163 Lines, grades, and cross-sections of ditches shall be as shown on the plans, unless otherwise established to obtain proper drainage. 500 Ditches and gutters emptying from cuts onto embankment shall be constructed to avoid eroding the embankment. Exploration of underground drainage a nd sinkholes may be required, and payment will be hereinafter provided. Should any underground drain be encountered, the location of which is not shown on the plans, notification shall be made at once. Drainage shall be explored as directed an d, if deemed necessary, taken care of under applicable provisions of these specifications, or as otherwise directed. 510 If existing surface drains, tile drains, se wers, or other undergr ound drains, or parts thereof, are not to be replaced or are not required by the terms of the contract or directed to be changed, whether such drainage facilities are shown on the plans or not, all such drainage facilities or parts thereof shall be protected, preserved, and satisfactorily continued in use without change. If in the prosecution of the work such existing drainage is changed or interrupted, or through negligence such drainage is interrupted or damaged, satisfactory perm anent repairs shall be immediately provided or adequate temporary drainage facilities shall be maintained until permanent repairs are made. If temporary facilities are provided, before the work is accepted, such damage or interrupted drainage facilities shall be restored to the original condition or 520 to an altered state which is at least equal to their original condition. If slopes or ditches which were graded for a grading contract become eroded or scoured during the paving contract work, the scoured or eroded areas shall be reshaped to the original cross-section and reseeded or resodded as shown on the plans, all in accordance with 208 and 621. When so provided by the plans or special provisions, or when ordered, all tile drains, sewers, or other underground drains encountered in the prosecution of the contract shall be repaired, replaced, extend ed, reconstructed, connected, or otherwise 530 changed. Unless otherwise provided in the contract, the cost of replacing, restoring, or connecting an underground drain which is substantially in its original location and incidental to roadway and drainage excavation, structures, or other drains will not be paid for directly, but the cost thereof shall be included in the cost of various pay items. Unless otherwise provided, any necessary drainage change or restoration not shown on the plans and not due to negligence or operations of the Contractor will be paid for at the contract unit price or prices thereof. If there is no such contract unit 540 price or prices, such work shall be done and payment made in accordance with 104.03. 203.14 164 203.15 Excavating Rock If material is encountered during excavation which appears to belong in the classification of rock excavation in accordanc e with 203.03, notification shall be made in writing. Ample time shall be allowed to make such investigation and measurements that are necessary to determ ine the class and volume of the material in question. Exploratory cores shall be taken from the top of the rock to approximately subgrade elevation as directed. The cores shall be cut with standard diamond core bits 550 and series X double tube core barrels to obtain 2 1/8 in. diameter samples. All cores shall be suitably marked and identified to show the location of the core by station, offset from centerline, elevation of top of rock, depth below top of rock, and percent recovery within each core. All cores shall be retained. The cores shall be placed in suitable compartmented wooden boxes in the order in which removed from the boring, with dividers between core runs. The top and bottom of each run shall be appropriately marked. The cores shall be trans ported to a location as directed. The top of rock elevations shall be determined prior to locating the top of soil cut slopes where finished rock slopes are planned to be 1:1 or steeper. 560 Final breakage of rock excavation shall be in accordance with, or closely to, the slope lines as shown on the plans unless different slope lines are fixed, and the Contractor so notified. The final slopes shall be left reasonably smooth and uniform, and all loose and overhanging rock removed. Unless otherwise specified, no rock shall finally project more than 1 ft beyond established slopes. If natural seams intersect an established slope, the excavation may be carried, with permission, along the face of such seams for the distance approved. Rock shall be excavated to the required elevation for the full width of the roadbed 570 as shown on the plans or as directed. Where rock is excavated below the required elevation, the area shall be backfilled to the subgrade elevation with crushed stone, spalls, subbase material, or other approved granular material, which shall be shaped and compacted to the required elevation and cross-section. Exploratory drilling, which