........................................ GAL. type CYS TON DRUM EACH Regulated Materials, Transport, _____ ..................................... GAL. type CYS TON DRUM 670 EACH Structures and Obstructions, Remove........................................ LS Testing for Asbestos .................................................................. EACH Testing for Wastes, _____ ......................................................... EACH type Underground Storage Tank, Liquid Waste Disposal, _____ ..... GAL. type Underground Storage Tank, Remove and Dispose, Under 3,000 Gallons Capacity ............................................ EACH Underground Storage Tank, Remove and Dispose, 680 3,000 through 6,000 Gallons Capacity ............................... EACH Underground Storage Tank, Remove and Dispose, 6,000 through 10,000 Gallons Capacity ............................. EACH Underground Storage Tank, Remove and Dispose, Over 10,000 Gallons Capacity ............................................ EACH
The cost of removal and disposal of buildings, foundations, debris and unsuitable material, guide posts, delineator posts, temporary road material, existing asphalt patches, the filling of abandoned wells; terminating utilities; sealing floor drains where necessary; breaking basement floors; furnis hing and erecting all barricades, fences, 690 and other safety measures necessary for ade quate protection of the sites; and backfill of basements or depressions left by demolition shall be included in the cost of the pay items of this section. All fence posts a nd concrete footings shall be completely removed and the resulting holes backfilled accordingly. If no contract price is listed in the Schedule of Pay Items for work set out herein, no direct payment will be made for compliance with the requirements for such work, except as set out herein. The cost thereof shall be included in the cost of other pay items. 700 If the houses and buildings listed for removal from a designated parcel are not in existence at the time of the letting, no payment will be made for removal work on such parcel.
The cost of removing the tanks and all pipe from the ground, removal and disposal of all miscellaneous parts associated with the tank such as concrete pads or holding devices, filing of all required notifications, preparation and implementation of a site 202.14 150 operation plan, excavation of all materials necessary in order to remove the tank, compliance with closure requ irements, all necessary pedestrian safety fencing, cleaning and draining of tanks and pipes, dismantling or transport, and all required 710 record keeping or reports shall be included in the cost of underground storage tanks, remove and dispose. However, disposal of waste contents and removal of contaminated soil will be paid for separately. No payment will be made for work not performed in accordance with the specifications or not required by the contract. The cost of all on-site or off-site storage of the materials shall be included in the cost of transportation. All disposal fees and recycling or treatment costs required for regulated materials found within the project limits shall be included in the cost of regulated materials, 720 dispose. If regulated materials are treated on site and not disposed of at an approved location, payment will be in accordance with 104.03. The cost of removal of all regulated asbestos-containing materials and all safety procedures shall be included in the cost of regulated asbestos containing materials, remove. The cost of packaging regulated materials, excavation, restoring ground lines, and maintaining and filing required documents and reports shall be included in the cost of the pay items. 730 The cost of removal of regulated asbestos-containing materials shall include only the removal of material identified in the contract or by the Engineer as regulated asbestos-containing material. Regulated asbestos-containing materials include the following:
friable or will be subjected to sanding, grinding, cutting, abrading, 740 or burning;
high probability of becoming or has become crumbled, pulverized, or reduced to powder by the forces expected to act on the material in the course of normal demolition operations. Unless directed by the contract or the Engineer, the cost of asbestos removal shall 750 not include the removal of Category I or II non-friable asbestos-containing material that is not friable or does not have a high probability of becoming friable but which becomes friable because the Contractor uses demolition methods that cause such 202.14 151 materials to become regulated. Such cost shall be included in the cost of other pay items.
The cost of all labor, equipment, materials, and documentation required for complying with the applicable laws, regulations and procedures, including but not limited to, licenses, permits, other legal fees, or disposal charges shall be included in the cost of the pay items. No payment will be made for work not performed in 760 accordance with the specifications or is not required by the contract.
The cost of removal of specific work shall include the removal and disposal of such obstructions, the necessary excavation required, salvage of materials removed, their custody, preservation, storage on the right-of-way, and disposal as provided herein. All damage to existing facilities caused by the Contractor’s operations or equipment shall be satisfactorily replaced or repaired with no additional payment.
If it is necessary to package the contaminated soil in a container, the cost of the container and all cost related to packaging shall be included in the cost of removal. 770 The cost of all excavation pertaining to contaminated soil, removal of all soil within the limits established by the Engineer, restoring ground lines, maintaining required records and filing of reports shall be included in the cost of contaminated soil, remove. No payment will be made for work beyond the limits established by the Engineer, work not performed in accordance with the specifications, or work not required by the contract unless in accordance with 104.03. The cost of all handling of the product, removal of the product from the tank, disposal, all required packaging, and transportation shall be included in the cost of underground storage tank, liquid waste disposal. 780 All necessary cleanup of spills caused by the Contractor will not be paid for. For steel that the Contractor elects to take to a recycling facility, the cost of handling, hauling, and all other costs invol ved with removing and properly disposing of existing steel at a recycling facility shall be included in the cost of present structure remove, or present structure remove, porti ons pay item. The Depa rtment will withhold a payment equal to 50% of the present structure remove, or present structure remove, portions pay item until the Contractor presen ts a receipt from the recycling facility indicating that the recycling facility is now in possession of the steel. 790
For steel that will become the property of the Contractor, the cost of cleaning existing steel, removal of mill scale, testing, disposal of the waste stream, containment, and all other costs involved with removing and properly disposing of the existing coating shall be included in the cost of pr esent structure remove, or present structure remove, portions pay item. The Departme nt will withhold paym ent of 50% of the present structure remove, or present structure remove, portions pay item until the Contractor presents a receipt from the facility where the waste stream disposal occurred. 202.14 152