for Highway Construction Page 319 of 715 Use the proper mix design and combination of low shrink materials, low temperature concrete, proper curing techniques, or other procedures necessary t o eliminate or minimize the development of cracks. The Engineer will determine surface crack intensity after completion of concrete cure and before prestressing or releasing of forms or falsework . The surfac e crack intensity of concrete bridge deck s is determined by the number and size of cracks in the top surface of the concrete. Remove equipment and material from the deck and clean the surface as necessary for the Engineer to measure the crack intensity. Fill cracks in any 60 square yard portion of deck when there are more than 50 feet of cracks whose width exceeds 0.02 inch with a 2 component modified methacrylate penetrating sealer or equal, as approved. Fill the cracks in accordance w ith the penetrating sealer manufacturer’s written instructions at no additional cost to the Department. Decks that have excessive cracking or cracking that jeopardizes the structural integrity of the deck may be determined unacceptable and require removal. Work after the placement is incidental and the cost included in the contract unit price for concrete .
2.Vibrating. Consolidate the concrete with suitable vibrators oper ating within the concrete. Supplement vibrating by hand- spading with suitable tools to ensure proper and adequate consolidation, especially around obstructions. Use vibrators that operate at frequencies of at le ast 5,000 impulses per minute. Use vibrators in concrete containing epoxy -coated reinforcement that have a resilient covering to prevent damage to the epoxy coating. Vibrate deck concrete with internal vibrat ors turning at least 10,800 revolutions per minute in air and are fully submerged. Space the vibrator i n the concrete mix approximately 18 to 24 inches measured in longitudinal and transverse directions. Work the concrete thoroughly aroun d the reinforcement , embedded fixtures, and into corners and angles of the forms with vibrators. Do not use vibrators to cause the concrete to flow or run into position instead of placing. Ensure vibrati on is sufficient to accomplish thorough consolidation, but not prolonged to the point where segregation occurs. The vibrators are not required for seal concrete or concrete in shell piles .
3.Underwater Concrete. Use seal concrete in or under water. Carefully place concrete in a compact mass, in its final position, by means of a tremie, a bottom dump bucket, or other approved method to prevent segregation. Do not disturb concrete after being deposited. Do not place concrete in running water. Construct the forms for underwater concrete to provide still water inside the forms. Continuously place the concrete until the required depth is reached and keep the surface of the concrete as nearly level as possible. Comply with the following requirements for placing if a tremie is used:
a.Use a watertight tube having a diameter of at least 10 inches with a hopper at the top.
b.Provide a device that will prev ent water from entering while charging the tube with concrete .
c.Support the tremie to allow free movement of the discharge end over the entire top surface and to allow r apid lowering when necessary to slow down or stop the flow of concrete. for Highway Construction Page 320 of 71 5 d. Use a method to fill the tremie that will prevent washing of the concrete.
e.Completely submerge the discharge end in concrete and maintain sufficient concrete in the tremie tube to prevent water entry.
f.When concrete is dumped into the hopper, induce the flow of concrete by slightly raising the discharge end, always keeping it in the deposited concrete.
4.Massive Placement . Concrete placements with the least dimension greater than 4.5 feet are considered mass concrete placements. The Engineer will indicate mass placements in the Contract documents. This specification does not apply to drilled shafts unless otherwise specified . The Contractor must produce a mass concrete placement free of cracks caus ed or worsened by concrete heat of hydration. Accomplish this through appropriate concrete mix design and control of concrete temperatures and temperature differences. Use of concrete pre- cooling, concrete post - cooling, application of insulation or external heat, and or selection of reduced heat of hydration concrete mix may be appropriate for this purpose. Compliance with this specification may result in long durations of temperature control which could impact the sequenc e and schedule of planned work. The Contractor must implement procedures to control concrete temperatures that are compatible with the work plan and project schedule. The Contractor must provide a thermal control plan signed and stamped by an Idaho licensed engineer . Unless otherwise specified, the following temperature limits apply:
a.Maximum temperature in concrete after placement cannot exceed 160°F.
