104 — MAINTENANCE OF TRAFFIC 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104 — MAINTENANCE OF TRAFFIC
104.00 General
This Section sets forth the traffic control requirements necessary for the safe and continuous maintenance of traffic throughout the area affected by the work and is intended to minimize inconveniences to the traveling public, while providing for the safety of motorists, pedestrians, and workers. Maintain vehicular and pedestrian traffic on or along any transportation facility as specified in the Contract Documents. When speed of traffic is noted, this means the posted speed or prevailing travel speed, whichever is higher, unless otherwise specified. All applicable Maintenance of Traffic equipment shall conform to NCHRP Report 350 and/or MASH 2016 criteria for Test Level 3. When no longer needed, remove items used for temporary maintenance of traffic from the project site. All removed items shall become the property of the Contractor, unless otherwise specified. Ensure that at least 90 percent of all reflective barrier markers, warning lights, and raised pavement markers are operational at any given time. Correct deficiencies within 24 hours after notification. Upon initial installation, temporary traffic control signs shall have at least 70 percent of the reflectivity specified in 950.03 over 90 percent of the reflectorized surface. Channelizing devices shall have at least 80 percent of the reflectivity specified in 950.03 over 90 percent of the reflectorized surface. Replace damaged traffic control signs within four hours of notification. Take necessary corrective action, as approved, to adequately warn and protect the public until the signs are replaced. The Contract Documents will specify one or more of the items listed in the following sections. When work is specified to be accomplished under the Maintenance of Traffic item, the work will be incidental to the Contract price for Maintenance of Traffic.
104.01 Traffic Control Plan (Tcp)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.01 — TRAFFIC CONTROL PLAN (TCP)
104.01.01 Description
Develop and implement a TCP. The TCP will include the design and placement of items such as signing, pavement markings, delineation, channelization, barriers, crash cushions, and other items as required. TCPs may be implemented within a single project or jointly between two or more projects. In situations where TCPs are jointly implemented, ensure that correct and nonconflicting guidance is presented to the traveling public. Prior to commencement of Contract work, the successful bidder shall complete a Traffic Control Plan Certification. Indicate whether the Administration's TCP will be implemented (Option 1), the Administration’s TCP will be modified (Option 2), or a TCP will be developed (Option 3). Submit the TCP in writing to the Engineer at least 20 days prior to starting any work. Submit changes to the approved TCP in writing at least five days prior to implementing the change. For emergencies, the approval process will be completed within four hours. All changes to the TCP shall be approved in writing by the Engineer prior to implementation. Submit for approval supporting documentation containing an assessment of safety and mobility impacts of the modified or proposed TCP. Contact the Engineer to determine what level of detail and types of analysis are required for the assessment. No work shall begin until the required traffic control patterns and devices are in place. Refer to Contract Documents for Work Restrictions. When TCP Option 2 or Option 3 is selected, the following shall apply:
104.01 Traffic Control Plan (Tcp)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.01.02 Materials
Not applicable.
104.01.03 Construction
Not applicable.
104.01.04 Measurement and Payment
Any traffic control plan developed by the Contractor will not be measured but the cost will be incidental to other pertinent items specified in the Contract Documents.
104.02 Maintenance of Traffic (Mot)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.02 — MAINTENANCE OF TRAFFIC (MOT)
104.02.01 Description
Maintain traffic safely and efficiently through and around the area affected by the work.
104.02.02 Materials
Traffic Materials Section 950
104.02.03 Construction
104.02 Maintenance of Traffic (Mot)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.02 Maintenance of Traffic (Mot)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.02 Maintenance of Traffic (Mot)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.02 Maintenance of Traffic (Mot)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.02.04 Measurement and Payment
Unless otherwise specified, Maintenance of Traffic will not be measured but will be paid for at the Contract lump sum price. The payment will be full compensation for relocating, turning, completely covering and uncovering or removing and resetting, maintaining in like new condition, and cleaning existing and temporary traffic signs and other traffic control devices. Included is the inventory of all existing pavement markings and the treatment of any other traffic control device not included in these Specifications but necessary for the fulfillment of the Contract requirements and implementation of the approved Traffic Control Plan, and for all material, labor, equipment, tools, and incidentals necessary to complete the work. Payment of the Contract lump sum price will be prorated and paid in equal amounts on each monthly estimate. The number of months used for prorating will be the number estimated to complete the work.
