412.01 412-1 SECTION 412 PORTLAND CEMENT CONCRETE PAVEMENT DESCRIPTION
412.01 This work consists of constructing a pavement composed of Portland Cement Concrete
on a prepared subgrade or base course per these specifications and in conformity with the lines, grades, thicknesses, and typical cross sections shown on the plans or established. MATERIALS
412.02 Materials shall meet the requirements of the following subsections:
Fine Aggregate 703.01 Coarse Aggregate 703.02 Portland Cement 701.01 Fly Ash 701.02 Water 712.01 Air- Entraining Admixtures 711.02 Joint Sealant with Backer Rod 705.01 Curing Materials 711.01 Reinforcing Steel 709.01 Chemical Admixtures 711.03 Dowel Bars and Tie Bars 709.03 CONSTRUCTION REQUIREMENTS
412.03 Classification . Concrete shall conform to the requirements for Class P concrete as
specified in Section 601. Fast track concrete pavement is accelerated Class P concrete.
412.04 Proportioning. Proportioning shall conform to the requirements of subsection 601.05.
412.05 Batching . Batching shall conform to the requirements of subsection 601.06.
The Contractor shall provide a Process Control Plan (PCP) to minimize voids in the concrete pavement, such as clay balls, mud balls and other deleterious materials. It shall also identify the Contractor’s method for ensuring that the provisions of the PCP are met. This PCP shall be submitted to the Engin eer at the Pre- construction Conference. Paving operations shall not begin until the Engineer has approved the PCP . This PCP shall identify and address issues affecting the quality of aggregates incorporated into the concrete mix including but not limited to:
2.Inspection at the pits, plants and aggregate storage areas.
3.Base or floor of pits, plants and aggregate storage areas.
4.Inspection of truck beds. 412.06 412-2 (5) Methods and frequency of aggregate testing.
6.Training of operators, haulers and inspectors in regard to aggregate quality.
7.Plant site selection and layout .
8.Grizzlies and screens on conveyors.
9.Stabilization of haul roads and construction accesses. When the Engineer determines that any element of the approved PCP is not being implemented, the paving shall stop, the cause shall be identified and corrected by the Contractor before paving operations resume.
412.06 Mixing . Mixing shall conform to the requirements of subsection 601.07.
412.07 Equipment . Equipment and tools shall be capable of handling materials,
performing the work, producing a product of specified quality, and shall be approved. The equipment shall be at the job site sufficiently ahead of the start of paving operations to be examined and approved.
a.Hauling Equipment. Concrete may be hauled and placed with non -agitator equipment. Bodies of non -agitating equipment shall be smooth, mortar tight containers, and shall be capable of discharging the concrete at a controlled rate without segregation.
b.Consolidating and Finishing Equipment . Concrete shall be spread, struck -off and finished by mechanical equipment, either from fixed forms or by slip form method, unless otherwise permitted. The Contractor shall use an approved longitudinal paver wedge system to create a sloped SafetyEdge SM. The Contractor shall modify the paver screed to create a SafetyEdge SM that meets the final cross -section shown on the plans. The system shall provide a sloped SafetyEdge SM equal to 32 degrees plus or minus 5 degrees measured from the pavement surface cross slope extended. There may be areas where it is not possible to place the SafetyEdge SM in conjunction with mainline paving but where the SafetyEdge SM is required, such as transitions at driveways, intersections, interchanges, etc. In these areas the Engineer may allow the Contractor to use handwork for short sections or to saw cut the sloped SafetyEdge SM after paving operations are completed. The Contractor shall submit the proposed paver wedge system for approval at the Pre-construction Conference. The Engineer may require proof that the system has been used on previous projects with acceptable results or may require a test section constructed before the beginning of work to demonstrate that it creates an acceptable wedge shape. Paving shall not begin until the system is approved in writing by the Engineer. The finished shape of the SafetyEdge SM shall extend for the full depth of the concrete pavement or for the top 5 inches whichever is less. The full width and depth of concrete requiring a finishing machine shall be consolidated by a single pass of an approved internal vibrator. Internal vibrators shall be operated within a frequency range of 4,000 to 8,000 vibrations per minute (VPM). Vibrators shall not be operated in a manner to cause a separation of the mix materials, either a downward displacement of large aggregate particles or an accumulation or laitance on the surface of the concrete. Avoidance of separation of the mix may require reduction in the vibrator frequency when forward motion of the paver is reduced. 412.07 412-3 Paving machine operations shall stop if any vibrator fails to operate within specifications. Vibration shall be stopped whenever forward motion of the paver is stopped. The use of surface vibrators shall be approved by the Engineer before use. Surface vibrators shall be operated within a frequency range of 3,500 to 6,000 VPM. An electronic monitoring device displaying the operating frequency of each individual internal vibrator shall be required for mainline pavement exceeding 600 feet in length. The monitoring device shall have a readout display near the operator’s controls v isible to the paver operator and to the Engineer. It shall operate continuously while paving and shall display all vibrator frequencies with manual or automatic sequencing among all individual vibrators. If a vibrator monitor fails to function properly, a handheld device may be used until the monitor is repaired. The Contractor shall measure the vibrations of each vibrator at least once an hour. The vibrator monitor repair must be made within 48 hours. The depth of penetration into the concrete pavement slab of internal vibrators shall be between the surface and mid slab and passing above any reinforcing steel. An operating position -locking device shall be provided so that no part of the vibrating unit can be lowered to the extent that it will come in contact with reinforcing steel or tie bars while paving. Vibrators shall have a minimum eccentric diameter of 1 1/2 inches or as approved by the Engineer. Horizontal spacing of vibrators shall not exceed the manufacturer’s recommendations and shall not exceed 18 inches from center to center. The longitudinal axis of the vibrator body shall be mounted approximately parallel to the direction of paving. Vibrators shall meet or exceed the following specifications at manufacturers design frequenc y of 10,000 VPM:
1.Amplitude (peak to peak) 0.070 inch.
2.Centrifuge force 1 ,200 pounds. Within the frequency range, the Contractor shall adjust the frequency to provide optimum consolidation for the mix and placement conditions. If any vibrator ceases to function properly, the paving operation shall be stopped immediately and not resumed until the faulty vibrator has been repaired or replaced. Concrete shall be thoroughly consolidated against and along the faces of all forms and along the full length and on both sides of all joint assemblies by means of vibrators inserted in the concrete. Vibrators shall not come in contact with or cause displacement of the joint load transfer devices, subgrade, or side forms and shall not interf ere with placement of reinforcing steel. Any variation from the above method must have prior written approval from the Engineer. The Contractor’s documentation shall include evidence that the proposed method of consolidation will provide equal or better consolidation than the method described ab ove.
c.Concrete Saw . When sawed joints are required, the Contractor shall provide sawing equipment adequate in number of units and power to complete the sawing to the required dimensions and at a rate that will control cracking. The Contractor shall provide at least one standby concrete saw i n good working order at all times. An ample supply of saw blades shall be maintained at the site of the work at all times during sawing operations. The Contractor shall provide adequate artificial lighting facilities for night sawing. All of this equipm ent shall be on the job during concrete placement. 412.08 412-4 Wastewater generated from concrete saw operations shall be contained and disposed of per subsection 107.2 5.
d.Test Bridge . The Contractor shall furnish a movable bridge that conforms to subsection 601.15(g) for use by the Department.
412.08 Preparation of Subgrade . After the roadbed has been graded and compacted, the
subgrade shall be trimmed to the correct elevation and slope. For slip form paving, the elevation and slope of the trimmer shall be automatically controlled from outside reference lines established for this purpose. The trimmed subgrade shall extend at least 2 feet beyond each edge of the proposed concrete pavement when forms are used and at least 1 foot outside the track width of finishing, curing, and tining equipment for slip form operations. Any work required beyond the planned roadbed necessary to support the Contractor’s paving equipment or hauling vehicles, will not be paid for separately, but shall be included in the work. The subbase or base course shall be brought to the specified cross section. High areas shall be trimmed to the proper elevation. Low areas in untreated bases may be filled and compacted to a condition similar to that of the surrounding grade or filled with concrete integral with the pavement. Low areas in treated bases shall be filled with concrete integral with the pavement. The finished grade shall be maintained in a smooth and compacted condition until the pavement is placed. Untreated subgrade or base course shall be uniformly moist during concrete placement. If it becomes too dry, the untreated subgrade or base course shall be sprinkled without forming mud or pools of water.
412.09 Limitations of Placing Concrete. Limitations on the placing of concrete shall
conform to subsections 601.12 (b) and (c), and 412.15.
