for Highway Construction Page 710 of 71 5 SECTION 720 – MISCELLANEOUS
720.01 Water for Concrete, Grout, and Mortar .
The Contractor may use water from municipal drinking water supplies for concrete, grout , or mortar . The Contractor may use water from other sources, provided it is reasonably clear without oil, contains less than 1,000 parts per million of chlorides and less than 1,000 parts per million of sulfates in accordance with ASTM C1602. If a water source other than a municipal drinking water supply is proposed, submit independent laboratory test reports verifying compliance with these chemical requirements. Submit reports that are less than 2 years old before using a nonmunici pal drinking water supply.
720.02 Elastomeric Bearings .
720.03 PTFE Bridge Bearing Pads .
Provide PTFE pads and stainless steel mating surface where specified that meet A ASHTO Specifications for Highway Bridges. If filled PTFE sheet is used, only glass -fiber filler will be approved.
720.04 Epoxy -Resin -Base Bonding Systems for Concrete .
Meet ASTM C881 with the classification (type and grade) of the system selected as specified. The Contractor and the Contractor’s supplier, with approval, will determine the class after work conditi ons have been for Highway Construction Page 711 of 715 established. Provide materials and applications that meet applicable ACI Standards 503.1, 503.2, 503.3, or 503.4. Submit the manufacturer’s certification verifying compliance to material specifications.
720.05 Recycled G lass.
Provide recycled glass , whole bottles or crushed glass, for use in roadway fills, and crushed glass for use in granular borrow , granular subbase, or aggregate base meeting the requirements of AASHTO M 318. Certify in writing the glass is from a waste stream generated in Idaho.
720.06 Hydrat ed Lime .
Provide hydrated lime as follows:
720.07 Recycled Asphalt Pavement (RAP).
Prepare and maintain a RAP processing and stockpiling quality control plan and make these records available to the Department.
720.08 Glass Beads Used in Pavement Markin gs.
Glass beads used in pavement markings will be tested in accordance with Federal Specification TT -B-1325. Provide glass beads meeting AASHTO M 247, Type I and as follows:
720.09 Fibrillated Fiber
Fibrillated fiber must comply with ASTM C1116 Section 4.1.3, Type III, and ASTM D7508.
720.10 Detectable Warning Surfaces.
Provide detectible warning surface ( DWS) products that have been evaluated and meet testing specifications through NTPEP. Meet the geometric requirements of Standard Drawing 614- 3. Meet the requirements in Table 720. 10-1 Table 720. 10-1 – Detect able Warning Surface Crite ria DWS Property Test Method Minimum Requirement Slip Resistance - AASHTO T388 -22 Section 8 Dry Coefficient of Friction – 0.80 Wet Coefficient of Friction – 0.65 (Include field areas between truncated domes) Adhesive, Coating and Single Dome Bond Strength Testing AASHTO T388 -22 Section 13 150 psi with elapsed concrete panel cure time of less than 72 hours 2023 S tandard Specifications for High way Construction - 1 - of - 16 - INDEX Abbreviations ............................................... 615 ABS ....................................... 6, 15, 473, 480, 650 Acceptance 10, 11, 14, 16, 19, 23, 26, 34, 36, 42, 43, 47, 56, 61, 62, 72, 73, 74, 82, 89, 90, 91, 113, 114, 115, 140, 141, 163, 187, 201, 202, 203, 204, 210, 216, 217, 219, 220, 221, 222, 223, 224, 226, 227, 228, 229, 230, 232, 233, 242, 257, 259, 261, 277, 278, 290, 302, 303, 304, 327, 348, 355, 369, 372, 380, 382, 424, 427, 437, 465, 466, 469, 470, 483, 523, 539, 541, 542, 543, 551 , 579, 595, 606, 607, 612, 618, 621, 622, 652, 657, 672 Acceptance and Final .............................. 114 Additive Anti-Stripping 101, 205, 209, 213, 2 35, 237, 238, 239, 622, 623 Adjustment 11, 30, 37, 45, 82, 97, 102, 103, 104, 105, 108, 110, 147, 213, 214, 222, 223, 230, 258, 270, 285, 324, 329, 349, 369, 409, 481, 503, 508, 581, 583, 586, 681, 691 Minor ........................................ 249, 309, 475 Pay ............................................... 31, 232, 233 Price 6, 7, 36, 102, 103, 105, 106, 242, 243, 255, 262, 263, 270, 278, 290, 302, 303, 328, 329, 369, 372, 373, 561 Admixtures 82, 244, 245, 246, 249, 250, 281, 301, 304, 305, 308, 309, 310, 312, 313, 370, 372, 400, 479, 626, 646, 671 Lithium Nitrate ................ 244, 304, 370, 671 Set Retarding ........... 244, 300, 304, 370, 671 Wate r Reducing ....................................... 370 Aggregate 8, 11, 16, 63, 64, 69, 70, 100, 140, 141, 142, 144, 145, 156, 157, 158, 159, 164, 168, 172, 178, 179, 183, 185, 186, 187, 188, 199, 200, 201, 203, 205, 206, 207, 208, 209, 210, 211, 215, 216, 2 17, 218, 223, 224, 225, 231, 233, 234, 235, 236, 237, 238, 239, 244, 245, 246, 247, 249, 250, 251, 259, 266, 269, 273, 274, 275, 276, 277, 278, 281, 285, 287, 290, 291, 293, 302, 304, 305, 306, 307, 309, 325, 360, 369, 370, 372, 373, 376, 378, 382, 383, 38 6, 389, 393, 395, 400, 403, 405, 406, 407, 410, 411, 412, 413, 417, 418, 419, 420, 421, 426, 432, 433, 476, 477, 478, 479, 482, 495, 496, 497, 526, 556, 559, 560, 566, 567, 568, 570, 607, 610, 625, 626, 627, 628, 629, 630, 631, 632, 633, 634, 635, 636, 637, 638, 639, 640, 641, 646, 647, 676, 7 11, 712, 713 Aggregate Base 145, 185, 187, 188, 495, 711 Coarse 140, 142, 158, 159, 209, 210, 227, 245, 246, 247, 256, 266, 302, 305, 368, 373, 376, 377, 393, 394, 395, 396, 411, 419, 443, 444, 476, 477, 478, 479, 482, 526, 625, 627, 628, 632, 639, 640, 64 1 Course ....................................................... 610 Fine 64, 210, 215, 247, 373, 376, 407, 625, 626, 628, 632, 639, 640, 641 Placing ...................................................... 235 Air Entrainment ........................... 283, 301, 370 Aluminum 18, 251, 311, 346, 366, 367, 418, 485, 500, 511, 649, 650, 653, 665, 666, 667, 668, 688, 689, 691, 692, 695 Extruded ................... 499, 500, 501, 669, 686 Sheet ......................... 499, 500, 505, 669, 686 Anchorage Devices ...................................... 362 Anti-Skid ............................................... 556, 638 Approaches Surfacing .................................................. 236 Urban ........................................................ 325 Asphalt 4, 6, 7, 8, 9, 10, 12, 83, 101, 102, 103, 138, 185, 186, 189, 195, 196, 197, 199, 200, 201, 204, 205, 206, 207, 208, 209, 210, 211, 212, 213, 214, 215, 216, 217, 218, 219, 221, 222, 223, 224, 225, 226, 231, 232, 233, 234, 2023 S tandard Specifications for High way Construction - 2 - of - 16 - 235, 236, 237, 238, 239, 240, 251, 273, 274, 277, 278, 286, 287, 288, 290, 293, 295, 325, 380, 384, 385, 386, 388, 3 89, 411, 419, 426, 427, 428, 429, 446, 449, 497, 498, 528, 550, 560, 561, 566, 619, 620, 622, 623, 624, 631, 635, 641, 643, 649, 708, 711, 712, 713 Assemblies 253, 254, 332, 334, 341, 348, 358, 360, 364, 503, 505, 591, 592, 595, 597, 659, 660, 661, 665, 66 8 Audits ................................................ 