104.02.04 01 When specified in the Contract Documents, Maintenance of Traffic will be
measured and paid for at the Contract price per unit day.
104.02.04 02 When there is no item in the Contract Documents, maintenance of traffic will not
be measured but the cost will be incidental to other pertinent items specified in the Contract Documents.
104.03 Temporary Raised Pavement Markers (Rpms)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.03 — TEMPORARY RAISED PAVEMENT MARKERS (RPMS)
104.03.01 Description
Furnish, install, and remove as necessary, temporary RPMs.
104.03.02 Materials
Temporary RPMs QPL
104.03.03 Construction
Install temporary RPMs, as specified in the Contract Documents and in accordance with the manufacturer's recommendations.
104.03.04 Measurement and Payment
The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work. Increases or decreases in quantities will not be a basis for renegotiation of the Contract unit price.
104.04 Temporary Concrete Traffic Barrier (Tcb) for Maintenance of Traffic
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.04 — TEMPORARY CONCRETE TRAFFIC BARRIER (TCB) FOR MAINTENANCE OF TRAFFIC
104.04.01 Description
Furnish, place, reset, and remove TCB.
104.04.02 Materials
Precast Concrete Traffic Barrier 950.01 Vertical Panels and Reflective Barrier Markers QPL TCB shall conform to NCHRP Report 350 and/or MASH 2016 criteria for Test Level 3.
104.04.03 Construction
Maintain TCB in alignment and in a like new condition. Remove and relocate TCBs as directed. Install reflective barrier markers and vertical panels (object markers) on the TCB as specified. Connections. In addition to the pin and loop connection shown on the Standards, the channel splice, vertical I beam, and lapped joint connections specified in the AASHTO Roadside Design Guide, and the proprietary T-Lok and J-J Hook Systems will be allowed provided only one type of joint connection is used for the length of the barrier.
104.04.04 Measurement and Payment
The payment will be full compensation for furnishing, placing, maintaining and removal from the project site as directed, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.
104.04 Temporary Concrete Traffic Barrier (Tcb) for Maintenance of Traffic
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS The payment for Reset Temporary Concrete Traffic Barrier for Maintenance of Traffic will include removal from its original placement, transporting, and resetting it in its new temporary location.
104.05 Traffic Barrier W-Beam (Tbwb) for Maintenance of Traffic
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.05 — TRAFFIC BARRIER W-BEAM (TBWB) FOR
104.05.01 Description
Furnish, install, maintain, reset, and remove temporary TBWB. Refer to 605.01.01 and 605.01.02.
104.05.02 Materials
Traffic Barrier W-Beam 918.01 Traffic Barrier Posts 918.02 Hardware for Traffic Barriers 918.03 Wood Offset Blocks 918.04 Composite Offset Blocks Section 605 TBWB shall conform to NCHRP Report 350 and/or MASH 2016 criteria for Test Level 3.
104.05.03 Construction
Refer to 605.03.01, 605.03.02, and 605.03.03. TBWB. Use construction methods in accordance with the applicable portions of Section 605. TBWB Replacement. Immediately replace damaged portions of the TBWB. Install the TBWB to the correct horizontal and vertical alignment using offset blocks in kind. TBWB Reset. When work is sufficiently completed through a traffic control area and TBWB is no longer required, remove and reset the TBWB and all components to a new work area as specified. Restore the previous location to original condition. TBWB End Treatments. Refer to Section 104.09 and Section 104.10. Place an approved end treatment at all ends of TBWB prior to opening to traffic.
104.05 Traffic Barrier W-Beam (Tbwb) for Maintenance of Traffic
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.05.04 Measurement and Payment
The payment will be full compensation for furnishing and installing all cables, posts, brackets, traffic barrier W-beam, hardware, galvanizing, excavation, backfilling, connections to rigid structures, removal, restoration of the area, and for all material, labor, equipment, tools, and incidentals necessary to complete the work as directed.
104.06 Tubular Markers
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.06 — TUBULAR MARKERS
104.06.01 Description
Furnish, install, and remove tubular markers for maintenance of traffic.