412.10 Placing Concrete . The concrete shall be uniformly deposited on the grade in a
manner that requires as little re- handling as possible. Concrete for areas that contain load transfer devices shall not be dumped directly from the hauling vehicles onto the grade. Concrete shall be placed by an approved placer spreader machine. Concrete shall be deposited as near to expansion and contraction joints as possible withou t disturbing them but shall not be dumped from the discharge bucket or hopper onto a joint assembly unless the dis charge is well centered on the joint assembly. Necessary hand spreading shall be done with Shovels, not rakes. Workers shall not walk -in freshly mixed concrete with footwear coated with earth or foreign substances. All footprints in the fresh concrete shal l be vibrated and finished flush with the adjacent surface. Construction equipment other than standard paving equipment will not be allowed to handle plastic concrete in advance of the paver in the roadway without approval. Where concrete is placed adjacent to a newly constructed lane of pavement with the concrete paving equipment operating on the newly constructed pavement, the concrete shall have attained a minimum compressive strength of 2 ,000 psi before commencing paving. Determination that the concrete has reached 2 ,000 psi shall not relieve the Contractor of the responsibility for protecting the pavement. Any concrete or foreign material that falls on or is worked into the surface of a completed slab shall be removed immediately. 412.11 412-5 Following placement, the concrete shall be struck off to conform to the cross section shown on the plans and to an elevation such that when the concrete is properly consolidated and finished, the surface of the pavement will be at the elevation shown on th e plans or established. The Contractor shall provide a MIT -Scan-2, which is manufactured by MIT GmbH. The Contractor shall ensure the MIT -Scan-2 is calibrated for the specific dowel bar size or load transfer device being placed and is operating within the manufacturer’s tolerances. The Contractor shall also ensure that the operator of the MIT -Scan-2 is fully competent in the use of the device. The Contractor shall supply the serial number of the device to be used on the project.
412.11 Test Specimens. The Contractor shall furnish the concrete necessary for casting test
cylinders and performing air and slump tests.
412.12 Finishing . The sequence of operations shall be strike -off and consolidation, floating ,
and final surface finish. Water shall not be added to the surface of the concrete to assist in finishing operations. The surface shall be finished to a uniform texture, true to grade and cross section, and free from porous areas. When the finishing machine, either form, slip form, or hand finishing method, leaves a surface that is not acceptable, the operation shall stop, and corrective action shall be taken. Inability of the finishing machine to provide an acceptable surface finish, after corrective action, will be cause for requ iring replacement of the finishing machine. Wastewater generated from concrete finishing operations shall be contained and disposed of per subsection 107.2 5.
a.Hand Finishing . Hand finishing shall be minimized wherever possible. The Engineer shall be notified beforehand finishing work and the proposed hand finished work shall be addressed in the Process Control Plan for concrete finishing. Unless otherwise specified, hand finishing methods will be permitted only under the following conditions. Hand finished concrete shall be struck off and screeded with a portable screed that is at least 2 feet longer than the maxim um width of the slab to be struck off. It shall be sufficiently rigid to retain its shape. Concrete shall be thoroughly consolidated by hand vibrators. Hand finishing shall not be allowed after concrete has been in -place for more than 30 minutes or when initial set has begun unless otherwise approved by the Engineer. Finishing tools made of aluminum shall not be used. The Contractor shall provide a Process Control Plan (PCP) to ensure that proper hand finishing is accomplished per current Industry standards for concrete pavement placement. It shall also identify the Contractor’s method for ensuring that the provisions of the PCP are met. The PCP shall be submitted to the Engineer at the Pre -construction Conference. Paving operation s shall not begin until the Engineer has approved the PCP . The PCP shall identify and address issues affecting the quality of finished concret e pavement including but not limited to:
1.Timing of hand finishing operations
2.Methodology to place and transport concrete
3.Equipment and tools to be utilized
4.Qualifications and training of finishers and supervisors 412.13 412-6 When the Engineer determines that any element of the approved PCP is not being implemented or that hand finished concrete is unacceptable, work shall be suspended. The Contractor shall supply a written plan to address improperly placed material and how to remedy future hand finishing failures and bring the work into compliance with the PCP . The Engineer will review the plan for acceptability before authorizing the resumption of operations.
b.Floating . Hand floating will be permitted only as specified in subsection 412.12 (a). The Contractor shall not use floats made of aluminum.
c.Final Finish and Stationing . The final surface of the pavement shall be uniformly textured with a broom, burlap drag, artificial turf or diamond ground in order to obtain the specified texture depth. The Contractor shall submit the proposed method of PCCP texturing at the Pre -construction Conference for approval by the Engineer. Surface imperfections resulting from the texturing operation shall be corrected by the Contractor at no additional cost. Broom, burlap drag, or artificial turf texture shall be installed within 15 minutes after strike -off, or as pavement conditions allow. Diamond grinding shall be performed using diamond blades mounted on a self -propelled machine designed for diamond grinding and texturing concrete pavement. The equipment shall have a positive means of vacuuming the grinding residue from the pavement surfac e, leaving the surface in a clean, near -dry condition. Diamond grinding shall not occur until the concrete has attained strength of at least 2,500 psi. The diamond grinding process shall produce a pavement surface that is true to grade and uniform in appearance. The grooves shall be evenly spaced. Any ridges on the outside edge next to the shoulder, auxiliary, or ramp lanes greater than 3/16- inch high shall be feathered out to the satisfaction of the Engineer in a separate, feather pass operation. The pavement surface after diamond grinding shall have no depressions or misalignment of slope in the longitudinal direction exceeding 1/8 inch in 12 feet when measured with a 12-foot straightedge placed parallel to the centerline. All areas of deviation shall be reground at no additional cost. Stationing shall be stamped into the outside edge of the pavement, as shown on the plans.
412.13 Joints . Joints shall be constructed of the type, dimensions, and at locations
required by the Contract. When a joint is saw cut more than 3 inches from the designated location, the pavement shall be removed and replaced to the nearest correct joints. When portions of concrete pavement are removed and replaced, the portion removed shall be the full width of the lane and length of the affected slabs. This corrective action shall be at the Contractor’s expense. Immediately after sawing, the sawed joints shall be flushed with water to remove any saw residue, and the saw residue shall be completely removed from the surface of the pavement. This residue shall be removed by approved methods. All equipment other than saws shall be kept off the pavement until the sawing is complete. 412.13 412-7 After the proper curing period, the sawed joint shall be thoroughly cleaned and immediately sealed per subsection 412.18.
a.Construction Joints Construction joints shall be slightly tooled while the concrete is plastic and later sawed to the dimensions specified in the Contract. The tooling shall not exceed the width of the sawed joint at any point. In the event tie bars cannot or are not placed in plastic state concrete, then the tie bars shall be placed according to the following minimum requirements: Holes with a diameter 1/4 inch greater than the bar diameter shall be drilled laterally into the hardened concrete slabs at one half the slab depth, 36 inches on center, 15 to 16 inches deep. Each hole shall be cleaned out with compressed air using a wand attachment that fits into the hole and is long enough to reach to the back of the hole. Each hole shall be brushed out with a stiff bristled cylindrical brush that is at least 1/4 inch larger than the diameter of the hole. Each hole shall be blown out w ith compressed air a second time using a wand attachment that fits into the hole and is long enough to reach to the back of the hole. Each hole shall be blown out until there is no longer any evidence of dust, debris or loose material in the hole. An approved epoxy shall be used and installed according to the manufacturer’s instructions. Epoxy shall be placed in the back of each hole with an applicator that will reach the end of the drilled hole. A sufficient amount of epoxy shall be placed in each hole to ensure that the bar will be completely covered with epoxy. Epoxy shall be placed on the bar before inserting the bar into the hole. The bar shall be inserted into the hole using a twisting motion to facilitate covering the bar and the inside su rface of the hole with epoxy minimizing voids or air pockets. When tie bars are placed in plastic state concrete or drilled and epoxied into a construction joint, and if required by the Engineer, the Contractor shall demonstrate by testing at least 15 of the tie bars that the bar pullout resistance is at least 11,250 pounds with slippage of 1/16 inch or less. If two or more tie bars do not meet the required pullout resistance, then another 15 tie bars shall be tested. If any of the second 15 do not meet the required pullout resistance, then all remaining tie bars sh all be tested. The Contractor shall perform additional pullout tests and take corrective action when and as directed. All steps taken to test bars, and to correct, repair or replace failed tie bars and the surrounding failed area shall be at the Contractor ’s expense. Concrete strength shall have a compressive strength of at least 2 ,500 psi before testing. ASTM E488 shall be used for performing pullout testing.
