A.Proportioning. The concrete mix design is the Contractor’s responsibility and includes making and testing compressive strength specimens. Make and test compressive strength specimens using the Contractor’s laboratory or a Department -approved independent laboratory. Uniquely identify each mix design submitted. For work exceeding 2,500 cubic yards, submit the following at least 60 calendar days before proposed use:
1.The proposed mix design.
2.Copies of test reports.
5.Samples of the proposed aggregate, cement, SCM, and admixtures . for Highway Construction Page 247 of 715 6. "Final set" time with the mix design as measured using AASHTO T 197M / T 197.
8.Proposed curing compound.
9.Theoretical maximum density.
10.Rate of development of electrical resistivity to 28 calendar days.
11.Modulus of elasticity at 28 calendar days.
13.Coefficient of thermal expansion. Do not produce concrete until the mix design is approved by the Central Materials Laboratory . For work less than 2,500 cubic yards, submit the following at least 14 calendar days before proposed use:
1.The proposed mix design.
2.Copies of test reports.
5."Final set" time with the mix design as measured using AASHTO T 197M / T 197.
7.Proposed curing compound.
8.Theoretical maximum density.
9.Rate of development of electrical resistivity to 28 calendar days.
10.Modulus of elasticity at 28 calendar days.
12.Coefficient of thermal expansion. Do not produce concrete until the mix design is approved. Limit the fine aggregate by weight of total aggregate to 40 percent in the proposed mix designs. Use only angular coarse aggregate . Angular aggregate is defined as having greater than 40 percent fractured faces. The Department will base fracture on the aggregate particles retained on the No. 4 sieve with 1 or more fractured faces as determined by AASHTO T 335 Method 1. The minimum mix design compressive strength is 5,600 psi when tested at 28 calendar days and is determined from the average of 3 specimens produced and cured in the laboratory. In addition to strength, report the air content and slump. Strength data is valid only if air content, slump, and water -cement ratios are within the required limits for the specified mix class. CRD- C 662CRD- C 662Use number 4 coarse aggregate . Establish the exact proportions from trial mixes from the materials to be used in the work and make adjustments to use the least amount of sand necessary to produce concrete with the required workability and strength. for Highway Construction Page 248 of 71 5 At the Contractor’s option, a combined gradation number 4C may be used. Design the proposed mix using the KU Mix Program from the University of Kansas and submit for approval. Include documentation and worksheets i n the submittal . Base the combined gradation and sand equivalent on the average of the stockpile as determined by the production quality control tests. Submit quality control charts and tests wi th the mix design. The Contractor may reduce minimum cementitious material contents by 20 percent if a combined gradation is used. If the contract does not require SCM, the Contractor may submit a mix design subject to the same requirements as if the contract requires SCM. Do not vary calcium oxide (CaO) content more than 2 percent above that used for AASHTO T 380 testing where fly ash is used in the concrete m ix for ASR mitigation. If the fly ash has a CaO content greater than 2 percent above the fly ash used for testing, additional AASHTO T 380 testing at the higher CaO content is required by the Department. Wherever SCM are is used, use the same SCM source, c ement source (mill), and cement type throughout the work for each mix design. Submit lab test reports to verify the revised mix design meets specification requirements. A 3.5 inch maximum slump is allowed for hand finishing if a sl ipform concrete paver is not used to construct concrete pavement . A 4.5 inch maximum slump and a 5 percent reduction in 28- day compressive strength is permissible for concrete media ns and other nontraveled surfaces, excluding shoulders.
B.Equipment.
1.Mixers and Hauling Equipment .
a.Mixers, agitators and nonagitating hauling equipment . Mixers may be stationary mixers or truck mixers. A gitators may be truck mixers or truck agitators. Equip truck mixers and agitators with an accessible revolution counter for the drum, blades, or paddles to verify revolutions. Ensure a NRMCA standard metal plate or plates are attached to each mixer and agitator by the manufacturer and plainly marked with the various uses for which the equipment is designed, the volume of the drum, the capacity of the drum or container in terms of the volume of mixed concrete , and the speed of rotation of the mixing drum or blades. Equip stationary mixers with an acceptable timing device that will prevent discharge until the specified mixing time has elapsed. Equip truck mixers with a calibrated water flow meter or other approved measuring device to control the quantity of mixing water added in the field.
b.Provide mixers that, when loaded to the rated mixing capacity and the concrete is mixed for the time or revolutions prescribed, combine the ingredients of the concrete into a thoroughly mixed uniform mass and discharge the concrete with satisfactory uniformity as specified in 409.03.D.
c.Provide agitators that maintain the mixed concrete in a thoroughly mixed and uniform mass and are capable of discharging the concrete with a satisfactory degree of uniformity when loaded to rated capacity as specified in 409.03.D.
d.Provide nonagitating equipment with bodies that are smooth, mortar -tight metal containers capable of discharging the concrete without segregation .