104.06.02 Materials
Tubular Markers QPL Reflectorization 950.03 Tubular Markers may be manufacturer-certified as NCHRP Report 350 and/or MASH 2016 compliant as long as there are no attachments to the device.
104.06.03 Construction
Install tubular markers as recommended by the manufacturer and as approved by the Engineer.
104.06.04 Measurement and Payment
Tubular Markers will be measured and paid for at the Contract unit price per each. The payment will be full compensation for removal and for all material, labor, equipment, tools, and incidentals necessary to complete the work. Tubular markers damaged due to traffic operations will be measured and paid for at the Contract unit price per each for Replacement of Tubular Marker Mast. If the base detaches from the pavement, replace the entire tubular marker assembly at no additional cost to the Administration, unless damaged by Administration snow removal operations.
104.07 Arrow Panel (Ap)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.07 — ARROW PANEL (AP)
104.07.01 Description
Furnish and place APs for temporary use.
104.07.02 Materials
Arrow Panel QPL
104.07.03 Construction
At least 24 hours before use, furnish and test the arrow panel (AP). The AP shall be self-contained, vehicle-mounted or portable. Use a self-contained trailer unit unless otherwise specified. If a full matrix display board is used as an AP, it shall comply to this specification and it shall be able to display a left arrow, right arrow, double arrow, and a four-corner caution mode per the Arrow Panel tables. Elements. The AP unit shall conform to the Arrow Panel tables and be arranged with double- pointed arrow configuration capable of displaying a left arrow, right arrow, double arrow, and a four-corner caution mode. A sequential chevron, sequential arrow and single bar caution panel shall not be displayed. ARROW PANEL UNIT MdMUTCD TYPE Portable A, D Vehicle Mounted B Self-Contained Trailer C Arrow Board Type Minimum Size Minimum Legibility Distance Minimum Number of Elements A 48 in. x 24 in. 1/2 mile 12 B 60 in. x 30 in. 3/4 mile 13 C 96 in. x 48 in. 1 mile 15 D None* 1/2 mile 12 ∗Length of arrow equals 48 in., width of arrowhead equals 24 in.
104.07 Arrow Panel (Ap)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Type A, B, and C arrow boards shall have solid rectangular appearances. A Type D arrow board shall conform to the shape of the arrow. The color presented by the AP lights shall be yellow. Lights with the pre-flash option of white strobe or pulsed lighting shall not be displayed. APs shall have both manual and automatic dimmer devices capable of reducing the light intensity by 50 percent. Periodically clean the photocells in order to prevent malfunctioning of the brightness control. Dimmer devices are mandatory during night operation. The devices shall include a fail-safe system that ensures maximum brightness during daytime operations and a reduction in brightness of up to 50 percent during periods of darkness, regardless of which dimmer device is operational. The APs shall provide full illumination within at least a 24 degree cone perpendicular to the panel face. The flashing rate shall be not less than 25 or more than 40 flashes per minute as required in the MdMUTCD. Power Supply. The AP shall operate from a solar powered electrical system and consist of battery power and solar array panels and be capable of providing power supply to the AP for 21 consecutive days without auxiliary charge. Deployment. Place APs as specified. Maintain APs in good operating order.
104.07 Arrow Panel (Ap)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.07.04 Measurement and Payment
Arrow Panels will be measured and paid for at the Contract price per unit day. A unit day will consist of any approved usage within a work shift, regardless of start time or whether the shift runs into another calendar day. Each arrow panel will be paid for only once per unit day, regardless of how many times it may be relocated. When an arrow panel is used for part of a day, it will be measured and paid for as a unit day. When operations require continuous 24 hour use of an arrow panel, the unit day will be measured as 24 hour periods from start to finish. The payment will be full compensation for all material, labor, equipment, tools, and incidentals required to set up and operate at the site as required, and at any relocated site as specified and as directed.
104.08 Temporary Traffic Signs (Tts)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.08 — TEMPORARY TRAFFIC SIGNS (TTS)
104.08.01 Description
Furnish, install, and maintain TTS on or along all transportation facilities.