shall consist of drilling holes for the purpose of determining the existence of cavities affecting underground drainage and possible sinkholes in cut sections, may be required at locations as directed. Unless otherwise directed, the holes shall be drilled on the centerline of the proposed pavement at approximately 100 ft intervals and shall extend for a depth of 7 ft below the proposed 580 grade and have a minimum diameter of 1 1/2 in. Where cavities are discovered on centerline, additional holes shall be drilled at 25 ft intervals along the edge of the proposed pavement, and unless otherwise directed, extend for a depth of 7 ft below the proposed grade. Where any cavity is discovered or exposed having a minimum cover of less than 5 ft, the cover shall be removed, and the treatment of such areas shall be in acco rdance with details in the plans or as otherwise directed. 203.15 The final surface of rock excavation under the roadbed area shall be left so that 590 drainage between the rock surfaces and any material placed thereon will be substantially complete. Where seams of clay or other soft material 1 ft or less in thickness are encountered in rock excava tion, the volume of such seams will be considered as rock excavation and paid for as such. Unless otherwise specified or directed, rock shall be pre-split by drilling and the use of explosives in such a manner as results in minimum breakage outside neat lines of the typical cross-section and slope stakes as established. Deposits of commercial building stone outside the right-of-way shall not be damaged. Holes for pre-splitting shall be drilled along the established slope stake lines. The holes shall be from 2 to 600 4 in. in diameter and, unless otherwise dir ected, be spaced approximately 3 ft apart. Holes shall be drilled approximately 2 ft below the established grade of the cut, or the predetermined bench elevation, or as directed. The maximum depth of any pre-split lift shall be 30 ft, unless otherwise directed. If more than one lift is required, the first line of drill holes shall be set in such a manner as to allow for a specified offset for each su cceeding lift and an offset of 2 ft from the back of the paved side ditch line. The explosives used and the method of loading depends on the material to be blasted. These explosives may vary from a single strand of detonating cord, for blasting unconsolidated formations, to a solid column of 610 dynamite for massive formations. However, the explosive shall be of a type to accomplish the pre-splitting with a minimum of breakage outside the excavated area. After the charges are placed, the holes sha ll be filled with sand or other suitable granular material. Except as indicated below, all pre-splitting charges shall be detonated simultaneously by the use of instantaneous electric blasting caps or by means of a detonating cord trunkline. The line holes shall be fired before the main excavation is blasted. Pre-splitting shall be kept well in advance of regular blasting operations. Primary blasting holes shall be drilled no less than 6 ft from the pre-split face, unless 620 otherwise directed. If additional charges are required, holes shall be placed at 1/2 the distance of a full depth hole to a depth such that the bottom of the hole clears the pre-split face approximately 2 ft. The pre-split face shall deviate no more than 6 in. from the front line of drill holes or more than 12 in. from the back line of drill holes, except where the character of the rock will unavoidably result in some irregularities. The amount of explosives per shot for instantaneous firing or the amount of explosives per delay for delay firing sha ll not be great enough to damage nearby structures, rock formations, or other property. Where commercial building stone formations are located in the effective vicinity, adequate seismograph readings shall 630 be obtained, with no additional payment, as evidence that blasting operations have not altered existing commercial building stone formations outside the right-of-way limits of the project. 203.15 166 Permission may be granted to use machine methods to establish the finished slopes in those cuts where machine methods are used to remove roadway excavation, provided final machine finished slopes are equal or superior to that which would be obtained by pre-splitting methods. When or where any direct or indirect damage or injury is done to public or private 640 property by or on account of any act, omission, neglect, or misconduct in the execution of the work or in consequence of the non-execution thereof, such property shall be restored, with no additional payment, to a condition similar or equal to that existing before such damage or injury was done by re pairing, rebuilding, or otherwise restoring as directed, or such damage or injury sh all be made good in an acceptable manner. No direct payment will be made for pre-splitting, but the cost thereof shall be included in the pay item of rock excavation or unclassified excavation.