1.Longitudinal Construction Joints . Keyways and epoxy -coated, deformed steel tie bars shall be placed as specified in the Contract. Tie bars shall be placed perpendicular to the longitudinal joint by an approved method. When adjacent lanes of pavement are constructed separately, tie bars may be bent at right angles against the edge of the first lane constructed and straightened into final position before the concrete of the adjacent lane is placed. In lieu of bent tie bar s, approved two-piece connectors may be used. If the coating of epoxy coated tie bars is damaged, the bars shall be repainted with epoxy paint before placement of concrete.
2.Transverse Construction Joints . Transverse construction joints shall be constructed at a transverse contraction joint as specified in the Contract. Transverse construction joints shall be constructed when the concrete placement is interrupted for more than 30 minutes, or initial set is imminent. The concrete back to the preceding transverse joint 412.13 412-8 shall be removed and the bulkhead placed per the requirements for a standard transverse contraction joint. Transverse construction joints shall be placed at the end of each day’s placement.
b.Weakened Plane Joints . Weakened plane joints shall be spaced and skewed as specified in the Contract and formed by sawing. The time of sawing shall be determined by the Contractor to prevent random cracking and raveling from the sawing. The time will depend upon weather conditions, temperature, and other factors affecting the setting of concrete. If uncontrolled cracking occurs during or before joint sawing, the Contractor shall move the sawing operation ahead and, if necessary, add additional sawing units to eliminate uncontr olled cracking.
1.Longitudinal Weakened Plane Joints . Epoxy coated deformed steel tie bars shall be inserted into the plastic state concrete after the auger. In the event the tie bars are placed behind the machine paving mold, vibration will be required during placement. Other methods of bar placement may b e acceptable if the Contractor can demonstrate satisfactory performance of the alternate method. Proposals of alternate methods or additional costs associated with other methods shall be at the Contractor’s expense. Tie bars shall be placed according to a method approved by the Engineer. The Contractor shall use an MIT Scan -2 to evaluate the location of tie bars that cannot be visually inspected. Each longitudinal joint located within the dowel bar test locations described in subsection 412.13 (b) 2 that were not visually inspected shall be evaluated with the MIT Scan -2. The MIT Scan -2 shall be calibrated for the tie bar size placed. The tie bars shall be located within the middle third of the slab, and a minimum of 1/2 inch below the saw cut. Tie bars shall have a minimum embedment of 12 inches on each side of the joint. The weakened plane joint shall be made by sawing in hardened concrete per the plan details. Tie bars that are cut during sawing operations shall be replaced at the Contractor’s expense. Tie bars that are located less than 2 inches above the bottom of the slab shall be replaced at the Contractor’s expense. Tie bars that are not embedded a minimu m of 12 inches on each side of the joint shall be replaced. When the spacing between two in- place tie bars exceeds 40 inches but less than 72 inches, a tie bar will be installed halfway between the two tie bars, unless this installation location is within 12 inches of a transverse weakened plane joint. When the spacing between two in -place tie bars exceeds 72 inches, tie bars will be installed at an even spacing not to exceed 36 inches but shall not be installed within 12 inches of a transverse weakened plane joint. The Contractor shall submit to the Engineer a method for replacing the tie bars. The Contractor shall not proceed to replace the tie bars until the method for replacement has been approved by the Engineer.
2.Transverse Weakened Plane Joints . When dowel bars are specified in the Contract, they shall be installed within the tolerances and of the size, grade, and spacing specified. Dowel bars shall be furnished in a rigid welded assembly or placed by a dowel bar insertion (DBI) machine. The center of the dowel assembly or the insertion location shall be marked on both sides of the pavement slab for reference in sawing the joint. When a DBI is used, the Contractor shall submit details and specifications of the proposed slip- form paver and DBI to the Engineer a minimum of 14 calendar days before the Concrete Pavement Pre-paving Conference. The Contractor shall detail his methodology for ensuring correct marking of dowel bar insertion points and correct sawing of the joints. The Contractor shall ensure that the slip -form paver is compatible with the DBI. 412.13 412-9 When a rigid assembly (dowel basket) is used, the rigid assembly shall be fabricated from number 1/0 wire or heavier with vertical support wires every 1 foot. The rigid assembly shall be securely fastened to the subbase and constructed to firmly hold all t he dowel bars at T/2 depth, parallel to each other and to the pavement grade and alignment. Horizontal support wires or shipping braces shall be non - deformed bars or wires with a diameter less than or equal to 0.307 inches (gauge 0 wire). The number of h orizontal support wires or shipping braces shall be limited to five per rigid assembly. Shipping braces shall not be cut. The Contractor shall perform a pull test after baskets are staked. The minimum staking method will be determined using the pullout test. The pullout test shall be performed on all dowel baskets placed in a test section and one dowel basket per day thereafter when the minimum staking method is used. The test section for determining staking method shall be the first 10 joints with dowel baskets for each base type. Each dowel basket in the test section shall withstand a minimum of 25 pounds of force when p ulled vertically at three equally spaced locations along the length of the dowel basket using a fish scale, or approved equivalent. If any basket moves more than 0.5 inches, a new staking method and test section will be required. The use of the MIT Scan -2 will be used for joint acceptance. Joint acceptance or rejection will be based on the Joint Map generated by the MIT Scan software. Should the joint map show missing or misaligned bars the Contractor will have the choice of either performing additional testing using a method approved by the Engineer or perform corrective measures. Colorado Procedure 79 in the CDOT Field Materials Manual will be used to determine if dowel bars are misaligned or missing. Dowels in rigid assemblies will be inspected by the Engineer before concrete placement for misalignment and dowel bar depth. If misalignments and dowel bar depths exceeding the rejection tolerances are found, the rigid assembly shall be reset and re- inspected. The MIT Scan -2 shall be used for determining the depth of dow el bars placed by a DBI. See Standard Plan M -412-1 for schematic describing the measurement of each tolerance. Joint Rejection Criteria:
A.Any joint that does not have at least three acceptable dowel bars in each wheel path.
B.Rotational misalignment: Bars with misalignment greater than 1.5 inches.
C.Longitudinal ( side) shift: Bars that are not embedded at least 6 inches on each side of the joint (saw -cut).
D.Depth: Bars within the top 3 inches of the pavement or at a depth less than the saw - cut depth. Bars within the bottom 3 inches of the pavement. Corrective Measures: The following corrective measures will be allowed for the bars or joints that are rejected .
A.Rotational misalignment : Saw-cut the misaligned bars. Joints with less than three un- cut bars in each wheel path will require the addition of dowel bars using an approved dowel bar retrofit method.
B.Longitudina l (side) Shift and missing bars: Addition of dowel bars using an approved dowel bar retrofit method.
C.Depth: Inadequate cover above the bar —Saw-cut the bar and install a replacement bar using an approved dowel bar retrofit method. 412.13 412-10 Inadequate cover below the bar — Addition of dowel bars using an approved dowel bar retrofit method . Retrofitted dowel bars shall not exceed the dowel bar rejection criteria. In addition to the above procedures, the Contractor may propose removal and replacement of the affected slabs. The Contractor shall submit his method of repair to the Engineer for approval. The Contractor shall demonstrate his ability to place dowel bars in conformance with the specifications by placement of a test section. The test section shall be a minimum of 300 feet in length. Upon completion of the test section, the Contractor shall shut down paving operations. During the shutdown period, the Contractor shall evaluate all joints in the test section using the MIT -Scan-2 and CP- 79 and submit the results to the Engineer. Paving operations shall not be restarted until the Engineer approves the test section results. The test section will be found acceptable if 100 percent of the joints are found to be acceptable. All unacceptable joints must be addressed using the above corrective measures. The Contractor may continue paving at his own risk before the test section evaluation is complete. If the Project has less than 500 linear feet of pavement, the test section will not be required. If a Project does not have sections of continuous pavement greater than 45 linear feet, the test section will not be required. Upon completion of the test section(s) and for each week of production, the Contractor shall prepare an electronic report generated using MagnoProof software and submit it to the Engineer at the start of each working week during production , for the previous week’s work. The reports shall show the joint map generated by the MIT -Scan-2 and the joint pass/fail rating according to CP -79. When the test section is found to be unacceptable, the Contractor shall perform corrective actions and place a second test section. If the second test section is found to be unacceptable, the Contractor shall pave no more than 500 feet per day until an acceptable test section has been achieved. Once a test section is successfully completed, Dowel Bar Placement testing frequency shall be a minimum of one location per 1,250 linear feet of each continuous lane including climbing lanes, passing lanes, acceleration and deceleration lanes and ramps. Sections greater than 45 linear feet and less than 1,250 linear feet require a minimum one of test location. Testing locations shall be determined by a random procedure so that each area has a randomly selected transverse joint location. At each location, five consecutive joints shall be tested. Sections of continuous pavement constructed by the project less than 45 linear feet will not require Dowel Bar Placement Testing. When any joint exceeds the rejection criteria, joints shall be tested in each direction from the rejected joint, until two consecutive joints in each direction are found to be acceptable. All delays or costs associated with equipment being rejected for use by the Engineer will not be paid for by the Department and will be considered a Nonexcusable Delay 412.14 412-11 per subsection 108.08 (c) 2. When concrete shoulders or widenings are constructed subsequent to the driving lanes, transverse weakened plane joints shall immediately be formed in the plastic concrete of these widenings to create an extension of the existing transverse joint. This tool ed joint shall be formed in such a manner that it controls the cracking and shall be sawed and sealed per the above requirements.
c.Expansion Joints . Preformed joint filler expansion joints shall be constructed at all existing or proposed structures and features projecting through, into, or against the pavement and at other locations specified in the Contract.