104.08.02 Materials
Wood Sign Supports 921.05 and 921.06 Reflectorization 950.03 Sign Material 950.08 Square Perforated Tubular Steel Sign Supports As Approved by the Office of Traffic and Safety Composite Aluminum Signs, Plastic Signs, Flexible Roll Up Signs, Portable Sign Supports, and Mounting Hardware QPL Use fluorescent orange for all orange colored work zone signs. Use reflectorized signs for both daytime and nighttime use. Temporary traffic signs and supports shall conform to MASH 2016 criteria for Test Level 3.
104.08.02 01 Sign Thickness.
104.08 Temporary Traffic Signs (Tts)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.08.03 Construction
104.08.03 01 Sign Design and Fabrication. Design and fabricate signs according to the
Administration’s Standard Highway Sign Book (SHSB). You may request a copy of the SHSB from the Office of Traffic and Safety, Traffic Engineering Design Division. S u b m i t designs of signs not included in the SHSB in scaled sketches for approval. Direct written requests to the Engineer. All work area warning signs with the exception of the “2(3) LEFT(RIGHT) LANE CLOSED XX” (W20-5a(1)) signs shall be 48 in. x 48 in., unless otherwise specified. Sign W20-5a(1) shall be 60 in. x 60 in., unless otherwise specified.
104.08.03 02 Sign Installation. Place signs in accordance with the MdMUTCD and the Contract
Documents. Adjust signs along the highway to provide adequate sight distance to work zone signs and existing signs. Ensure that signs are not obscured or obstructed. Ensure that supplemental signs do not cover any part of the face of the primary sign. Mount signs that will be in place for more than three working days on wood posts or on square perforated tubular steel posts, unless otherwise specified. Do not place any additional bracing on wood posts unless the sign is behind a protective barrier. The tops of the wood posts shall not protrude more than 3 in. beyond the nearest edge of the sign. Portable sign supports shall be self-erecting. They shall be able to withstand a wind velocity of 70 mph and be able to maintain themselves within 5 degrees of rotation around their vertical axis. Do not install signs before they are inspected and approved. Do not display signs to traffic until directed. Properly maintain the TTS, leave in place while applicable, and remove immediately when no longer required. When operations are performed in phases or stages, display only those signs to traffic that apply to the present conditions. When one or more signs do not indicate of actual conditions, such as during periods of temporary shutdown or extended periods of no work being performed (including lunchtimes and overnight periods), remove the entire work zone setup, remove the inapplicable signs, turn them away so they are not visible to any traffic, or completely cover them with an approved opaque material. When signs are no longer needed, remove temporary traffic signs, associated materials and incidentals from the project site. Remove materials become the property of the Contractor.
104.08.03 03 Sign Maintenance and Sign Replacement. Maintain signs in a new or like new
condition. Maintain sign faces free of tape, tape residue, or any other foreign matter. Remove all advertisements from signs and supports.
104.08 Temporary Traffic Signs (Tts)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS When directed, replace signs with poor reflectivity or those that become faded, illegible, or damaged. Signs that are not new may be used only if the reflective intensity at a divergence angle of 0.2 degrees and incidence angle of minus 4 degrees conforms to at least 70 percent of the values as specified in 950.03 over 90 percent of their reflectorized surface. At other times throughout the duration of the Contract, the sign reflectivity intensity shall be at least 60 percent. The acceptability of the signs shall be determined by 1 ft square test plates calibrated in accordance with these requirements.
104.08.04 Measurement and Payment
104.08.04 01 Temporary Traffic Signs will be measured and paid for at the Contract unit price
per square foot of sign for the Temporary Traffic Sign item. The payment will be full compensation for furnishing the signs and supports, installation, relocation, maintenance, cleaning, replacement due to non-traffic damage and normal wear, removal, and for all materials, labor, equipment, tools, and incidentals necessary to complete the work.
104.08.04 02 Where signs have been set and damaged by traffic, and the Engineer determines
that they are not repairable, replacement will be measured and paid for at the Contract unit price per square foot of sign for the Temporary Traffic Sign item. The payment will be full compensation for furnishing the signs and supports, installation, relocation, maintenance, cleaning, removal, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.
104.09 Temporary Traffic Barrier End Treatments
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.09 — TEMPORARY TRAFFIC BARRIER END TREATMENTS
104.09.01 Description
Furnish, install, maintain, reset, and remove temporary traffic barrier end treatments in conformance with the manufacturer's recommendations or as directed. Refer to 605.01.01 and
605.01 02.