203.16 Peat Deposit Treatment 650
If construction is specified at a location where a peat deposit is to be treated, the deposit shall be treated ahead of paving operations to obtain maximum settlement. If settlement has not been obtained when paving operations are at the limits of any peat deposit treatment, a gap in the pavement shall be left as directed. Gaps not constructed as part of the project will become an exception to the contract. Treatment shall be by the following methods: (a) Treatment of Existing Fills If the required alignment is on an existing fill over a peat deposit, treatment may 660 be required by any one or any combination of the following methods: 1. removal of the existing fill with or without the removal of the underlying peat and of the material at the sides of the existing fill;
203.17 Cased Test Holes As displacement progresses, cased test holes shall be placed at locations as
directed to determine the extent of peat displacement and for use in conjunction with final measurement. These holes shall extend to the bottom of the deposit. The boring shall be conducted in such a manner that accurate information may be obtained as to the nature of the materials th rough which the test holes ar e placed. If these test holes indicate that full displacemen t has not been obtained, th e remaining peat shall be 750 blasted or additional treatment shall be performed as required. Unless otherwise specified in writing, ca sed test holes shall be placed by hydraulic boring. The external casing shall be a minimum of 2 in. in diameter and of such additional size as to perform the operation satisfactorily. A continuous supply of fresh water shall be jetted through an internal pipe so that the wash water and loosened material is carried to the surface between the jet rod and the external casing. Pumps and other miscellaneous tools and equipment shall be used as required to perform a satisfactory operation.
203.18 Embankment Construction Embankment construction shall consist of constructing roadway embankments,
including preparation of the areas upon which they are to be placed; the construction of dikes within or outside the right-of-way; the placing and compacting of approved material within roadway areas where unsuita ble material has been removed; and the placing and compacting of embankment material in holes, pits, and other depressions within the roadway area. Only approved materials shall be used in the construction of embankment backfill. Recycled concrete pavement shall be from past documented Department projects. RAP shall be the product resulting from the cold milling or crushing of an existing HMA pavement. Rocks, broken concrete, RAP, or other solid 770 materials shall not be placed in embankment areas where piling is to be placed or driven. 203.17 169 Recycled concrete pavement shall meet the gradation requirements of B borrow in accordance with 904.06. Construction re quirements shall be in accordance with 203.20(a) or 211.03. Only RAP particles measuring 2 in. or less in all directions shall be incorporated into the top 5 ft of the embankment. RAP particles incorporated anywhere in the embankment shall be 5 in. or less. 780 When two sizes are used for one embankment, materials shall be separated with a layer of geotextile in accordance with 918.02(c), Type 2A. Geotextile used between recycled material lifts shall be included in the cost of the embankment pay item. Recycled concrete pavement and RAP sha ll not be mixed together or with other materials. When two or more approved materials are allowed for one embankment, materials shall be separated with a layer of geotextile in accordance with 918.02(c), Type 2A. Geotextile used between recycled material lifts shall be included in the cost of the embankment pay item. 790 Recycled concrete pavement or RAP shall only be used below the elevation of the pavement underdrains. Compacted lift thickness for RAP shall not be greater than 6 in. within the top 5 ft of the embankment. Where the depth of the embankment exceeds 5 ft, the compacted lift thickness for RAP shall not be greater than 12 in. Recycled concrete pavement and RAP shall not be used within 2 ft of the water table. Recycled concrete pavement shall be constructed in accordance with 203.20. RAP shall be constructed in accordance with 203.23 or 203.24. Proofrolling in accordance with 203.26 shall be performed to cover the entire grade for every 5 ft of fill. 800 A geotextile in accordance with 918.02(c), T ype 2B shall be placed in accordance with 214 prior to the placement of subgrade treat ment Type IC, Type II, or Type IV in accordance with 207 when recycled conc rete pavement or RAP is used for embankment construction. Recycled concrete pavement or RAP shall not be used for embankment construction when subgrade Type I, Type IBC, or Type IBL is specified. Geotextile shall be placed completely covering the top of the embankment. A minimum 24 in. soil encasement shall be constructed concurrently with the recycled concrete pavement or RAP lift. The soil encasement shall be suitable for vegetation growth and shall be constructed in accordance with 203.09. 810
203.19 Embankment Over and Around Structures Fill shall not be placed against any new masonry abutment, wingwall, retaining wall, or culvert, or over any culvert, bridge, or arch until approved. Applicable provisions of 702.23 shall be met.
