13 to 38 mm}, have three pairs of legs near the head, and characteristically rest in a C-shaped position. Their heads and rear ends are brown. Green June Beetle grubs crawl on their backs with their legs up. Pine Bark Beetles: These beetles are distinguished from other bark beetles in that the rearward end of the abdomen is scooped out and spined (4 to 6 spines on each side). The southern pine beetle and black turpentine beetle have a more rounded abdomen. The black turpentine beetle is the larger of the two, being about 1/4 inch {6 mm} long . The southern pine beetle is about 1/8 {3mm} inch long. All of the pine bark beetles are roughly cylindrical and are dark brown to black.
666.02Material
The treatments to be used under this Section shall be as per the current Alabama Pesticide Handbook or Guidelines as may be issued by the Alabama Cooperative Extension Service. As new pesticide materials are approved by the State Department of Agriculture and Industries, the Bureau of Construction may allow their use upon written request by the Contractor. All chemicals shall be a product of a reputable manufacturer, processed in accordance with all State and Federal regulations for such manufacture. Restricted Use of Insecticides Whenever the State Department of Agriculture and Industries or other Federal or State agency restricts the use of any insecticide on highway right-of-way, its initial or continued use shall require the approval of the Construction Engineer. It is illegal to place herbicides in a manner that is not consistent with the requirements shown on the insecticide container labeling.
666.03Construction Requirements
The Engineer after verification of the pest occurrence and identification of the type pest shall direct the use of treatments as noted in Article 666.02 in accordance with the following: Equipment used in the application shall be designed for the application method to be used and approved by the Engineer for use. The application of pesticides shall be performed by or under the direct supervision of a licensed pesticide applicator, licensed in the area of right-of-way pest control. Uniform coverage is required. If uniform coverage is not obtained, the Contractor shall retreat the entire area in such a manner that uniform coverage is obtained. Retreatment because of uneven coverage shall be without additional cost to the State. Retreatment shall not be performed within seven days of the original treatment. All treatments shall be at the direction of the Engineer. In all treatments, dilutions of liquids and technical material dosage applied shall follow label instructions, these Specifications and be verified by the Engineer. Any change to the dilution rates of a specific chemical or the substitution of chemicals other than those meeting the requirements of Article 666.02 must have prior written approval of the Construction Engineer and any such approved change must be without additional cost to the State.
Get an email when 665 changes