47, 97, 113 Award 2, 10, 12, 14, 16, 21, 22, 23, 25, 26, 27, 51, 52, 66, 90, 95, 118, 123, 125, 126, 216, 546, 616 Backfill 17, 134, 140, 142, 143, 144, 145, 158, 164, 165, 166, 178, 179, 189, 283, 299, 367, 390, 391, 393, 395, 443, 457, 474, 476, 477, 478, 479, 481, 482, 485, 486, 487, 489, 491, 492, 497, 498, 501, 502, 505, 508, 510, 525, 559, 560, 563, 583, 584, 585 Compacting 164, 165, 166, 172, 178, 179, 391, 460, 476, 477, 478, 481, 486, 488, 491, 500, 525 Barrier 18, 311, 325, 375, 424, 449, 492, 493, 505, 529, 530, 532, 533, 534, 535, 536, 551, 572, 605, 612 Base 6, 7, 14, 16, 17, 32, 40, 41, 56, 61, 64, 101, 102, 103, 104, 108, 119, 123, 132, 138, 140, 142, 144, 154, 159, 183, 185, 186, 187, 188, 189, 191, 192, 193, 195, 219, 226, 227, 231, 235, 236, 237, 244, 247, 248, 251, 258, 267, 280, 283, 284, 285, 287, 288, 302, 334, 335, 338, 360, 372, 377, 382, 383, 386, 387, 389, 409, 417, 433, 437, 496, 498, 502, 503, 510, 511, 529, 536, 567, 585, 593, 595, 604, 608, 610, 624, 631, 636, 641, 646, 647, 657, 662, 667, 668, 688, 689, 690, 701, 703, 713 Base Course ............................ 14, 32, 41, 641 Bases 339, 393, 489, 511, 532, 583, 585, 666, 667, 668 Breakaway Device ................... 511, 689, 690 Emulsion Treated ............................ 185, 186 Open -Graded ........................................... 191 Treated ............................. 168, 251, 630, 631 Untreated 140, 158, 164, 168, 178, 179, 476, 477, 478, 479, 630 Base Breakaway Device ................................ 689 Basin .............................................. 169, 424, 483 Catch 18, 325, 474, 479, 480, 481, 483, 497, Sediment .................. 168, 169, 170, 171, 424 Bearing Bridge ....................................................... 710 Bending ........... 36, 330, 331, 339, 440, 510, 664 Bidders ................ 10, 15, 20, 21, 23, 24, 26, 125 Bidding ........................ 21, 33, 48, 105, 116, 118 Blasting 19, 68, 75, 76, 134, 139, 146, 147, 148, 149, 150, 151, 152, 153, 154, 155, 156, 157, 158, 159, 253, 342, 376, 403, 410, 411, 412, 419, 421, 461, 464, 465, 466, 468, 530, 538, 539, 543 Operations 68, 139, 146, 147, 148, 14 9, 151, 152, 153, 155, 158, 464, 466 Plan Submittals ................................. 68, 146 Production ............................... 146, 153, 154 Blocks ............................ 316, 331, 489, 593, 672 Blotter 199, 202, 204, 205, 208, 235, 240, 241, 291, 295, 465, 468, 635, 636, 682 Bolts 59, 299, 314, 315, 323, 3 36, 340, 342, 343, 344, 345, 349, 350, 367, 469, 486, 492, 502, 511, 555, 657, 658, 659, 660, 661, 664, 665, 666, 667, 668, 688, 689, 690 Bond 12, 14, 15, 22, 26, 74, 114, 142, 204, 226, 254, 260, 315, 359, 361, 376, 386, 387, 407, 409, 413, 414, 419, 421, 426, 428, 430, 433, 439, 448, 450, 451, 454, 455, 467, 546, 552, 592, 647, 683, 686, 710, 715 Bonds 2023 S tandard Specifications for High way Construction - 3 - of - 16 - Contract ........................ 12, 14, 18, 26, 27, 87 Borrow 15, 20, 104, 139, 141, 156, 157, 158, 171, 389, 612, 640, 641 Bridge Deck 18, 201, 206, 229, 249, 258, 267, 284, 296, 299, 312, 314, 315, 318, 319, 323, 324, 325, 328, 332, 349, 350, 351, 375, 376, 377, 378, 380, 384, 385, 386, 388, 389, 403, 408, 411, 412, 413, 414, 417, 419, 420, 421, 430, 437, 449, 454, 455, 460, 528, 551, 552, 553, 601, 611, 618, 627, 629, 645 Cambe r .......... 312, 315, 335, 339, 349, 364, 611 Cattle Guard ......................................... 201, 491 Certificate Loading ..................................................... 622 Certification 10, 40, 45, 61, 65, 66, 80, 119, 123, 130, 135, 140, 278, 281, 282, 290, 304, 334, 354, 358, 369, 370, 372, 373, 376, 382, 407, 427, 428, 432, 439, 445, 446, 454, 461, 464, 467, 479, 482, 493, 515, 540, 541, 543, 562, 589, 618, 623, 643, 648, 654, 672, 673, 675, 678, 679, 681, 700, 705, 711 Fabricator ................................................. 334 Manufacturer ............................. 61, 682, 685 Materials ............................................ 61, 407 Claim Review ............................................ 43, 46, 49 Classification 107, 128, 129, 130, 145, 242, 301, 336, 368, 448, 474, 634, 678, 686, 710 Cleanup 136, 153, 177, 276, 404, 424, 430, 465, 467, 514, 549 Clearing and Grubbing ................ 132, 161, 609 Coarse 64, 140, 142, 144, 158, 159, 173, 183, 185, 187, 209, 210, 212, 215, 227, 245, 246, 247, 256, 266, 302, 305, 368, 373, 376, 377, 393, 394, 395, 396, 411, 419, 443, 444, 476, 477, 478, 479, 482, 526, 578, 625, 627, 628, 632, 634, 639, 640, 641, 676, 711 Cofferdams and Cribs 36, 164, 166, 299, 317, Compaction 140, 143, 144, 145, 146, 158, 159, 164, 165, 1 78, 183, 184, 185, 187, 189, 191, 192, 193, 194, 206, 209, 212, 213, 219, 221, 225, 226, 227, 228, 235, 236, 238, 290, 291, 293, 294, 389, 390, 410, 412, 413, 414, 476, 514, 558, 641 Classes of .................................................. 144 Composite 11, 174, 213, 232, 233, 382, 407, 473, 507, 509, 518, 519, 650, 687, 698, 712 Compression Seal Neoprene ......................... 260, 261, 528, 643 Concrete 2, 4, 5, 32, 82, 104, 139, 140, 142, 144, 158, 159, 164, 165, 166, 178, 201, 226, 242, 243, 244, 245, 246, 247, 248, 249, 250, 251, 252, 253, 254, 255, 256, 257, 258, 259, 260, 261, 262, 263, 266, 267, 268, 269, 270, 271, 280, 281, 282, 283, 284, 285, 286, 287, 288, 299, 300, 301, 302, 303, 304, 305, 306, 307, 308, 309, 310, 311, 312, 313, 314, 315, 316, 317, 318, 319, 320, 321, 322, 323, 324, 325, 326, 327, 328, 329, 331, 3 32, 342, 343, 349, 350, 351, 352, 353, 355, 356, 357, 358, 359, 360, 361, 362, 363, 364, 368, 369, 370, 371, 372, 373, 374, 375, 376, 377, 378, 379, 380, 381, 382, 383, 384, 385, 386, 387, 389, 393, 394, 395, 400, 403, 405, 406, 4 08, 409, 410, 411, 412, 413, 414, 417, 419, 420, 421, 423, 424, 427, 430, 432, 433, 434, 435, 437, 438, 439, 440, 441, 442, 443, 445, 446, 447, 449, 450, 451, 452, 453, 454, 455, 456, 460, 473, 474, 476, 477, 478, 479, 480, 482, 483, 484, 486, 487, 489, 491, 492, 493, 494, 495, 497, 500, 505, 507, 509, 510, 511, 525, 526, 528, 529, 530, 532, 533, 534, 535, 536, 543, 551, 552, 553, 585, 588, 591, 595, 597, 604, 606, 610, 625, 626, 627, 628, 629, 639, 640, 641, 642, 643, 647, 648, 649, 653, 656, 670, 671, 683, 685, 689, 697, 698, 700, 703, 710, 713, Finishing ................................................... 323 2023 S tandard Specifications for High way Construction - 4 - of - 16 - Hand Placing .................................... 252, 267 Placing 251, 252, 267, 268, 299, 312, 314, 318, 321, 322, 324, 326, 331, 355, 393, 430, Concreting .................... 259, 322, 324, 355, 362 Cold Weather ........................... 259, 269, 322 Hot Weather ............................................ 323 Conditioning ......................................... 