412.14 Curing. Immediately after the finishing operations have been completed the entire
surface and exposed sides of the newly placed concrete, shall be sprayed uniformly with a curing compound meeting the requirements of ASTM C309, Type 2. The ASTM C309 Type 2 curing compound shall be volatile organic content (VOC ) compliant. The curing compound shall be applied within 10 minutes after the final finish has been applied. Failure to cover the surface of the concrete within 10 minutes shall be cause for immediate suspension of the paving operations. An initial application of curing compound shall be applied under pressure by mechanical sprayers at the rate of at least 1 gallon per 180 square feet of pavement surface. A second application of curing compound shall be applied within 30 minutes after the initial application. The second application rate shall be at least 1 gallon per 180 square feet of pavement surface. Alternatively, the Contractor may apply the curing compound in one application of at least 1 gallon per 120 square feet. Additional curing compound shall be applied as needed to ensure that 100 percent of the pavement is covered. The spraying equipment shall be fully automated, equipped with a tank agitator, and a wind guard. During application, the compound shall be in a thoroughly mixed condition with the pigment uniformly dispersed throughout the vehicle and the compound shall be stirred continuously by effective mechanical means. Hand spraying of irregular widths or shapes and surfaces exposed by removal of forms will be permitted. Curi ng compounds shall not be applied to the inside faces of joints to be sealed. Should the curing film become damaged from any cause, within 72 hours after concrete placement, except for concrete open to traffic, the damaged portions shall be repaired immediately with additional curing compound, payment for which shall be at the Contractor’s expense. The sides of pavement slabs shall be immediately sprayed with curing compound when the forms are removed.
412.15 Cold Weather Concrete Paving . The Contractor is responsible for the strength and
quality of the concrete placed during cold weather. Before starting paving operations, the Contractor shall be prepared to protect the concrete from freezing. Maturity meters, to monitor and record time and pavement temperature, shall be installed at the t ime of placement when the air temperature is expected to fall below 40 ˚F during the next three days or as requested by the Engineer when the air temperature is expected to fall below 45 ˚F during the ne xt three days. The Contractor shall maintain the temperature of the pavement at or above 40 ˚F until the pavement has attained a compressive strength of at least 2000 psi. The compressive strength of the concrete shall be determined by the use of maturity meters. Maturity meters shall be placed in three locations for each day’s concrete paving operations. One maturity meter shall be placed in the final 15 feet of paving, and the two other maturity meters shall be 412.16 412-12 placed at locations designated by the Engineer. The maturity meter probes shall be located on the outside edge of the slab, at least 1 foot and not more than 2 feet from the edge and at mid depth of the slab. Each maturity meter shall be capable of recording the time and temperature. The maturity meters shall remain in place until the concrete has attained a compressive strength of 2000 psi. The Contractor shall develop maturity relationships for each mix placed during the cold weather conditions described above per CP 69: The development of the maturity relationship is part of the trial mix and shall be submitted to the Engineer before cold weather concrete paving. The Contractor shall provide the maturity meters and all necessary wires and connectors. The Contractor shall be responsible for the placement, protection and maintenance of the maturity meters and wires. Locations where the maturity meters are placed shall be protected in the same manner as the rest of the concrete pavement. The following procedures shall be followed if the temperature of the concrete pavement falls below 32 °F before the concrete reaches 2 ,000 psi:
1.The Contractor will take cores at locations designated by the Engineer.
2.The Engineer will take immediate possession of the cores and submit the cores to a petrographer for examination per ASTM C856.
3.All costs associated with coring, transmittal of cores, and petrographic examination shall be borne by the Contractor regardless of the outcome of the petrographic examination.
4.Pavement damaged by frost as determined by the petrographic examination, shall be removed and replaced at the Contractor’s expense.
412.16 Repair of Defective Concrete Pavement . Defective concrete pavement shall be
repaired or replaced at the Contractor’s expense. This corrective work shall be accomplished before joint sealing and final smoothness measurement. Defective concrete pavement replaced after smoothness measurement shall be retested for localized roughness. The Contractor’s corrective work plan shall be approved before performing the work. When necessary, the extent of defects will be determined by the inspection of cores drilled at the Contractor’s expense. Crack depth shall be determined by taking one core at the center of the crack or as approved by the Engineer. The Contractor shall tak e the cores and supply to the Engineer immediately after the coring.
1.Pavement thickness (T) shall be as shown on the plans.
2.Pavement slabs with any of the following conditions are unacceptable and shall be removed and replaced:
A.Pavement slabs in driving lanes containing one or more cracks that are T/3 in depth or greater that separate the slab into two or more parts.
B.Pavement slabs in driving lanes containing one or more cracks that are 30 inches or greater in length and T/3 in depth or greater.
C.Pavement slabs containing honeycombed areas.
D.Pavement slabs containing an extreme void as defined below. 412.16 412-13 E. Pavement slabs containing more than one void greater in depth than half the pavement thickness.
F.Pavement slabs containing a cumulative surface area of moderate and severe voids, as defined below, greater than one percent of the slab’s total area.
G.Pavement slabs containing 20 or more severe voids as defined below. Voids are defects in a slab consisting of air pockets, clay balls, or foreign materials such as cans, rags, bottles, etc. Voids may also consist of clumps of sand, cement or reinforcing fibers caused by incomplete mixing. The defect will be considered a moderate voi d when the largest dimension, either height, width or length is at least 1/2 inch but not more than 2 inches. The defect will be considered a severe void when the largest dimension, either height, width or length is greater than 2 inches. The defect w ill be considered an extreme void when the largest dimension, either height, width or length is greater than the thickness of the pavement. When the Engineer determines that voids are at an unacceptable level, the paving shall stop, and the cause shall be identified and corrected by the Contractor before paving operations are allowed to resume. Concrete slabs that are determined by the Engineer to be acceptable if repaired shall have voids filled using materials from the Department’s Approved Products List and methods approved by the Engineer. When portions of concrete pavement are removed and replaced, the portion removed shall be the full width of the lane and length of the affected slab. Slabs with cracks penetrating the full depth of pavement shall be removed as required above. Cracks that are 30 inches or longer and are between 1 inch and T/3 in depth shall be repaired. The Contractor shall submit in writing a plan to repair the partial depth cracks for approval by the Engineer. The Engineer will have seven calendar days to review and approv e the Contractor’s repair plan in writing. Joints and cracks that are spalled shall be repaired as follows:
1.A saw cut at least 1 inch outside the spalled area and to a minimum depth of T/3 shall be made parallel to the joint or crack.
2.The concrete between the saw cut and the joint or crack shall be chipped out to solid concrete to a minimum depth of T/3.
3.The cavity formed shall be thoroughly cleaned.
4.A prime coat of epoxy -resin binder shall be applied to the dry, cleaned surface on all sides of the cavity, except the face of the joint. The prime coat shall be applied by scrubbing prime coat material into the surface with a stiff bristle brush.
5.Placement of portland cement concrete or epoxy -resin concrete shall immediately follow the application of the prime coat. If the spalled area, to be repaired, abuts a working joint or a working crack that penetrates the full depth of the pavement, an insert or other bond -breaking medium shall be used to maintain the working joint or crack during the repair work. If concrete paving exhibits the above defects for two or more days, production will be suspended. The Contractor shall submit a written plan to correct these defects. The plan shall detail, at a minimum , changes in paving procedures, materials and 412.17 412-14 equipment required to construct concrete pavement that meets the specifications. The Engineer will approve the Contractor’s plan before the continuation of the concrete paving operation.