b.Maximum temperature difference between center and any surface of placement , and with ambient temperature, must not exceed 35°F. (1) The surface is 2 to 6 inches internal to the outer dimension of the placement and can include the upper surface and the sides. (2) The center is the vertical centerline horizontally centered with the element where mass concrete is being placed. Submit a thermal control plan for each mass concrete placement that includes:
a.Concrete materials , mixture proportions, and ranges of chemical admixture dosages using ITD - 0916.
b.Permissible changes to concrete materials and mixture proportions that do not require the thermal control plan to be updated.
c.Calculated and measured adiabatic temperature rise of concrete ;
d.Upper limit for concrete temperature at time of placement ;
e.Description of specific measures and equipment that will be used to ensure maximum temperature in placement will not exceed the specified maximum temperature;
f.Calcula ted maximum temperature difference in placement based on expected conditions at time of placement and use of proposed measures to control temperature differences;
g.Description of equipment and procedures that will be used to monitor and l og temperatures and temperature differences; for Highway Construction Page 321 of 71 5 h. Drawings of locations for temperature sensors in placement ;
i.Description of format and frequency of reporting temperature data;
j.Description of measures to address and reduces excessive temperat ures and temperature differences if they occur;
k.Description of curing procedures, including materials and methods, and curing duration;
l.Description of formwork removal procedures to ensure temperature difference at temporarily exposed surface will not exceed temperature difference limit, and how curing will be maintained. Update thermal control plan if changes in concrete materials or mixture proportions affect compliance with temper ature limits. Unless otherwise specified, preserve moisture by maintaining forms in place. For surfaces not in contact with forms either apply water -retention sheeting material without holes or gaps, or apply membrane- forming curing compound. Control concrete temperature and temperature difference within the concrete from the time concrete is placed until internal temperature has cooled from its maximum so that the difference between average daily ambient temperature and internal temperatures at time of protec tion removal is less than the specified temperature difference limit. Do not use ice in the concrete mix. Place two temperature sensors (one redundant backup) at the center of the largest portion of placement , two temperature sensors (one redundant backup) at a depth 2 to 3 inches from the edge of exterior surface that is nearest to the vertical center of the placement, and two temperature sensors (one redundant backup) at a depth 3 to 4 inches from the upper surface nearest the horizontal center of the placement. In addition, place two temperature sensors (one redundant backup) in a shaded location for monitoring ambient onsite temperature. Monitor temperatures hourly using electronic sensors capable of measuring temperatures from 0 to 212°F to an accuracy of 2°F . Ensure temperature sensors are operational before placing concrete . Provide temperature monitoring data daily to the Engineer until the internal temperature has cooled from maximum so that the difference between the average daily ambient temperature and the internal temperature at the time of protection removal is less than 35°F. Do no place fresh concrete between hardened concrete placed within the previous four weeks . If unavoidabl e, obtain approval from the Engineer. If temperatures are nearing the maximum temperature or maximum difference in temperature, take immediate action as described in the thermal control plan. Do not place additional concrete until the cause of excessive temperatures or temperature difference has been identified and corrections are accepted. Care must be taken to avoid construction j oints where they are not specified. If unavoidable, obtain approval from the Engineer. If the temperature difference limit is exceeded, the Engineer may require additional testing at no cost to the Department to determine if a pay deduction or removal of material is required. If there is no apparent damage with the concrete, the material may remain in place. If the maximum temperature limit is exceeded, strengths may be reduced and internal expansion and cracking of concrete may not be apparent for several years after the placement ; therefore, the material must be removed and replaced at the discretion of the Engineer. for Highway Construction Page 322 of 715 G. Cold Weather Concreting.