251, 267 Conduit 446, 460, 474, 509, 510, 511, 518, 583, 585, 592, 593, 597, 603 , 649, 688, 689, 697 Plastic ................................ 509, 510, 595, 697 Rigid Steel ......................... 509, 510, 595, 697 Conference ......... 52, 58, 91, 374, 408, 602, 609 Preconstruction ..................... 15, 90, 91, 169 Preoperational ........................................... 91 Conformity ...................................................... 36 Continge ncy ................................. 7, 12, 98, 177 Contract 2, 3, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 47, 48, 49, 50, 51, 52, 53, 56, 57, 59, 60, 61, 62, 63, 64, 65, 66, 67, 69, 70, 71, 72, 73, 74, 75, 76, 77, 78, 80, 81, 82, 86, 87, 88, 89, 90, 91, 92, 93, 94, 95, 96, 97, 98, 99, 100, 101, 102, 103, 104, 105, 106, 111, 112, 113, 114, 116, 117, 118, 119, 120, 121, 122, 123, 124, 125, 126, 127, 128, 129, 130, 132, 133, 134, 137, 138, 139, 141, 146, 147, 150, 158, 159, 161, 162, 163, 166, 167, 16 8, 170, 171, 175, 178, 181, 191, 195, 197, 198, 199, 203, 208, 213, 214, 217, 219, 220, 221, 229, 232, 233, 234, 237, 238, 240, 243, 248, 258, 262, 263, 270, 277, 284, 288, 295, 303, 304, 311, 312, 319, 320, 328, 329, 330, 333, 334, 335, 352, 355, 357, 358, 364, 367, 369, 371, 373, 379, 380, 389, 391, 394, 399, 400, 408, 409, 415, 421, 424, 428, 429, 431, 434, 435, 437, 438, 442, 444, 445, 447, 448, 449, 453, 455, 456, 458, 460, 462, 475, 476, 477, 478, 481, 482, 484, 485, 486, 487, 488, 490, 491, 493, 494, 495, 496, 497, 498, 503, 505, 508, 512, 515, 516, 524, 525, 527, 528, 532, 535, 536, 542, 543, 546, 552, 555, 556, 561, 566, 570, 573, 579, 583, 584, 591, 592, 595, 598, 601, 607, 612, 616, 640, 643, 644, 658, 681 Change Order 11, 12, 29, 30, 31, 32, 33, 34, 38, 45, 46, 48, 71, 88, 92, 104, 114, 126, 219 Default and Termination .......................... 95 Execution ................................................... 26 Failure to Execute ..................................... 26 Intent of ..................................................... 28 Revisions 10, 29, 31, 56, 75, 94, 104, 105, 114 Subletting of .............................................. 87 Contract Revisions 31, 56, 75, 94, 104, 105, 114 Contract Time 12, 13, 20, 30, 31, 33, 66, 71, 73, 75, 78, 88, 89, 90, 92, 93, 94, 95, 147, 409 Contractor Requested ............................ 29, 75 Contractor -Provided ....................... 62, 63, 200 Control Measures ........ 150, 169, 170, 328, 423 Cooperation ............................................. 37, 40 Administrative ........................................... 37 Coordination ........................ 36, 42, 43, 75, 219 Course 16, 19, 48, 52, 78, 120, 122, 124, 127, 128, 183, 205, 218, 223, 226, 227, 231, 236, 251, 267, 275, 294, 296, 374, 377, 380, 389, 420, 421, 527, 534, 551, 607, 608 Bottom ..................................................... 593 Leveling 6, 209, 227, 228, 231, 232, 233, 234, 446, 560 Pavement ................................................. 593 Surface ........................................ 17, 189, 235 Cover Coat 200, 204, 205, 206, 207, 208, 634, 2023 S tandard Specifications for High way Construction - 5 - of - 16 - Culvert 61, 170, 171, 367, 445, 446, 447, 473, 476, 486, 487, 605, 611, 612, 648 Curb and Gutter 17, 201, 206, 207, 269, 296, 322, 32 5, 351, 368, 378, 412, 417, 449, 495, 496, 497, 498, 531, 532, 534, 535, 536, 605, 609, 611, 612 Curing 82, 208, 219, 245, 247, 256, 259, 261, 266, 269, 276, 280, 287, 291, 305, 318, 319, 321, 322, 325, 326, 327, 356, 359, 370, 375, 378, 383, 385, 387, 411, 414, 419, 420, 437, 448, 450, 466, 468, 479, 521, 522, 540, 541, 542, 543, 578, 647, 674, 683, 684, 700 Curing Compound Membrane -Forming 244, 259, 304, 317, 321, 325, 326, 327, 671 Damage Responsibility for Injury ........................... 68 Definitions ...................................... 10, 146, 662 Delineator ............................................. 505, 545 Assemblies ............................................... 505 Density Requi rements .................. 144, 145, 164, 293 Deposits .................. 35, 161, 433, 455, 640, 681 Designated 11, 12, 16, 17, 18, 23, 62, 63, 64, 75, 80, 114, 116, 120, 132, 133, 134, 139, 145, 161, 167, 173, 175, 183, 188, 194, 199, 213, 214, 235, 238, 240, 242, 250, 281, 283, 284, 292, 29 7, 301, 310, 336, 337, 342, 368, 380, 434, 437, 464, 467, 470, 483, 526, 538, 552, 556, 577, 582, 589, 631, 672 Detours ............................................... 41, 42, 91 Differing Site Conditions ......................... 29, 77 Direct Tension Indicators ................... 342, 661 DTI ......................................... 7, 343, 344, 661 Disadvantaged Business Enterprise 7, 13, 15, 118, 122 DBE 7, 13, 25, 36, 118, 119, 120, 121, 122, 123, 124, 125, 126, 127 Disincentive .......................................... 232, 233 Resolution ................................................ 50, 62 Dispute Resolution .................. 43, 49, 229, 257 Test Result ................................................. 62 Dispute Review Board 7, 13, 49, 50, 51, 52, 53, 54, 55, 56, 57, 58 Disqualification ...................... 23, 122, 127, 538 Bidders ....................................................... 23 Ditches Small ......................................................... 163 Dowel Bars ... 244, 254, 255, 330, 439, 441, 656 Drain Rock .................................... 479, 482, 483 Drainage Structures ................................. 134, 609, 611 Substructure ............................................ 299 Drains Rural Edge ................................ 482, 483, 484 Urban Edge ...................................... 482, 484 Duct ........ 330, 358, 359, 360, 361, 362, 363, 364 Dust Abatement 41, 42, 62, 140, 156, 157, 158, Earthwork 17, 42, 132, 133, 137, 138, 157, 169, Elastomeric Bearings .......................... 365, 710 Elastomeric Sheet ....................................... 644 Electrical Conductors .. 509, 58 3, 585, 594, 698 Electr ical Conductors and Cables .................. 698 Electrical Service Pedestals ........................... 689 Embankment 17, 99, 139, 141, 142, 143, 144, 145, 158, 165, 169, 170, 473, 485, 492, 497, 517, 520, 607 2023 S tandard Specifications for High way Construction - 6 - of - 16 - Construction ............................................ 142 Protectors ................................. 473, 485, 497 Emulsified 7, 102, 185, 186, 197, 199, 205, 237 , 239, 240, 273, 274, 277, 278, 290, 293, 295, 384, 498, 550, 619, 620, 623 Engineer .................................................... 35, 39 Chief .................................... 11, 23, 24, 46, 49 Initiated ...................................................... 29 Resident .................................. 13, 39, 48, 220 Environmental Protection ........ 