182 At locations inaccessible to the above compacting equipment, the required compaction shall be obtained with approved mechanical tamps or vibrators, in which case the depth of lifts, loose measurement, shall not exceed 4 in.
203.26 Proofrolling When proofrolling is specified, the work shall be performed with an on-highway
dump truck with a minimum tire pressure of 90 psi. 1270 Proofrolling for original ground or embankment construction shall be performed using a dump truck weighing at least 15 t. Proofrolling for subgrade preparation shall be performed using a dump truck weighing at least 33 t. All proofrolled surfaces shall be covered completely with a single pass. Operating speed of the proofrolling truck shall not exceed 2 mph. Deflections or rutting in excess of 1/2 in. shall require remediation of the surface as directed. Deflection or rutting in excess of 3 in. shall require corrective remediation measures and the Department’s Geotechnical Engineering Division will be contacted. 1280 Proofrolling shall be performed after remediation measures on embankment or subgrade prior to the placement of additiona l material. There shall be one or two complete coverages as directed. Roller marks, irregularities, or failures shall be corrected.
203.27 Method of Measurement
203.28 Basis of Payment
The accepted quantities of excavation and embankment will be paid for at the 1430 contract price per unit of measurement for each of the pay items listed below which is included in the Schedule of Pay Items. Common excavation and unclassified excavation will be paid for on the unit basis of contract quantities in accordance with 203.27(a), without any quantity limit, unless otherwise shown in the Schedule of Pay Items. Combined quantities of borrow, common and unclassified excavation not exceeding 15,000 cu yds will be paid for on the basis of contract quantities in accordance with 203.27(a) with no adjustme nt to plan shrinkage factor. Except as noted above, borrow, as well as all other excavation, will be paid for on the basis of measured quantities in accordance with 203.27(b), unless otherwise shown in the Schedule of Pay Items. Linear grading will be paid for at the contract unit price per 1440 linear foot. If the class of excavation is linear grading, additional borrow and the excavation of and disposal of unsuitable material not included as pay items will be paid for as follows: 203.28 186 If the total quantity exceeds 5,000 cu yds at a given location, it will be paid for at $8.00 per cu yd. If the total quantity exceeds 1,000 cu yds, but does not exceed 5,000 cu yds at a given location, it will be paid fo r at $12.00 per cu yd. If the total quantity does not exceed 1,000 cu yds at a given locati on, it will be paid for at $15.00 per cu 1450 yd. Linear grading includes only such grading within the construction limits. All grading the Contractor is directed to perform outside the construction limits, except for the Contractor’s convenience, will be paid for in accordance with 104.03 or 109.03 unless such grading is shown on the plans or in the Contract Information book. Existing concrete building foundations, c oncrete walls, concrete columns, or concrete steps not visible and not shown on the plans within the limits of the planned excavation will be paid for at 10 times the contract unit price per cubic yard for 1460 common or unclassified excavation, whichever is set out as a pay item. Unless a waste area is established within the contract limits, the minimum pay for this work will be $80.00 per cu yd. Excavation and disposal of unsuitable material will be paid for at the contract unit price for the class of excavation involved. If no such pay item is included in the contract and embankment is included as a pay item, the excavation and disposal will be paid for at the contract unit price for embankment, unless otherwise directed. If there is no pay item for rock excavation and such is encountered, it will be paid 1470 for at $125.00 per cu yd for quantities less than or equal to 100 cu yds. For quantities greater than 100 cu yds pay will be determined in accordance with 104.03. If there is no pay item for common excav ation and if such is encountered, it will be paid for at the contract unit price per cubic yard for borrow. If the contract includes a pay item fo r waterway excavation, and if class Y excavation is encountered and there is no pay item for such, the class Y excavation will be paid for at 10 times the contract unit price per cubic yard for waterway excavation, or $100.00 per cu yd, whichever is greater. 1480 If the contract does not include a pay item for waterway excavation and such is encountered, pay will be determined in accordance with 104.03. If excavation is necessary to investigate or to seal sinkholes, or to explore underground drainage, the accep ted quantity involved at each location will be paid for as follows. The first 10 cu yds or fraction thereof will be paid for at 10 times the contract unit price for the class of excavation encountered. The next 40 cu yds or fraction thereof will be paid for at seven times the contract unit price for the class of excavation involved. Additional quantities will be paid for at three times the contract 1490 unit price per cubic yard for the class of excavation involved. 203.28 187 Material overlying the peat deposits which is excavated and used in embankment will be considered as common excavation and will be paid for as such. Excavation for standard side ditches or other side ditches which are constructed through peat areas at locations shown on the plans, or where directed, will be paid for at the contract unit price per cubic yard for common excavation. Mechanical treatment of embankment foundation soils will be paid for by the square yard as embankment foundation soils treatment. 