412.17 Surface Smoothness. The roadway surface smoothness shall be tested per
subsection 105.07.
412.18 Sealing joints. Before installation of the backer rod or sealant, the following shall
be completed:
1.Repair of defective pavement slabs and repair and proper curing of cracks or spalls per subsection 412.16.
2.Corrective work for texturing.
3.Corrective work for pavement smoothness per subsection 105.07. A copy of the manufacturer’s recommendations pertaining to the storage, heating and application of the sealant shall be submitted to the Engineer before commencing work. These recommendations shall be adhered to by the Contractor , with such exceptions as required by these specifications. The Contractor shall cut the transverse and longitudinal joints to the width and depth required. The cut shall be made with a power drive saw equipped with diamond blades. The residue from sawing shall be removed from the pavement by the Contractor. The material shall be removed at the time of the sawing operation. Any damage to the concrete pavement such as spalling or fracturing shall be repaired by the Contractor as directed by the Engineer at no cost to the project. Sawing residue shall be immediat ely removed from all joints. Cleaning, repairing, and proper curing of all spalls, fractures, breaks, and voids in the concrete surface of the joints shall be accomplished before installing the backer rod material or joint sealant. The backer rod shall be placed in such a manner that the grade for the proper depth of the seal material is maintained. The Contractor shall thoroughly clean the joint and adjacent pavement for a width of at least 1 inch on each side of the joint of all scale, dirt, dust, residue, and other foreign material that will prevent bonding of the joint sealant. This operation is t o be accomplished by sandblasting or jet water -blasting on the same day as the joint sealing operation. Immediately before the placement of backer rod material and sealant, the joints shall be cleaned using a minimum of 100 psi of compressed air. Work shall be stopped when and if it is found that there is oil or moisture in the compressed air. Work shall not resume until oil and moisture are removed from the compressed air. Sealant shall not be placed unless the surfaces of the joint and the pavement are dry, and the weather is dry. Joint sealing will not be allowed when the air or surface temperature falls below 50 °F . Manufacturer’s recommendations shall be followed if a higher temperature is recommended. Sealant shall not be placed before expiration of the sealant manufacturer’s recommended concrete pavement curing period, if any. 412.19 412-15 The Contractor shall not place the sealant if there is dust, moisture, oil, or foreign material on that portion of the concrete that is to receive the backer rod or sealant. The Contractor shall prevent smearing of the joint sealant material onto the concrete pavement driving surface. Smeared joint sealant shall be removed from the pavement before it is opened to traffic. Sealing shall be completed before opening the pavement to traffic, unless otherwise specified or approved.
412.19 Construction by Form Method . Straight side forms shall be made of a metal having a
thickness of at least 7/32 inch and shall be furnished in sections at least 10 feet in length. Forms shall have a depth equal to or greater than the specified edge thickness of the concrete, without horizontal joint, and a base width equal to or greater than the depth of the forms. Top surface of the forms shall be set flush with the proposed concrete surface. Flexible or curved forms of proper radius shall be used for curves of 100 feet radius or less . Flexible or curved forms shall be of a design acceptable to the Engineer. Forms shall be provided with adequate devices for secure setting so that when in place they will withstand, without visible spring or settlement, the impact and vibration of the co nsolidating and finishing equipment. Flange braces shall extend outward on the base at least ⅔ the height of the form. Forms with battered top surfaces, and forms that are bent, twisted, or broken shall not be used. Repaired forms shall not be used until inspected and approved. Built -up forms shall not be used except where the total area of the pav ement, of any specified thickness, on the project is less than 2 ,000 square yards. The top face of the form shall not vary from a true plane by more than 1/8 inch in 10 feet, and the vertical leg shall not vary more than 1/4 inch from vertical. The forms s hall contain provisions for locking the ends of abutting form sections together tightly, and for secure setting. Forms for bridge approach slabs or for pavement areas with irregular dimensions shall be made of metal or straight, sound timber. Forms shall be free from warp and of sufficient strength to resist springing out of shape. Forms shall be staked securely to line and grade to the sati sfaction of the Engineer. All mortar and dirt shall be removed from the forms.
a.Setting Forms . The foundation under the forms shall be compacted true to grade so that the form, when set, will be firmly in contact for its whole length and at the specified grade. The roadbed shall be prepared per subsection 412.08; however, where the grade at the form line is found to be below specified grade it shall be filled and thoroughly compacted to specified grade with granular material in lifts of 1/2 inch or less. Imperfections or variations above grade shall be corrected by tamping or by trimming as necessary. Forms shall be set sufficiently in advance of concrete placement to provide time for the Engineer to check the line and grade and allow a continuous concrete placement operation. Forms shall be staked in place and free from play or movement in any directio n. The forms shall not deviate from true line by more than 1/4 inch at any point. No excessive settlement or springing of the forms under the finish machine will be tolerated. Forms shall be cleaned and coated with a form release agent or oiled before placement of concrete. The alignment and grade elevations of the forms shall be checked, and corrections made by the Contractor immediately before concrete placement. When any form has been disturbed or any grade has become unstable, the form shall be reset and rechecked. 412.20 412-16 (b) Removing Forms . Unless otherwise provided, forms shall not be removed from freshly placed concrete until the concrete is strong enough to withstand damage when the forms are removed. After the forms have been removed, the sides of the slab shall be cured per subsection 412.14.
412.20 Construction by Slip Form Method . The subgrade shall be completed per
subsection 412.08 and then checked and approved by the Engineer before installation of load transfer units, if required, and placement of concrete. Concrete shall not be placed on a subgrade that has not been approved. If any traffic uses the finished subg rade, the grade shall be checked and corrected immediately before placement of the concrete. The concrete shall be finished with an approved, self -propelled slip form paver capable of spreading, consolidating, screeding, and finishing the freshly placed concrete with one pass of the paver. The paver shall be capable of providing a dense and homogeneous pavement with an even texture and no porous areas, and to the slope and elevation specified. The alignment and elevation of the paver shall be automatically controlled from outside reference lines established to obtain a smooth alignment and profile. For mainline paving of Pavement Smoothness Category I roadways, as defined in Table 105 -14 all slip form paving shall be accomplished by a machine capable of paving at least a 24 feet minimum width as recommended by the equipment manufacturer.
a.Stabilized Bases . The Contractor is responsible for irregularities in the stabilized base and payment will not be made for overruns in concrete quantities if extra concrete is used to correct the irregularities.
b.Concrete Pavement Overlays. Trimming will not be required. The Contractor shall place a bond breaker, if specified in the Contract, before placing the concrete. Payment will be made for irregularities under pay item of Furnish Concrete Pavement. The Contractor shall furnish a machine to develop and establish a profile grade for the new pavement. The method used will be by dual slope laser mounted on a 30 -foot ski. The Engineer may approve an alternative method of establishing the profile grade, if the Contractor demonstrates that equal or superior results will be achieved by the alternative method.
412.21 Determining Pavement Thickness. Pavement thickness will be determined by
cores or magnetic pulse induction (MPI). The Contractor shall select the pavement thickness determination method at the Pre- paving Conference.