5, 79, 423, 538 Epoxy 244, 255, 280, 28 1, 284, 319, 329, 330, 331, 332, 333, 417, 418, 419, 420, 421, 432, 440, 448, 450, 451, 452, 453, 537, 540, 643, 647, 652, 653, 656, 661, 710, 714 Epoxy- Resin -Base Bonding Systems ......... 710 Erosion and Sediment Control 35, 78, 79, 80, 168, 169, 170, 171, 172, 51 7 Erosion Blankets .......................... 168, 517, 522 Eros ion Control Products 8, 9, 169, 522, 523, 524, 682, 685 Hydraulically Applied ...................... 521, 524 Evidence 21, 23, 48, 54, 55, 56, 57, 73, 84, 104, 106, 109, 118, 121, 125, 126, 147, 191, 243, 303, 314, 335, 359, 363, 376, 377, 46 5, 577, 605, 644 Excavation 17, 75, 7 6, 85, 99, 104, 139, 141, 142, 146, 149, 151, 152, 153, 154, 156, 157, 158, 164, 165, 166, 170, 171, 175, 179, 189, 283, 287, 299, 329, 352, 390, 391, 393, 395, 423, 424, 457, 460, 476, 477, 478, 481, 483, 485, 486, 488, 491, 492, 498, 509, 512, 513, 525, 527, 596, 605 Structure 164, 165, 166, 172, 179, 481, 500, Extension 31, 33, 44, 64, 71, 78, 92, 93, 95, 122, 127, 347, 476, 478, 579, 595, 688 Extra Work 13, 29, 38, 40, 41, 42, 64, 76, 77, 154, 158, 166, 189, 602 Extrusions ............................................. 430, 669 Fabrication 15, 39, 59, 60, 61, 89, 243, 253, 303, 314, 327, 334, 336, 337, 338, 339, 342, 346, 358, 364, 365, 366, 369, 445, 486, 500, 502, 591, 657, 664, 665, 666, 688, 690, 701, 710 Falsework 311, 312, 314, 316, 317, 318, 319, 335, 350 Falsework and Forms .................. 311, 312, 316 Fence 82, 134, 136, 170, 171, 489, 490, 491, 515, 516, 663, 664, 675, 708 Barbed ...................................... 489, 663, 674 Barbed or Woven ............................ 663, 674 Chain Link ................................................. 489 Hardware for ................................... 489, 663 Films Direct Applied Transparent ................... 686 Fly Ash 242, 248, 281, 282, 287, 301, 308, 313, 368, 372, 374, 400, 626, 700 Fog Coat 134, 137, 203, 205, 208, 230, 240, 291, 295, 550 Force Account 12, 13, 15, 85, 105, 106, 107, 108, 109, 110, 136, 158, 429, 535, 580, 612 Forest Protection .......................................... 68 Forms 10, 11, 12, 15, 20, 21, 22, 23, 24, 26, 61, 106, 124, 125, 149, 249, 252, 262, 266, 267, 268, 287, 300, 304, 312, 313, 314, 315, 316, 317, 318, 319, 321, 323, 324, 327, 349, 359, 360, 361, 362, 378, 380, 384, 438, 440, 495, 542, 594, 604, 618, 670 Permanent Metal Conc rete ........... 313, 670 Foundation 50, 64, 141, 142, 156, 164, 165, 166, 178, 299, 302, 352, 390, 424, 457, 494, 501, 502, 505, 509, 511, 558, 595, 596, 597 Preparation of ......................................... 390 2023 S tandard Specifications for High way Construction - 7 - of - 16 - Foundation Seal ........................................... 299 Gabion ... 168, 169, 170, 172, 390, 391, 702, 703 Gaskets .......................... 343, 473, 474, 475, 649 Rubber ...................................................... 650 Geotextile 142, 168, 171, 172, 178, 191, 390, 391, 482, 527, 552, 558, 559, 560, 561, 572, 703, 705, 706, 707, 708 Pavement Overlay ................... 559, 561, 708 Riprap/Erosion Control ... 390, 561, 706, 707 Subgrade Separation 140, 141, 142, 158, 178, 179, 191, 482, 559, 561, 572, 707, 708 Temporary Silt Fence .............................. 708 Geotextiles Drainage ........................... 446, 559, 561, 706 Granular Borrow 100, 139, 145, 156, 157, 158, 164, 165, 390, 641, 711 Granular Subbase 14, 140, 145, 158, 159, 164, 183, 184, 638, 641, 711 Grout 226, 255, 267, 268, 280, 281, 282, 283, 284, 287, 288, 358, 361, 362, 363, 446, 479, 482, 483, 484, 502, 646, 647, 710 Guardrail 61, 104, 139, 140, 141, 156, 157, 158, 159, 196, 201, 206, 227, 297, 325, 457, 492, 493, 505, 510, 529, 612, 662, 664, 672, 673, 675 Stee l .......................................................... 492 Steel Posts ................................................ 492 Hauling Equipment ...................... 219, 248, 266 Hierarchy of Organization .............................. 2 Hydrated Lime ...... 209, 290, 291, 622, 640, 711 Illumination 38, 509, 512, 591, 596, 598, 666, 689, 690, 693 Service Poles for .............................. 509, 674 Illumination Poles ........................................... 689 Imperative Mood ............................................. 2 Incentive 34, 228, 229, 230, 231, 232, 233, 255, 263, 264 Incidental 14, 16, 40, 42, 57, 81, 85, 89, 100, 111, 132, 133, 137, 138, 143, 158, 159, 161, 166, 167, 171, 176, 179, 183, 185, 187, 195, 198, 204, 208, 234, 262, 270, 276, 280, 287, 288, 295, 319, 329, 333, 334, 351, 357, 364, 379, 391, 394, 396, 399, 415, 421, 438, 442, 444, 453, 455, 458, 460, 471, 476, 477, 478, 481, 484, 485, 486, 487, 488, 490, 491, 493, 494, 496, 498, 503, 504, 512, 516, 524, 525, 527, 532, 536, 544, 549, 550, 551, 552, 555, 570, 573, 576, 580, 592, 594, 595, 596, 614, 643, 658, 695 Inlets 296, 403, 474, 479, 480, 481, 483, 497, 611, 669 Inspection 5, 6, 15, 16, 18, 20, 40, 42, 43, 47, 58, 59, 61, 73, 74, 78, 80, 81, 82, 85, 93, 122, 127, 172, 254, 259, 314, 3 27, 334, 336, 345, 348, 352, 354, 355, 363, 373, 424, 431, 452, 455, 457, 465, 467, 471, 474, 483, 484, 514, 515, 523, 535, 540, 541, 542, 543, 569, 570, 572, 586, 591, 592, 594, 602, 672, 673, 674, 680, 681, 713 of Work ....................................................... 40 Quality Control ................................ 334, 471 Inspector Duties of ..................................................... 39 Insurance 47, 48, 69, 70, 88, 104, 107, 151, 546, Inter ceptor Ditches ..................................... 162 Irrigation Lines ..................................... 473, 583 Irrigation or Drainage ......................... 473, 648 Joint Pre-formed Expansion .................... 528, 643 Seals .......................................................... 645 Joint Filler 244, 253, 256, 268, 283, 427, 526, 528, 643 2023 S tandard Specifications for High way Construction - 8 - of - 16 - joint sealer .................................................... 329 Joint Sealer ........................................... 528, 643 Hot Poured Elastomeric Type Concrete ....................................................... 528, 643 Joints 150, 201, 206, 207, 224, 226, 227, 253, 254, 255, 256, 257, 258, 259, 260, 263, 267, 268, 269, 271, 276, 280, 281, 282, 283, 284, 285, 286, 287, 288, 300, 314, 315, 316, 317, 321, 323, 324, 325, 334, 338, 339, 342, 343, 349, 350, 362, 375, 377, 384, 403, 404, 411, 412, 421, 426, 428, 429, 430, 431, 438, 446, 449, 460, 465, 473, 474, 476, 477, 478, 479, 495, 497, 510, 528, 541, 551, 559, 560, 561, 563, 578, 584, 585, 701, 702 Junction Box 510, 511, 592, 593, 594, 595, 697, Composite ........................................ 509, 698 Concrete ........................................... 509, 697 Laboratory Central Materials 11, 217, 218, 219, 220, 247, 259, 278, 290, 327, 462, 540, 547, 623, 624, 705, 706 Landscape ............................................. 