Filling around culverts, bents, and piers, and fill below the natural ground surface at abutments, wings, and retaining walls shall be deposited on both sides to approximately the same elevatio n at the same time. Piers or bents shall not be displaced 203.19 170 and shall be checked for proper location as the work progresses. Corrective measures 820 shall be made if necessary. Filling at arch structures shall be carried up in horizontal layers, symmetrically from haunch to crown, and simultaneously over and against all piers, abutments, and arch rings. Wedging action of filling material against structures shall be prevented. If directed, back slopes of excavation shall be destroyed by stepping or serrating. The embankments around the end bents shall be constructed to approximate subgrade elevation for a distance of no less than 75 ft. This work shall be done before piling in the end bents are driven, and before the end bent or abutment is constructed. 830 Compaction shall be in accordance with 203.23. After the embankments are completed, the embankments shall be excavated to construct the end bents and berms. Before driving piles, pilot holes to receive the piling shall be predrilled through the embankment in accordance with 701.09(a). After the piles have been driven, the space between the pile and the predrilled hole shall be backfilled with granular material as directed. If the embankment in the area of the end bents is to consist of sand, gravel, or other permeable material in which a predrilled hole would not remain open, the piling shall be driven before the embankment is constructed. No direct payment will be made for excavation of the embankment at the end bents or abutments, or for predrilling, backfilling holes, or excavating fill; those costs shall be included in the 840 cost of other pay items. 203.20 Rock and Shale Embankment Utilization of these materials in embankment construction shall be in accordance with the following.
203.22 Embankment Over Existing Roadbeds If embankment for new pavement is to be placed over an area where a rigid 960
pavement or any pavement havi ng a concrete base is in place, or in other cases when required, the upper surface of which is 1 ft or less below the subgrade elevation of the proposed new pavement, the existing old pave ment, including any concrete base, shall be removed. The method of removal, dis posal, and basis of payment shall be in accordance with 202.05 and 202.14. If embankment for new pavement is to be placed over an area where an existing rigid pavement is in place, the upper surface of which is more than 1 ft but less than 3 ft below the subgrade elevation of the proposed new pavement, or in other cases when required, the existing pavement shall be broke n. Pavement shall be broken so the area 970 of any individual unbroken slab does not exceed 1 sq yd. If embankment for new pavement is to be placed over an area where an asphalt filled brick-type or an asphalt-type surface on a concrete base is in place, and such existing surface is more than 1 ft but less th an 3 ft below the subgrade elevation of the proposed new pavement, or in other cases when required, the brick and cushion material, or the asphalt courses, shall be removed and the concrete base broken. Removal of the surfacing material, breaking the base, disposal of removed material, and basis of payment shall be in accordance with 202.05 and 202.14. 980 If embankment for new pavement is to be placed over an area where a flexible-type pavement is in place, the top of which is at the approximate elevation of, or is 1 ft or less below the required subgrade elevation of the proposed new pavement, the existing pavement shall be loosened to the depth directed, but no less than 1 ft. This loosened material shall be spread uniformly over the full width of the subgrade plus 1 ft on each side and compacted. No direct payment will be made for this loosening, spreading, and compacting, the co st thereof to be included in the various pay items of the contract. If embankment for new pavement is to be placed over an existing macadam, the 990 surface of which is more than 1 ft but less than 3 ft below the subgrade elevation of the proposed new pavement, the existing macadam shall be loosened to a depth sufficient to prevent possible trapping of water above the existing surface. No direct payment will be made for this loosening, the cost thereof to be included in the various pay items of the contract. Where the existing roadbed is too narrow, except as otherwise herein provided, new pavement shall not be placed partly on old and partly on new embankment. If the fill supporting an existing roadbed is 1 ft or more in depth, and is too narrow to carry the entire width of the proposed new pavement, the existing width of roadbed shall be 1000 taken