104.09.02 Materials
Temporary Traffic Barrier End Treatments Refer to the Contract Documents or QPL Temporary Crash Cushion Sand Filled Plastic Barrels (SFPB)
104.10 02
Temporary Traffic barrier End Treatments shall conform to NCHRP Report 350 and/or MASH 2016 criteria for Test Level 3.
104.09.03 Construction
Refer to 605.03.01, 605.03.02, and 605.03.03. Document each step of the installation, and complete and submit the manufacturer installation checklist for the installed product. Temporary End Treatments.
104.09 Temporary Traffic Barrier End Treatments
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Inspection of End Treatments.
104.09.04 Measurement and Payment
Temporary Traffic Barrier End Treatments, Remove and Reset Temporary Traffic Barrier End Treatments, and Repairing Temporary Traffic Barrier End Treatments will be measured and paid for at the Contract unit price for one or more of the items listed below unless otherwise specified.
104.09 Temporary Traffic Barrier End Treatments
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.10 Temporary Crash Cushion Sand Filled Plastic Barrels (Sfpb)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.10 — TEMPORARY CRASH CUSHION SAND FILLED PLASTIC BARRELS (SFPB)
104.10.01 Description
Furnish and install SFPB.
104.10.02 Materials
Sand 901.01 Plastic Barrels (Yellow) QPL SFPB shall conform to NCHRP Report 350 and/or MASH 2016 criteria for Test Level 3.
104.10.03 Construction
Prior to installing the SFPB, level the ground supporting the system utilizing material comparable to the existing ground or as approved. The components, assembly, placing configuration, and filling of the individual plastic barrels with varying weights of sand shall be in accordance with the manufacturer's recommendations or as specified in the Contract Documents. Barrels shall be watertight. SFPB may stand on pallets up to 4 in. high. Reflectorize the first barrel of the SFPB configuration as specified. Following an impact, an approved reflectorized drum will suffice temporarily as reflectorization for the SFPB. Replace damaged barrels within four hours after notification. Use dry and loose sand in the barrels. Do not use bags of sand. Add an antifreeze agent to the sand in accordance with the manufacturer's recommendations. Have sufficient replacement materials available. Immediately after the SFPB have served the intended purpose, is to remove the installation and restore the site as directed.
104.10 Temporary Crash Cushion Sand Filled Plastic Barrels (Sfpb)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.10.04 Measurement and Payment
Temporary Crash Cushion Sand Filled Plastic Barrels will be measured and paid for at the Contract unit price per barrel for one or more of the items listed below and specified in the Contract Documents.
104.11 Temporary Pavement Markings
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.11 — TEMPORARY PAVEMENT MARKINGS
104.11.01 Description
Furnish, install, and remove temporary pavement markings as specified or as directed by the Engineer. Markings include lines, letters, numbers, arrows, and symbols.
104.11.02 Materials
Pavement Marking Paint 951.01 Black Out Tape 951.02 Removable Pavement Markings 951.08
104.11.03 Construction
104.11.03 01 Quality Assurance/Quality Control. Refer to 549.03. Employ certified
technicians to perform quality control testing. The Engineer will perform quality assurance checks by completing the Nighttime Visibility Evaluations per MSMT 729.
104.11.03 02 Warranty Period. Maintain and correct any defects in the pavement markings for
a period of 180 days from the date of application for tape, thermoplastic or epoxy, and 60 days for paint. Replace defective pavement markings within this warranty period as necessary and as directed at no additional cost to the Administration. When paint is used as a temporary marking for a lane shift/closure that is to be greater than 60 days in length, it shall be reapplied every 60 days.
104.11.03 03 Application and Removal. Apply pavement markings per the manufacturer’s
recommendations and as specified. Apply markings in the same direction as the flow of traffic. Apply the markings to the locations specified or as directed. Pavement markings may be applied to either new or existing paved surfaces. Apply markings to newly paved surfaces before traffic is allowed on the pavement. For milling and paving operations, non tape markings may be used for temporary markings between lifts and temporary raised pavement markings (RPM)s are not required. Use removable tape for temporary markings applied to the final surface. When temperatures are too low to allow the placement of removable tape on the final surface, request a written exception for the use of other type of markings in lieu of removable tape.