197, 578 Laws to be Observed ..................................... 66 Liability 32, 37, 57, 66, 69, 70, 72, 74, 87, 102, License 22, 24, 25, 26, 2 7, 66, 67, 83, 84, 148, 513, 678 Licensed 11, 15, 18, 82, 85, 98, 274, 311, 320, 335, 366, 390, 398, 423, 445, 456, 457, 473, 501, 508, 518, 569, 601 Licensing ................................. 24, 26, 67, 147 Licensing of Bidders .................................. 24 Licensing of Contractors ........................... 67 Limestone ............................. 281, 618, 625, 640 Limitation of Operations ...................... 91, 387 Lithium Nitrate 244, 245, 304, 306, 308, 370, Load Regulations ........................................... 40 Luminaire ...... 318, 668, 688, 689, 690, 691, 692 Mailbox ................................................. 232, 555 Maintenance During Construction ............. 41 Maintenance of Public Haul Roads ............. 41 Maintenance of Tempo rary Detours .......... 42 Manhole ............................... 479, 480, 481, 669 Covers and Rings ............................. 480, 669 Material Department -Provided .............................. 64 Protection of ............................................ 330 Rights In and Use of .................................. 63 Secondary Cementitious 244, 301, 304, 368, 370, 700 Stripping Designated Source ................. 161 Material on Hand ........................................ 114 Materials Batching ................................... 249, 267, 309 Concrete ........................... 165, 299, 320, 321 Foundation ....................................... 299, 390 Maturity Curve ............................ 261, 262, 317 Mesh 173, 489, 663, 684, 685, 697, 701, 702, Metals ................. 11, 77, 82, 351, 465, 479, 681 Methods, Equipment, and Character of Workers ...................................................... 92 Milepost ........................................ 141, 505, 711 Mix Design 9, 210, 211, 212, 213, 215, 216, 217, 218, 219, 222, 224, 225, 226, 227, 234, 242, 244, 245, 246, 247, 248, 249, 250, 273, 274, 277, 293, 301, 302, 304, 305, 306, 307, 308, 309, 311, 318, 319, 320, 368, 369, 370, 371, 2023 S tandard Specifications for High way Construction - 9 - of - 16 - 373, 374, 375, 400, 404, 407, 408, 411, 482, 551, 619, 629, 630, 634, 671, 712 Mixer 193, 248, 250, 251, 274, 275, 276, 281, 282, 290, 291, 292, 309, 310, 311, 374, 376, 377, 409, 410, 411, 419, 420, 646 Mixing 62, 104, 185, 189, 192, 193, 195, 213, 218, 235, 236, 238, 247, 248, 250, 251, 252, 259, 267, 274, 275, 276, 281, 282, 291, 292, 293, 309, 310, 311, 318, 323, 362, 363, 370, 375, 376, 377, 382, 400, 403, 404, 407, 408, 409, 410, 411, 412, 417, 418, 419, 433, 448, 452, 464, 520, 540, 567, 568, 578, 619, 646, 647, 700, 711 Plants ........................................................ 218 Time .......................... 248, 250, 309, 310, 377 Mixing and Delivering ......................... 250, 267 Mixing and Delivery .................................... 310 Mortar 242, 245, 246, 248, 251, 256, 266, 280, 281, 282, 284, 301, 306, 311, 315, 316, 323, 350, 358, 362, 411, 419, 433, 454, 455, 479, 482, 483, 484, 495, 627, 639, 641, 710 Mulch 86, 167, 168, 169, 174, 175, 513, 514, 515, 517, 518, 519, 520, 521, 522, 523, 524, 577, 580, 682, 683, 684, 685 Mulch Anchoring ......... 517, 518, 521, 523, 524 National Pollutant Discharge Elimination System .......................................... 79, 85, 141 Notice of Rolling and Fabrication .............. 334 Notification 14, 2 9, 30, 31, 32, 38, 42, 43, 95, 114, 135, 136, 149, 217, 515, 540, 601, 604 Obliteration .................................. 138, 415, 421 Open -Graded ............................................... 191 Ordering, Producing, and Delivering Materials .................................................... 60 Organization of Specifications ....................... 2 Overlay Concrete ........... 372, 373, 374, 375, 378, 379 Packaging ...................... 359, 373, 418, 547, 702 Paint 132, 134, 152, 224, 314, 330, 334, 336, 339, 340, 342, 345, 349, 350, 360, 411, 419, 433, 440, 455, 461, 462, 464, 465, 466, 467, 468, 469, 470, 471, 507, 511, 514, 529, 530, 532, 534, 537, 538 , 539, 540, 541, 543, 5 44, 547, 548, 549, 582, 603, 652, 653, 654, 656, 658, 663, 697, 714, 715 Formula .................................... 543, 652, 654 Painting 327, 336, 337, 339, 342, 350, 461, 464, 466, 467, 468, 471, 538, 539, 540, 541, 542, 543, 544, 652 Structural Steel ................................ 467, 471 Partial 42, 43, 62, 74, 97, 112, 113, 114, 115, 225, 231, 236, 280, 283, 693, 700 Patented Devices, Materials, and Processes ..................................................................... 67 Pavement 14, 16, 17, 18, 40, 41, 104, 134, 137, 138, 140, 141, 142, 156, 158, 192, 193, 195, 197, 201, 203, 204, 205, 208, 209, 210, 211, 218, 219, 224, 225, 226, 227, 228, 229, 230, 231, 232, 233, 245, 246, 248, 249, 251, 252, 253, 254, 255, 256, 257, 258, 259, 260, 261, 262, 263, 264, 266, 267, 268, 269, 270, 271, 275, 276, 280, 282, 283, 284, 285, 286, 287, 288, 290, 291, 292, 293, 294, 295, 296, 305, 389, 411, 415, 419, 420, 421, 441, 442, 446, 480, 492, 528, 529, 530, 531, 532, 533, 534, 536, 547, 548, 549, 550, 559, 560, 561, 578, 593, 603, 606, 610, 614, 654, 708, 711, 713 Asphalt ..................................................... 446 Asphalt and Concrete 6, 9, 210, 219, 528, Concrete 104, 245, 248, 249, 251, 253, 255, 256, 259, 260, 262, 267, 270, 280, 281, 284, 286, 287, 288, 439, 441, 442, 528, 643 Flexible ..................................................... 475 Miscellaneous .................. 227, 230, 234, 264 Portland Cement Concrete 138, 230, 242, 258, 266, 280, 285 2023 S tandard Specifications for High way Construction - 10 - of - 16 - Recycled Asphalt 9, 16 , 102, 139, 145, 157, 158, 183, 184, 209, 211, 213, 214, 215, 216, 217, 218, 223, 234, 292, 293, 711, 712, 713 Rigid .......................................................... 475 Road Mix .................................. 235, 236, 237 Urban Concrete ....................................... 270 Pavement Overlay 226, 389, 559, 560, 561, 708 Paver 194, 219, 226, 228, 248, 249, 254, 293, 294, 389, 411, 413, 561 Paving Production 216, 219, 220, 221, 223, 224, 225, Pay Items 10, 12, 20, 21, 33, 36, 41, 59, 61, 64, 72, 81, 87, 89, 99, 101, 105, 106, 132, 133, 134, 137, 138, 158, 159, 161, 166, 167, 171, 195, 198, 278, 364, 389, 434, 475, 4 84, 488, 493, 496, 502, 503, 512, 601, 604 Eliminated .................................................. 