2.Paving Equipment. Construct pavement using paving equipment that uniformly spreads at the proper thicknes s for the width of the area being paved, consolidates the freshly placed concrete and produces a finished surface meeting straightedge and profile index requirements of 409.03.K, for Highway Construction Page 249 of 71 5 before grinding. If the pavement produced does not meet these requirements, suspend concrete paving operations until the deficiencies or malfunction is corrected. Use self -propelled paving machines that comply with the following:
a.Placer/Spreader: Receive the concrete mixture into hopper(s) adjac ent to the area to be paved.
b.Slipform paver: Equipped with automatic screed control mechanisms that operate from stringlines erected near the right and left side of the machine. Check the depth of placement at 50 feet i ntervals to achieve the design thickness between the outside edges after the stringlines are established. Consolidate the concrete with internal vibrators. Limit the rate of vibration to less than 3,500 vibrations per minute for surface vibrators and 8,000 to 12,000 vibrations per minute for internal vibrators. Provide a tachometer or other suitable device for measuring and indicating the actual frequency of vibrations. Do not rest vibrators on new pavements or side forms . Con nect power to the vibrators so the vibration will stop when the forward or backward motion of the machine is stopped.
c.Machine Paving with Forms: The Contractor may finish concrete pavement in sm all irregular areas as specified in 411.03.B instead of using slipform pavers, when approved.
d.Bridge Deck Machine: The Contractor may finish concrete pavement in small irregular areas with a concrete bridge deck finishing machine as specified in 502.03 instead of using slipform pavers, when approved. Finishing and surface test specifications apply.
3.Concrete Sawin g Equipment. Provide at least 3 production saws, including 1 standby unit, adequately powered to perform the work. Provide saws that are multiple arbor or multiple blade gang saws. Mount saws operating on 3 to 4- hour old, nonrigid pavement on a work bridge so the machine weight is not placed on the new concrete. Provide adequate artificial lighting for night sawing. Maintain equipment in good working order and have it on the job before the first placement and continuously during concrete paving operations. Maintain an ample supply of saw blades during the sawing operations. Do not pave until concrete sawing equipment is onsite and ready for use.
C.Handling, Measuring, and Batching Materials . Produce concrete that meets the approved mix design. Submit the proportioned ingredients for each batch. Request changes to the mix design and obtain approval from the Engineer for a new mix design befor e batching concrete. Minor adjustments due to varying moisture in the aggregates, changes in aggregate gradation when using a combined gradation, and minor adjustments of approved admixtures are not considered changes in the mix design and will not require another approval. Report the minor mix adjustments in writing to the Engineer before batching.
1.Measure cement by weight. Weigh cement in an individual hopper and keep separate from the aggregates until released for discharge. Attach the cement hopper to a separate scale for individual weighing or to the aggregate scale for cumulative weighing. Weigh cement before adding the other ingredients, if weighing cumulatively. Use a cement scale and weigh hopper that is separate and distinct from the aggregate weighing equipment. Provide cement batchers with a dust seal between the charging mechanism and hopper. Install the dust seal so it does not affect the for Highway Construction Page 250 of 715 weighi ng accuracy and is vented to allow the escape of air. Provide a self -cleaning hopper fitted with a means to ensure complete discharge . Provide sufficient wind protection to prevent interference with batching accuracy. Ensure the cement, as weighed, is within 1 percent of the design weight.
2.Measure aggregates by weight. Weigh individual aggregates within two percent of the required weights and the total weight of the aggregate within 2 percent of the total required weight. Handle aggregates from stockpiles or other sources to the batching plant so uniform grading and stable moisture content is maintained. Stockpile or bin aggregates to drain for at least 12 hours before batching aggregates produced or handled by hydrauli c methods or washed aggregates. Verify aggregate gradation meets the requirements for the proposed mix design.
3.Measure water by volume or by weight. Arrange the measuring device so the measurements will not be affected by variable pressures in the water supply line. Do not use wash water as a portion of the mixing water. Weigh or measure water within 1 percent of the required amount.
4.Measure SCM by weigh t. Weigh the SCM within 1 percent of the design weight.
5.Measur e dry admixtures by weight and paste or liquid admixtures by weight or volume. Dispense admixtures used in small quantities in proportion to the cement, as air -entraining admixtures, with the mixing wate r. Adjust the quantity of admixtures used in accordance with manufacturer’s written instructions. Use admixtures that meet 709.02 .