1.Heating and Placing Concrete. Obtain approval for a cold- weather concreting and curing plan detailing the methods and equipment to ensure the required concrete temperatures are maintained before placing concrete when ther e is a probability of air temperatures below 40°F during the placing and curing periods. Meet the following cold- weather concreting operation requirements when the ambient temperature falls below 40°F:
a.Compl etely remove ice, snow, and frost before placing concrete .
b.Provide concrete that will have a temperature of at least 50°F and less than 80°F at the time of placing.
c.Do not place concrete against material with a temperature of 32°F or less.
d.Heat the mix water and/or the aggregates when necessary, before batching to produce concrete of the specified temperature. Heat in a manner that is not detrimental to the mix and does not prevent the entrainment of the required amount of air. Heat the materials uniformly.
e.Do not heat aggregates directly by gas or oil flame or on sheet metal over fire.
f.Do not heat aggregates or water to over 150°F. If either is heated to over 100°F, mix together before adding the cement so the cement does not come into contact with materials that are in excess of 100°F.
2.Protection of Concrete. Maintain a concrete temperature of at least 50°F for 7 calendar days or 70°F for 3 calendar days after placement except when steam curing is used. When SCM is used, increase the time to 10 calendar days for 50°F and 5 calendar days for 70°F. Maintain the temperature of uniform surfaces of concrete (e.g., decks) at the temper atures and the times shown. Do not allow the water to freeze during the curing period when water cure is required for concrete as specified in 502.03.J. Protecting and curing concrete under water is allowed provided the temperature of the w ater does not fall below 35°F and at least 6 inches of water is maintained over the concrete for at least 10 calendar days. Block up combustion heaters off the surface of the concrete and vent to the outside of the enclosure. Do not allow the maximum temperature within the enclosure to exceed 120°F when the concrete is protected by means other than steam. The maximum drop in temperature of the concrete throughout the first 24 hours after the end of protection will be 50°F for protection methods other than the use of steam. Meet the requirements of 502.03.J when steam is used in the protection of the concrete. Provide calibrated temperature recording devices with a range of 20°F to 212°F for steam -cured concrete and a range of 20°F to 160°F for other concrete. Continuously record temperatures for at least 24 hours. Provide a sufficient number of recording devices to keep adequate records of temperatures. On s mall quantities used in minor structures , sign foundations, and other nonstructural placement (e.g., sidewalks, curb and gutter ), protect the concrete from freeze dam age by covering the for Highway Construction Page 323 of 71 5 concrete with suitable blanketing material. Maintain protective covering for at least 5 calendar days. Use recording thermometers to show that concrete used in minor structures was not expos ed to freezing temperatures .
H.Hot Weather Concreting. Do not allow the temperature of concrete to exceed 80°F at time of placement. Take measures (e.g., erecting sunshades, placing at ni ght or early morning) to slow evaporation to tolerable limits when the combination of ambient air temperature, concrete temperature, humidity, and wind promotes rapid evaporation of moisture from the concrete surface. Ice may be used as a part of the mixing water if it has completely melted by the time mixing is completed. Ensure the temperature of the surface to be covered by concrete does not exceed 90°F.
I.Finishing Concrete . Provide an ordinar y surface finish for all formed surfaces that are not exposed. Provide a rubbed surface finish on exposed surfaces, except the soffits of superstructures and the interior faces and bottoms of concrete girders. Concrete surfaces are define d as follows:
1.Ordinary Surface Finish. Remove form bolts and tie wires immediately after the forms have been removed. If rock pockets materially affect the strength of the structure or endanger the life of the steel reinforcemen t, the Engineer may declare the concrete defective and require the removal and replacement of that portion of the structure affected. Clean, thoroughly wet, and fill holes and depressions with a cement mortar composed of 1 part of cement and 2 parts of sand. The Department may require an approved bonding agent. Remove fins caused by form joints and other projections above the ground line. Ensure the resulting surface is reasonably smooth and uniform in texture and color.