down to include the new roadbed width and rebuilt from the lowest elevation of 203.22 174 the disturbed old roadbed to the required new width. This rebuilding shall be in accordance with these specifications for cons tructing embankment and as directed. For the necessary tearing down of the existing embankment, payment will be made at the contract unit price per cubic yard for the class or classes of excavation encountered. If an embankment is to be widened, due precautions shall be taken to ensure a firm foundation. After all sod and other perishable material has been removed, the existing shoulders shall be plowed down 2 ft out from the existing pavement. This material shall be used for widening. Benches, a minimum of 4 ft wide, shall be cut into 1010 the slope of the old embankment, unless otherwise directed. The materials from plowing down the shoulders and benching the slopes shall be deposited, spread, and compacted as set out herein for embankment, after which any remaining required embankment shall be finished with additional material, deposited and compacted in like manner. No direct payment will be made for benching, plowing, spreading, and compacting, the cost thereof to be included in the various pay items of the contract.
203.23 Embankment other than Rock, with Strength or Density Control
The compaction will be determined by dynamic cone penetrometer, DCP, testing in accordance with ITM 509 and the moistu re content in accordance with ITM 506. 1020 Soil classification will be performed in ac cordance with the ITM 512 and the following DCP blow counts will be used for compaction control: 203.23 175 Textural Classification Maximum Dry Density (pcf) Optimum Moisture Content Range (%) Acceptable Minimum DCP value for 6 in. for 95% compaction Acceptable Minimum DCP value for 12 in. for 95% compaction Acceptable Minimum DCP value for 6 or 12 in. for 100% compaction CLAY SOILS Clay < 105 19 - 24 6 * Clay 105 - 110 16 - 18 7 * Clay 111 - 114 14 - 15 8 * SILTY SOILS Silty 115 - 116 13 - 14 9 * Silty 117 - 120 11 * SANDY SOILS Sandy 121 - 125 8 - 12 12 * Sandy > 125 15 * GRANULAR SOILS - STRUCTURE BACKFI LL and A-1, A-2, A-3 SOILS No. 30 6 9 No. 4 7 10 1/2 in. 11 14 1 in. 16 19 * Test section re quired in accordance with ITM 513. Unless otherwise specified, all material directed to be compacted in accordance with 203.23 shall meet the acceptable minimum DCP value for 95% compaction. Subgrade shall meet the acceptable minimum DCP value for 100% compaction when required. As an alternate, all embankments shall be compacted to at least 95% of their 1030 maximum dry density and all subgrade shall be compacted to at least 100% of their maximum dry density. In situ density will be determined in accordance with AASHTO T 191 and the moisture content as specified. For clay, silty, and sandy soils compacted to 100% of their maximum dry density, a test section is required in accor dance with ITM 513 for DCP testing. Clay soils shall be constructed and tested with DCP in 6 in. lifts, whereas silty, sandy, and granular soils shall be constructed in 6 in. lifts and tested with DCP for 12 in. 1040 The moisture compaction range for all soil types shall be as follows: 203.23 176 Soil Type Moisture Compaction Range Clay (< 105 lb/cu ft) -2 to +2% of optimum moisture content Clay (105 - 114 lb/cu ft) -2 to +1% of optimum moisture content Silty and Sandy (> 114 lb/cu ft) -3 % to optimum moisture content Granular 5 to 8% DCP testing will be performed in accordance with the Frequency Manual at random locations determined in accordance with ITM 802. Moisture testing will be performed in accordance with the Frequency Manual. If the embankment material is too wet or too dry, either the material shall be 1050 aerated to remove excess moisture or wate red and disked to increase the moisture content, until in either case the moisture content is within the specified range. Sufficient moisture tests will be made to ensure that this range is maintained throughout the embankment. The embankment material shall be placed in uniform level layers, left properly shaped as set out above, and compacted with approved compacting equipment. Compacting equipment shall include at least one 3-wheel roller or other approved compacting equipment capable of providing a smooth and even surface on the embankment as directed. 1060 Each lift shall be disked or treated by some other mechanical means which shall ensure the breaking up of any existing lumps and clods. The loose depth of each lift shall be su ch that the required compaction can be obtained, but in no case shall it exceed 8 in . Where a tamping roller is used, the loose depth of lift shall not exceed the length of th e tamper feet. The surface area of the end of each foot of the tamping roller shall be no less than 5 1/2 sq in.