D.Mixing and Delivering .
1.Mix and deliver concrete by any of the following means:
a.Central mixed concrete. Mix completely in a stationary mixer and transport the mixed concrete to the point of delivery in agitating equipment or in approved nonagitating equipment.
b.Transit mixed concrete . Mix completely in a truck mixer at the batching plant or while in transit.
c.Truck mixed concrete. Mix completely in a truck mixer at the point of delivery after adding mixing water.
d.Shrink mixed concrete . Mix partially in a stationary mixer and complete the mixing in a truck mixer.
e.Mix in an approved mixer that volumetricall y measures the concrete ingredients and continuously produces concrete that meets the requirements of ASTM C685.
2.Operate truck mixers and truck agitator s within the rated capacity, and at a speed of rotation for mixing or agitating, as designated by the equipment manufacturer.
3.The minimum mixing time for mixers of 10 cubic yards or less capacity is 50 seconds when a stationary mixer is used for the complete concrete mixing. Obtain approval of the mixing time for mixers of 10 cubic yards or more capacity. Measure mixing t ime from the time cement and aggregates are in the drum. Charge the batch into the mixer so some water will enter bef ore cement and aggregates, and water is in the drum by the end of the first ¼ of the specified mixing time.
4.The Contractor may reduce the mixing time in the stationary mixer at least 30 seconds for shrink mixed concrete. Complete the mixing in a truck mixer with between 50 and 100 revolutions of the for Highway Construction Page 251 of 715 drum or b lades at mixing speed. Do not exceed a batch volume of 70 percent of the drum gross volume.
5.When a truck mixer is used for complete mixing, mix each batch of concrete with between 70 and 100 revolutions of the drum or blades at mixing speed. Use agitating speed for additional revolutions.
6.When a truck mixer or agitator is used for transporting concrete completely mixed in a stationary mixer, use agitating speed for mixing during transport.
7.When a truck mixer or agitator is used for transporting concrete , apply the following:
a.Deliver the concrete to the project site and complete discharge within 1.5 hours after the introduction of the cement to the aggregates or before the drum has revolved 300 revolutions, whichever comes f irst.
b.In hot weather, or under conditions contributing to quick stiffening of the concrete, a time less than 1.5 hours may be necessary.
c.Begin the mixing operation within 30 minutes after the cement has been intermingl ed with the aggregates when a truck mixer is used for the complete mixing of the concrete.
d.If additional mixing water is approved, at least 30 additional revolutions of the truck mixer drum at mixing speed are required before discharge of concrete. T he Engineer may allow mixing water only 1 time during the discharge of the concrete.
e.The Engineer may require tests for consistency at approximately the beginning, the midpoint, and the end of the load. If the results vary by more than 1 inch, do not us e the mixer or agitator until the condition is corrected.
8.Transport central mixed concrete in suitable nonagitating equipment. Provide covers when specified. Equip bodies with smooth, mortar -tight metal cont ainers capable of discharging the concrete at a controlled rate without segregation. Completely discharge concrete within 45 minutes after the introduction of the cement to the aggregates.
9.Do not use aluminum pipe or aluminum truck beds to convey concrete .
10.Provide concrete at a temperature of at least 50°F and not more than 85°F at the time of placing.
F.Temperature Limitations . Place concrete pavement with the following precautions:
1.During cold weather, when ambient temperature falls below 40°F, produce mixed concrete with a temperature at least 50°F and less than 85°F at the time of placing. The water and/or the aggregate may need t o be heated to a temperature of between 70°F and 150°F. The Contractor may place concrete pavement when the air temperature is below 40°F as specified in 409.03.M. for Highway Construction Page 252 of 71 5 2. Do not place concrete on frozen subgrade or use frozen aggregates in the concrete.
3.Do not place concrete if the concrete temperature is greater than 85°F at time of placement . Do not place concrete when the evaporation rate is greater than 0.15 pounds per square foot per hour when tested in accordance with Idaho IT 133. Night or early morning placement may be necessary to avoid excess evaporation. Ice used as a part of the mixing water must be completely melted by the time mixing is completed.
4.Do not place concrete on a surface with a temperature exceeding 90°F.
G.Hand Placing Concrete . The following conditions allow hand placing and finishing methods:
1.Breakdown of the mechanical equipment when the concrete is already deposited on the grade.
2.Narrow widths or areas of irregular dimensions where operating mechanical equipment is impractical. Obtain approval before placing concrete in wood or metal forms .
