SECTION 609 REINFORCED CONCRETE BRIDGE SLABS
609.01 DESCRIPTION. Construct reinforced concrete slabs on bridges.
609.02 Materials and Equipment.
609.02.01 Steel Reinforcement. Conform to Section 811.
609.02.02 Concrete. Conform to Subsection 601.02 and 601.03.
609.02.03 Joint Materials. Conform to Section 807.
609.02.04 Structural Steel Joints. Conform to Section 812.
609.02.05 Forms. Conform to Subsection 601.02.13.
609.02.06 Concrete Curing Materials. Conform to Section 823.
609.02.07 Welded and Seamless Steel Pipe for Bridge Floor Drains. Conform to
Section 810.
609.02.08 Zinc Oxide-Zinc Dust Primer. Conform to Federal Specification TT-P-
641, Type II.
609.02.09 Finishing Machines. Provide each finishing machine with at least 2
movable footbridges from which to perform finishing and curing. Furnish a self-propelled finishing machine equipped with:
609.02.10 Hand Operated Internal Vibrators. Conform to Subsection 601.02.
609.03 Construction.
609.03 01.
609.03.02 Forming. Form according to Subsection 601.03.12. Construct falsework
according to Subsection 601.03.11. Construct falsework and forms for multiple slab spans to provide the camber required in the finished structure. Department will allow the use of permanent steel bridge deck forms as follows:
609.03.03 Placing and Fastening Reinforcement. Place all steel reinforcement to
within 1/4 inch vertically and horizontally of the position shown and according to applicable requirements of Subsection 602.03. When concrete overlays are included in the original bridge construction, construct according to the tolerance requirements for a new slab. Tie down reinforcing mats securely with wire 0.148 inch or greater in diameter at intervals of no greater than 8 feet in both th e longitudinal and transverse directions to prevent upward movement of reinforcement during construction operations. When tied to the forms, extend the ties through the forms. Do not deposit any concrete until the reinforcement is in place and the Engineer has inspected and approved it, and observed a complete and thorough “dry run” with the finishing machine over the entire slab area to be placed to ensure accurate placement of steel top clearance and proper slab depth. The Engineer may allow splicing the reinforcement according to Subsection 602.03.
609.03.04 Expansion and Fixed Joints. Place all joints according to the details
specified in the Plans or as directed. Correct improperly placed joints to the satisfaction of the Engineer even when the correction requires removal and replacement.
609.03.05 Drainage. Install deck drains at the locations shown or as directed and
place them before placing the bridge deck slab. Paint all drain pipes according to Subsection
607.03.23 Provide transverse drainage of the roadway surface by means of a suitable crown
or cross slope in the floor slab. Effectively drain gutters using weep holes or drain scuppers constructed at locations and in the manner specified in the Plans. Install drain scuppers to prevent drainage water from staining exposed surfaces of girders and abutment walls. In general, extend drain pipes through the concrete slab to a distance of no less than one inch below the slab or underlying beam. Provide the under surface of cantilever brackets and overlapping slabs with a V groove (drip strip) 1/2 inch in depth at a point no more than 6 inches from the outside face of the overhang for the purpose of arresting flow of moisture to prevent staining.
609.03.06 Weather Limitations and Placing Concrete. Do not place any concrete
within deck slabs during the months of January or February, except for barriers, plinths, curbs, walks, etc, without Engineer approved cold weather plan. Place all deck concrete according to Subsection 601.03.09. Any time the ambient temperature is anticipated to be 85 F or higher, place concrete in the deck slab during evening hours after ambient temperatures cool to below 85 F and cease placement before temperatures rise above 85 F. Cool forms and beams tops by water spray if their temperature exceeds 85 F. Always protect deck placement from rain water being introduced into the concrete and from rainwater surface damage. Cease deck placement immediately or cover it for complete protection when rain occurs.