203.23.1 Coal Ash Embankment 1070
When used as borrow, coal ash shall be placed in the em bankment, compacted, and encased upon delivery to the project unless stockpiled at an approved location and in an approved manner. The Contractor shall include appropriate measures to prevent the movement of coal ash from the embankment area. These measures include, but are not limited to controlling stormwater runoff and fugitive dust. The top of coal ash embankments shall be temporarily encased if embankment construction will be delayed for more than seven days or if weather conditions warrant encasement. Control measures shall be amended into the SWQCP in accordance with 205. 1080 Coal ash shall not be mixed with other embankment materials within a given lift of the embankment. 203.23.1 Coal ash shall not be placed in any of the following locations:
203.25 Embankment Without Stiffness Control
When aggregate is used for embankment construction and it is not possible to 1250 perform stiffness testing in accordance with ITM 508 or strength testing in accordance with ITM 509, such material shall be comp acted with several passes of crawler-tread equipment or with approved vibratory equipment, or both. The equipment weight shall be at least 10 t. The materials shall be placed in lifts not to exceed 9 in. loose measurements, or as directed by the Engin eer. Each lift shall be compacted with a minimum of five passes. The tread areas shall overlap enough on each trip so that the entire embankment is compacted uniformly. When the embankment reaches 24 in. below the proposed subgrade elevation, proofrolling shall be performed in accordance with 203.26. Proofrolling shall also be performe d at every 5 ft of fi ll placed. Any defect shall be corrected as directed. Upon acceptance, a layer of geotextile in accordance 1260 with 918.02(a) Type 2B, shall be placed and the remaining embankment shall be constructed with No. 53 aggregate in accordance with 301. 203.25 182 At locations inaccessible to the above compacting equipment, the required compaction shall be obtained with approved mechanical tamps or vibrators, in which case the depth of lifts, loose measurement, shall not exceed 4 in.
203.26 Proofrolling When proofrolling is specified, the work shall be performed with an on-highway
dump truck with a minimum tire pressure of 90 psi. 1270 Proofrolling for original ground or embankment construction shall be performed using a dump truck weighing at least 15 t. Proofrolling for subgrade preparation shall be performed using a dump truck weighing at least 33 t. All proofrolled surfaces shall be covered completely with a single pass. Operating speed of the proofrolling truck shall not exceed 2 mph. Deflections or rutting in excess of 1/2 in. shall require remediation of the surface as directed. Deflection or rutting in excess of 3 in. shall require corrective remediation measures and the Department’s Geotechnical Engineering Division will be contacted. 1280 Proofrolling shall be performed after remediation measures on embankment or subgrade prior to the placement of additiona l material. There shall be one or two complete coverages as directed. Roller marks, irregularities, or failures shall be corrected.