3.Do the following when hand placing and finishing methods are allowed:
a.Place a test section to show the proposed operation is capable of satisfactorily consolidating and striking off the concrete to the required grade, section, and applicable smoothness requirements when Engineer requested.
b.Spread concrete evenly. Do not use vibrators for extensive shifting of the concrete mass. Us e surface vibrators, internal vibrators, or other methods that produce equivalent results without segregation to consolidate concrete. Thoroughly consolidate concrete against and along forms or adjoining pavement so gravel pockets along the edges of the finished pavement are prevented. Repair gravel pockets found after removing the forms. Consolidate uniformly across the full pavement width. Strike off the concrete to the intended surface profile after cons olidation.
c.Provide a screed at least 2 feet longer than the maximum width of the slab to be struck off. Use a screed constructed of metal or other suitable material clad with metal, rigid enough to keep its shape, and is approved.
d.Move the screed forward on the forms with a combined longitudinal and transverse shearing motion, always moving in the direction in which the work is progressing, and manipulated so neither end is raised from the side forms during the stri king off process. Repeat until the surface has uniform texture, is true to grade and cross -section, and has no porous areas, if necessary.
e.Smooth the concrete by floating after it has been consolidated and struck off. Do not float concr ete within 3 0 feet of consolidation and strike off. The Contractor may use long handled floats having blades at least 4 feet in length to smooth and fill in open textured areas in the pavement . The Contractor may use a full width float. Move ahead in successive advances of not more than one- half the length of the float. Continue floating until irregularities are removed. Remove free water on the pavement with the float or other suitable tool.
f.Float the surface transversely using a long h andled float when the crown of the pavement will not allow using a longitudinal float. Do not work the crown out of the pavement.
g.Remove excess water and laitance from the pavement surface after floating. Use a straight edge at least 10 feet long with a long handle for operating at the edge of the pavement. Lap successive drags ½ the length of the blade. for Highway Construction Page 253 of 71 5 h. Finish the surface of the concrete pavement as specified in 409.03.J. Us e hand methods that result in the finish as specified in 409.03.J when a self -propelled comb is not practical.
i.Smoothness requirements apply.
j.Do not place additional water on the concrete surface during the machine or hand finish opera tion.
H.Joints . Construct joints as specified. Use suitable guidelines or devices to ensure sawing the joints at the proper location.
1.Stress Relief Joint Sawing. Make the initial stress relief saw cuts, to control shr inkage cracking, as soon as the concrete has hardened enough to allow sawing without raveling. Saw to the depth, width, line, and spacing as specified. Continue stress relief sawing operations at night or under inclement weather conditions as required. Keep the sawing operation up to pace with the paving operation; otherwise stop paving work until the sawing operation can keep pace with the paving operation. Single cut stress relief joints will be ¼ inch wid e and will be saw cut to 1/3 depth of the concrete pavement. Single cut stress relief joints will be sealed with a hot poured elastomeric joint filler meeting the requirements of 704.03. Backer rods will not be used. When a single saw cut joint is specified, thoroughly clean the sides of the joint and the adjacent pavement surface, approximately 1 inch on each side of the joint, of scale, dirt, dust, and other foreign material by jet water bl asting immediately after sawing. Remove the residue from sawing and water blasting from the pavement surface before it is blown by traffic or wind. Prevent the residue from entering lanes used by traffic.
2.Sealant Reservoir Construction. Allow the concrete to cure at least 72 hours and then saw the joints to the width and depth as specified to accommodate sealant placement, when a sealant reservoir is specified. Do not saw wider than speci fied. Thoroughly clean the sides of the sealant reservoir and adjacent pavement surface, approximately 1 inch on each side of the joint, of scale, dirt, dust, and other foreign material by jet water blasting immediately af ter sawing. Remove the residue from sawing and water blasting from the pavement surface before it is blown by traffic or wind. Prevent the residue from entering lanes used by traffic. Repair damage (e.g., spalling, fracturing) to the concrete pavement . Properly cure repairs before installing the joint sealant.
3.Tie Bars. Place deformed tie bars of the specified length, size, and material. Place tie bars using approved mechanical equipment, rigidly secured by chairs or other supports to prevent displacement. Do not treat the tie bars; this will impair bonding with the concrete. Locate tie bar within tolerances as specified or as directed.
4.Load T ransfer Devices. Incorporate load transfer devices into the concrete pavement by using dowel bar assemblies or dowel bar inserters.
