SECTION 401 ASPHALT MIXING PLANT REQUIREMENTS
401.01 DESCRIPTION. Provide and maintain a plant and all equipment necessary to
produce and test asphalt mixtures.
401.02 Equipment.
401.02.01 All Asphalt Mixing Plants. Ensure that all asphalt mixing plants are
inspected and approved by the Department before initial use and a minimum of once annually thereafter. For initial approval, s ubmit a “Contractor’s Master Certification of Asphalt Mixing Plant and Related Equipment” form for each plant to the Engineer. For previously approved plants, submit an “Annual Renewal Certification for Previously Approved Plants and Related Equipment” form to the Engineer before beginning each season. When significant changes are made in the plant equipment or in the method of operation at an approved plant, reapply for approval. Ensure the manufacturer’s plate, listing the maximum capacity of the plant, is attached to the plant. Do not operate the plant at a production rate greater than the operational capacity of any plant component. Operate the plant so that it produces a fully coated mixture within the specified properties, gradation tolerances, and asphalt binder tolerances. When plants are in operation, the Department will require one computer with a printer attached on the site of operations for the purpose of recording and submitting test data. Ensure the computer is installed with and utilizes the following minimum system requirements: Microsoft Office 2003 Professional (full installation). Additionally, the Department will require that each Company provide at least one Internet access site for sending and receiving electronic mail.
401.02.02 Special Requirements for Batch Plants.
401.02.03 Special Requirements for Automatic Batching. Provide a system with
equipment for accurately proportioning batches of the various components of the mixture by weight in the proper sequence and for controlling the sequence and timing of mixing operations. Equip the plant with adjustable timing devices and other time-delay circuits that integrate the individual components of batching and mixing operations with the auxiliary interlock cut-off circuits necessary to stop the automatic cycling of the batching operations whenever the quantity of any ingredient falls outside the tolerance specified below: Ensure that the accumulated weight of the batches is within 2.0 percent of the total batch weight. Record batch quantities according to AASHTO M 156.
401.02.04 Special Requirements for Dryer Drum Plants.
401.03 Construction.
401.03.01 Preparation of Mixtures. Deposit the coarse and fine aggregates in the
cold elevator(s) at a rate to ensure correct and uniform temperature control of the heating and drying operations. If the supplier heats the asphalt binder outside the specified range, let it reach a temperature within the specified range before mixing it with the aggregates. The Engineer may retest or reject asphalt mixture, in storage at the plant, that has been heated by the Contractor outside the specified range. Do not use asphalt binder while it is foaming in a storage tank. Maintain the temperature of the component materials and asphalt mixture within the ranges listed in the following table: 401-6 MIXING AND LAYING TEMPERATURES ( F) Material Minimum Maximum Aggregates 240 330 Aggregates used with Recycled Asphalt Pavement (Reclaimed Materials) 240 Asphalt Binders PG 58-28* PG 64-22 230 230 330 PG 76-22 285 350 Asphalt Mixtures at Plant PG 64-22 HMA 250 330 (Measured in Truck) PG 76-22 HMA PG 64-22 WMA** PG 76-22 WMA** 310 250 350 Asphalt Mixtures at Project PG 64-22 HMA 230 330 (Measured in Truck PG 76-22 HMA 300 350 When Discharging) PG 64-22 WMA** PG 76-22 WMA** 210 240 330 * See Section 409 – Asphalt Mixtures Using Reclaimed Materials. ** See Section 109- Measurement and Payment 401.03.02 Mixing and Holding. Measure each size of aggregate and the asphalt binder separately. Regulate the proportion for each component to produce a mixture within the limits of the job-mix formula (JMF) and having all particles coated with asphalt binder. Thoroughly mix the hot aggregates at the te mperatures specified, and proportion them by weight. The Engineer may establish maximum mixing times when deemed necessary.
401.04 MEASUREMENT. Reserved.
401.05 PAYMENT. Reserved.
401-8 SECTION 402 CONTROL AND ACCEPTANCE OF ASPHALT MIXTURES
402.01 DESCRIPTION. Provide the process control and quality control testing for the
Department’s acceptance determination of all classes and types of asphalt mixtures which may be furnished either as hot mix asphalt (HMA) or warm mix asphalt (WMA) produced with water injection systems.
402.01.01 Warm Mix Asphalt (WMA) Evaluation and Approval. The
Department will evaluate trial production of WMA by use of a chemical, wax, or water injection system provided the system is installed according to the manufacturer’s requirements and satisfies the requirements of Section 401. Evaluation will include production and placement of WMA to demonstrate adequate mixture quality including volumetric properties and density by Option A as specified in Subsection 402.03.02 D). Do not place WMA for evaluation on Department projects. Provided production and placement operations satisfy the applicable quality levels, the Department will approve WMA production on Department projects using the system as installed on the specific asphalt mixing plant evaluated.
402.02 Materials and Equipment.
402.02.01 Personnel. Provide a qualified Superpave Mix Design Technologist
(SMDT) to be responsible for the submission and adjustment of the mix designs. Provide a qualified Superpave Plant Technologist (SPT) to be present during production and to perform the daily inspection, process-control, adjustments of the job mix formula, and quality control testing at the plant site for the Department’s acceptance determination. The Department will use a qualified SMDT for approval of all mix designs and a qualified SPT for verification testing.
402.03 Construction.
402.03.01 Responsibilities.
402.03.02 Contractor Quality Control and Department Acceptance.
403.03 10.
402.03.03 Mixture Verification. For volumetric properties, the Department will
perform a minimum of one verification test for AC, AV, and VMA according to the corresponding procedures as given in Subsection 402.03.02. The Department will randomly determine when to obtain the verification sample using the Asphalt Mixture Sample Random Tonnage Generator. For specialty mixtures, the Department will perform one AC and one gradation determination per lot according to the corresponding procedures as given in Subsection
402.03.02 However, Department personnel will not perform AC determinations according to KM 64-405. The Contractor will obtain a quality control sample at the same time the
Department obtains the mixture verification sample and perform testing according to the procedures given in Subsection 402.03.02. If the Contractor's quality control sample is verified by the Department's test results within the tolerances provided below, the Contractor's sample will serve as the quality control sample for the affected sublot. The Department may perform the mixture verification test on the Contractor's equipment or on the Department's equipment. 402-4
402.03.04 Testing Equipment and Technician Verification. For mixtures with a
minimum quantity of 20,000 tons and for every 20,000 tons thereafter, the Department will obtain an additional verification sample at random using the Asphalt Mixture Sample Random Tonnage Generator in order to verify the integrity of the Contractor’s and Department’s laboratory testing equipment and technicians. The Department will obtain a mixture sample of at least 150 lb at the asphalt mixing plant according to KM 64-425 and split it according to AASHTO R 47. The Department will retain one split portion of the sample and provide the other portion to the Contractor. At a later time convenient to both parties, the Department and Contractor will simultaneously reheat the sample to the specified compaction temperature and test the mixture for AV and VMA using separate laboratory equipment according to the corresponding procedures given in Subsection 402.03.02. The Department will evaluate the differences in test results between the two laboratories. When the difference between the results for AV or VMA is not within ± 2.0 percent, the Department will investigate and resolve the discrepancy according to Subsection 402.03.05.
402.03.05 Dispute Resolution. When differences between the Department and
Contractor continue to exist and impact acceptability or payment, resolve the dispute according to Subsection 113.07.
402.04 MEASUREMENT. The Department will measure asphalt mixtures by the ton.
On initial treatment and resurfacing jobs, the Department will not measure material placed in excess of the 5-percent tolerance specified in Subsection 403.03.06. The Department will not measure for payment any extra materials, methods, or construction techniques, determined by the Engineer not to be a part of the specified construction, used to protect, maintain, or repair any portion of the uncompleted work during the winter months. The Department will not measure the filling of core sample holes of asphalt mixtures for payment and will consider them incidental to the asphalt mixture. When Reshape and Compact is not listed as a bid item, the Department will not measure the preparation of the foundation for the mixture courses. The Department will not measure anti-strip additive for payment and will consider it incidental to the asphalt mixture. For initial treatment, the Department will not measure excavation at bridge ends and related disposal of materials for payment and will consider it incidental to the asphalt mixture. The Department will not measure construction of rolled rumble strips or pavement wedge texturing for payment and will consider them incidental to the asphalt mixture.
402.04.01 Weight. The Department will weigh asphalt mixtures according to Section
109. The actual weight equals the pay weight except when the aggregates used have a combined bulk specific gravity in excess of 2. 75. When the combined bulk specific gravity is greater than 2.75, the Department will determine the pay weight according to the 402-6 following formula: T = W [%AC + %MF + (%Aggregate x 2.75)/G] / 100 Where: T = Pay weight. W = Actual weight. %AC = Percent, by weight, of asphalt binder in the total mixture. %Aggregate = Percent, by weight of total mixture, of mineral aggregates excluding mineral filler. G = Calculated combined, bulk, oven-dry, specific gravity of aggregates used in the mixture, excluding mineral filler. %MF = Percent, by weight, of mineral filler. The Department will determine the bulk, oven-dry specific gravity for the fine and coarse aggregates according to KM 64-605 and AASHTO T 85, respectively. The Department will determine the frequency of testing for specific gravity of the actual project aggregates to determine the pay weight.
402.04.02 Thickness on New Construction. When the core thickness exceeds the
compacted plan thickness by more than 1/2 inch, the Department will deduct the thickness exceeding the 1/2-inch tolerance. When calculating the deduction for excess thickness, the Department will not include in the thickness measurements any leveling course placed at the Contractor’s expense or any materials placed on top of the completed base at the direction of the Engineer. When the Engineer determines the asphalt base is deficient in thickness by more than 1/2 inch from the compacted plan thickness, the Department will measure material required according to Subsection 403.03.06 B) for the overlay as asphalt base. The Department will only measure the calculated quantity necessary to bring the deficient area to the plan thickness. The Department will not measure material placed in excess of the plan thickness to achieve smooth transitions or to match grades. When the Engineer waives the overlaying requirement, he will make a reduction in payment for the theoretical quantity of asphalt base as determined deficient. The Department will not measure initial thickness check coring or coring of corrective work for payment and will consider it incidental to the asphalt mixture.
402.05 Payment.
402.05.01 Specialty Mixtures. The Department will calculate pay for OGFC, ATDB,
Asphalt Mixture for Pavement Wedge, Leveling and Wedging, Scratch Course, asphalt mixtures for temporary applications, and aspha lt mixtures for Base Failure Repair according to the Lot Pay Adjustment Schedule for Specialty Mixtures. The Department will assign a pay value for AC and gradation within each sublot and average the sublot pay values to determine the pay value for each lot.