104.11 Temporary Pavement Markings
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Completely remove all non-applicable pavement markings within the travel way and adjacent to the travel way for lane shifts as necessary and as directed. Surface Condition. Ensure the pavement surface is clean, dry, and free of all contaminants prior to applying any pavement markings. Remove all residual, loose or poorly applied pavement markings as necessary and as directed. Pavement Marking Removal. Completely remove all removable pavement markings prior to applying permanent markings. Remove any objectionable adhesive residue on stage construction or final surfaces of Portland cement concrete pavements by water blasting or other methods as approved. Do not use open flame to remove any pavement markings or adhesive residue. Remove all pavement markings in a manner that ensures there is no damage to the existing or final surface. Black out Tape. Black out tape may be used for masking existing markings in accordance with MdMUTCD. Use to mask existing marking for temporary shift conditions of less than 14 days and where the traffic will return to the original alignment and markings. For shifts longer than 14 days, remove the existing marking by hydro blasting and replace with new permanent /final markings when original alignment returns. Retroreflectance. The initial retroreflectance readings for temporary pavement markings shall be a minimum of 250 millicandelas/lux/square meter and 150 millicandelas/lux/square meter for white and yellow markings, respectively. The pavement markings will be monitored per MSMT 729 during the Warranty Period.
104.11.04 Measurement and Payment
Payment for Removable Pavement Markings, Removal of Removable Pavement Markings, Pavement Marking Paint, and the Removal of Existing Pavement Markings will be measured and paid for using one or more of the items listed below and as specified. Payment will be full compensation for furnishing, placing, complete removal of lines, letters, numbers, arrows, symbols, and the removal of all residue. Payment will also cover maintenance and replacement of the markings during the 180 day period, and for all material, labor, equipment, tools, and incidentals necessary to complete the work. Removal and replacement of temporary pavement markings required beyond the 180 day period will be measured and paid for at the Contract unit price for the pertinent temporary pavement marking item. Temporary markings replaced during the 180 day period as a result of plowing will be paid for at the Contract unit price for the pertinent temporary marking item, as determined.
104.11 Temporary Pavement Markings
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.12 Drums for Maintenance of Traffic
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.12 — DRUMS FOR MAINTENANCE OF TRAFFIC
104.12.01 Description
Furnish, set, reset, maintain, and remove drums for maintenance of traffic.
104.12.02 Materials
Reflectorization 950.03 Plastic Drums QPL Drums may be manufacturer-certified as NCHRP Report 350 and/or MASH 2016 compliant as long as there are no attachments to the device. Drums shall be manufactured of low density polyethylene (LDPE), 36 in. in height, and have a diameter of at least 18 in. The drum shall have four, 6 in. wide horizontal, circumferential, alternating orange and white stripes, with the top stripe being orange. Drums may have one or more flat sides as long as the minimum 18 in. diameter is satisfied. Drums may include recycled plastic content. The drum base may contain up to 100 percent recycled content. Use high performance wide angle white and fluorescent orange sheeting on all drums.
104.12.03 Construction
Use sand-filled bases or bags of sand to keep the drums from moving. Install sandbags on the base of the drum only. Rubber or plastic bases or recycled tires, weighing between 20 lb and 40 lb, may be used as a substitute for sandbags. The Contractor’s name or identification mark may be neatly stenciled at the bottom of the nonreflective portion of the drum in letters no more than 2 in. high. No other markings or wording may be on the vertical side of the drum. Maintain drums in a new or like new condition. Replace drums damaged by traffic within four hours after notification. Damaged drums shall be recycled to the extent possible. The disposition of the damaged drums shall be provided prior to payment for any replacement drums.
104.12 Drums for Maintenance of Traffic
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.12.04 Measurement and Payment
Drums for Maintenance of Traffic will be measured and paid for once at the Contract unit price per each. The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work. Where drums have been set and damaged by traffic and the Engineer determines that they are not repairable, replacement will be measured and paid for at the Contract unit price. A disposition as specified in 104.12.03 is required prior to payment.
