SECTION 104 SCOPE OF WORK
104.01 INTENT OF CONTRACT. The intent of the Contract is to provide for the
construction and completion of the full scope of the work described. Furnish all labor, materials, equipment, tools, transportation, and supplies required to complete the work according to the Contract.
104.02 Alterations of Plans Or Character of Work.
104.02.01 General. At any time, and without invalidating the Contract or releasing
the surety, the Engineer reserves the right to make, in writing, changes in quantities and alterations in the work when necessary to complete the project satisfactorily. Perform the work as altered. When alterations or changes in quantities si gnificantly change the character of the work under the Contract, the Department will adjust the Contract. The Department will not consider loss of anticipated profits. Before performing the significantly changed work, reach agreement with the Department concerning the basis for the adjustment. Absent an agreement, the Engineer will determine a fair and equitable adjustment. An adjustment to the unit price for an item whose final quantity is less than 75 percent of the original bid quantity will be considered if the Contractor can show that fixed expenses could not be fully recovered du e to the decreased quantity. However, total payment for the item shall not exceed 75 percent of original contract item times contract unit bid. A decrease in price due to a significant change may be requested by either party. If both the Engineer and Contractor are in agre ement with the new price then a supplemental agreement shall be executed as per Section 109.04.01. If an agreement cannot be reached then the Contractor will be directed to perform the affected work on a force account basis as per Section 109.04.02 except the final payment per unit shall not exceed what would have been made at the contract unit bid price. If the alterations or changes in quantities do not significantly change the character of the work, the Department will make payment as provided elsewhere in the Contract. A significant change occurs when:
104.02.02 Overrun and Underrun Formulas. The Department will use the
following supplemental formulas to determine the adjusted unit prices for the items listed herein when a listed item is a major item and either an underrun or overrun of more than 25 percent occurs in its constructed quantity. This formula does not apply to items not specifically listed in this Subsection. The excessive underrun of an item is defined as 75 percent of the original Contract quantity of the item minus the final quantity of the item. The excessive overrun of an item is defined as the final quantity of the item minus 125 percent of the original Contract quantity of the item. The Department will apply this subsection when all the following conditions are met:
104.02.03 Differing Site Conditions. Differing site conditions exist when one party
discovers that:
104.03 EXTRA WORK. Perform Extra Work for which there is no quantity or price in
the Contract only by supplemental agreement. The Department will pay for this Extra Work at a unit price or lump sum price agreed upon and included in a written supplemental agreement executed by all parties to the Contract as specified in Subsection
109.04 The Department will consider an extension of Contract time for Extra Work
according to Subsection 108.07. When requested by the Engineer, provide justification and all necessary documentation to support proposed prices or time extensions. The Engineer may direct, in writing, time-sensitive or emergency work be progressed while the supplemental agreement is being processed. In the event work is directed without an executed supplemental agreement, cost records shall be kept and reconciled daily conforming to specification 109.04.02. Waiting for an executed supplemental agreement when the Engineer directs work to progress as above, waives the right to claim for delays associated with the subject extra work.
104.04 RIGHTS IN AND USE OF MATERIALS FOUND ON THE WORK. The
Contractor, with the Engineer’s approval, may use on the project stone, gravel, sand, or other material found in the excavation that the Engineer determines is suitable. The Department will pay both for the excavation of such materials at the corresponding Contract unit price and for the pay item for which the excavated material is used. Replace all excavated material so removed and used with other acceptable material at no additional expense to the Department. The Department will not charge the Contractor for the materials found in the excavation and used in the work. Do not excavate or remove any material from outside the grading limits, as indicated by the slope and grade lines, without the Engineer’s written authorization. Take ownership of and dispose of any materials of value, such as merchantable timber or coal, that may be encountered during construction of the project and that are not necessary to perform or complete the work. Leave a sufficient amount of material on the site to complete the project according to the Contract. 104-3