402.05.02 Asphalt Mixtures, HMA and WMA, Including Mixtures With
Reclaimed Material. The Department will pay for the mixture at the Contract unit bid price and apply a Lot Pay Adjustment for each lot placed based on the degree of compliance with the specified tolerances. Using the appropriate Lot Pay Adjustment Schedule, the Department will assign a pay value for the applicable properties within each sublot and average the sublot pay values to determine the pay value for a given property for each lot. The Department will apply the Lot Pay Adjustment for each lot to a defined unit price of $50.00 per ton. The Department will calculate the Lot Pay Adjustment using all possible incentives and disincentives. Final payment will be made for each mixture bid item for a project, using the cumulative lot pay values. Each lots pay value will be averaged to determine the final overall bid item pay value but will not allow the bid item pay value to 402-7 exceed 1.00.
403.01 DESCRIPTION. This section includes general requirements that are applicable
to all types of asphalt mixtures. Deviations from these general requirements are indicated in the specific requirements for each type mixture Provide a Superpave Plant Technologist (SPT) or Superpave Mix Design Technician (SMDT) qualified by the Laboratories' Quality Acceptance program. Be available to address all Quality Control concerns arising during work performed under section 403. Construct one or more courses of asphalt mixture on the prepared foundation according to these Specifications and the requirements of the type specified in the Contract.
403.02 Materials and Equipment.
403.02.01 Fine Aggregate. Conform to Section 804.
403.02.02 Coarse Aggregate. Conform to Section 805.
403.02.03 Asphalt Binder. Conform to Section 806.
403.02.04 Self-Leveling Silicone Rubber Sealant. Conform to Section 807.
403.02.05 Asphalt Release Agent . Provide materials conforming to KM 64-422.
Ensure each shipment is accompanied by a certification of conformance.
403.02.06 Transport Equipment. Provide trucks for transporting asphalt mixtures
that have tight, clean, and smooth metal beds that have been sprayed with a minimum amount of release agent. Drain excess release agents from truck beds. Do not load trucks that are contaminated with an unapproved release agent. When such contamination is identified after loading, reject the load. In either case, remove the truck and respective driver from the project for the duration of the project. Equip all trucks with covers made of heavy canvas, or similar material suitable for protecting the mixture from the weather, that completely cover the loaded material.
403.02.07 Asphalt Pavers. Use asphalt pavers that are self-propelled and capable of
spreading and finishing all courses to the indicated widths and depths, line, grade, and cross section, with a smooth finish, uniform in density and texture, without requiring an undue amount of back-dressing for correcting irregularities. Equip the paver with the following:
403.02.08 Rollers. Provide self-propelled rollers that are capable of reversing
smoothly. Equip steel-wheel rollers with adjustable scrapers, spray bars, and wetting pads to keep the wheels clean at all times.
403.02.09 Small Tools and Portable Equipment. Provide all necessary small tools
and portable equipment required for satisfactory execution of the work and devices necessary for routine checks of finishing requirements. Do not use an unapproved release agent on any small tools or equipment incidental to the paving operation. Provide standard 10-foot long straightedges. Have straightedges available on the project before the work is started and all times thereafter until completion of the work.
403.02.10 Material Transfer Vehicle (MTV). In addition to the equipment
specified above, provide a MTV with the following minimum characteristics::
403.03 Construction.
403.03.01 Seasonal and Weather Limitations. Do not load trucks with asphalt
mixtures when the ambient air temperature is below 35 F. Do not place asphalt mixtures on any wet surface, when the ambient air and existing surface temperatures on the project are less than those specified in the table below, or when weather conditions otherwise prevent the proper handling or finishing of the asphalt mixtures. Between November 30 and April 1, do not place asphalt mixture courses that will become a permanent part of the work without obtaining the written approval from the Engineer. Make every effort to have all asphalt base and binder courses covered before November 30. If all asphalt mixture courses are not completed before November 30, perform all further work necessary to protect and maintain the uncompleted work during the winter months. Perform any work necessary to repair or restore the uncompleted work before the beginning of spring paving operations. Perform all work necessary to protect, maintain, or repair the base subject to the Engineer’s approval. 403-2 TEMPERATURE LIMITATIONS Minimum Ambient Air Temperature and Minimum Temperature of the Existing Surface for Placing Asphalt Mixtures ( F) Open-Graded Friction Course (OGFC) 60 SMA Base and Surface 50 Asphalt Mixture, Surface (PG76-22) 45 Asphalt Mixture, No. 4 Surface 50 Asphalt Mixture, Surface (one inch thick or less) 45 Leveling and Wedging and Scratch Course 45 Asphalt Mixture, Surface (thicker than one inch) 40 Asphalt Mixture for Pavement Wedge 40 Asphalt Mixture, Base and Binder 35 Asphalt-Treated Drainage Blanket 35
403.03.02 Preparation of Base. Prepare the foundation before placing the asphalt
mixture courses. The preparation may include fine grading and recompaction of earth or blasted rock subgrades, or crushed or natural aggregate bases. Maintain prepared subgrades and/or granular bases until placing the initial course of asphalt mixture to ensure that the foundation is true to the required grade and cross section. Grade and shape existing traffic bound base to the required grade and cross section before applying any asphalt mixture course. Wet and roll any salvable floater material into the existing traffic bound base. When required, apply curing seal, prime, or tack coat, or a combination, according to Section 406. When applying the initial asphalt mixture surfacing on the traffic bound base, excavate as necessary at both ends of all bridges within the limits of the project. Excavate deep enough to apply the total thickness of the asphalt mixture courses being constructed. The excavation should be wide enough to accommodate the width of the course, or wider when directed, and as long as necessary, up to 100 feet, for smooth transitions from the top surface course to the bridge deck. Sweep existing or previously placed asphalt mixture or concrete courses clean of all foreign material. Apply tack coat according to Section 406. Remove existing markers installed in groove s, and fill the recess with the compacted asphalt mixture. The Department will not require filling of the grooves when milling of the existing pavement is included in the Contract and the milling operation removes the grooves. Remove and dispose of the existing Type V markers off of the right-of-way. Fill the recess and any additional damaged area with co mpacted asphalt mixture within 24 hours of removal. Fill the damaged areas, even when the Contract includes milling, unless the Engineer determines the damaged areas are not hazardous to public traffic. Adjust small drainage structures such as catch basins as required to match the finished pavement, or to provide proper drainage, according to Subsection 710.03. Only when the Engineer directs, adjust manholes according to Subsection 710.03. Return manhole adjusting rings that are removed and not reused to the utility owner.
403.03.03 Preparation of Mixture.
403.03.04 Transporting Material. For all types of sizes of HMA and WMA, load all
tri-axle or larger trucks with a minimum of three drops, utilizing the three drop method to prevent segregation of the asphalt mixture. Securely fasten all covers in place on the truck before leaving the plant. During cool weather, or when an unexpected delay occurs, keep the loads covered until just before unloading. Insulate truck beds, when necessary, to maintain the specified temperature to the point of delivery. Do not use any truck that causes excessive segregation of mixture or that leaks.
403.03.05 Spreading and Finishing. Prevent segregation of the fine and coarse Aggregate Consensus Properties
Class FAA (% min) SE (% min) CAA 1 (% min) F&E (% max) 2 40 40 85/80 10 3 43 45 95/90 10 4 45 50 100/100 10 403-5 aggregates during all phases of construction. Sp read the mixtures with a paver. Heat the screed uniformly throughout its length. Do not allow flames to directly contact the mixture. Adjust the paver speed to provide the best results for the mixture being used and to coordinate with the rate of delivery of the mixture to the paver to provide a uniform placement rate without intermittent operation. Operate the screed or strike-off assembly without tearing, shoving, or gouging the mixture when laying the mixture. Operate vibrating screeds or other compacting features of the paver according to the manufacturer’s recommendations during the placement of the pavement. Use automatic screed and slope controls. However, if the Engineer determines that under certain conditions better results may be obtained without using the controls, then the Engineer may waive using either the grade cont rol or slope control requirements, or both. Notify the plant to stop shipment whenever the automatic screed controls break down or malfunction. Obtain the Engineer’s approval to manually operate the equipment, or operate it by other methods, to place the remainder of material already in transit, provided the method of operation produces results otherwise conforming to this section. Obtain vertical control for the outer edges of each mainline roadway from reference lines or by using a ski arrangement. The Department will allow obtaining horizontal control from the reference line. Automatically control the grade and slope for intermediate lines using reference lines, or a ski and a slope control device, or a dual ski arrangement. Immediately after striking off and before rolling, visually inspect each course for irregularities, and correct if necessary. Keep hand raking of the mixtures to the absolute minimum. Ensure that the finished surface has a uniform appearance, free from segregated areas. Immediately remove and replace, as dir ected, all portions of a pavement course that are defective in mixture composition, show excessive segregation, or do not otherwise comply with the Contract. Correct irregularities in alignment of the outside edge or edges of longitudinal joints by adding or removing material before compacting the edges. Over uniform, narrow areas, such as widening or narrow, paved shoulders where the use of pavers would be impractical, spread by a mechanical spreader. Ensure that the material is placed to the required lines, grad es, and cross section without segregation of the mixture. Over areas where machine spreading is impract ical due to irregularities or obstructions, spread the mixture by approved methods. Pl ace the material to avoid segregation and to reduce to a minimum the amount of patching required during compaction. Discard all coarse aggregate particles brought to the surface by raking. Do not scatter or broadcast excess mixture or particles across the surface of the uncompacted mat. Spread all surface courses with allowances made for compacting to finish approximately 3/8 inch above forms, gutters, or similar construction. The Department may allow shoulders and Asphalt Mixture for Pavement Wedge to be paved monolithically with the mainline if it is in the best interest of the Department. Obtain the Engineer’s approval before doing so. Do not place or compact asphalt mixture when the natural light is insufficient without providing artificial lighting satisfactory to th e Engineer. Unless the Contract specifies nighttime paving, do not place binder, surface, or other asphalt mixture wearing courses at night, without first obtaining the Engineer’s permission. The Engineer may require daytime paving if the Engineer deems the nighttime work unsatisfactory.