a.Pavement Thickness Using Cores. The Contractor shall perform the process control (PC ) testing for pavement thickness. A process control testing plan shall be submitted and must be approved before the start of paving. This PC testing plan shall include determining the thickness of freshly finished concrete pavement at a minimum frequency of one measurement per 1 ,250 linear feet of each traffic lane. All shoulders 8 feet or greater in width shall be tested as a separate traffic lane. Shoulders less than 8 feet wide shall be included in the adjacent lane. Areas such as sections of mainline pavement that are less tha n 1,250 linear feet long, intersect ions, entrances, crossovers, ramps, shall be grouped into units of 1 ,000 square feet or remaining fraction. A minimum of one random measurement shall be taken in each unit. The Engineer may inspect the Contractor’s PC tests at any time during the paving operations. Approval and inspection of the Contractor’s PC plan and operations does not 412.21 412-17 constitute acceptance of the pavement thickness and does not relieve the Contractor of the responsibility for providing the required hardened pavement cores for project acceptance testing. The Contractor shall provide daily written reports to the Engineer listing the results of the day’s PC thickness measu rements. Project acceptance (PA ) testing will be the responsibility of the Engineer. PA testing consists of determining pavement thickness by measuring the length of cores taken by the Contractor from the hardened pavement as outlined below. Acceptance of the pavement thickness and price adjustme nt for deficient thickness will be based on project acceptance tests. The Engineer will designate the time and location of the coring and will be present during the coring operation. The Contractor shall obtain 4 -inch or 6-inch nominal diameter cores from the hardened pavement that are suitable for measuring per AASHTO T148. When the cores are removed from the pavement, the Engineer will take possession and determine their length per AASHTO T148. The lower tolerance limit (TL ) for pavement thickness shall be Plan Thickness (PT) minus 0.4 inches. This TL shall be used in the formulas in Section 105 for Incentive and Disincentive Payments (I/DP ), Quality Levels (QL) and Pay Factor (PF ) determinations. Any pavement thickness test value that exceeds the PT by more than 1.0 inch shall be assigned a value of PT plus 1.0 inch for the purpose of calculating the QL, PF and I/DP . Core locations shall be determined by a random procedure so that each area has a randomly selected coring location. One core will be taken at each location. Where the new portland cement concrete pavement (PCCP) overlays an existing roadway, cores for measuring pavement thickness shall be determined by a stratified random procedure in the longitudinal direction and by the point of minimum required thickness in the lateral direction as shown in the plans. If exist ing field conditions show a condition where the point of minimum thickness in the lateral direction as shown in the plans is not appropriate, the Contractor shall identify the location and extent of th e area to the Engineer at least 24 hours before paving. The Engineer may exclude this area from pavement thickness measurements for incentive and disincentive payments. Pavement thickness tests will be evaluated per subsection 105.06. Additional cores will be taken at the direction of the Engineer as follows:
1.One additional core at the location of each PC or PA test that is less than PT minus 1.0 inch.
2.If the length of the additional core is greater than PT minus 1.0 inch, no additional actions will be taken, and the PA test core will be used to compute I/DP for the process that includes this material.
3.If the length of the additional core is less than PT minus 1.0 inch, the area represented by this core shall become a separate process and this core will not be used to compute an I / D P. Exploratory cores shall be taken at intervals of 15 feet or less, parallel to the centerline in each direction from the affected location until two consecutive cores are found in each direction which are not less than PT minus 1.0 inch. Four additional randomly selected cores will be taken within the area represented by these cores. The four additional cores will be used to compute an I/DP per Section 105. Cores taken at locations not randomly determined, such as process control cores will not be used to compute I/DP . 412.21 412-18 Pavement areas found to be less than PT minus 1.0 inch shall be removed and replaced at the Contractor’s expense. When the removal and replacement have been completed, four additional randomly selected cores will be taken within the area represented by this core. The four additional cores will be used to compute an I/DP per subsection 105.06. Exploratory cores will not be used to compute I/DP . The Contractor shall repair all core holes by filling them with an approved nonshrink high strength grout.
b.Pavement Thickness Using MPI. The Contractor shall perform the process control (PC) testing for pavement thickness using MPI. A process control testing plan shall be submitted and must be approved before the start of paving. This PC testing plan shall include determining the thickness of hardened concrete pavement at a minimum frequency of one measurement per 1,250 linear feet of each traffic lane. All shoulders 8 feet or greater in width shall be tested as a separate traffic lane. Shoulders less than 8 feet wide shall be included in the adjacent lane. Areas such as sections of mainline pavement that are less than 1,250 linear feet long, intersections, entrances, crossovers, ramps, etc., shall be grouped into units of 1,000 square feet or remaining fraction thereof. A minimum of one random measurement shall be taken in each unit. The Contractor’s PC test results using MPI for pavement thickness will be used for Project Acceptance (PA) and used to calculate I/DP. PC testing will be witnessed by the Engineer. The MPI results will be considered acceptable when the range of the three individual scans is less than or equal to 0.10 inches. If the three scans are not within 0.10 inches, a second set of three scans shall be taken. The three new scans will be consid ered acceptable when the range of the three individual scans is less than or equal to 0.10 inches. If the second set of three scans are not within 0.10 inches, the MPI for this location will not be used. A MPI test will be the result of the average of a set of three acceptable scans at a location. The average of the set of three scans shall be rounded to the nearest 0.04 inches. If a MPI location is unable to obtain three acceptable scans, a core shall be taken and used for thickness determination and I /DP. A test section shall be conducted to verify the calibration and correlation of the MPI pavement thickness determination at the start of PCCP operations. The test section correlation shall be established in the first 7,500 square yards of PCCP per a stratif ied random sampling schedule as established in CP 75. The test section correlation verification shall consist of conducting ten pavement thickness measurements by taking a core at the MPI test locations. The Contractor shall obtain 4-inch nominal diameter cores from the hardened pavement that are suitable for measuring per AASHTO T148. When the cores are removed from the pavement the Contractor shall determine their length and then the Engineer will take possession and determine their length per AASHTO T148. A verification must be run for each MPI device used on the project. The verification of any MPI device can be run at the initial verification locations. The comparison of the PC MPI measurements and hardened concrete cores shall be within 0.15 inc hes to be considered a valid correlation between the tw o test methods. 412.21 412-19 After successful completion of the thickness measurement correlation verification process, a minimum of one hardened concrete core will be taken for every 25 MPI thickness measurements for core thickness determination. When a change in thickness or process occurs, the first three MPI location shall be cored for thickness. At a minimum, one MPI test location will be cored for thickness for each pavement thickness process, or as directed by the Engineer. A core may be taken when the MPI result is in doubt. The correlation between core and MPI thickness measurements shall be verified to be within 0.15 inches at the same location. If the thickness difference between the methods exceeds 0.15 inches, the next five MPI locations will be cored. If the thicknes s difference between the two methods exceeds 0.15 inches on any location the contractor shall use the coring method for acceptance until the MPI is repaired or replaced and verified. Previous MPI locations shall be cored until three successive thickness d ifferences between the two methods is equal to or less than 0.15 inches. If the MPI device is not able to be repaired or replaced within 10,000 sq yd of paving, the acceptance method will revert to coring acceptance from the last acceptable MPI measuremen t. A new process for pavement thickness will be started for the change in method of measurement. The lower tolerance limit (TL) for pavement thickness shall be Plan Thickness (PT) minus 0.4 inches. This TL shall be used in the formulas in Section 105 for Incentive and Disincentive Payments (I/DP), Quality Levels (QL) and Pay Factor (PF) determinations. Any pavement thickness test value that exceeds the PT by more than 1.0 inch shall be assigned a value of PT +1.0 inch for the purpose of calculating the QL, PF and I/DP. MPI test locations shall be determined by a random procedure so that each area has a randomly selected coring location. A MPI test plate will be installed before paving. The location of the MPI test plate shall be at least 4 feet from any dowel bar locations, tie bar location and utility box cover locations. The operator of the MPI device should use composite safety boots to not interfere with the device. Where the new PCCP overlays an existing roadway, MPI test locations shall be determined by a stratified random procedure in the longitudinal direction and by the point of minimum required thickness in the lateral direction as shown in the plans. If existing field conditions show a condition where the point of minimum thickness in the lateral direction as shown in the plans is not appropriate, the Contractor shall identify the location and extent of the area to the Engineer at least 24 hours before paving. The Engineer may exclude this area from pavement thickness measurements for incentive and disincentive payments. Pavement thickness tests will be evaluated per subsection 105.06. Additional cores will be taken at the direction of the Engineer at the contractor’s expense as follows: One additional core at the location of each process control (PC) test that is less than PT minus 1.0 Inch.
1.If the length of the additional core is greater than PT minus 1.0 inch, no additional actions will be taken, and the core test result will replace the MPI result to compute I/DP 412.22 412-20 (2) If the length of the additional core is less than PT minus 1.0 inch the area represented by this PC test shall become a separate process and will not be used to compute an I/DP. The thickness of the pavement in this area will be determined by taking cores. Cores shall be taken at intervals of 15 feet or less, parallel to the centerline in each direction from this location until two consecutive cores are found in each direction which are not less than PT minus 1.0 inch. The pavement found to be less than PT minus 1.0 inch shall be removed and replaced at the Contractor’s expense. When the removal and replacement have been completed, four additional randomly selected cores will be taken within the area represented by this core. The four additional cores will be used to compute an I/DP per subsection 105.06. The Contractor shall repair all core holes by filling them with an approved non-shrink high-strength grout.