1500 Cased test holes and exploratory drilling will be paid for at the contract unit price per linear foot. If there is no pay item for borrow, the costs of identifying the borrow areas, the archeological investigation, all required permits, and the opening and closing of the borrow area will be included in a change or der developed in accordance with 109.05 and paid for as borrow area. If the contract documents do not identify excess excavation or require removal of 1510 any items from the site, the cost of identifying a disposal area, archeological investigation, all required permits, and the opening and closing of the disposal area will be included in a change order devel oped in accordance with 109.05 and paid for as disposal area. If a type of excavation for which no pay item exists is required and the new type of excavation requires the Contractor to use equipment not otherwise being used on the contract, all cost involved in determining the type of equipment necessary to complete the work and making this equipment available for the project will be included in a change order developed in accordance with 109.05 and paid for as 1520 additional mobilization and demobilization. If a type of excavation for which no pay item exists is required and the new type of excavation requires additional traffic control not shown on the plans or results in traffic control being required for an additional period of time, all cost involved in providing the additional traffic control will be included in a change order developed in accordance with 109.05 and paid for as additional maintaining of traffic. Coal ash used as borrow will be paid for at the contract unit price for borrow. Excavation of coal ash will be paid for at the contract unit price for common excavation. Payment will be made under: Pay Item Pay Unit Symbol Borrow ....................................................................................... CYS 203.28 188 Breaking Pavement .................................................................... SYS Cased Test Holes ....................................................................... LFT 1540 Embankment Foundation Soils Treatment ................................ SYS Embankment .............................................................................. CYS Excavation, Common ................................................................ CYS Excavation, Peat ........................................................................ CYS Excavation, Rock ....................................................................... CYS Excavation, Unclassified ........................................................... CYS Excavation, Waterway ............................................................... CYS Excavation, Y ............................................................................ CYS Exploratory Cores ...................................................................... LFT Exploratory Drilling .................................................................. LFT 1550 Linear Grading .......................................................................... LFT Water for Shale .......................................................................... kGAL. If embankment is specified as a pay item, borrow and common excavation, unless otherwise specified, will not be paid for directly. The costs thereof shall be included in the cost of embankment. Such price shall be full compensation for preparation of the natural ground on which the embankment is to be placed and excavating, hauling, placing, spreading, and compaction of mate rials in accordance with 203.23. The costs of labor, equipment, tools, and necessary incidentals shall be included in the cost of embankment. The cubic yards of suitable material used in the embankment excavated 1560 from the right-of-way and paid for under a specific pay item will not be deducted from the embankment quantities. The quantity of material to be paid for as B borrow and placed within the embankment area as specified will be deducted from the quantity of embankment. The costs of excavating, backfilling, disposal of surplus material, labor, equipment, tools, and necessary incidentals necessary shall be included in the cost of excavation required to seal sinkholes or explore underground damage. The costs of all excavated or displaced p eat, regardless of de pth, peat disposal, 1570 temporary surcharge, machine operation, and machine availability shall be included in the cost of peat excavation. However, the Department may provide temporary right-of-way for peat dispos al when so specified. Cost for providing additional lighting for grading operations shall be included in the cost of other pay items in this section. No payment will be made for the construction or restoration of borrow or disposal sites. 1580 No payment will be made for the inspection of disposal and borrow areas for wetland identification, obtaining of permits, the development and construction of all mitigation measures, or the fulfillment of permit requirements. 203.28 189 The cost of boring the holes, casings and fittings, labor, equipment, tools, and all necessary incidentals shall be included in th e cost of cased test holes or exploratory drilling. The cost of reshaping scoured or eroded ar eas shall be included in the cost of other pay items. 1590 The cost of surface roughening shall be included in the cost of other pay items. The cost of identification of borrow areas, archeological investigations, and changes to construction operations caused by the identification of an archeological site shall be included in the cost of borrow, unless otherwise agreed to in writing. The cost of all classes of excavation, ex cept required borrow, within the limits of linear grading shall be included in the cost of linear grading. The cost of geotextiles shall be included in the cost of other pay items. The costs for the use of coal ash in embankment construction, including, but not limited to testing of the material, encasement, additional erosion and sediment control measures, lateral underdrains and all incidentals shall be included in the cost of other pay items in this section.