403.03.06 Thickness Tolerances. Place asphalt mixtures at the lift thickness specified
in the Contract. When lift thickness is not specified in the contract or when deviations to the 403-6 pavement thickness is approved by the Engineer, use the following table for application of asphalt mixture thickness. Nominal Maximum A ggregate Size (Inches) Lift Thickness (Inches) 1.50 4.50 – 5.00 1.00 3.00 – 4.50 0.75 2.25 – 3.50
403.03.07 Joints. When curbs, gutters, pavement, and other structures adjoin the new
construction, coat all contact surfaces of the existing construction and joints of previously placed new construction, both longitudinal and transverse, with tack. When the pavement construction consists of 2 or more courses, offset the longitudinal joint a minimum of 6 inches. Place the longitudinal joint in the final surface course along the dividing line between the lanes. Clean adjacent surfaces of all loose materials so the joint shall receive full compaction from the rollers. Place and spread all courses as continuously as possible, keeping the number of joints to a minimum. When a transverse joint is nece ssary, complete the spreading of the material by the finishing machine, and adjust the course to a straight line, square with the pavement. Before work is resumed, cut back the joint on the previous run, exposing the full depth of the course. Remove all excess material. Check the joint with a 10-foot straightedge at intervals of 2 feet or less immediately afte r initial rolling. Immediately correct any irregularities not conforming to Subsection 403.03.11 either by additional raking or adding hot material, or both. Discard all coarse aggregat e particles brought to the surface by raking. Do not scatter or broadcast excess mixture or particles across the surface of the uncompacted mat. Roll joints to compress the material and to produce as tight a joint as possible. Avoid cold longitudinal joints when practical by either placing the full width of the course in one pass, operating pavers in echel on, or moving pavers back each day after placing sufficient tonnage in each traffic lane so the course placed will be the full width of 403-7 the pavement at the end of each day. Obtain the Engineer’s approval for the method of paving. Comply with Subsection 402.03.02 D) for density of joint cores obtained from surface mixtures when Option A applies.
403.03.08 Shoulder Rumble Strips and Pavement Texturing.
Unless directed otherwise by the Engineer, DO NOT install centerline, edgeline, and/or shoulder rumble strips where the posted speed limit is 45 MPH or less. Before sawing centerline and/or edgeline rumble strips, pre-mark the pavement surface and obtain the Engineer’s approval for the proposed location, alignment, and control guides. After sawing the centerline and/or edgeline rumble strips, apply permanent centerline and/or edgeline striping, according to Section 713, on the sawed rumble strip locations approved by the Engineer. Before sawing shoulder rumble strips, obtain the Engineer’s approval of the proposed layout, location and alignment. Notify the Engineer if questions arise regarding changes in striping and/or rumble patterns. If necessary, the Engineer may obtain guidance from the District Traffic Engineer and/or the Division of Traffic Operations.
403.03.09 Leveling and Wedging, and Scratch Course.
403.03.10 Compaction. Compact asphalt mixtures by Option A or B, as specified in
the Contract. Operate the rollers to eliminate all roller marks and obtain the specified compaction. Operate vibratory rollers of a design, wei ght, and frequency that produces the specified compaction without damaging the mat. During the initial rolling of each course, visually inspect its surface for any irregularities that may develop. Remove and replace areas in which the material is not in compliance as specified in Subsection 403.03.05. Do not allow the rollers at any time to stand on the material being placed immediately behind the paver. When rolling is temporarily suspended, stop the rollers as far behind the paver as practical. Move the rollers at a slow but uniform speed with the drive roll or wheels nearest the paver. Immediately correct any displacement due to reversing the direction of a roller, or from other causes, using rakes and adding fresh mixture when required. While rolling, do not displace the line and grade of the edges of the asphalt mixture. When the Engineer allows, use a pneumatic-tired roller for final rolling on base courses. To prevent adhesion of the material to the wheels of steel-wheeled rollers, keep the wheels moistened with water, but do not use excess water. Do not use kerosene, oil, or other harmful liquids. The Department will allow a small quantity of detergent to be mixed with the water. Compact areas adjacent to manholes, curbs, narrow widening, and other small areas inaccessible to a roller, by mechanical tampers.
403.03.11 Surface Tolerances. Check the surface of each course with templates,
straightedges, or stringlines. Check the surfaces of the finished courses longitudinally with a 10-foot straightedge placed parallel to the centerline over the width of the surface. Ensure the following:
403.03.12 Transverse Joints. When specified in the Contract, cut transverse joints in
overlays of JPC pavement, base, and shoulders. Seal with self-leveling silicone rubber sealant.
403.03.13 Pavement Marking. Apply and maintain pavement marking as specified
in Section 112.
403.03.14 Durable Pavement Edge . The contractor will have the option to pave
roadway shoulders monolithically with mainline pavement or by separate operation. However, if the shoulder is placed monolithically, with mainline material, the Durable Pavement Edge shoe shall be used for the placement of the asphalt. For divided highways, the Durable Pavement Edge must be added to both median and outside bituminous shoulders when the paved shoulder width is 6 feet or narrower. Construct the edge to the depth width and slope the contract specifies where existing conditions permit. Remove the sod or perform trench excavation only when necessary to obtain the specified depth and width. Do not remove solid rock. Provide enough area to construction the Durable Pavement Edge so that the Durable Pavement Edge will be placed on solid material, free of debris such as loos e material, grass, weeds or mud. The edge should be compacted such that there is no loose material. Short sections of handwork will be allowed for pavement transitions and turnouts. Durable Pavement Edge is not intended for the following:
403.04 Measurement.
403.04.01 Removing Type V Pavement Markers. The Department will measure the
quantity by each individual unit. The Department will determine the quantity by dividing the length of each run of markers by the markers’ average spacing, plus one. The Department will not measure other marker types for removal, disposal, or filling of their grooves for payment. The Department will consider all of this work incidental to the surfacing items in the Contract.
403.04.02 Adjust Manhole. The Department will measure the quantity by each
individual unit.
403.04.03 Asphalt Mixtures. The Department will measure the quantity according
to Subsection 402.04. The Department will not measure rolled rumble strips or pavement wedge texturing for payment and will consider them incidental to this bid item.
403.04.04 Leveling and Wedging. For resurfacing projects, when leveling and
wedging is listed as a bid item, the Department will measure the quantity in tons according to Subsection 402.04. For reconstruction and new construction, the Department will measure the quantity of leveling and wedging placed on the first base course in tons as base material. The Department will not measure leveling and wedging used to correct irregularities in subsequent courses for payment and will consider it incidental to placing the course.
403.04.05 Asphalt Scratch Course. The Department will measure the quantity
according to Section 402.04.
403.04.06 Protective and Restorative Work. The Department will not measure for
payment any extra materials, methods, or construction techniques, determined by the Engineer not to be a part of the specified construction, used to protect, maintain, or repair any portion of the uncompleted work during the winter months.
403.04.07 Centerline, Edgeline, and Shoulder Rumble Strips. The Department will
measure the quantity of sawed rumble strips in linear feet. The Department will measure permanent striping in accordance with Section 713. The Department will measure temporary striping, when required, by Section 112, the Traffic Control Plan, and/or when directed by the Engineer. When bicycle gaps are required in the rumble pattern, the Department will include the length of the bicycle gaps in the measurement of the rumble. 403-11 The Department will not measure the areas where rumble strips are omitted, such as at intersections, crosswalks, bridges, railroad cro ssings, etc. The Department will not measure temporary striping that is only used for pre-marking centerline and/or edgeline rumble strips. The Department will not measure the removal of existing pavement markings, pre-marking and layout, surface preparation, corrective work, labor, equipment, and any incidentals necessary to construct rumble strips, and will consider these items incidental to the installation of the rumble strips.
403.04.08 Asphalt Placement with MTV. The Department will not measure the
MTV for payment and will consider its use incidental to the asphalt mixture.
403.04.09 Durable Pavement Edge . The Department will not consider the Durable
Pavement Edge for payment and will consider its use incidental to the asphalt mixture.
403.05 PAYMENT. The Department will make payment for the completed and accepted
quantities under the following:
403.05.01 Adjust Manhole. The Department will make payment for the completed
and accepted quantities according to Subsection 408.05.02.
403.05.02 Asphalt Mixtures. The Department will make payment for the completed
and accepted quantities according to Section 402.
403.05.03 Leveling and Wedging. The Department will make payment for the
completed and accepted quantities according to the Lot Pay Adjustment Schedule for Specialty Mixtures in Section 402.
403.05.04 Asphalt Scratch Course. The Department will make payment for the
completed and accepted quantities according to the Lot Pay Adjustment Schedule for Specialty Mixtures in Section 402.
403.05.05 Adjust Manhole Frame to Grade. The Department will make payment
for the completed and accepted quantities according to Subsection 408.05.02. Code Pay Item Pay Unit 06600 Remove Pavement Marker Type V Each 01791 Adjust Manhole Frame to Grade Each 02697 Edgeline Rumble Strips Linear Foot 20458ES403 Centerline Rumble Strips Linear Foot 02696 Shoulder Rumble Strips Linear Foot ----- Asphalt Mixture, Type Ton The Department will consider payment as full compensation for all work required under this section. 403-12 SECTION 404 OPEN-GRADED FRICTION COURSE (OGFC)
404.01 DESCRIPTION. Construct one course of hot-mixed, hot-placed, OGFC
approximately 3/4-inch thick on a foundation provided by either new or existing pavements.
404.02 Materials and Equipment.
404.02.01 Aggregates. Conform to Subsection 403.02 and the following:
404.02.02 Asphalt Binder. Provide the PG binder specified in the Contract
conforming to Section 806.
404.02.03 Anti-stripping Additive. Select from the Department’s List of Approved
Materials.
404.02.04 Tack. Conform to Section 406.
404.02.05 Reclaimed Materials. Limit the use of reclaimed materials to a maximum
of ten percent in the mixture.
404.03 CONSTRUCTION. Conform to Section 403, except as provided in this section
and in the Contract. The OGFC is intended to provide a coarse-textured, well-draining, skid-resistant wearing surface. Construct this course at a higher elevation than adjacent gutters to provide proper lateral dr ainage of water through the course. For multiple lanes in the same direction, place the material continuously in one lane each day. Protect it from traffic until it has cured overnight. When placing OGFC on two-lane, two-way pavements, operate the paver according to Subsection 403.03.05.
404.03.01 Weather Limitations. Follow weather limitations outlined in Subsection
403.03 01.
404.03.02 Leveling and Wedging. Perform the necessary leveling, wedging, and
patching to repair an existing pavement before beginning construction of this surface course.
404.03.03 Tack Coat. Apply according to Section 406, except as follows. When
furnishing emulsions for the tack coat, do not dilute the emulsions. Apply undiluted SS-1, SS-1h, or RS-2 at an approximate rate of 0.8 pounds (0.1 gall ons) per square yard.