1.Fabrication. Fab ricate dowel bar assemblies, or baskets, in single units for appropriate lanes before being placed on grade. Submit material detail sheets with basket size and complete anchoring details for approval. for Highway Construction Page 254 of 71 5 (2) Anchoring. Securely anchor dowel bar assemblies at grade to prevent displacement during concrete paving. Secure baskets with at least 8 pins to ensure they hold bars within tolerance. The Engineer will check dow el basket placement and anchorage before concrete placement. Cover dowel bar assemblies with fresh concrete immediately ahead of the paver . Properly realign and re- anchor any dowel baskets removed to accommodate delivery of concrete before the paver arrival.
3.Location. Check and document dowel bar location at least every 30 joints after placement of concrete. Locate the baskets and dowels in plastic concrete with a hand tr owel, or other approved method, to verify location and accuracy. Note and mark the joint locations that are not acceptable and take action to determine and correct the deficiencies ahead of the paver .
4.Dowel Bars . Coat d owel bars in accordance with AASHTO M 254 Type A or B. Give Type B dowel bars in assemblies a thin coating of graphite grease, or approved equal, as a bond breaker. On ramps, tapers, and widenings, use less than 2 assembly sections in a joint.
b.Dowel Bar Inserters. As an alternative to dowel bar assemblies on grade, the Contractor may insert dowel bars into the plastic concrete by an approved mechanical device that ensures reconsolidation around the bars. Place the bars parallel to the pavement centerline and surface. Insert the bars before the passage of the final finishing beam or screed.
1.Approval. Do not use dowel bar inserters without prior Engineer approval. Use an approved method to detect and verify the location of dowel bars .
2.Location. Use ground penetrating radar (GPR), magnetic tomography (MIT -scan), pacometer, or other approved device to establish the location and to ensure compliance with the tolerances of the dowel bar placement of at least 10 percent of the joints . The Engineer will select the joints to be inspected at random. Take at least 2 cores to verify the calibration of the insertion equipment. When inspection shows dowel bars out of tolerance, inspect remaining joints with the approved device. Repair holes left in the pavement by the coring operation at n o additional cost to the Department. Obtain approval for repair methods and materials bef ore beginning repairs .
3.Dowel Bars . Coat dowel bars in accordance with AASHTO M 254 Type A or B. Give Type B dowel bars to be inserted a 2 layer bond breaker coating. Use an approved dry film (e.g., 3M™ PT FE) on the first layer. Apply a thin layer of form oil over the dry film. Use extra precautions to prevent form oil runoff from contaminating the fresh concrete. Locate load transfer devices within tolerances as specified or as directed regardless of method of incorporation. Dowel bars, whether placed in baskets or inserted, must have at least 6 inches of bar embedded in each slab. Retrofit missing dowels, or dowels out of tolerance in the wheel path area. The Engineer may accept payment in place of retrofitting bars in areas outside of the wheel path. As payment, missing dowel bars will be charged by the Department to the Contractor at the cost to retrofit the bars into the slabs. for Highway Construction Page 255 of 715 Provide positive control and an approved method of marking dowel bar locations for correlation to sawed joints . Dowels are r equired where the new concrete pavement abuts the existing concrete pavement . Drill holes into the existing concrete pavement as specified or as directed and epoxy grout dowel bars into the holes. Obtain approval of epoxy grout bef ore use.
5.Construction Joints . Place construction joints at right angles to the centerline when there is an interruption of more than 45 minutes in the conc rete paving operations. Do not place transverse joints closer than 6 feet apart. Place the construction joint at the same location as would be used for a transverse joint whenever possible.
6.Random Cracks. After sawing i s completed, remove random cracks penetrating the full depth of the pavement , whether transverse or longitudinal, by replacing the cracked slabs. Remove and replace cracked slabs at no additional cost to the Department.
I.Tolerance in Pavement Thickness. Construct pavement as specified. The pavement thickness is subject to price adjustment in accordance with Table 409.05- 1. Once the pavement is sufficiently cured to support foot traffic, the Engineer will check the completed pavement thickness of the concrete by measuring the distance from the concrete pavement surface to the underlying surface in accordance with FOP for AASHTO T 359. Provide five 2 inch diameter cores for verification of the depth, as directed. The Contractor may take cores, as approved, to dispute depth measurements taken by the Engineer. The Engineer will witness the coring. Core, test, and repair the concrete pavement at no additional cost to the Department. The E ngineer will determine pavement thickness by average depth measurements in accordance with FOP for AASHTO T 359. An adjusted unit price for pavement is defined as a single placement width 0.1 mile long. The Engineer will determine the average thickness of the pavement in accordance with FOP for AASHTO T 359 calculated as follows:
1.When the thickness is more or less than 0.1 inch of the specified thickness, but less than 0.5 inch, that section is eligible for an incentive or disincentive price adjustment as specified in Table