31 Payment 2, 10, 11, 12, 13, 14, 15, 26, 29, 32, 34, 39, 47, 51, 57, 58, 66, 67, 72, 73, 74, 78, 81, 88, 96, 97, 99, 101, 102, 103, 104, 105, 106, 107, 109, 110, 112, 113, 114, 115, 117, 122, 126, 127, 130, 132, 133, 137, 138, 155, 157, 159, 161, 162, 163, 166, 167, 170, 175, 177, 178, 181, 183, 184, 186, 188, 189, 191, 195, 197, 199, 203, 204, 208, 218, 221, 224, 230, 231, 232, 234, 237, 238, 239, 240, 242, 254, 255, 261, 262, 263, 264, 270, 271, 278, 283, 288, 295, 297, 300 , 301, 328, 329, 333, 336, 351, 357, 364, 365, 367, 371, 379, 389, 391, 394, 395, 399, 400, 415, 421, 424, 428, 429, 431, 434, 435, 437, 438, 442, 444, 447, 448, 449, 453, 455, 456, 458, 460, 471, 475, 476, 477, 478, 481, 483, 485, 4 86, 487, 490, 491, 493, 494, 495, 497, 503, 505, 508, 512, 515, 524, 525, 526, 527, 528, 535, 544, 545, 546, 549, 550, 552, 555, 556, 561, 564, 570, 573, 576, 580, 586, 589, 592, 595, 598, 599, 601, 606, 612, 614, 616 Final ............................................................. 85 Partial ..................... 62, 74, 97, 112, 113, 114 Scope of .................................................... 102 Permanent Control Measures ................... 169 Permit 7, 67, 70, 74, 75, 79, 80, 85, 117, 141, 147, 231, 562, 569 Permits and Licenses .................................... 66 Piles 319, 328, 352, 353, 354, 355, 356, 357, 371, 393, 394, 395, 397, 443, 558, 663, 669, 670, 673, 674 H- 352, 357, 443 Piling .............................. 104, 328, 336, 355, 371 Defective .................................................. 356 Followers .................................................. 355 H-Beam ..................................................... 663 Heaved ..................................................... 356 Pile Bearing Capacity ...................... 353, 397 Predrilling ................................................. 396 Steel Shell ......................... 352, 357, 669, 670 Timber ...................... 352, 354, 355, 357, 673 Pipe 8, 15, 61, 104, 164, 168, 170, 171, 251, 311, 331, 336, 362, 363, 366, 367, 393, 395, 443, 446, 460, 473, 474, 475, 476, 477, 478, 479, 480, 481, 482, 483, 484, 485, 486, 523, 525, 581, 583, 584, 585, 586, 605, 611, 648, 649, 650, 663, 664, 667, 668, 669,688, 689, 691 Apron ................................................ 476, 486 Arches ......................... 18, 340, 366, 649, 6 68 Concrete 4, 473, 474, 479, 486, 648, 649, 703 Metal Aprons ................................... 486, 669 PE .............................................................. 650 Polypropylene ................................. 473, 650 Reinforced Concrete ............................... 473 Ribbed PVC .............................................. 650 Sewer ........................ 473, 481, 585, 648, 650 2023 S tandard Specifications for High way Construction - 11 - of - 16 - Structural Plate ........................................ 668 Placement 61, 142, 143, 144, 158, 164, 165, 173, 174, 175, 185, 1 95, 197, 207, 213, 217, 226, 227, 228, 243, 249, 251, 252, 253, 254, 255, 257, 261, 262, 263, 266, 267, 276, 278, 287, 296, 300, 302, 303, 306, 308, 312, 313, 314, 315, 317, 318, 319, 320, 321, 322, 323, 324, 325, 326, 329, 362, 368, 371, 374, 375, 376, 37 7, 378, 383, 389, 393, 395, 400, 403, 404, 408, 409, 410, 411, 412, 414, 417, 423, 424, 427, 433, 438, 440, 443, 448, 451, 455, 518, 519, 520, 521, 558, 559, 560, 561, 563, 577, 592, 607, 608, 610, 612, 614, 643, 705 Placing and Fastening ................................. 331 Placing and F inishing ................... 252, 287, 377 Plant Inspection ............................................. 61 Planting 86, 138, 513, 514, 515, 516, 577, 584, Plants 15, 61, 64, 85, 86, 100, 174, 211, 291, 358, 513, 514, 515, 516, 523, 577, 679, 680, 681, 683 Pole Keys ............................................... 509, 674 Poles 505, 509, 510, 511, 545, 595, 596, 597, 664, 665, 666, 667, 668, 673, 674, 687, 688, 689 Flexible Snow ................................... 545, 687 Illumination .............................. 509, 666, 689 Signal ................................................. 594, 688 Pollution Prevention Plan 9, 78, 79, 81, 141, 168, 170 Polytetrafluoroethylene ......... 9, 254, 365, 710 Polyvinyl Chloride 9, 15, 446, 460, 473, 476, 482, 572, 581, 650, 697, 698, 702 Portland Cement 82, 138, 192, 193, 195, 224, 230, 242, 244, 245, 258, 266, 280, 281, 285, 290, 291, 301, 304, 305, 306, 315, 368, 370, 372, 389, 400, 495, 497, 507, 618, 646, 647, 700 Post 25, 80, 137, 147, 148, 149, 150, 155, 156, 158, 302, 317, 320, 338, 358, 359, 360, 361, 362, 368, 483, 489, 499, 500, 501, 502, 503, 504, 505, 507, 508, 532, 545, 555, 662, 663, 672, 673, 674, 675, 693 Posts Marker ...................................................... 508 Rigid .......................................... 505, 545, 664 Witness ............................................. 507, 508 Wood Sign ........................................ 500, 672 Power Service Poles for ...................................... 673 Precedence .................................................... 36 Preparation .......................... 375, 403, 408, 420 Preparation and Stressing .......................... 361 Preser vation, Protection, and Restoration of Property and Landscape .......................... 68 Preservative Treatment ............................. 674 Prime Coat 195, 199, 205, 208, 235, 404, 405, 407, 408, 412, 54 0, 541 Process Old Road ................................. 141, 158 Project Schedule 12, 13, 32, 38, 44, 45, 88, 89, 91, 92, 93, 320 Property 42, 62, 68, 70, 72, 152, 153, 156, 174, 196, 200, 400, 405, 406, 407, 413, 417, 418, 450, 451, 467, 507, 562, 620, 621, 622, 676, 706, 707, 708, 715 Adjacent ....................... 42, 92, 197, 201, 206 Damage ............ 57, 68, 69, 70, 104, 107, 148 Material .................................................... 145 Owner ..................... 42, 62, 68, 132, 141, 156 Physical ............. 290, 380, 382, 383, 387, 644 Real ....................................................... 60, 66 Requirements .......... 290, 562, 706, 707, 708 2023 S tandard Specifications for High way Construction - 12 - of - 16 - Proportioning 193, 246, 266, 274, 306, 370, 371, 375, 415 Proposal Delivery of .................................................. 22 Preparation of ............................................ 21 Protesting ................................................... 23 Public Opening of ...................................... 23 Proposals Conditional ................................................. 22 Consideration of ........................................ 25 Contents of ................................................. 20 Irregular 23, 25, 119, 123, 152, 153, 227, 249, 252, 267, 268, 324, 375, 469, 606 QPL Product s9, 59, 65, 213, 454, 482, 519, 521, 522, 652, 654, 682, 683, 684, 685 Non -QPL Products ..................................... 