404.03.04 Preparation of Mixtures. Submit the JMF for OGFC for approval
according to Subsection 402.03. Conform to the gradation requirements specified. The Department will perform a mix design according to KM 64-424. Test the approved JMF of the mixture according to KM 64-433 or KM 64-620, and ensure that it conforms to the requirements shown in the table below. During the operation of the plant, conform to the following tolerances from the approved JMF, and also maintain the master gradation ranges below at all times. 404-1 Obtain the Engineer’s approval for the percent by weight of asphalt binder in the mixture. Do not deviate from the established AC by more than 0.4 percent. Test the mixture according to KM 64-405, KM 64-436, KM 64-437, KM 64-438, or AASHTO T 308. Use the anti-stripping additive at the rate of 0.5 percent by weight of asphalt binder. Maintain temperatures of the ingredient materials and the mixture within the following ranges: MIXING AND LAYING TEMPERATURES ( F) Material Minimum Maximum Aggregates 240 330 Asphalt Binders PG 64-22 230 330 PG 76-22 285 350 Asphalt Mixtures at Plant PG 64-22 230 265 (Measured in Truck) PG 76-22 275 320 Asphalt Mixtures at Project PG 64-22 175 265 (Measured in Truck PG 76-22 260 320 When Discharging) Spread the OGFC at an approximate rate of 65 pounds per square yard to provide an approximate thickness of 3/4 inch. Roll in the static mode with a steel-wheeled, tandem roller weighing between 5 and 8 tons. Begin rolling immediately after placing the course. Limit rolling to the minimum necessary for consolidating the mixture and bonding it to the underlying surface. Avoid excessive rolling and breakage of the aggregate.
404.04 MEASUREMENT. The Department will measure the quantity in tons according
to Subsection 402.04. The Department will not measure asphalt tack coat and anti-strip additives for payment and will consider them incidental to this item of work.
404.05 PAYMENT. The Department will calculate payment by the Lot Pay Adjustment
Schedule for Specialty Mixtures in Section 402. The Department will apply the schedule’s tolerances to the average of the absolute values of deviations from the JMF. When the deviation is on the fine side of the JMF, the Engineer will evaluate each occurrence and determine if it is detrimental to the pavement performance. The Department will evaluate the acceptability of the material to determine if it will remain in place at a reduced pay factor or be removed and replaced at no expense to the Department. When a pay factor less than 1.00 is determined for gradation on more than one sieve, the Department will use the lowest single pay factor determined. When a pay factor less than 1.00 is determined for both AC and gradation on one or more sieves, the Engineer will evaluate and determine if the deficiencies will have a cumulative negative influence on the mixture. If so, the Engineer will apply both the reduced pay factor for the AC and the largest deduction for the gradation failures. If not, SIEVE MASTER GRADATION RANGE JMF SIZE (Percent Passing by Weight) TOLERANCES 1/2 inch 100 3/8 inch 90-100 No. 4 25-50 ± 6% No. 8 5-15 ± 4% No. 16 - No. 200 2.0-5.0 404-2 the Engineer will apply the larger single deduction. The Department will make payment for the completed and accepted quantities under the following: Code Pay Item Pay Unit 00266-00268 Asphalt Surface, Open-Graded, Grade Ton The Department will consider payment as full compensation for all work required under this section. 404-3 SECTION 405 ASPHALT SEAL COAT
405.01 DESCRIPTION. Construct an asphalt seal co at consisting of one or more
applications each of asphalt material and cover aggregate.
405.02 Materials and Equipment.
405.02.01 Asphalt Material. Furnish RS-2 or HFRS-2 conforming to Section 806.
405.02.02 Aggregate. Conform to Section 804 or 805, as applicable.
405.02.03 Equipment. Provide, and keep on the project at all times, an accurate
thermometer, hand brooms, and other small tools and equipment essential for completion of the work. Provide equipment for heating the asphalt material and pressure distributors conforming to Subsection 406.02.05. Provide a mechanical broom or sweeper for cleaning the existing surface and for sweeping the completed seal coat. Provide an aggregate spreader equipped with a mechanical feed. Ensure that the spreader is capable of depositing aggregate from the transporting vehicle directly onto the fresh asphalt material at the rate specified, in smooth, uniform layers, independent of the forward speed. Ensure that the spreader is capable of being filled and moved without discharging aggregate. Provide a pneumatic-tired roller for roadway surfaces. On slopes, the Department will allow a steel-wheel roller.
405.03 Construction.
405.03.01 Weather Limitations. Do not construct any seal coat when the ambient
temperature is below 45 F, nor when the ambient temperature within the preceding 24 hours has been 35 F or lower, except with the Engineer’s written permission.
405.03.02 Preparation of Surface. Sweep the road with a mechanical sweeper and
with wire hand brooms, when necessary. Clean the edges of the surface so that the full width of the roadway to be treated is unifo rmly clean. Where any mud or earth exists, remove it in advance of the application of the asphalt material, and allow the surface to thoroughly dry. If cracks cannot be adequately filled by the seal coat, fill them with asphalt material and apply cover aggregate before applying the seal coat.
405.03.03 Heating and Applying Asphalt Material . Heat and maintain the asphalt
material between 125 and 175 F during application. Apply asphalt material by means of a pressure distributor in a uniform, continuous spread over the section to be treated in the quantity per square yard specified in the Contract or as the Engineer directs. Keep the nozzles of the spray bar clean at all times. Immediately make any streaked areas uniform by use of a hand hose equipped with a nozzle. Treat areas over which it is impractical to operate a distributor by means of a hand hose equipped with a nozzle or by means of a pouring pot. Do not apply the asphalt material farther in advance of the spreading of the aggregate than can be covered directly by the aggregate immediately available at the site of work. When the seal coat treatment is constructed in half-widths, provide complete coverage by overlapping the 2 applications approximately 4 inches along the centerline. Prevent spotting or discoloring curbs, headwalls, and other structures. When such discolorations occur, remove them at no expense to the Department. Make joints utilizing an approved method. 405-1
405.03.04 Application of Cover Material. Provide the gradation specified in the
Contract. Ensure that the aggregate for cover material is surface-dry when applied, unless damp aggregate is allowed or required due to the type of asphalt material being used. Spread the aggregate immediately following the application of the asphalt material. Spread the aggregate before the asphalt material breaks. Ensure that the spreading equipment does not contact the asphalt material before it is covered with aggregate. Apply the cover material at the rate designated in the Contract, with precautions taken not to exceed the designated rate by more than 5 percent. Use hand brooms to correct any irregularities. When applied on the roadway lanes and shoulders, roll the entire surface width with pneumatic-tired rollers immediately following the spreading of the aggregate. Do not use steel-wheel rollers except as specified in Subsection 405.02.03. Operate the rollers parallel to the centerline, and cover the entire surface with at least 3 passes of the rollers, or more when the Engineer directs. When applied on the roadway lanes and shoulders, after rolling, mechanically sweep the completed seal coat to remove all excess cover aggregate after the asphalt material has cured sufficiently to allow sweeping without dislodging the imbedded aggregate, when deemed necessary. If an asphalt surface course is to be applied over the seal coat, do not allow traffic on the seal coat before applying the surface course unless required by the traffic control plan or the Engineer.
405.04 MEASUREMENT. When an authorized adjustment is made, the Department
will measure quantities up to 5 percent in excess of the designated application rate for payment. The Department will not measure quantities exceeding the designated application rate by more than 5 percent for payment.
405.04.01 Asphalt Material for Asphalt Seal Coat. The Department will measure
the quantity in tons according to Section 109.
405.04.02 Asphalt Seal Aggregate. The Department will measure the quantity in tons
according to Section 109.
405.05 PAYMENT. The Department will make payment for the completed and accepted
quantities under the following: Code Pay Item Pay Unit 00103 Asphalt Seal Coat Ton 00100 Asphalt Seal Aggregate Ton The Department will consider payment as full compensation for all work required under this section. 405-2 SECTION 406 ASPHALT CURING SEAL AND ASPHALT PRIME AND TACK COATS
406.01 DESCRIPTION. Prepare existing bases or surfaces, and apply asphalt material
before placing covering courses of asphalt mixtures or treatments.
406.02 Materials and Equipment.
406.02.01 Tack Coat. Furnish SS-1 or SS-1h conforming to Section 806.
406.02.02 Prime Coat. Furnish SS-1h conforming to Section 806 unless the Contract
allows another material.
406.02.03 Curing Seal. Furnish RS-2, SS-1, or SS-1h conforming to Section 806.
406.02.04 Water. Conform to Section 803.
406.02.05 Equipment. Provide hand brooms and other small tools and equipment
essential to completing the work in addition to a mechanical broom or sweeper, asphalt heating equipment, and a pressure distributor. Provide a mechanical broom or sweeper that is adjustable to make uniform contact with the surface and that thoroughly cleans without cutting into the surface being swept. Provide equipment for heating the asphalt material in tanks, railroad cars, trucks, and distributors that is capable of heating the material to the required temperature without introducing moisture, localized overheating, or otherwise changing the characteristics of the material. Mount the pressure distributor on a self-propelled, motor vehicle equipped with pneumatic tires, and ensure that it has sufficient power to maintain a constant and uniform speed under all operating conditions. Use a distributor designed to apply the material uniformly at the rate required for the type of construction. Use a distributor conforming to the following requirements:
406.03 CONSTRUCTION. For the asphalt prime coat, apply liquid asphalt material to
granular-type bases. For the asphalt tack coat, apply liquid asphalt material to the surface of concrete or bases, and to existing asphalt surfaces and, when necessary, to newly constructed asphalt courses.
406.03.01 Weather Limitations. Conform to the temperature limitations specified
for the asphalt mixture to be placed. Do not apply prime and tack coats to wet surfaces.
406.03.02 Preparation of Surface. Obtain the Engineer’s approval of the prepared
surface before applying the prime or tack coat.
406.03.03 Application. Provide necessary barricades, warning signs, and flaggers to
prevent traffic from traveling over a freshly applied prime or tack coat. Also, provide for public convenience and safety as specified in Sections 104 and 107. Prevent spotting or discoloring curbs, headwalls, and other structures. When discolorations occur, remove them at no expense to the Department. Protect the exposed, treated surfaces from damage. Repair all damaged areas. Maintain the material within the following temperature ranges during application: SS-1, SS-1h 70-160 F RS-2 70-140 F
406.04 MEASUREMENT. The Department will not measure for payment the removal
of discolorations, maintenance, and repair of the applied coating, or removal of excess material.
406.04.01 Asphalt Prime Coat. The Department will measure the quantity according
to Section 109. The Department will not measure water used to prepare dry surfaces for payment.
406.04.02 Asphalt Material for Tack. The Department will measure the quantity
according to Section 109.
406.04.03 Asphalt Curing Seal. The Department will measure the quantity according
to Section 109. The Department will not measure water used to prepare dry surfaces for payment.