412.22 Opening to Traffic . The pavement shall not be opened to traffic until the concrete
has achieved a compressive strength of 3 ,000 psi. Concrete compressive strength shall be determined by maturity meters . Before opening the pavement to traffic the roadway shall be cleaned, as approved. Before placement of concrete whose strength will be determined with maturity meters, the Contractor shall provide the Engineer a report of maturity relationships per CP 69. The Contractor shall provide maturity meters and all necessary wires and connectors. The Contractor shall be responsible for the placement and maintenance of the maturity meters and wires. At a minimum a maturity meter will be placed once per day and then once per 5,000 square yards. Placement shall be as directed by the Engineer. For placements with multiple maturity meters, the lowest compressive strength shall determine when the pavement may be opened to traffic. If a maturity meter fails, is tampered with, is destroyed or was not placed, the section of pavement represented by the maturity meter shall remain closed to traffic for a period of 28 days. The Contractor may choose at his own expense to core the section of pavement represented by the maturity meter. Cores will be obtained and tested according to CP 65. Cores will be a minimum of 4 inches in diameter. A minimum of three cores in a two square foot area will be obtained. If the compressive strength of a ny one core differs from the average by more than 10 percent that compressive strength will be deleted and the average strength will be determined using the compressive strength of the remaining two cores. If the compressive strength of more than one core differs from the average by more than 10 percent, the average strength will be determined using all three compressive strengths of the cores. To open the section of pavement, the average compressive strength of the cores shall be a minimum of 3,000 psi. METHOD OF MEASUREMENT
412.23 The quantities of Concrete Pavement, and Place Concrete Pavement to be paid for
under these items will be the number of square yards completed and accepted. The width for measurement will be the width of the pavement shown on the typical cross section of the plans, including additional widening where called for, or as otherwise direct ed by the Engineer in writing. The length will be measured horizontally along the centerline of each roadway or ramp. 412.24 412-21 The quantity of Furnish Concrete Pavement to be paid for under this item will be the number of cubic yards of concrete delivered and accepted. The concrete volume will be based on batch weights of the concrete converted to volumes by use of the conversion factor developed with the specific mix design. Quantities of concrete that are wasted, spilled, or used as a result of excessive thickness shall be deducted from the pay quantity. Excessive thickness shall be considered any thickness in excess of 1/2 inch greater than the specified depth that continues for a length of 200 feet or more. Yield shall be determined per AASHTO T 121. Where concrete is paid for by cubic yard batched, the pay quantities for all concrete produced with a relative yield less than 0.99 shall be corrected per the following formula: Corrected cubic yards = (cubic yards batched) • (relative yield) Reinforcement other than dowels, tie bars, and other joint material will be measured by the pound. BASIS OF PAYMENT
412.24 General. The accepted quantities will be paid for at the contract unit price for each of
the pay items listed below that appear in the bid schedule. Payment will be made under: Pay Item Pay Unit Concrete Pavement ( Inch) Square Yard Place Concrete Pavement Square Yard Furnish Concrete Pavement Cubic Yard The price per square yard of Concrete Pavement shall be full compensation for furnishing and placing all materials, including dowels, tie bars, joint materials, texturing, sawing, finishing, and rumble strips. The price per square yard for Place Concrete Pavement shall include everything included in the pay item, Concrete Pavement, except furnishing concrete. The price per Cubic Yard for Furnish Concrete Pavement shall be full compensation for furnishing the concrete to the project site. Reinforcing steel will be measured and paid for per Section 602. Furnishing, installing, and monitoring vibrators and vibrator monitoring device will not be measured and paid for separately, but shall be included in the work for concrete pavement. Incentive and Disincentive Payments (I/DP) will not be made on interim estimates. I/DP will be made when the concrete pavement or a major phase of the concrete pavement has been completed and all the data for computing the I/DP is available. Furnishing, calibrating and use of maturity meters, wire and other appurtenances including the molding, curing and breaking of cylinders for calibration and placement of calibration slabs will not be measured and paid for separately, but shall be included in the work. All costs associated with developing correlation curves used to evaluate low flexural strength results per the Contract, or as requested by the Engineer, shall be included in the work. This shall include all materials, forms, testing, equipment and labor. 412.25 412-22 (a) Where the pavement thickness is more than Plan Thickness (PT) minus 1.0 inch, I/DP for the element of pavement thickness will be applied to the contract unit price per subsections 105.06 and 412.21. I/DP for other elements will be applied to the contract unit per Section 105. Adjustments in payment because of deviations in air content will be per subsection 601.17 using $100 per cu. yd. for the unit bid price. DESCRIPTION
412.25 Cross Stitching . This work consists of cross stitching longitudinal cracks and joints
by directionally drilling holes in concrete pavement, injecting grout, and inserting deformed steel reinforcing bars per these specifications and the details shown on the plans. Cross stitching shall not be used for thin concrete overlays (8 inches or less). MATERIALS
412.26 Materials for cross stitching shall be #6 or #8 deformed steel reinforcing bars, grade
60, epoxy coated, with length as specified on the plans. Epoxy or cementitious grout shall be on the Department’s Approved Products List. The epoxy shall be either an epoxy or polyester resin. The epoxy or cementitious grout shall be submitted to the Engineer for approval at least five working days in advance of the commencement of cross stitching work.
412.27 Placement. Directionally drilled holes shall be 1.000 to 1.125- inch diameter for #6
bars and 1.125 to 1.375- inch diameter for #8 bars and drilled at an angle from the horizontal designated on the plans. Holes shall be started at a distance shown on the plans on a line perpendicular to the crack/ joint and shall extend through the crack/joint. Drilled holes shall be spaced on 20 -inch centers and shall alternate from side to side along the full length of the crack/joint. Holes shall not be drilled within 24 inches of an existing transverse joint. Holes shall not extend through the bottom of the slab. Drilled holes shall be blown free of drill dust, dirt, and moisture with oil and moisture -free compressed air immediately before placing the grout. Holes shall be filled with epoxy/grout by injecting from the bottom of the hole. The Contractor shall insert the tie bar and remove excess epoxy/grout and finish flush with the pavement surface. Pavement may be opened to traffic when the epoxy/grout is dry to the touch .
412.28 Equipment . The drill for boring the cross stitch holes shall be selected to minimize
damage to the concrete surface. The drill shall be capable of low -impact operation in order to minimize spalling damage and prevent bottom breakout of the concrete pavement. The drill shall be skid or frame mounted. Handheld drilling will not be allowed. The first ten holes shall be visually inspected to determine if the bottom of the slab has broken out and measured for length of minimum embedment. Installation of the tie bars and epoxy shall not occur until the Contractor ’s drilling method has been inspected and approved. After the Contractor’s method has been approved, the Contractor may proceed with cross stitching so long as the method and equipment remain the same. 412.29 412-23 Drill bit changes do not require re- inspection. If the Contractor’s method or equipment changes, the first 10 holes made with the new method shall be visually inspected to determine if the bottom of the slab has broken out and measured for length of minimum embedment. BASIS OF PAYMENT
412.29 Cross stitching will be measured for payment by the number of cross stitches placed.
Payment will be made under: Pay Item Pay Unit Cross Stitching Each The accepted quantity of drilled holes, filled with epoxy/grout and reinforcing bars will be paid for at the contract unit price per each hole drilled. Payment for deformed bars, grout, labor , materials, equipment, tools and incidentals necessary for completion of the work will not be measured and paid for separately but shall be included in the work. DESCRIPTION
412.30 Slot Stitching . This work consists of installing tie bars across cracks in concrete
pavement per these specifications and the details shown on the plans. Slot stitching shall not be used for thin concrete overlays (4 inches or less). MATERIALS
412.31 Concrete patching material to be used as backfill shall be a product on the
Department’s Approved Products List. Concrete patching material shall attain an average compressive strength of at least 4,500 psi at 24 hours. Concrete patching material compressive strengths shall be tested according to ASTM C39 or ASTM C109. Concrete patching material shall provide a minimum bond strength of 1,000 psi at 24 hours, as tested by ASTM C882. Concrete patching material shall have a relative durability factor gre ater than 90 as tested by ASTM C666 method A. Concrete patching material shall have a maximum shrinkage of 0.13 percent at four days as tested by ASTM C157. Steel tie bars shall be 18 inches long #6 deformed steel tie bars, grade 60, and epoxy coated. CONSTRUCTION REQUIREMENTS
412.32 Slot Formation . Slots shall be made from multiple saw cuts made with a diamond
impregnated saw blade to a depth as shown on the plans. Slots shall be approximately perpendicular to the general trend of the crack. Slots shall be 1.75 to 2.25 inches wide. Lightweight jackhammers weighing less than 35 pounds or hand tools shall be use d to remove the “fins” formed by sawing. The length of the slot shall allow the tie bar to be placed at the mid-depth of the slab with a 1 -inch space between the ends of the tie bar and the ends of the slot. Deviations from this method require a method statement detailing the means and methods for how the Contractor will perform the work. The Contractor shall demonstrate slot stitching work for approval using the proposed equipment and procedures. The first five slots shall be visually inspected for bottom of the slab breakouts and minimum dimensions. Installation of tie bars and concrete patching 412.33 412-24 material shall not occur until the Contractor’s method has been inspected and approved. After the Contractor’s method has been approved, the Contractor shall proceed with slot stitching as long as the method and equipment remain the same. Saw blade chang es do not require re- inspection. If the Contractor’s method or equipment changes, the first five slots of the new method shall be visually inspected for bottom of the slab breakouts and measured for minimum dimensions. Tie bars shall be provided at locat ions and spacing as detailed on the plans. Damages to the concrete pavement caused by the Contractor’s operations shall be repaired at the Contractor’s expense. Slots shall be sand blasted or water blasted to remove saw slurry and blow n clean with high pressure oil -free air to remove sand, water, and dust. Tie bars shall be placed on support chairs to rest horizontal at the mid -depth of the slab. Concrete patching material mixing, placement, placement during cold temperatures, consolidation, and curing shall be per the manufacturer’s recommendations. A mix may be extended with aggregate per the manufacturer’s recommendations up to 90 percent of the manufacturer’s maximum extension. The maximum aggregate size shall be 3/8 inch for the extending aggregate. Patching material shall be placed and consolidated in the slot. Patching material shall fill the space under and around the bar. Tie bars shall not be dislodged or moved out of position. The surface of the concrete patching material shall be level with the adjacent pavement.