65 Quality Requirements 59, 61, 183, 185, 200, 347, 637, 712 Quantities 10, 11, 16, 20, 21, 29, 30, 33, 42, 59, 60, 61, 72, 93, 98, 99, 101, 102, 103, 104, 107, 113, 114, 132, 133, 135, 137, 138, 141, 155, 156, 157, 159, 161, 162, 163, 166, 167, 175, 177, 178, 181, 184, 186, 188, 189, 191, 195, 197, 199, 208, 221, 227, 234, 236, 237, 238, 240, 250, 259, 260, 262, 278, 288, 292, 295, 297, 303, 310, 322, 327, 328, 329, 330, 333, 334, 351, 357, 364, 365, 367, 369, 371, 379, 385, 389, 391, 394, 399, 400, 404, 415, 421, 424, 428, 429, 431, 434, 435, 437, 438, 442, 444, 447, 448, 449, 453, 455, 456, 458, 460, 475, 476, 477, 478, 481, 483, 485, 486, 487, 490, 491, 493, 494, 495, 497, 503, 505, 508, 512, 515, 524, 525, 526, 527, 535, 545, 546, 548, 552, 555, 556, 561, 564, 573, 580, 595, 598, 601, 604, 605, 612, 646, 652 Measurement of ............................... 98, 166 Plan ................... 101, 166, 231, 329, 333, 351 Variation ........................................... 104, 105 Quantity 14, 15, 17, 18, 20, 21, 30, 31, 33, 35, 60, 61, 63, 64, 98, 99, 101, 102, 103, 104, 105, 107, 113, 132, 136, 139, 149, 150, 157, 165, 166, 170, 175, 178, 184, 186, 193, 195, 203, 206, 208, 218, 219, 231, 232, 233, 234, 235, 243, 248, 250, 262, 270, 287, 291, 292, 293, 295, 309, 310, 315, 328, 329, 330, 351, 359, 373, 376, 377, 379, 408, 409, 415, 418, 420, 523, 552, 563, 589, 601, 602, 604, 607, 615, 655, 713 Reconditioning ..................................... 189, 579 Records ........................................................... 73 Recycled Glass ..................................... 139, 711 Reinforcement 10, 300, 313, 318, 319, 323, 324, 330, 331, 332, 333, 356, 357, 358, 424, 439, 440, 442, 445, 446, 455, 487, 507, 648, 656, 682, 693 Metal 318, 330, 331, 333, 446, 454, 487, 491, 492, 500, 656 Reinforcing Stee l 5, 36, 244, 268, 317, 318, 328, 329, 330, 331, 332, 333, 358, 364, 371, 446, 448, 455, 487, 494, 497, 498, 502, 551, 552, 656 Removal Class B ....................................................... 552 Selective ................................................... 133 Removal and Replacement .. 36, 280, 323, 469 Removal of 62, 75, 76, 92, 109, 133, 134, 135, 136, 137, 138, 154, 158, 161, 164, 169, 172, 283, 286, 314, 316, 317, 321, 341, 378, 424, 434, 435, 449, 454, 455, 461, 466, 46 8, 471, 490, 532, 536, 551, 572, 573, 575, 657, 665, 668 Repair of Soft Spot ...................... 141, 157, 158 Repairs 71, 72, 118, 155, 156, 202, 203, 243, 253, 254, 281, 303, 334, 380, 384, 389, 439, 469, 541, 542, 559, 585 Resolution .................................... 43, 48, 49, 50 Resource, Cultural ....................... 13, 73, 77, 78 2023 S tandard Specifications for High way Construction - 13 - of - 16 - Retarding Set ............................. 244, 300, 304, 370, 671 Ribbed ............................................. 15, 473, 650 Right -of-Way ................................................ 592 Riprap 18, 168, 390, 423, 424, 527, 559, 560, 561, 676, 677, 678, 706, 707 Riprap/Erosion Control 390, 527, 559, 561, 706, Road Mix 168, 193, 235, 236, 237, 238, 239, 630, 631 Roadbed Preparation of .................................. 193, 235 Roadside Cleanup ........................................ 177 Roller Pneumatic -Tire ................................ 236, 238 Vibratory ........................................... 143, 194 Rolling 9, 16, 17, 143, 145, 172, 184, 189, 194, 195, 206, 207, 211, 226, 227, 228, 235, 236, 238, 290, 293, 294, 619, 657, 661 Samples, Tests, and Cited Specifications ... 61 Sampling and Testing 10, 14, 19, 61, 63, 359, 372, 482, 623, 639, 643 Sand 11, 63, 135, 139, 173, 205, 210, 247, 248, 261, 274, 315, 323, 377, 378, 389, 403, 407, 410, 413, 433, 439, 482, 494, 495, 501, 510, 563, 567, 578, 583, 627, 629, 630, 631, 632, 639, 640, 646, 647, 667, 713 Choke ................................ 205, 207, 635, 636 Sanitary, Health, and S afety Provisions ...... 73 Scope 11, 13, 28, 31, 33, 48, 49, 55, 88, 102, 110, 335, 404 Scrub Coat ............................................ 238, 239 Seal Coat 11, 12, 14, 104, 200, 202, 203, 204, 205, 208, 227, 240, 296, 547, 551 Seams 16, 362, 468, 541, 558, 559, 561, 649, 661, 676, 705, 706 Seed 4, 9, 19, 85, 167, 169, 174, 517, 518, 519, 520, 521, 522, 523, 524, 577, 578, 579, 588, 589, 678, 679, 682, 683, 685 Seeding 86, 138, 168, 169, 171, 174, 175, 513, 517, 518, 519, 520, 521, 522, 523, 524, 577, 578, 589, 678 Segregation 64, 248, 251, 252, 267, 2 75, 294, 295, 302, 306, 308, 311, 318, 319, 713 Sewer 135, 473, 474, 479, 480, 481, 483, 585, 616, 648, 650 Shipment and Rust Protection .................. 359 Shipment and Storage ........................ 558, 563 Shop Drawings 36, 332, 335, 337, 338, 346, 358, 364, 366, 430, 445, 446, 457, 502, 572, 643, 657, 688, 690, 697 Shop Plans .................... 335, 337, 339, 346, 447 Shrink ............ 226, 250, 281, 310, 319, 446, 647 Shrinkage ...... 247, 253, 283, 339, 360, 454, 647 Sidewalk . 201, 206, 314, 368, 495, 496, 511, 534 Sign 8, 26, 48, 49, 61, 79, 80, 85, 88, 134, 137, 196, 318, 3 22, 325, 335, 368, 499, 500, 501, 502, 503, 504, 505, 509, 510, 530, 531, 532, 534, 535, 536, 596, 605, 615, 665, 666, 672, 675, 686, 690, 691, 695 Steel and Aluminum ....................... 500, 665 Wood ........................ 499, 500, 501, 504, 672 Signal 9, 10, 38, 318, 325, 397, 530, 533, 534, 536, 591, 592, 593, 594, 595, 596, 597, 598, 599, 688, 689, 692, 693, 694, 695, 696, 697, Signal Head Covers ...................................... 693 Signal Heads ......................................... 592, 693 Signal Installatio n ........................ 591, 595, 597 Significant Changes in the Character of the Work ........................................................... 30 2023 S tandard Specifications for High way Construction - 14 - of - 16 - Signs Hardware for .................................... 500, 666 Signs and Sign Supports ...................... 529, 597 Silica Fume 301, 308, 372, 374, 375, 377, 378, Silicone Sealant .................................... 528, 643 Silk Screen Opaque Inks .............. 500, 505, 686 Silk Screen Transparent Inks ...... 500, 505, 686 Siphons ............................................ 72, 473, 477 Site of Work .................................................... 15 Slag ........................................ 242, 301, 308, 618 Ground Granulated Blast Furnace 368, 700 Slope Finishing ............................................. 141 Slope Paving ......................................... 325, 526 Soft Ground .................................................. 558 Source ................................. 63, 64, 67, 167, 219 Depletion of ............................................... 64 Material .................... 21, 59, 62, 74, 161, 169 Material Quality ...................................... 640 Production of Material In ......................... 63 Property ...................................................... 62 Reclamation ............................................. 167 Source of Supply ............................................ 59 Splice 300, 330, 332, 333, 347, 349, 350, 354, 356, 357, 455, 489, 501, 511, 593, 594, 657, Splicing .................................. 