406.04.04 Sand for Blotter. When listed as a bid item, the Department will measure
the quantity in tons according to Section 109. The Department will not measure sand for payment when used to treat excessive asphalt material application.
406.05 PAYMENT. The Department will make payment for the completed and accepted
406-3 quantities under the following: Code Pay Item Pay Unit 00296 Asphalt Prime Coat Ton 00358 Asphalt Curing Seal Ton 02702 Sand for Blotter Ton 00356 Asphalt Material for Tack Ton The Department will consider payment as full compensation for all work required under this section. 406-4 SECTION 407 ASPHALT MIXTURE FOR PAVEMENT WEDGE
407.01 DESCRIPTION. Construct a pavement wedge composed of a hot-mixed or
warm-mixed asphalt mixture. Prepare the area to be covered by the mixture when necessary.
407.02 Materials and Equipment.
407.02.01 Asphalt Binder. Furnish PG 64-22 conforming to Section 806.
407.02.02 Aggregate. Conform to Sections 804 and 805. Use a gradation within the
requirements in the following table: Sieve Size Percent Passing 1 1/2 inch 100 3/4 inch 70-100 3/8 inch 45-80 No. 4 30-60 No. 8 20-45 No. 16 15-35 No. 50 5-20 No. 100 3-10 Test gradation according to KM 64-433 or KM 64-620. Use an asphalt binder content (AC) between 4.5 and 6.0 percent by weight of the mixture. When using a porous aggregate, in crease the AC as needed to compensate for asphalt absorption by the aggregate. Submit a JMF to the Engineer for approval according to KM 64-421. Maintain the approved AC within 0.5 percentage points as determined according to KM 64-405, KM 64-436, KM 64-437, KM 64-438, or AASHTO T 308.
407.03 CONSTRUCTION. Conform to Section 403 except as specified in this section
and in the Contract. Construct the wedge to the depth, width, and slope the Contract specifies where existing conditions permit. Remove the sod or perform trench excavation only when necessary to obtain the specified depth and width. Do not remove solid rock. Compact the mixture with a roller weighing at least one ton.
407.04 MEASUREMENT. The Department will measure the quantity according to
Subsection 402.04. The Department will not measure trench excavation or sod removal performed as specified in this section for payment and will consider them incidental to this item of work.
407.05 PAYMENT. The Department will make payment for the completed and accepted
quantities according to the Lot Pay Adjustment Schedule for Specialty Mixtures in Section 402 under the following: Code Pay Item Pay Unit 00263 Asphalt Mixture for Pavement Wedge Ton The Department will consider payment as full compensation for all work required under this section. 407-1 SECTION 408 ASPHALT PAVEMENT MILLING AND TEXTURING
408.01 DESCRIPTION. Remove existing pavement by milling and texturing.
408.02 MATERIALS AND EQUIPMENT. Provide a power-operated, self-propelled
milling machine capable of:
408.03 CONSTRUCTION. The depth of cut indicated in the Contract is approximate
only. The Engineer will specify the actual depth of cut. When the Contract requires a bottom-of-rut cut, remove only the amount of material necessary to acceptably texture the bottom of the rut. Where there are no ruts, remove only the amount of material necessary to obtain an acceptable texture. Remove the material in successive cuts of approximately 1 to 1 1/2 inches, measured at the edge of the cutting drum. Complete each cut over the entire length and width of the area. Do not begin the next cut until the Engineer examines the area and determines that additional cutting is necessary. When maintaining public traffic is not necessary, the Department may allow deeper cuts, provided the final cut does not exceed 1 1/2 inches and satisfactory results are obtained. Provide an average depth of 0.20 inch be tween the high and low points on the milled pavement. After milling and texturing, ensure that the finished surface conforms to the required grade and cross section and provides a smooth riding surface free from gouges, ridges, oil film, and other imperfections of workmanship. Do not allow the elevation of the longitudinal edges of adjacent cuts to differ more than 1/8 inch. Unless the Engineer allows, do not leave vertical longitudinal faces duri ng non-working hours in areas exposed to public traffic. Limit the vertical longitudinal faces to 1 1/2 inches in height, and taper them in a manner the Engineer approves to avoid creating a hazard for traffic. When the Engineer deems necessary, apply water to control dust. Remove excess millings and fines that have collected at the vertical longitudinal faces and thoroughly sweep up all millings. Load and haul away all materials swept up. Repair pavement that is gouged, torn, or otherwise damaged during milling operations, and repair damage done to any other property of any kind including utility frames, grates, and covers.
408.03.01 Surface Tolerance. Ensure that the finished surface after the final cut does
not deviate more than 1/8 inch from a 10-foot straightedge and that the cross slope does not deviate more than 3/8 inch in 10 feet. Correct all irregularities exceeding these limits.
408.03.02 Approaches and Tapers. Mill approaches and ta pers as required by, and
to the satisfaction of, the Engineer. The Engineer will determine the length, width, and depth of cut on approaches and tapers. Match the approaches and tapers to the finished cut 408-1 on the mainline, and transition them to the existing surface within 1/8 inch. When the Engineer deems necessary, transiti on private entrances to provide a smooth approach to the roadway.
408.03.03 Pavement Marking. Apply and maintain pavement markings according to
Section 112.
408.03.04 Adjusting Small Drainage Structures. Adjust small drainage structures,
such as catch basins, as required to match the finished pavement, or to provide proper drainage, according to Subsection 710.03.03. Wh en existing catch basin grates are below the finished grade, the Department will require no adjustments. Keep all small drainage structures, utility va lves, etc. free of cuttings and other debris during the milling operation.
408.03.05 Adjusting Manholes. Only when the Engineer directs, adjust manholes
according to Subsection 710.03.03. Return manhole adjusting rings that are removed and not reused to the utility owner.
408.04 Measurement.
408.04.01 Asphalt Pavement Milling and Texturing. The Department will measure
the quantity of material removed from the areas milled and textured in tons. When the original Contract quantity is 2,000 tons or more, weigh the material according to Section 109, except that the Department will accept commercial or portable scales, certified by the Kentucky Department of Agri culture, Division of Weights and Measures, and approved by the Engineer. When the original Contract quantity is less than 2,000 tons, arrange for 3 trucks of each capacity to be weighed to determine the average net weight per load. The Department will calculate the total quantity using the average weight per load and the load count for each size of truck. The Engineer may require ad ditional weighing if excessive variation in loading is apparent. The Engineer may perform check-weighing. The Department will not measure additional milling performed to correct deficiencies in the finished grade, cross section, or text ure for material removed when the deficiencies are due to unsatisfactory workmanship. The Department will not measure work to repair damage caused by the milling operations. The Department will not measure water used to control dust for payment and will consider it incidental to this item of work.
408.04.02 Mobilization for Asphalt Pavement Milling and Texturing. The
Department will measure the quantity by the lump sum. The Department will measure Mobilization for Asphalt Pavement Milling and Texturing for payment only once per Contract and will consider any additional mobilization operations for milling and texturing incidental to this item of work. The Department will not measure Mobilization for Asphalt Pavement Milling and Texturing for payment when milling is performed to correct deficiencies in the finished grade, cross section, or texture for material removed when the deficiencies are due to unsatisfactory workmanship. For group contracts, the Department will measure the quantity for each project (subsection) that has a bid item for Mobilization for Asphalt Pavement Milling and Texturing.
408.04.03 Adjusting Small Drainage Structures. The Department will measure the
quantity according to Subsection 710.04.
408.04.04 Adjust Manhole. The Department will measure the quantity by each
individual unit. 408-2
408.05 PAYMENT. The Department will make payment for the completed and accepted
quantities under the following:
408.05.01 Asphalt Pavement Milling and Texturing. When Asphalt Pavement
Milling and Texturing is a major item, the Department will use the supplemental formulas established in Subsection 104.02.02 for determining adjusted unit prices when either an underrun or an overrun of 25 percent occurs in the quantity of milling and texturing actually performed.
408.05.02 Adjust Manhole. In the event the Engineer directs the Contractor to adjust
existing manholes and the Contract does not include a bid item for this work, the Department will make payment at an agreed unit price of $250.00 for each manhole acceptably adjusted by using the adjusting ring method, or an agreed unit price of $350.00 for each manhole acceptably adjusted by removing or adding masonry. Code Pay Item Pay Unit 02677 Asphalt Pavement Milling and Texturing Ton 02676 Mobilization for Milling and Texturing Lump Sum 01709, 01719 Adjusting Small Drainage Structures, Type, Size See Subsection 710.05 01791, 01792 01791 Adjust Manhole Frame to Grade Each The Department will consider payment as full compensation for all work required under this section. 408-3 SECTION 409 ASPHALT MIXTURES USING RECLAIMED MATERIALS
409.01 DESCRIPTION. Use reclaimed asphalt pavement (RAP) from Department
projects or other approved sources in hot mix asphalt (HMA) or warm mix asphalt (WMA) provided mixture requirements are satisfied. Fo r other sources to be approved, satisfactorily establish to the Engineer that the quality of the material is acceptable. Use either pre-consumer (manufacturer wa ste or new) or post-consumer reclaimed asphalt shingles (RAS) that are processed such that all the material passes the 3/8-in. sieve. Ensure pre-consumer RAS is free of deleterious materials. Ensure post-consumer RAS does not contain more than 1.5 percent wood by mass or more than 3.0 percent deleterious materials by mass.
409.02 MATERIALS AND EQUIPMENT. Conform to the guidelines in Subsection
409.03.03 for the required grade of asphalt binder which is based on the percentage of effective binder content of the mixture.
409.03 CONSTRUCTION. Keep reclaimed material of different gradation, asphalt
binder content, asphalt binder properties, and aggregate properties separate at all times, including when stockpiling and feeding. The Department may approve other methods and procedures provided that all characteristics of the reclaimed material remain uniform.
409.03.01 Polish-Resistant Aggregate. When electing to utilize polish-resistant
aggregate in reclaimed material to satisf y a portion of the polish-resistant aggregate requirements for the mix, provide documentation to the Engineer’s satisfaction that the reclaimed material consists of the specified amount of polish-resistant aggregate. Provide samples of the reclaimed material to the Engineer for verification testing.
409.03.02 Asphalt Binder Content Adjustment for RAS. Recognizing that not all
asphalt binder in RAS is activated during the mixing operation to fully blend with the virgin materials, the Department will reduce the asphalt binder content determined by Kentucky Method 64-405 for RAS by 25 percent.
409.03.03 Preparation of Mixture.
409.04 MEASUREMENT. The Department will not measure reclaimed material
separately but will include it in the measured quantities of asphalt mixture produced.