203.27 Method of Measurement
203.28 Basis of Payment
The accepted quantities of excavation and embankment will be paid for at the 1430 contract price per unit of measurement for each of the pay items listed below which is included in the Schedule of Pay Items. Common excavation and unclassified excavation will be paid for on the unit basis of contract quantities in accordance with 203.27(a), without any quantity limit, unless otherwise shown in the Schedule of Pay Items. Combined quantities of borrow, common and unclassified excavation not exceeding 15,000 cu yds will be paid for on the basis of contract quantities in accordance with 203.27(a) with no adjustme nt to plan shrinkage factor. Except as noted above, borrow, as well as all other excavation, will be paid for on the basis of measured quantities in accordance with 203.27(b), unless otherwise shown in the Schedule of Pay Items. Linear grading will be paid for at the contract unit price per 1440 linear foot. If the class of excavation is linear grading, additional borrow and the excavation of and disposal of unsuitable material not included as pay items will be paid for as follows: 203.28 186 If the total quantity exceeds 5,000 cu yds at a given location, it will be paid for at $8.00 per cu yd. If the total quantity exceeds 1,000 cu yds, but does not exceed 5,000 cu yds at a given location, it will be paid fo r at $12.00 per cu yd. If the total quantity does not exceed 1,000 cu yds at a given locati on, it will be paid for at $15.00 per cu 1450 yd. Linear grading includes only such grading within the construction limits. All grading the Contractor is directed to perform outside the construction limits, except for the Contractor’s convenience, will be paid for in accordance with 104.03 or 109.03 unless such grading is shown on the plans or in the Contract Information book. Existing concrete building foundations, c oncrete walls, concrete columns, or concrete steps not visible and not shown on the plans within the limits of the planned excavation will be paid for at 10 times the contract unit price per cubic yard for 1460 common or unclassified excavation, whichever is set out as a pay item. Unless a waste area is established within the contract limits, the minimum pay for this work will be $80.00 per cu yd. Excavation and disposal of unsuitable material will be paid for at the contract unit price for the class of excavation involved. If no such pay item is included in the contract and embankment is included as a pay item, the excavation and disposal will be paid for at the contract unit price for embankment, unless otherwise directed. If there is no pay item for rock excavation and such is encountered, it will be paid 1470 for at $125.00 per cu yd for quantities less than or equal to 100 cu yds. For quantities greater than 100 cu yds pay will be determined in accordance with 104.03. If there is no pay item for common excav ation and if such is encountered, it will be paid for at the contract unit price per cubic yard for borrow. If the contract includes a pay item fo r waterway excavation, and if class Y excavation is encountered and there is no pay item for such, the class Y excavation will be paid for at 10 times the contract unit price per cubic yard for waterway excavation, or $100.00 per cu yd, whichever is greater. 1480 If the contract does not include a pay item for waterway excavation and such is encountered, pay will be determined in accordance with 104.03. If excavation is necessary to investigate or to seal sinkholes, or to explore underground drainage, the accep ted quantity involved at each location will be paid for as follows. The first 10 cu yds or fraction thereof will be paid for at 10 times the contract unit price for the class of excavation encountered. The next 40 cu yds or fraction thereof will be paid for at seven times the contract unit price for the class of excavation involved. Additional quantities will be paid for at three times the contract 1490 unit price per cubic yard for the class of excavation involved. 203.28 187 Material overlying the peat deposits which is excavated and used in embankment will be considered as common excavation and will be paid for as such. Excavation for standard side ditches or other side ditches which are constructed through peat areas at locations shown on the plans, or where directed, will be paid for at the contract unit price per cubic yard for common excavation. Mechanical treatment of embankment foundation soils will be paid for by the square yard as embankment foundation soils treatment. 