332, 354, 455, 594 Spreading and Finishing .............................. 225 Spreading, Compacting, and Finishing ..... 238 Steel Castings ............................... 337, 339, 662 Steel Forgings ....................................... 351, 662 Steel Reinforced Ribbed ........... 9, 15, 473, 650 Stockpile 60, 64, 74, 114, 140, 174, 175, 183, 184, 188, 205, 215, 217, 234, 236, 237, 248, 250, 275, 278, 281, 286, 297, 310, 556, 610, 630, 631, 711, 712, 713 Storage 57, 61, 62, 76, 86, 97, 111, 113, 146, 148, 171, 209, 213, 260, 274, 286, 287, 291, 292, 336, 343, 347, 355, 359, 373, 376, 385, 404, 408, 440, 461, 464, 470, 471, 501, 502, 503, 539, 542, 563, 575, 577, 620, 621, 622, 623, 700 Storage and Handling of Material ............... 61 Street Markers ............................................. 669 Street Monuments 83, 84, 201, 204, 208, 268, 275, 296, 507, 508 Stres ses and Losses ..................................... 360 Structural Metal .................. 334, 336, 491, 500 Structural Plate .................................... 367, 668 Structural Steel 134, 329, 334, 336, 337, 342, 346, 351, 376, 430, 461, 537, 539, 540, 652, 657, 663, 665, 666 Structural Steel and Related Materials .... 657 Structural Timber and Lumber .................. 672 Structures 13, 18, 19, 32, 35, 36, 39, 40, 42, 67, 72, 75, 76, 77, 99, 134, 138, 147, 150, 151 , 152, 153, 164, 165, 166, 170, 178, 181, 196, 224, 297, 299, 312, 316, 323, 325, 330, 334, 335, 342, 350, 362, 366, 381, 423, 460, 462, 467, 480, 487, 499, 500, 501, 503, 514, 526, 539, 540, 559, 583, 585, 594, 596, 611, 652, 661, 665, 666, 668, 674, 688 Bearing and Anchorage .......................... 299 Erection Plans .................................... 36, 335 Minor ................................................ 322, 487 Stud Connectors .................................. 661, 662 Subgrade Separation 140, 141, 142, 158, 178, 179, 191, 482, 559, 560, 561, 572, 707, 708 Submittal 21, 32, 33, 36, 44, 45, 46, 53, 54, 79, 80, 85, 124, 130, 146, 147, 148, 212, 215, 216, 2023 S tandard Specifications for High way Construction - 15 - of - 16 - 217, 244, 248, 304, 335, 347, 366, 370, 409, 410, 411, 572, 601, 712, 713 Superpave 9, 140, 209, 210, 211, 212, 213, 215, 216, 218, 219, 224, 227, 228, 231, 232, 233, 234, 282, 497, 566, 568, 570, 631, 632, 641, 712 Supports 11, 216, 25 3, 314, 315, 316, 317, 318, 331, 333, 334, 365, 440, 442, 456, 471, 490, 502, 542, 555, 665, 667, 668, 688, 690 Surface preparation 275, 276, 384, 385, 403, 409, 410, 411, 415, 419, 421, 427, 437, 455, 461, 462, 464, 465, 466, 467, 469, 539, 542, 551, 560, 612 Surface Smoothness 228, 229, 230, 236, 257, 260, 325, 375, 413, 480 Surface Treatment ............... 205, 207, 208, 273 Survey 5, 9, 11, 13, 18, 39, 68, 82, 83, 84, 85, 98, 149, 150, 152, 156, 170, 181, 380, 403, 457, 601, 602, 603, 604, 605, 606, 607, 608, 609, 610, 611, 612, 615, 616 Grades 35, 39, 141, 142, 192, 194, 214, 286, 292, 296, 311, 316, 390, 400, 446, 483, 511, 578, 603, 605, 607, 610, 611, 612, 615, 619, 657, 672, 710 Lines 28, 35, 39, 40, 99, 141, 142, 165, 166, 192, 201, 207, 226, 230, 258, 268, 316, 350, 377, 390, 400, 412, 446, 456, 468, 475, 479, 508, 509, 528, 532, 541, 572, 582, 584, 601, 603, 611, 615, 616 Stakes 16, 17, 39, 132, 572, 602, 60 3, 605, 607, 608, 609, 610, 611, 612, 684, 685 Suspension of Work .............................. 35, 409 System Types ............................................... 380 Tack Coat 197, 223, 224, 232, 235, 238, 286, 288, 380, 384, 386, 388, 498 Taxes Increases or Decreases ........................... 111 Temperature Limitations .... 218, 251, 267, 291 Temperature Viscosity Curve .................... 623 Temporary Erosion and Sediment Control Measures ................................... 80, 169, 171 Temporary Traffic Control De vices 529, 531, 532, 536, 686 Termination for Convenience of the Department ............................................... 96 Test Facilities ................................................. 62 Test Strip Accept ance Test Strip 210, 216, 217, 219, 220, 221, 222, 224, 226, 227, 229, 230, 232, Testing 4, 5, 8, 10, 11, 15, 16, 19, 39, 61, 62, 63, 65, 77, 81, 136, 145, 163, 174, 178, 183, 184, 185, 187, 192, 205, 210, 211, 213, 216, 217, 218, 219, 222, 226, 227, 2 28, 243, 245, 246, 248, 257, 259, 261, 262, 278, 281, 285, 290, 291, 302, 303, 305, 308, 317, 321, 324, 327, 333, 334, 339, 343, 347, 348, 354, 355, 364, 365, 376, 380, 381, 382, 386, 387, 397, 398, 399, 403, 407, 408, 410, 413, 428, 431, 439, 448, 457, 461, 462, 465, 470, 471, 474, 475, 480, 509, 512, 519, 522, 540, 541, 542, 543, 547, 548, 562, 566, 568, 569, 583, 584, 588, 591, 592, 594, 619 , 623, 624, 625, 626, 627, 630, 632, 640, 643, 649, 654, 657, 658, 659, 660, 662, 671, 674, 676, 679, 682, 685, 688, 690, 693, 702, 703, 705, 706, 710, 712, 713, 715 Tie Bars 244, 253, 268, 269, 281, 283, 287, 330, Time Delays ......................................................... 19 Extension of ............................................... 92 Failure to Complete on ............................ 95 Tolerance 153, 154, 211, 220, 221, 228, 230, 254, 255, 269, 292, 293, 294, 376, 452, 547, 558, 606, 607, 630, 669, 672, 686, 702, 710 2023 S tandard Specifications for High way Construction - 16 - of - 16 - Topsoil 19, 104, 142, 158, 161, 167, 169, 173, 174, 175, 513, 514, 515, 517, 518, 519, 578, 580, 583 Trade Names and Alternatives .................... 64 Traffic Control Devices 8, 41, 42, 67, 91, 529, 531, 532, 694, 697 Traffic Control M aintenance 531, 532, 534, 535, 536 Transportation and Storage ....... 134, 148, 363 Tubing ........................................... 482, 650, 651 Tubular Markers .......... 529, 532, 533, 534, 536 Unacceptable and Unauthorized Work ...... 40 Underdrains 18, 164, 473, 482, 483, 484, 559, Underground Drainage ....................... 316, 559 Use of Explosives ........................... 67, 147, 156 Utility Facilities ................................... 37, 38, 72 Voice Active ............................................................ 2 Waiver of Legal Rights .................................. 72 Water for Concrete, Grout, and Mor tar .. 710 Water Reducing ........................................... 370 Watercourse .......................................... 16, 572 Wate ring 86, 189, 513, 514, 515, 517, 523, 524, Waterproof System ............................. 380, 389 Weather Limitations ........... 192, 218, 275, 560 Wire 6, 10, 59, 171, 193, 261, 262, 286, 314, 315, 317, 331, 332, 333, 358, 361, 378, 390, 446, 467, 489, 490, 511, 528, 543, 567, 569, 583, 585, 592, 593, 594, 595, 603, 656, 663, 664, 666, 667, 668, 680, 692, 697, 698, 699, 701, 702, 703, 708 Withdrawal or Revision of a Proposal ........ 23 Woven ................... 489, 663, 684, 685, 706, 707 Woven Wire ......................................... 489, 663