409.05 PAYMENT. The Department will make payment for the completed and accepted
quantities under the appropriate pay item for the asphalt mixture being produced. The Department will not make separate payment for incorporating reclaimed material. The Department will not increase or decrease the Contract unit prices for any asphalt mixture on the project as a result of using, or not using, reclaimed material in the asphalt mixtures. 409-3 SECTION 410 ASPHALT PAVEMENT RIDE QUALITY
410.01 DESCRIPTION. This section covers the requirements for the ride quality of
completed asphalt pavements. Ride quality is a measurement of surface tolerance in terms of an International Roughness Index (IRI). The IRI is an index derived from controlled measurements of the longitudinal profile in the wheel tracks and correlated with panel ratings of ride quality. The Contract will specify when ride quality requirements apply.
410.02 MATERIALS AND EQUIPMENT. The Department will measure the
longitudinal profile of the surface with an ASTM E 950, Class 1 device.
410.03 Construction.
410.03.01 Corrective Work. Submit corrective work procedure plans to the Engineer
for approval before performing the work. Provide a final, corrected surface comparable to adjacent, acceptable pavement placed within the project limits with respect to texture, appearance and skid resistance.
410.03.02 Ride Quality.
410.04 MEASUREMENT. The Department will measure the ride quality in terms of the
IRI according to Subsection 410.03. The Department will not measure the IRI as a separate pay unit but will use the IRI to calculate a Ride Quality Adjustment payment.
410.05 PAYMENT. The Department will apply a Ride Quality Adjustment for each 0.1-
lane-mile section tested. The Department will determine the Ride Quality Adjustments for each 0.1-lane-mile section using the Ride Quality Adjustment Schedule below. The Department will not apply positive ride quality adjustments to 0.1-lane-mile sections when their associated sublot’s density value is less than 0.95. The sum of the pay value adjustments for ride quality shall not exceed $0 for the project as a whole. When requesting tests on partially completed pavement, the Department will perform one test at no charge. The Department will perform additional requested testing and retesting for corrective work or pavement replacement at a cost of $300.00 per lane-mile. The Department will deduct charges for additional requested testing and retesting for corrective work from monies due on the Contract. RIDE QUALITY ADJUSTMENT SCHEDULES CATEGORY “A” PROJECTS CATEGORY “B” PROJECTS IRI Pay Value Adjustment(1) IRI Pay Value Adjustment(1) 30 or less $750 36 or less $500 31 $630 37 $420 32 $520 38 $350 33 $420 39 $280 34 $330 40 $220 35 $250 41 $170 36 $180 42 $120 37 $120 43 $80 38 $70 44 $45 39 $30 45 $20 40 to 70 0 46 to 80 0 71 -$30 81 -$20 72 -$70 82 -$45 73 -$120 83 -$80 74 -$180 84 -$120 75 -$250 85 -$170 76 -$330 86 -$220 77 -$420 87 -$280 78 -$520 88 -$350 79 -$630 89 -$420 80 -$750 90 -$500 81 or hi gher corrective work(2) 91 or hi gher corrective work(3)
411.01 DESCRIPTION. Construct extruded asphalt sections of constant width with an
extrusion-type machine. Construct asphalt sect ions of variable width by machine or hand.
411.02 Materials and Equipment.
411.02.01 Asphalt Materials. Conform to Section 806. For tack and paint coats, use
SS-1 or SS-1h. For the asphalt mixture, use PG 64-22.
411.02.02 Aggregate. Conform to Sections 804 and 805. Use a gradation that
conforms to the following table: Sieve Size Percent Passing 1/2 inch 100 No. 4 60-80 No. 8 45-65 No. 16 13-25 No. 200 6.0-12.0 Test gradation according to KM 64-433 or KM 64-620. Use an asphalt binder content (AC) between 6 and 8 percent by weight of the mixture. When using a porous aggregate, increase the AC as needed to compensate for asphalt absorption by the aggregate. Submit a JMF to the Engineer for approval according to KM 64-421. Maintain the approved AC within 0.5 percentage points as determined according to KM 64-405, KM 64-436, KM 64-437, KM 64-438, or AASHTO T 308. The Department may allow an alternate JMF. Submit alternates for the Engineer’s approval. When the Engineer determines that the results from an alternate JMF are not satisfactory, repair or replace the defective work, and complete the remainder of the work using the JMF specified in this section.
411.02.03 Extrusion Equipment. Furnish a self-propelled machine for placing
extruded asphalt sections. Ensure that it is equipped with a material hopper, a distributing screw, and adjustable forming devices; and capable of placing and compacting the asphalt mixture to the lines, grades, and cross section specified in a smooth, homogenous section free of honeycomb areas.
411.03 CONSTRUCTION. Conform to Section 403 except as specified in this section
and in the Contract. Thoroughly clean the surface where the extruded asphalt sections are to be placed, and apply tack at a rate to achieve an undiluted asphalt residue of 0.4 pounds (0.05 gallons) per square yard. Allow the tack material to cure before covering it. For curbs and medians of constant width, extrude the asphalt sections at the locations and to the dimensions specified in the Contract. In areas inaccessible to the machine and on variable-width medians, the Department will allow hand-placing. Ensure that the mixture is compacted and finished to a dense, uniform section comparable to the machine-placed mixture. Apply an asphalt paint coat to the sections after construction. Prevent spotting or discoloring of concrete curbs, headwalls, and other structures, and remove any discolorations that occur.
411.04 Measurement.
411.04.01 Asphalt Wedge Curb. The Department will measure the quantity in linear
feet along the top of the curb. The Department will not measure tack and paint coats for 411-1 payment and will consider them incidental to this item of work.
411.04.02 Mountable Medians. The Department will measure the quantity of each
type in square yards. The Department will not measure tack and paint coats for payment and will consider them incidental to this item of work.
411.05 PAYMENT. When an alternate JMF is approved for use, the Department will not
make any change to the Contract unit price for this item. The Department will make payment for the completed and accepted quantities under the following: Code Pay Item Pay Unit 01897 Asphalt Wedge Curb Linear Foot 01935-01950 Mountable Median, Type Square Yard The Department will consider payment as full compensation for all work required under this section. 411-2 SECTION 412 STONE-MATRIX ASPHALT (SMA)
412.01 DESCRIPTION. Construct one or more courses of a stone-matrix asphalt (SMA)
upon the prepared foundation according to these specifications. AASHTO R46 offers guidance for the design of SMA mixtures using the Superpave gyratory compactor (SGC). For CL4 SMA BASE 1.00D PG76-22, conform to all requirements for CL4 ASPH BASE 1.00D PG76-22 unless specifically modified herein. For CL4 SMA SURF 0.50A PG76-22, conform to all requirements for CL4 ASPH SURF 0.50A PG76-22 unless specifically modified herein. For CL4 SMA SURF 0.38A PG76-22, conform to all requirements for CL4 ASPH SURF 0.38A PG76-22 unless specifically modified herein.
412.02 Materials and Equipment.
412.02.01 Fine Aggregate.
412.02.02 Coarse Aggregate.
412.02.03 Asphalt Binder. Provide a performance-graded (PG) 76-22 asphalt binder
conforming to Section 806.
412.02.04 Reclaimed Materials. The use of reclaimed materials is prohibited in SMA
mixtures.
412.02.05 Stabilizing Additive. Select and utilize either cellulose or mineral fiber in
the SMA mixture. Conform to the dosage rates and quality requirements of AASHTO M325. Furnish the fiber manufacturer’s certif ication to the Engineer stating that the material conforms to all requirements therein.
412.02.06 Fiber-Supply System. Use a separate feed system to accurately proportion
the required quantity of fibers into the mixture in a manner that ensures uniform distribution. Interlock this proportioning device with the aggregate feed or weigh system to maintain the correct proportions for all rates of production and batch sizes. Add the fiber in such a manner to prevent the material from becoming entrained in the exhaust system of the drier or plant. Control the proportion of fibers to within 10 percent of the amount required. Provide flow indicators or sensing devices for the fiber system, interlocked with the plant controls, to interrupt mixture production if the introduction of fiber fails. Prior to performing the trial demonstration specified in Subsection 412.03.04, calibrate the fiber-supply system. Provide the Engineer at least 2 days notice of the calibration date so that a Department representative may inspect the calibration process and verify that the system operates correctly. 412-1 For batch plants, add the fiber to the aggregate in the weigh hopper or as the Engineer directs. Increase the dry mixing time by 8 to 12 seconds, or as the Engineer directs, from the time the aggregate is completely emptied into the mixer. Ensure the fibers are uniformly distributed prior to the injection of asphalt binder into the mixer. For continuous or drum plants, add the fiber to the aggregate, and ensure the fibers are uniformly dispersed, prior to the injection of asphalt binder.
412.02.07 Mineral Filler-Supply System. Use a totally enclosed, separate feed
system to accurately proportion the mineral filler into the mixture in a manner that ensures uniform distribution. Do not introduce the mineral filler through the cold-feed system. Prior to performing the trial demonstration specified in Subsection 412.03.04 of this note, calibrate the mineral filler-supply system to within 10 percent of the desired amount. Provide the Engineer at least 2 days notice of the calibration date so that a Department representative may inspect the calibration process and verify that the system operates correctly.
412.02.08 Rollers. Do not use pneumatic-tired rollers. Use vibratory rollers for
breakdown rolling only.
412.02.09 Material Transfer Vehicle (MTV). Provide and utilize a MTV with the
minimum characteristics outlined in section 403.02.10.
412.03 Construction.
412.03.01 Seasonal and Weather Limitations. Conform to the seasonal and weather
limitations outlined in 403.03.01.
412.03.02 Preparation of Mixture. Conform to the following aggregate composition
limits for the respective nominal-maximum size of SMA. AGGREGATE COMPOSITION LIMITS Sieve Size 1.00-in. Base % Passin g by Mass 0.50-in. Surface % Passin g by Mass 0.38-in. Surface % Passin g by Mass 1 1/2 inch 100 100 100 1 inch 85-100 100 100 3/4 inch ---- 100 100 1/2 inch 50-70 85-100 100 No. 4 20-36 20-36 30-50 No. 8 15-25 12-25 20-30 No. 200 7.0-11.0 7.0-11.0 8.0-12.0
412.03.03 Mix Design Criteria. Using a compaction effort of N des = 100 gyrations,
submit a preliminary mix design conforming to the following mixture specifications. 412-2 MIX DESIGN CRITERIA Property Re quirement % Air Voids (AV) 4.0 % Voids-in-Mineral A ggregate (VMA) CL4 SMA BASE 1.00D PG76-22 16.0 (minimum) CL4 SMA SURF 0.50A PG76-22 17.0 (minimum ) CL4 SMA SURF 0.38A PG76-22 17.0 (minimum) % Voids-in-Coarse A ggregate (VCA mix) of Compacted Mixture1 < VCA of Dr y Aggregate (VCA DRC)1 % Retained Tensile Stren gth (TSR) 80 (minimum) % Draindown at Production Temperature2 0.30 (maximum) % Asphalt Binder Content CL4 SMA SURF 0.50A PG76-22 6.0 (minimum ) CL4 SMA SURF 0.38A PG76-22 6.3 (minimum) 1Determine according to AASHTO R46. 2Determine according to AASHTO T305.