412.33 Opening to Traffic. The pavement shall not be opened to traffic until all tie bars
have been installed at a joint and the concrete has obtained a minimum compressive strength of 3,000 psi. Pavement shall be cleaned before opening to traffic. METHOD OF MEASUREMENT
412.34 Method of Measurement. Slot stitching will be measured for each completed and
accepted tie bar complete in place. BASIS OF PAYMENT
412.35 The accepted quantities will be paid for at the contract unit price for the pay
item listed below. Payment will be made under: Pay Item Pay Unit Slot Stitching Each The work performed and materials furnished per this item will be paid for at the unit price bid. This price is full compensation for furnishing all materials, tools, labor, equipment and incidentals necessary to complete the work. Payment will not be made for extra work required to repair damage to the adjacent pavement that occurs during slot stitching. 412.36 412-25 DESCRIPTION
412.36 Dowel Bar Retrofit. This work consists of placing epoxy coated smooth dowel bars in
transverse joints as identified on the plans. This shall be done by cutting slots into the existing concrete pavement, installing dowel bars, and filling the slots at locations as shown on the plans. The surface shall be finished as approved by the Engineer. All work, including the concrete pavement slot preparation, inserting dowel bars, filling the slot with backfill material, and finishing the surface shall be performed per these specifica tions and the details shown on the plans. MATERIALS
412.37 Materials for dowel bars shall meet the requirements in subsection 709.03. Dowels
shall be equipped with tight fitting, non- metallic end caps to allow 1/4- inch bar movement. Concrete patching material to be used as backfill shall be a product on the CDOT Approved Products List. Concrete patching material shall attain an average compressive strength of at least 4,500 psi at 24 hours. Concrete patching material compressive strengths shall be tested according to ASTM C39 or ASTM C109. Concrete patching material shall provide a minimum bond strength of 1,000 psi at 24 hours , as tested by ASTM C882. Concrete patching material shall have a relative durability factor greater than 90 as tested by ASTM C666 method A. Concrete patching material shall have a maximum shrinkage of 0.13 percent at four days as tested by ASTM C157. The proposed material shall be submitted to the Engineer for approval at least five days in advance of the start of dowel bar placement. Installation of dowel bars shall not begin until approval has been received in writing from the Engineer. CONSTRUCTION REQUIREMENTS
412.38 Slots for dowel bars shall be cut perpendicular to the transverse joint as shown on the
plans by using a slot cutting machine or walk -behind saw. Slots shall be of adequate length and width to accommodate the dowel bar, as shown on the plans or as directed. The concrete in the slot shall be removed by using a lightweight jackhammer weighing a maximum of 30 pounds, or hand tools, to half slab depth. All damage to the concrete slab outside of the slot shall be repaired or replaced at the Contractor’s expense. Slots shall be placed at locations shown on the plans. Slots shall be removed of all debris and cleaned before placement of dowel bars by sandblasting or other procedure so that clean aggregate is exposed. Before placement of backfill material, each dowel bar shall be equipped with a 1/4- to 3/8- inch-thick foam core board to provide a tight seal at the joint. Dowels shall be placed on chairs so that the bar is sitting a minimum of 1/2 inch above the bottom of slot and perpendicular to the transverse joint. The chairs shall be epoxy -coated steel or plastic rigid enough to hold the dowel in place during grout placement. The existing transverse joints shall be sealed with an approved joint sealant along the bottom and sides of the slot to prevent backfill material from infiltrating the joint. The joint sealant material shall be on the CDOT Approved Products list and shall be approved by the Engineer before use. Backfill material to be placed shall be mixed according to the manufacturer’s recommendations. Once in the slot, the material shall be vibrated thoroughly so that the entire bar is encased with the consolidated material. The slot shall be slightly overfill ed, and the area shall be diamond ground once the material has cured to provide a smooth pavement surface. 412.39 412-26 After grinding, transverse joints shall be sawed and sealed per subsection 412.18.
412.39 Opening to Traffic. The pavement shall not be opened to traffic until all dowel
bars have been installed at a joint and the concrete has obtained a minimum compressive strength of 3,000 psi. Pavement shall be cleaned before opening to traffic. METHOD OF MEASUREMENT
412.40 Dowel bar retrofit in concrete pavement will be measured as the actual number of
dowel bars placed and accepted. BASIS OF PAYMENT
412.41 The accepted quantities will be paid for at the contract unit price for the pay item
listed below. Payment will be made under: Pay Item Pay Unit Concrete Pavement Dowel Bar Retrofit Each The accepted quantity of dowel bar slots cut, filled with accepted patching material, and dowel bars will be paid for at the contract unit price per each bar installed. Payment for cutting slots, support chairs, joint sealant, patching, and all labor, mate rials, equipment, tools and incidentals necessary for completion of the work will not be measured and paid for separately but shall be included in the work. Payment will not be made for extra work required to repair damage to the adjacent pavement that occurs during dowel bar retrofitting. 420.01 420-1 SECTION 420 GEOSYNTHETICS DESCRIPTION
420.01 This work consists of furnishing and installing geotextiles and geomembranes for
paving, impervious lining, erosion control, drainage, separators and landscape weed barrier. MATERIALS
420.02 Geotextiles and geomembranes shall meet the applicable requirements of subsections
712.07 and 712.08 for the use intended. Geotextiles for erosion control for drainage or for
separators may be Class 1, Class 2, or Class 3, conforming to subsection 712.08, if the class is not specified on the plans. Asphalt cement binder for the paving geotextile shall be the same grade as the asphalt cement used for Item 403. Paving geotextile shall be a minimum Class 3, conforming to subsection 712.08. CONSTRUCTION REQUIREMENTS
420.03 Areas where the geosynthetic is to be placed shall have a uniform slope, be
reasonably smooth, free from mounds and windrows, and free of any debris or projections that could damage the material. Riprap or cobbles placed on the geosynthetic shall not be dropped from a free fall greater than 3 feet. The cushion layer or initial layer of riprap may require careful placement without free fall to avoid geosynthetic damage. Geosynthetics damaged or displaced before or d uring placement of overlying layers shall be replaced or repaired per the requirements of this section and to the satisfaction of the Engineer, at the Contractor’s expense.
420.04 Paving. The areas to be treated shall be as designated on the plans. The pavement
surface shall be broomed clean immediately before beginning the crack reduction geotextile treatment using a self -propelled power broom. The asphalt cement binder shall be applied to the pavement surface at the rate of approximately 0.25 gallon per square yard. The exact application rate shall be as recommended by the geotextile manufacturer, and at a temperature of 300 to 350 °F . Paving geotextile shall be applied, per the manufacturer’s recommendations, immediately after the application of asphalt cement binder. Construction equipment, including dump trucks, shall not make sudden stops or starts or sharp turning movements on the geotextile. Dump trucks shall not park on the geotextile before dumping into the asphalt paver. Traffic shall be kept off all newly placed binder and geotextile material until the asphalt surface has been placed. The minimum temperature of the hot mix asphalt at the time compaction begins shall be 250 ° F.
Source: Colorado Standard Specifications for Road and Bridge Construction, 2023 Edition. Pages 379–404 of 943.