609.03.07 Depositing, Consolidating, and Striking Off Slab Concrete. Wet the
reinforcing steel and forms with water prior to placing concrete. Deposit the concrete between the curbs or between the longitudinal joints when specified in the Plans to the full depth of the slab, and consolidate it. Consolidate by means of hand-operated internal vibrators according to Subsection 601.03.09. Us e a spade in addition to vibrating, if required, to ensure that no honeycomb, voids, or air pockets exist against the forms. Continue consolidating the concrete until there is complete contact between the reinforcing steel and the concrete, and until mortar flushes to the top surface. When using permanent steel bridge deck forms, place emphasis on proper vibration of 609-5 the concrete to avoid honeycombing and voids, especially at construction joints, expansion joints, and valleys and ends of form sheets . Obtain the Engineer’s approval of pouring sequences, procedures, and mixtures. Continuously place concrete in any slab between expansion joints or between construction joints as specified in the Plans. Prevent displacement of reinforcement during placing of concrete. Place concrete in the sequence as specified in the Plans and in the absence of such designation, place as directed. Obtain written approval to change the pouring sequence. Provide sufficient work capacity to place concrete at a minimum rate of 25 cubic yards per hour. When, in case of an emergency, it becomes necessary to introduce a construction joint, form it by means of a vertical bulkhead constructed to produce a keyed joint and located as approved by the Engineer. In placing concrete around steel shapes, place it only on one side of the shape until it flushes up over the bottom flange of the shape on the opposite side, after which place it on both sides to completion. Do not place concrete railings monolithic with the slab. On continuous, composite design structures, keep concrete in slabs plastic for a sufficient length of time to allow the structure to deflect to the natural deflected shape. Place the concrete in each integral unit of the superstructure continuously. Do not begin placing concrete without sufficient approved material on hand nor without sufficient forces and equipment to complete that unit without interruption. Avoid joints in the concrete due to work stoppage. Form construction joints, when necessary, according to Subsection 601.03.10. Place concrete in slab spans in one continuous operation for each span. Place concrete in transverse strips the entire width of the bridge. Place concrete for the full depth and ensure that the width of strips is such that concrete in any one strip does not take its initial set before placing the adjacent strip. When expansion devices such as rockers, expansion dams, and similar fixtures have been rigidly fixed to hold them in correct alignment, immediately release them upon completion of concrete placement in the portion of the structure in which they are installed. Immediately following consolidation of the concrete, strike off the surface to crown and cross section with the finishing machine. Move the machine in the direction that work is progressing. Maintain a slight excess of conc rete at all times so no low spots are left in front of the finishing machine. Prevent the excess concrete from tearing the surface. After finishing, do not work, walk on, or disturb the concrete in place except as described in this section. In general, do not add water to the surface of the concrete to assist in finishing operations. If the Engineer allows the application of water to the surface, apply it as a fog spray using approved spray equipment.
609.03.08 Working the Surface. Following the striking off or screeding, randomly
check the surface for irregularities and mortar ridge s, at least every 50 feet of bridge length, with an approved 10-foot straightedge operated parallel to the centerline of the bridge and slab surface. Eliminate all variations greater than 1/8 inch. After the concrete slab has cured, the Engineer will again check the slab for variations exceeding 1/8 inch. Perform any corrective action that the Engineer deems necessary. After completing the finishing operation, ensure that the surface of the concrete presents a uniform appearance; conforms to th e required grade and cross section; and is free from surplus water, rough and porous spots, irregularities, depressions, and other objectionable surface features resulting from improper finishing.
609.03.09 Finish with Burlap Drag. If the Contract does not require texturing, finish
the slab using a burlap drag. Use a burlap drag of double thickness, at least 3 feet wide, and long enough to span between curb faces. Lay the burlap on the slab surface and drag it in the direction the slab is being placed, keeping approximately 2 feet of its width in contact with the slab surface. Keep the burlap drag damp, clean, and free from hardened concrete. 609-6
609.03.10 Texturing. Texture the surface by forming transverse grooves. Form the
transverse grooves by approved manual tools such as rakes with spring steel tines. Form the grooves in the concrete at an appropriate time during concrete set, so that in the hardened concrete, the grooves will be between 0.09 to 0.13 inch in width, between 0.12 and 0.19 inch in depth, and be spaced at random intervals between 0.3 and 1.0 inch. Terminate the grooves approximately 18 inches from faces of the curbs, concrete barrier walls, or other vertical walls. Regardless of the method used to form the grooves, ensure that the grooves are relatively smooth and uniform, are formed without tearing the surface or without bringing pieces of the coarse aggregate to the top of th e surface, and are formed to drain transversely. Correct any individual areas of hardened grooved concrete that do not conform to these requirements by the cutting of acceptable grooves in the hardened surface with an approved cutting machine or by other approved methods.
609.03.11 Waterproofing Membranes and Surface Courses for Slabs. When a
waterproofing membrane overlay or special su rface course is specified in the Contract, prepare the slab surface according to the procedures designated in the Contract. Do not texture the surface and do not apply a liquid membrane forming curing compound when the slab is to be waterproofed or receive a surface course.
609.03.12 Curing. Immediately after finishing and while the surface is slightly damp,
apply Type II (white pigmented) membrane-forming curing compound to the slab between the curb lines. Do not dilute or alter the compound, but thoroughly agitate it immediately before applying it. When the compound is too viscous to apply, warm it in a water bath to approximately 100 F before applying it. Apply the compound uniformly using an approved pressure sprayer at a rate of one gallon per 120 square feet. If the Engineer deems the application is not uniform as it progresses, apply the compound in 2 applications, each at a minimum rate of one gallon per 240 or less square feet. Start the second application after completing the first application. The Engineer will determine the total quantity of compound actually applied to the slab and compute the actual rate of application. When the Engineer determines the total actual application rate is less than one gallon per 120 square feet actual coverage, apply additional compound immediately and uniformly over the entire surface at a rate the Engineer directs. When the Contract does not require texturing, reduce the total rate of application to one gallon per 150 square feet. If the Engineer deems the application is not uniform as it progresses, apply the compound in 2 applications, each at a minimum rate of one gallon per 300 square feet. Start the second application after completing the first application. When the Engineer determines the total actual application rate is less than one gallon per 150 square feet actual coverage, apply additional compound immediately and uniformly over the entire surface at a rate the Engineer directs. Prevent the compound from being applied to reinforcing steel, concrete surfaces to be bonded to other concrete, or any other surfaces not specifically designated to receive the compound. When having inadvertently applied the compound to areas or surfaces not designated, remove by sandblasting or other approved methods. After applying the compound, and as soon as possible without damaging the surface texture, cover the slab between the curb lines with curing blankets or a double thickness of burlap and keep the slab continuously wet until the required compressive strength is attained as determined by testing field cured cylinders . If other operations are not delayed, the Engineer may require 7 days wet cure regard less of cylinder strengths. If using curing blankets, place and maintain blankets and apply water as specified in Subsection 601.03.17.