412.03.04 Trial Demonstrations. At least two days prior to beginning mainline
paving, demonstrate that satisfactory produc tion and placement of the SMA mixture is possible. Furnish at least 200 tons each of tw o or more different asphalt binder contents (AC’s) for the trial demonstration. The Engi neer will determine the site, outside of the driving lanes, and exact quantity of the trial placement and trial AC’s. Perform a minimum of one volumetric analysis (two SGC specimens and two maximum-specific-gravity tests), one AC determination, and one gradation determination for each of the different AC’s demonstrated. Document that the SMA mixture meets a 1.00 minimum pay value for AC, AV, and VMA prior to beginning mainline paving.
412.03.05 Optimum AC Selection. The Engineer will select the optimum AC based
on the results of the trial demonstration(s). Contrary to Subsection 402.03.02, obtain the Engineer’s approval prior to adjusting the AC during the setup period or thereafter.
412.03.06 Mixture Handling.
412.03.07 Placement and Compaction. Use a MTV when placing SMA mixture in
the driving lanes. The MTV is not required on ramps and/or shoulders unless specified in the contract. When the Engineer determines the use of the MTV is not practical for a portion of the project, the Engineer may waive its requirement for that portion of pavement by a letter documenting the waiver. Compact the SMA mixtures by Option A. Do not allow traffic on the compacted mixture until it has cooled sufficiently to withstand traffic without damage (normally about oF). To expedite opening the pavement to construction equipment or traffic, the Department will allow the mat to be cooled by dousing it with water after compaction is complete.
412.04 Measurement.
412.04.01 Trial Demonstrations. The Department will measure up to 400 tons of
mixture used in the Trial Demonstration. The Department will measure the quantity as CL4 SMA BASE 1.00D PG76-22, CL4 SMA SURF 0.50A PG76-22, or CL4 SMA SURF 0.38A 412-3 PG76-22, as appropriate. The Department will not measure quantities exceeding 400 tons for payment and will consider them incident al to the CL4 SMA BASE 1.00D PG76-22, CL4 SMA SURF 0.50A PG76-22, or CL4 SMA SURF 0.38A PG76-22.
412.04 02SMA Mixtures for Driving Lanes. The Department will measure CL4
SMA BASE 1.00D PG76-22, CL4 SMA SURF 0.50A PG76-22, and CL4 SMA SURF 0.38A PG76-22 by the ton.
412.04.03 Material Transfer Vehicle (MTV). The Department will not measure the
MTV for payment and will consider its use incidental to the asphalt mixture.
412.05 Payment.
412.05.01 Trial Demonstrations. The Department will pay for the measured
quantities at the Contract unit bid price for CL4 SMA BASE 1.00D PG76-22, CL4 SMA SURF 0.50A PG76-22, or CL4 SMA SURF 0. 38A PG76-22, as appropriate, with no adjustments.
412.05.02 CL4 SMA BASE 1.00D PG76-22. The Department will calculate payment
by the Lot Pay Adjustment Schedule for Compaction Option A Base and Binder Mixtures in Subsection 402.05 except for the AV and Lane Density schedule. The Department will apply the following schedule for AV and Lane Density. AV Pay Value Test Result (%) AADTT Class 2,3, or 4 1.05 3.5-4.5 1.00 + 0.1 (AV-3.0) 2.0-3.4 1.00 + 0.1 (AV-5.0) 4.6-6.0 (2)> 2.0 or >6.0
412.05.03 CL4 SMA SURF 0.50A PG76-22 and CL4 SMA SURF 0.38A PG76-22.
The Department will calculate payment by the Lot Pay Adjustment Schedule for Compaction Option A Surface Mixtures in Subsection 402.05 except for the AV, Lane Density and Joint Density schedules. The Department will calculate the Lot Pay Adjustment using all possible incentives and disincentives but will not allow the overall pay value for a lot to exceed 1.00. The Department will apply the following schedules for Lane Density and Joint Density. Pay Value Lane Density Test Result (%) Joint Density Test Result (%) 1.05 95.0-96.5 92.0-96.0 1.00 93.0-94.9 90.0-91.9 0.95 92.0-92.9 or 96.6-97.0 89.0-89.9 or 96.1-96.5 0.90 91.0-91.9 or 97.1-97.5 88.0-88.9 or 96.6-97.0 0.75 ---- < 88.0 or > 97.0
412.05.04 Pay Items and Units. The Department will make payment for the
completed and accepted quantities under the following: C o d e P a y I t e m P a y U n i t 00395 CL4 SMA BASE 1.00D PG76-22 Ton 00396 CL4 SMA SURF 0.50A PG76-22 Ton 00397 CL4 SMA SURF 0.38A PG76-22 Ton 412-6 SECTION 413 - MICROSURFACING
413.01 DESCRIPTION. This work consists of constructing a cold-laid, polymer-
modified, emulsified asphalt pavement course to fill ruts or provide an intermediate or surface course for existing pavements. The paving mixture is composed of a polymer-modified emulsified asphalt, crushe d aggregate, mineral filler, water, and possibly other additives. Follow the requirements outlined in ASTM D 6372, Standard Practice for Design, Testing, and Construction of Microsurfacing, with modifications as found in this note. Apply this material according to the lines, grades, and typical cross-sections in the plan s or as established by the Engineer. Unless otherwise noted, Section references herein are to the Department’s Standard Specifications for Road and Bridge Construction.
413.02 Materials and Equipment.
413.02.01 Mineral Filler. Use Portland Cement, Type I, conforming to Section
801.
413.02.02 Aggregate. Provide 100-percent crushed aggregate conforming to
Sections 804 and 805. Contrary to Subsection 403.03.03, provide polish-resistant aggregate in the asphalt mixture conformi ng to one of the following requirements: Microsurfacing Type A 100 percent of total combined aggregate is Class A polish- resistant aggregate. Microsurfacing Type B 100 percent of total combined aggregate is Class B or Class A polish-resistant aggregate. Microsurfacing Type D No polish-resistant aggregate requirements Contrary to ASTM D 6372, test sand equivalent according to AASHTO T 176, soundness according to Kentucky Method (KM) 64-610, and LA abrasion according to AASHTO T 96. Ensure all aggregates satisfy ASTM D 6372 for sand equivalent, soundness, and LA abrasion. Do not use mineral aggregates that are inherently porous, such as blast- furnace slag, expanded shale, porous limestone, and lightweight aggregates, in this mixture.
413.02.03 Water. Conform to Section 803.
413.02.04 Emulsified Asphalt. The polymer-modified emulsion will be a CQS-1hP
conforming to AASHTO M 316 and tested according to T59. Distill sample at 350 ˚F. In addition, ensure that the emulsified asphalt conforms to the following criteria: 413-1 Test Criteria Ductility at 77 °F (AASHTO T 51) 40 cm (min) Ensure the asphalt supplied is on the List of Approved Materials.
413.02.05 Equipment. All equipment necessary for the satisfactory
performance of the work shall be on hand and approved before the work is permitted to begin. All equipment, tools, and machines used in the performance of this work shall be maintained in satisfactory working condition. All trucks shall be covered immediately after loading with a cover of canvas or other suitable material. The cover shall lap down along the sides and rear of the truck bed a minimum of 6 in. and be secured by tie downs at a maximum of 5 ft. spacing along the sides and rear of the truck bed. All trucks must be equipped to meet the above requirements prior to commencing hauling operations.
413.02.06 Mixing Equipment. Produce the mixture in a self-propelled, front-feed,
continuous-loading machine equipped with a conveyer-belt aggregate-delivery system and an interconnected, positive-displacement, water-jacketed gear pump and/or a variable displacement computerized rate control pump, to accurately proportion the aggregate and asphalt emulsion. Locate the mineral filler feed so the appropriate amount of mineral filler is added to the aggregate before discharge into the pug mill. Provide a spray bar to completely pre-wet the aggregate dropping into the pug mill with additive and water before the introduction of the asphalt emulsion. Provide a twin- shaft, continuous-flow, multi-blade pug mill that is a minimum of 49 inches long. Ensure that the blade size and side clearances meet the equipment manufacturer’s recommendations. Introduce the emulsion within the first one-third of the mixer length to ensure proper mixing of all materials before exiting the pug mill. Equip the machine with opposite-side driving stations to allow full control of the machine from either side. Equip the mixer with a remote, forward-speed control at the rear mixing platform so the rear operator can control the forward speed and level of mixture in the paving or rut box. Provide material control devices that are readily accessible and positioned so the amount of each material used can be determined at any time. Equip the mixing machine with a water pressure system and nozzle-type spray bar to provide a water spray ahead of and outside the spreader box, when required. Apply water at a rate that will dampen the surface but not create free-flowing water ahead of the spreader box. The mixer shall be equipped with a computerized material monitoring system with integrated material control devices that are readily accessible and positioned so the amount of each component material used can be determined at any time. The mixer shall be equipped with a back-up electronic materials counter that is capable of recording running count totals for each component material being monitored. The mixer shall include an attached radar ground measuring device or comparable device. All material control devices shall be calibrated prior to each mix application and at the discretion of the Engineer. The computer system shall have the capability to record, display, and print the following information: Individual sensor counts for emulsion, aggregate, cement, water and additive Aggregate, emulsion, and cement output in pounds per minute Ground travel distance Spread rate in pounds per square yard 413-2 Percentages of emulsion, cement, water and additive Cumulative totals of aggregate, emulsion, cement, water and additive Scale factor for all materials The computer system shall be functional at all times throughout the entire work operation.
413.02.07 Aggregate Equipment. Aggregate shall be weighed when removed
from the stockpile and screened directly into the trucks. The inspector shall view the screen for oversized aggregate. If the screen is found to have gaps, it shall be repaired or replaced before the continuing the placement of material.