2.Rubbed Surface Finish. Thoroughly wet and rub the entire surface with a carborundum stone or other approved method after the pointing has set sufficiently. The Department may require an approved bonding agent. Spread the paste by rubbing uniformly over the surface and finish by floating or rubbing to attain a uniform color and texture. Thoroughly clean concrete that has been discolored by the drip from the abrasi ve by using a dilute solution of muriatic acid, and then washing thoroughly with clean water. The Engineer may waive the requirement for a rubbed surface finish if the uniformity of color and texture obtained wit h ordinary surface finish are essentially the equal of a rubbed surface finish when metal forms, fiber forms, lined forms, or plywood forms in good condition are used. Grinding with powered disc grinders or light sandblasting with fine sand or other approved means may be used in conjunction with ordinary surface finish.
3.Slab Finish. Finish and straightedge deck slabs and wearing surfaces as follows: Finish deck slabs greater than 40 feet in length and other wearing surfaces subject to highway traffic that are greater than 40 feet in length by the machine method. Finish other deck slabs and wearing surfaces using machine or hand methods. Do not use additional water on the concrete surface during machine or hand- finish ing operations. Straightedge the concrete surface, broom finish, and meet the completed surface requirements of the following in paragraphs c, d, and e after finishing by machine or hand methods. for Highway Construction Page 324 of 71 5 a. Equipment. Use an Engineer -approved, power -driven finishing machine complying with the following requirements for finishing all areas of work with a width of at least 14 feet. Have at least 2 hand- operated, spud type internal vibrators available at all times for use as directed. Submit equipment ap proval re quests a t least 15 calendar days before the start of the work. Do not begin placing deck concrete until the screed and placing procedure is approved. Provide a self-propelled finishing machine capable of forward and reverse movement under positive control for placing, striking off and finishing the bridge deck surface, with provisions for raising screeds to clear the surface. Equip the machine with vibrating screeds designed to consolidate the modified composition. The Department requires the vibration frequency be variable with positive control between 3,000 and 11,000 vpm and the bottom face of the screeds be at least 4 inches wide and be metal covered. Provide screeds with positive control of the vertical position. Equip the finishing machine with one or more rollers, augers, and 1,500 or 2,500 vpm vibratory pans. Provide a Bid- Well 2450, or equivalent finishing machine. Modification to the Bid-W ell 2450 or equivalent is subject to Engineer approval. Texas, Allen, or Bunyan type screeds will only be allowed for small and/or irregular areas if approved. Before beginning concreting operations, operate the finishing machine over the full length of the bridge segment to be finished. Make this test run with the screed adjusted to its finishing position. Check the screed rails for deflection and proper adjustment , the cover on slab reinforcement , and form alignment while operating the finishing machine in this test. Make necessary corrections before placing concrete. Ensure the concrete carried ahead of t he screed does not cause slipping of the finishing machine wheels on the rails. Orient the transverse axis of the finishing machine parallel to the bearing centerline on prestress and steel girder spans. Ensure the concrete placement heading and the strike- off heading are parallel so equal loads are produced on each girder.
b.Hand Method. Strike the concrete off with a template or a vibrating screed after it is placed. Finish concrete to an even surface by means of longitudinal and transverse floats. Do not use a power tr owel.
c.Straightedging. Test the surface of the concrete for trueness while the concrete is still plastic. Use an approved 10- foot straightedge. Hold the straightedge in contact with the surface in successive positions parallel to the centerline and go over the whole area from 1 side of the slab to the other. Advance along the surface in successive stages of less than ½ the length of the straightedge. Immediately fill depressions found with freshly mixed concrete, strike off, consolidate, and refinish. Cut down high areas and refinish. Ensure the concrete surface across joints meets the requirements for smoothness. Perform straightedging and surface correction from foot bridges resting on the side forms and spanning, but not touching, the concrete. Continue straightedge testing and surface corrections until the entire surface is without observable departures from the straightedge and the slab conforms to the required grade and cross- section.
