129 SECTION 113 – PARTNERING OVERHEAD
113.01 Description
All major players for both the Contractor and the Department will be expected to attend a partnering workshop to develop a statement of goals and monthly follow-up meetings. Players need to attend the follow-up meetings only when they are active in the project. This workshop shall be held at a neutral location and may include a working lunch if the cost is less than $10.00 per person. The workshop should take place before the pre-construction conference, but shall not take the place of the pre- construction conference. 10
113.02 Requirements The requirements for the workshop shall be as follows:
113.03 Method of Measurement
Partnering overhead will not be measured for payment. 113.03 130 113.04 Basis of Payment Partnering overhead will be paid for at the contract lump sum price for partnering overhead. Payment will be made under the following: 50 Pay Item Pay Unit Symbol Partnering Overhead .............................................................. LS The cost of the room, facilitator, mailings, video and audio equipment required, and all other incidentals shall be included in the cost of partnering overhead. 113.04 131 DIVISION 200 – EARTHWORK