413.02.08 Spreading Equipment. If a leveling or surface course is specified,
apply the mixture uniformly by means of a conventional spreader box. If a rut-fill course is specified, apply the mixture with a 5-6 ft. top width, “V- shaped” rut-filling spreader box. Equip the rut-filling spreader box with a steel strike- off device. Attach either type of spreader box to the mixer, and equip it with augers mounted on an adjustable shaft to continually agitate and distribute the materials throughout the box. Ensure that the equipment provides sufficient turbulence to prevent the mix from setting in the box or causing excessive build-up or lumps. To prevent loss of the mixture from the box, attach flexible seals, front and rear, in contact with the road. Operate the spreading equipment in such a ma nner as to prevent the loss of the mixture on super-elevated curves. For surface courses, attach a secondary strike-off device to the spreader. Use neoprene rubber drags to obtain the desired finish. Replace drags having excessive buildup. Do NOT use burlap drags.
413.02.09 Calibration Equipment. Supply all of the equipment, materials, and
scales necessary to perform the calibration according to Section 3.5 of this note.
413.03 Construction.
413.03.01 Preparation and Proportioning of Mixture. Submit a complete mix
design to the Section Engineer and to the KY TC, Division of Materials, Asphalt Branch and Aggregate Section. Mix design shall be prepared by an approved laboratory, to verify the compatibility of the aggregate, asphalt emulsion, mineral filler, and other additives. Perform the mix design with the same materials that will be used on the project. Ensure the mix design has a residual asphalt content, by dry weight of aggregate, of 7.0 to 8.5 percent for leveling and surfa ce courses and 6.5 to 8.0 percent for rut- filling mixes. Also ensure the mixture contains no reclaimed materials and a mineral filler content between 0.25 and 2.0 percent by dry weight of aggregate. In addition to the mix design information required by KM 64-421, provide the following (all percentages are based on the dry weight of aggregate): minimum and maximum percentage of water; and percentage of mix-set additives, Provide test results from an accredited laboratory that conform to ASTM D 6372. 413-3 For testing and approval purposes, Submit the mix design and two full 5-gallon buckets of the aggregate blend for the mixture to the Division of Materials for verification according to Subsection 402.03 a minimum of four weeks prior to initial use. The Contractor shall calculate the percent asphalt content of the mixture from the equipment computer display readings randomly, a minimum of 3 times a day. The engineer may request additional calculations of the % asphalt content of the mixture readings. The quality control tolerances from the mix design is ± 0.5%.
413.03.02 Mixture Gradation. Conform to the Type II requirements from ASTM D
6372 for surface courses and Type III requirements from ASTM D 6372 for leveling and rut-fill courses.
413.03.03 Weather Limitations. In addition to the applicable requirements in ASTM
D 6372, apply the mixture only when rain is not imminent, and the existing pavement surface temperature is at least 50 F. The ambient temperature shall be at least 45 F and rising and no forecasted temperatures shall be below 32 F within a 24 hour period after placement. Do not place the material between November 1 and May 1.
413.03.04 Surface Preparation.
Before applying mixture, ensure the surface is clean and free from any debris. Remove pavement markers, existing thermoplastic and/or excessive paint markings prior to application. Prior to application, fill depressions with microsurface material, asphalt material, or other approved material meeting the engineer’s specifications. Contrary to Section 406, apply an approved tack coat material at rate of 0.03 to 0.06 gal/yd
413.03.05 Calibration. Before mix production, calibrate the mixing
equipment in the presence of the Engineer. Generate documentation for the Engineer, including individual calibrations of each material at various settings. Perform a new calibration if there is any change in the mix design. Following calibration and adjustments for changes in the mix design, do not make any further calibration adjustments to the mixing equipment without the Engineer’s approval.
413.03.06 Application. Apply the paving mixture in a manner to fill minor
surface irregularities and achieve a uniform surface without causing streaking, drag marks, skips, lumps, or tears. Carry a su fficient amount of material in the spreader box at all times to ensure complete and uniform coverage. Avoid overloading the spreader box. Do not allow lumping, balling, or unmixed aggregate in the spreader box. If a rut-fill course is specified, apply enough material to fill the wheel paths without excess crowning (overfilling). An excess crown is defined as 1/8 in. after 24 hours of traffic compaction. Apply rut-fill courses in widths from 5 to 6 ft for each wheel path. If rut depth exceeds 1.0 inches, apply rut fill course in multiple layers. Provide a smooth, neat seam where two rut-f ill passes meet. Restore the design profile of the pavement cross-section. Feather the edges of the rut-fill course to minimize the 413-4 use of excess material. Rut fill courses sh all not exhibit drag marks or tears greater than 1 inch wide, ½ inch in depth and greater than 12 inches in length. Rut fill courses shall not exhibit excessive flushing or excessive roughness. If a leveling course is specified, ensure the material covers the entire surface area. The leveling course may exhibit minor raveling upon opening to traffic but shall not exhibit any continued raveling after the first four hours of being opened to traffic. Leveling course shall not exhibit drag marks or tears greater than ½ inch wide, ¼ inch in depth and greater than 12 inches in length. Leveling course shall not exhibit flushing or excessive roughness. If a leveling course is specified, apply the paving mixture at a dry aggregate rate of 18 ± 2 lb/yd
413.03.07 Acceptance and Verification.
413.03.08 Documentation. The Contractor shall maintain a daily report including
the following information: Aggregate used, ton (dry) Microsurfacing emulsion used, ton Bituminous Materials for Tack Coat, ton Cement used, ton Water used in mixture, gallons Additive used in mixture, gallons
413.03.09 Test Strip Construction. Prior to production application,
the Contractor shall place a test section 1,000 ft. in length and one lane wide. The test strip shall demonstrate the mix and set time of the material and the ability to perform under traffic. If handwork will be required on the project, include handwork in the test strip. The test strip shall be placed at the same general time of day as paving is to take place (night or day), and under similar ambient conditions. The test strip shall be able to carry normal traffic within 60 minutes. If normal traffic cannot be carried, the emulsion or mixture must be adjusted and another test strip will be required. Upon approval of the test strip, the Contractor can begin application. Payment will only be made for the first test strip. 413-6
413.04 MEASUREMENT. The Department will pay for surface and leveling
Microsurfacing courses by the number of square yards, complete and accepted in place. The Department will pay for Microsurfacing rut-fill course by the number of tons of dry aggregate used, complete and accepted in place. The weight of the dry aggregate used will be based on the calibrated weight of aggregate provided by the paving machine. The Department will base the width of the pavement course on the width shown on the plans or as directed by the Engineer. The Department will measure the length along the centerline of each roadway or ramp. The Department will not measure the surface preparation for payment and will consider it incidental to the Microsurfacing. The Department will measure asphalt material for tack according to section 109. 413-7
413.05 PAYMENT. The Department will consider the unit bid price per square yard
to include all labor, materials, and equipment necessary to complete the work. The Department will make payment for the completed and accepted quantities according to the following: Emulsified Asphalt Price Adjustment Schedule Test Specification 100% Pay 90% Pay 80% Pay 50% Pay 0% Pay CQS-1hP Viscosity, 77 º F (SFS) 15 - 17 12 – 14 9 - 11 8 AASHTO T 59 20 - 100 18 - 110 111 - 120 121 - 130 131 - 140 ≥ 141 Residue Penetration, 77 ˚F 34 - 36 31 - 33 28 - 30 ≤ 27 AASHTO T 59 40 - 90 37 - 98 99 - 108 109 - 120 121 - 130 ≥ 131 Softening Point, AASHTO T 53 ≥ 135 ≥ 130 127 - 134 128 - 129 126 - 127 ≤ 125 Distillation Residue, % AASHTO T 59, 350 ˚F 62.0 60.0 59.5 59.0 58.5 58.4 Sieve, % AASHTO T 59 ≤ 0.1 ≤ 0.3 0.31 – 0.45 0.46 – 0.60 0.61 – 0.75 ≥ 0.76 Residue Elastic Recovery @ 50 º F, % AASHTO T 301 60.0 58.0 57.0 56.0 55.0 54.9 Residue Ductility @ 77 ˚ F, cm ≥ 40 ≥ 38 37 36 35 ≥ 34 Code Pay Item Pay Unit 20814EC, 24957EC, 24958EC MicroSurfacing-Surface Course – Type Square Yard 21652EN MicroSurfacing-Leveling Course Square Yard 24515EC MicroSurfacing-Rut Fill Course Ton 00356 Asphalt Material For Tack Ton 413-8
Division 500
PCC PAVEMENT AND NON- STRUCTURAL CONCRETE CONSTRUCTION SECTION 501 JPC PAVEMENT, PCC BASE, AND JPC SHOULDERS
501.01 DESCRIPTION. Construct a single course of JPC pavement, PCC base, or JPC
shoulders. Construct longitudinal and transverse joints when required. Construct pavement, base, and shoulders on a prepared subgrade or an aggregate base course.
501.02 Materials and Equipment.
501.02.01 Concrete. Conform to Subsection 601.02 and 601.03.
501.02.02 Joint Materials.
Conform to Section 807.
501.02.03 Tie Bars. Conform to Section 811 for steel reinforcement, No. 5 epoxy,
Grade 60 .
501.02.04 Reinforcing Bar Adhesive. Use Type IV epoxy or grout adhesive
conforming to Section 826.
501.02.05 Miscellaneous Steel. Conform to Section 811 for chairs, hook tie-bolts,
spacers, aligning bars, and upper tie bars used in joint assemblies.
501.02.06 Epoxy Coating Material. Conform to Section 811.
501.02.07 Dowel Bars and Sleeves. Conform to Section 811.
501.02.08 Curing Materials. Conform to Section 823.
501.02.09 Batching Plant Equipment. Conform to Subsection 601.02, except do not
use continuous mixers.
501.02.10 Mixers. Conform to Subsection 601.02.
501.02.11 Slip Form Pavers. Provide slip form pavers of an approved self-propelled
type designed to spread, consolidate, and finish the concrete in one complete pass of the paver, and in such a manner that minimizes hand finishing. Ensure that the paver consolidates the concrete without damaging or displacing the load transfer devices and finishes the concrete to produce a smooth, uniformly textured surface having the specified crown and slope ready for final finishing. Use an automatic sensing device in continuous contact with a sensing guide to control the alignment. Maintain pavers according to the manufacturer’s specifications.
501.02.12 Auxiliary Equipment for Slip Form Paving. Provide auxiliary equipment
used in placing and finishing slip formed concrete, that is self-propelled and designed to operate without unnecessary contact with the newly placed concrete.
501.02.13 Forms. Provide form sections 10 feet long or longer and with a base width
sufficient to ensure form stability. Use steel forms with self-aligning joints, designed to withstand the lateral and vertical loads imposed by spreaders, finishing machines, or other types of form-riding equipment. Use form sections that have the base of one end of each form section cut on a diagonal so the forms can be assembled to negotiate the inside and outside curves of roadways. Ensure that each 10-foot length of form has at least 3 stake pockets securely riveted or 501-1