1500 Cased test holes and exploratory drilling will be paid for at the contract unit price per linear foot. If there is no pay item for borrow, the costs of identifying the borrow areas, the archeological investigation, all required permits, and the opening and closing of the borrow area will be included in a change or der developed in accordance with 109.05 and paid for as borrow area. If the contract documents do not identify excess excavation or require removal of 1510 any items from the site, the cost of identifying a disposal area, archeological investigation, all required permits, and the opening and closing of the disposal area will be included in a change order devel oped in accordance with 109.05 and paid for as disposal area. If a type of excavation for which no pay item exists is required and the new type of excavation requires the Contractor to use equipment not otherwise being used on the contract, all cost involved in determining the type of equipment necessary to complete the work and making this equipment available for the project will be included in a change order developed in accordance with 109.05 and paid for as 1520 additional mobilization and demobilization. If a type of excavation for which no pay item exists is required and the new type of excavation requires additional traffic control not shown on the plans or results in traffic control being required for an additional period of time, all cost involved in providing the additional traffic control will be included in a change order developed in accordance with 109.05 and paid for as additional maintaining of traffic. Coal ash used as borrow will be paid for at the contract unit price for borrow. Excavation of coal ash will be paid for at the contract unit price for common excavation. Payment will be made under: Pay Item Pay Unit Symbol Borrow ....................................................................................... CYS 203.28 188 Breaking Pavement .................................................................... SYS Cased Test Holes ....................................................................... LFT 1540 Embankment Foundation Soils Treatment ................................ SYS Embankment .............................................................................. CYS Excavation, Common ................................................................ CYS Excavation, Peat ........................................................................ CYS Excavation, Rock ....................................................................... CYS Excavation, Unclassified ........................................................... CYS Excavation, Waterway ............................................................... CYS Excavation, Y ............................................................................ CYS Exploratory Cores ...................................................................... LFT Exploratory Drilling .................................................................. LFT 1550 Linear Grading .......................................................................... LFT Water for Shale .......................................................................... kGAL. If embankment is specified as a pay item, borrow and common excavation, unless otherwise specified, will not be paid for directly. The costs thereof shall be included in the cost of embankment. Such price shall be full compensation for preparation of the natural ground on which the embankment is to be placed and excavating, hauling, placing, spreading, and compaction of mate rials in accordance with 203.23. The costs of labor, equipment, tools, and necessary incidentals shall be included in the cost of embankment. The cubic yards of suitable material used in the embankment excavated 1560 from the right-of-way and paid for under a specific pay item will not be deducted from the embankment quantities. The quantity of material to be paid for as B borrow and placed within the embankment area as specified will be deducted from the quantity of embankment. The costs of excavating, backfilling, disposal of surplus material, labor, equipment, tools, and necessary incidentals necessary shall be included in the cost of excavation required to seal sinkholes or explore underground damage. The costs of all excavated or displaced p eat, regardless of de pth, peat disposal, 1570 temporary surcharge, machine operation, and machine availability shall be included in the cost of peat excavation. However, the Department may provide temporary right-of-way for peat dispos al when so specified. Cost for providing additional lighting for grading operations shall be included in the cost of other pay items in this section. No payment will be made for the construction or restoration of borrow or disposal sites. 1580 No payment will be made for the inspection of disposal and borrow areas for wetland identification, obtaining of permits, the development and construction of all mitigation measures, or the fulfillment of permit requirements. 203.28 189 The cost of boring the holes, casings and fittings, labor, equipment, tools, and all necessary incidentals shall be included in th e cost of cased test holes or exploratory drilling. The cost of reshaping scoured or eroded ar eas shall be included in the cost of other pay items. 1590 The cost of surface roughening shall be included in the cost of other pay items. The cost of identification of borrow areas, archeological investigations, and changes to construction operations caused by the identification of an archeological site shall be included in the cost of borrow, unless otherwise agreed to in writing. The cost of all classes of excavation, ex cept required borrow, within the limits of linear grading shall be included in the cost of linear grading. The cost of geotextiles shall be included in the cost of other pay items. The costs for the use of coal ash in embankment construction, including, but not limited to testing of the material, encasement, additional erosion and sediment control measures, lateral underdrains and all incidentals shall be included in the cost of other pay items in this section.