d.Final F inish. Float the deck slab after screeding to produce a uniform surface without porosity. Give the surface a steel tine finish if necessary. Use tines 1/8 inch wide, spaced at ½ to ¾ inch intervals, and producing grooves 5/32 inch ± 1/32 inch deep. Check groove depth in accordance for Highway Construction Page 325 of 71 5 with Idaho IT 147. If more than 3 readings in a set of 10 are outside the intended depth range, make adjustments to the tining operation. Minim ize surface tearing or aggregate removal when t ining. Tine-stroke transverse to the roadway centerline and the full width of the roadway except for troweled smooth strips 12 inches wide along curb faces. Do not overlap adjacent strokes. Finish the surface without porous spots, irregularities, depressions, small pockets, or rough spots. The Contractor may saw cut grooves instead of the steel tine finish, if approved. Use a width and spacing of the grooves 1/8 to ¼ inch. Do not perform saw cut grooving until after the curing duration. Continuously and completely remove residue from the grooving operation. Screed or float finish structures that will receive a deck membrane and asphalt overlay. Complete surface without porous spots, irregularities, depressions, small pockets, or rough spots.
e.Surface Smoothness. The Engineer will test the slab surface for smoothness in accordance with Idaho IT 87, at the end of the curing period. Ensure the surface does not vary more than ¼ inch in 10 feet from the lower edge of the straightedge and 90 percent of the readings do not exceed 1/8 inch in 10 feet. Grind concrete surfaces that do not meet surface smoothness requirements or replace as directed at no additional cost to the Department.
J.Curing Concrete . Keep concrete surfaces completely and continuously moist until a curing method is applied. Do not apply membrane- forming curing compound to concrete surfaces before the finishing has been accepted. Do not apply m embrane- forming curing compound to construction joints or to the inside faces of joints to be sealed. Cure concrete as specified in Tables 502.03- 6 and 502.03- 7. Table 502.03- 6 – Concrete Placement Type Placement No. 1 Bridge decks, including sidewalks on bridges, bridge curbs, or parapets. Placement No. 2 Sidewalks, urban approaches , curbs, or curb and gutter . Approach slabs and concrete slope paving. Placement No. 3 Prestressed girders. Concrete placements (e.g., beams, caps, columns, fo otings, catch basins, manholes, median barrier , median curbs, box girders excluding the deck portion, signal, luminaries, sign support foundations). Concrete g uardrail Sound walls for Highway Construction Page 326 of 71 5 Table 502.03- 7 – Cure Methods Placement Number Method A: Water Cure Method B: Membrane -Forming Curing Compound Method C: Form Cure Method D: Steam Cure 1 X — — — 2 X X-System 1 — — 3 X X-System 1 X X Cure concrete by one of the following methods:
1.Method A: Water Cure. Make a single application of a membrane- forming curing compou nd immediately after surface finishing is completed on each individual portion of the placement . Apply the membrane- forming curing compound under pressure at a rate of at least 1 gallon per 150 square feet. Use System 1 membrane- forming curing compound on placement numbers 2 and 3. Use System 2 membrane- forming curing compound on placement number 1. Start water curing after the concrete surface has set up enough so it will not be damaged, but not later than 4 hours following application of the curing compound. Keep the concrete surfaces in placement 1 continuously wet for at least 10 calendar days. Keep the concrete surfaces in placement 2 and 3 continuously wet for at least calendar 5 days. Parapet finishing may be performed during the wet cure period. The Contractor may have the burlap removed for finishing small, isolated areas of the parapet provided the surface of the concrete is not allowed to dry out. Keep the concrete surface wet using cotton mats, rugs, carpets, burlap, laminated moisture- retaining cover, or other approved coverings as a reservoir medium. Saturate the reservoir medium before placement on the concrete surface. Ensure the reservoir medium is in a saturated state, drained of free water, when initially placed. Add water as necessary to keep it from drying out during the curing period. Cover the reservoir medium with white plastic sheeting to reduce evaporation. Do not use plastic sheeting alone as a reservoir medium. Clear the surface of reservoir mediums at the end of the curing period. Show ability to provide the water cure as specified before placing concrete . The Engineer will immediately suspend the concrete placing operations for failure to provide sufficient cover material or sufficient water to adequately take care of water curing and other associated requirements.