609.03.13 Surface Finish. Finish exposed areas of curbs, railings, and plinths, as
specified in Subsection 601.03.18.
609.04 Measurement.
609.04.01 Concrete. The Department will measure the quantity in cubic yards
609-7 according to the Record Plans. The Department will base the final quantity on the design quantity. The design quantity includes beam haunches. The Engineer will not measure differences between the theoretical and actual haunch heights for payment. When there is an error or omission in the design quantity in excess of 2 percent, the Department will adjust the design quantity accordingly. The Department will adjust quantities resulting from authorized dimension changes. The Department will not subject these quantities to the 2 percent limitation. The Department may measure the depth of concrete cover above the top mat of steel reinforcement in inches according to KM 64-313. The Department will not measure the depth of concrete cover above the top mat of st eel reinforcement as a separate pay unit, but will use it to calculate an adjusted Contract quantity for Concrete. The Department will not measure furnishing inspection facilities, joint construction, or stenciling for payment and will consider them incidental to this item of work.
609.04.02 Steel Reinforcement. The Department will measure the quantity according
to Subsection 602.04.
609.04.03 Drain Pipe. If this item is a separate pay item, the Department will measure
the quantity in linear feet. If this item is not a separate pay item, the Department will not measure the quantity for payment and will consider it incidental to Structural Steel.
609.04.04 Structural Steel. The Department will measure the quantity, including
drainage systems and structural steel expa nsion joint systems, according to Subsection
607.04 The Department will not measure paint, fittings, and connections for payment and
will consider them incidental to this item of work.
609.04.05 Neoprene Expansion Dams. The Department will measure the quantity in
linear feet.
609.04.06 Joint Sealing. The Department will measure the quantity according to
Subsection 606.04.08.
609.05 PAYMENT. The Department will make payment for the completed and accepted
quantities under the following: 609-8 Code Pay Item Pay Unit 08100-08105, 02555 Concrete, Class(1) See Subsection 601.05 08150 Steel Reinforcement See Subsection 602.05 08160 Structural Steel See Subsection 607.05 02998 Masonry Coating See Subsection 601.05 08820, 08821 Drain Pipe, Size Linear Foot 08469-08472 Neoprene Expansion Dam, Size Linear Foot 08540 Joint Sealing See Subsection 606.05
610.01 DESCRIPTION. Build all concrete box culverts and concrete headwalls
according to the Contract. For box culverts constructed using precast sections, conform to Section 611. For precast headwalls, conform to Section 710.
610.02 Materials.
610.02.01 Concrete. Conform to Subsection 601.02 and 601.03.
610.02.02 Steel Reinforcement. Conform to Section 811.
610.02.03 Concrete Pipe. Conform to Section 810.
610.02.04 Joint Materials. Conform to Section 807.
610.02.05 Masonry Coating. Conform to Section 828.
610.02.06 Concrete Curing Materials . Conform to Section 823.
610.03 CONSTRUCTION. Conform to Subsection 601.03 for all concrete construction.
610.03.01 Footings. Construct footings to the elevation specified in the Plans, and
increase the depth when the Engineer determines that it is necessary to provide sufficient bearing or to prevent undermining. Only rais e footing elevations when encountering solid rock at elevations above those specified in th e Plans and with the approval of the Engineer. Form the outside face of all footings of concrete headwalls for pipe, box, or arch culverts to the full depth of the footing. Do not place any concrete in the foundation until the Engineer has inspected and approved the depth of excavation and character of the foundation material. Whenever the natural foundation material is not sufficiently stable to support the structure or whenever it is anticipated that high water may cause excessive erosion around the footings, the Engineer may order Extra Work to provide the structure with adequate support or protection according to Subsection 109.04. When the condition of excavation for footings is otherwise satisfactory but is such that concrete cannot be placed without mud becoming mixed with the concrete, remove the entire mass of mud and replace it with stable material or prevent infiltration of mud by methods such as a layer of coarse aggregate and geotextile fabric or a layer of plastic material. Perform work by methods other than removing and replacing the entire mass of mud according to Subsection 109.04.