2.Method B: Membrane- Forming Curing Compounds. Apply membrane- forming curing compounds, as specified in 709.01, to the finished concrete immediately after the bleed water or free water sheen leaves the surface of the finished concrete surface. for Highway Construction Page 327 of 715 Thoroughly mix membrane- forming curing compounds before using and agitate it during application to prevent settling or separation. Uniformly apply the membrane. Apply the second coat of membrane at right angles to the first coat when 2 coats are used, if possible. Immediately apply the same type of membrane material to membrane surfaces that are marred or damaged by scuffing or wearing before completion of the curing period, or water cure the area for the remaining cure period. Each manufacturer’s identified lot of curing compound is required to be sampled, tested, and approved before use. Allow 3 weeks for laboratory testing of the curing compound once it has been receiv ed by the Central Materials Laboratory . Quantities of curing compound over 1,000 gallons may be inspected and sampled by the Department at the manufacturer’s plant for acceptance testing. Request inspection from the Engineer and the Central Materials Laboratory in writing 30 calendar days before ordering material.
a.System 1 : AASHTO C309 Type 1 D Class B with Fugitive Dye. Prepare the concrete surface before painting if System 1 is used. Refer to 627.03.E. Provide 2 applications of the curing compound for a total coverage of 1 gallon per 150 square feet to co ncrete cured by this method. Apply each application of the curing compound under pressure at a rate of at least 1 gallon per 300 square feet. If the surface under the forms has dried, thoroughly wet the concret e with water and apply the curing compound just as the surface film of water disappears. Apply the first coat immediately after stripping the forms and before acceptance of the concrete finish. Apply t he second application immediately af ter the first application has set. Keep unsprayed exposed surfaces wet with water during curing operations.
b.System 2: AASHTO C309 , Type 2, Class B, White Pigmented. Apply curing compounds under pressure at a rate of at least 1 gallon per 150 square feet on surfaces.
3.Method C: Form Method. Protect concrete with forms for at least 7 calendar days. Intermittently moisten and protect forms from the sun during daytime periods of hot weather. Cure exposed surfaces b y water or approved membrane cure.
4.Method D: Steam Curing. When steam curing is used, protect the concrete for a minimum 2 -hour period when the temperature is 50°F to 100°F. Following thi s initial period, increase the temperature at a maximum rate of 40°F per hour to a temperature between 100°F and 175°F. Continue curing at this temperature until cylinder strengths are above the release strength for prestressed reinforced concrete or above 80 percent of the intended 28- day strength, whichever is greater. Cool the beam gradually by decreasing its temperature at a rate of 40°F per hour or less until the temperature differential between the beam and outside air is 25°F or less at the end of the cure cycle, when ambient air temperatures are below 40°F. Do not expose member to below freezing temperatures until at least 6 calendar days after fabrication or until the 28 -day strength has been achieved. for Highway Construction Page 328 of 71 5 502.04 Method of Measurement. The Engineer will measure acceptably completed work as follows:
1.Precast stringers, prestressed stringers, and concrete parapets by the foot.
2.Approach slabs by the square yard, including the exposed finished surface of the concrete deadman.
3.Other concrete by the cubic yard with the dimensions specified or ordered, except the volume of concrete placed under water and formed Class 15 concrete may be based on batch design volumes. The volume occupied by the reinforcing steel , anchors , conduits, weep holes, H piling, or chamfers will not be deducted. The volume of concrete displaced by culverts or piles, other than H piling, will be deducted.
4.Deck concrete by the square yard or cubic yard to the dimensions specified.
5.Thermal Control Plan will be paid by the lump sum including the thermal control plan, temperature monitoring and thermal control measures .