104.13 Barricades for Maintenance of Traffic
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.13 — BARRICADES FOR MAINTENANCE OF TRAFFIC
104.13.01 Description
Furnish, set, reset, maintain, and remove barricades for maintenance of traffic.
104.13.02 Materials
Reflectorization 950.03 Barricades QPL Barricades shall conform to NCHRP Report 350 and/or MASH 2016 criteria for Test Level 3.
104.13.03 Construction
Use barricade rails conforming to the MdMUTCD, with a minimum rail length of 5 ft. Use approved reflective sheeting and installation procedures. Replace barricades damaged by traffic within four hours after notification. Mount signs so that no more than half of the top two rails or one third of the barricade is covered. Mount signs on the barricade so that the bottom of the sign is at least 12 in. above the ground or surface. The bottom of rectangular signs shall not be mounted higher than the bottom of the top rail. Do not use aluminum signs.
104.13.04 Measurement and Payment
Barricades will be measured and paid for once at the Contract unit price per each for the pertinent barricade item specified in the Contract Documents. The payment will be full compensation for warning lights (when required), the maintenance and removal of any required warning lights, and for all material, labor, equipment, tools, and incidentals necessary to complete the work. Where barricades have been set and damaged by traffic, and the Engineer determines that they are not repairable, replacement will be measured and paid for at the Contract unit price.
104.14 Cones for Maintenance of Traffic
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.14 — CONES FOR MAINTENANCE OF TRAFFIC
104.14.01 Description
Furnish, set, reset, maintain, and remove cones for maintenance of traffic.
104.14.02 Materials
Reflectorization 950.03 Cones QPL Cones may be manufacturer-certified as NCHRP Report 350 and/or MASH 2016 compliant as long as there are no attachments to the device. All cones shall meet MdMUTCD and be new or like new condition. All cones shall be orange in color. Cones shall be at least 28 in. high, 10 in. diameter at the inside of the base, and reflectorized with two white retroreflective stripes. The top stripe shall be 6 in. wide and located 3 in. to 4 in. from the top of the cone. The second stripe shall be 4 in. wide and located 2 in. below the top band. Tall-Weighted Cones. When specified, tall-weighted cones shall be at least 42 in. high and 7 in. diameter at the inside of the base. Tall-weighted cones shall be manufactured of low density polyethylene (LDPE) and have four high performance wide angle white and orange retroreflective stripes. The stripes shall be horizontal, circumferential and 6 in. wide. Alternate stripe colors with the top stripe being orange. Any non-retroreflective spaces between the orange and white stripes shall not exceed 1/2 in.
104.14.03 Construction
The Contractor’s name or identification mark may be neatly stenciled at the bottom of the cone in a maximum of 2 in. high letters. Place no other markings or writings on the vertical area of the cone. Turn the cone so that the Contractor’s name or identification mark faces away from traffic. Equip all cones with approved weights or anchor collars (15 lb maximum) as needed to maintain an upright position. Anchor collars shall fit to the base of the cone. For tall-weighted cones use anchor collars weighing 10 lb to 30 lb. Replace cones damaged by traffic within four hours or as directed after being notified.
104.14 Cones for Maintenance of Traffic
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.14.04 Measurement and Payment
Cones for maintenance of traffic and cones that have to be replaced will not be measured but the cost will be incidental to the Contract price for Maintenance of Traffic.
104.15 Flagger
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.15 — FLAGGER
104.15.01 Description
Furnish flaggers when specified or directed. Flaggers shall have completed an Administration approved flagger training course within the last four years. The failure of any flagger to perform the required duties will be grounds for replacement. Flaggers shall utilize two-way radios, field telephones, or pilot vehicles when not within sight distance of each other, or when directed.
104.15.02 Materials
Reflective sheeting on the STOP/SLOW paddle 950.03 Paddles shall be 24 in. x 24 in. with letters at least 8 in. high and mounted at least 5 ft above the ground.
104.15.03 Construction
Flagging shall conform to MdMUTCD. All outfits and equipment (STOP/SLOW paddles, pilot cars or other vehicles, air horns or bullhorns, field telephones, two-way radios, site illumination, etc.) will be subject to approval. Use STOP/SLOW paddles unless otherwise permitted.
104.15.04 Measurement and Payment
Flagger will not be measured but the cost will be incidental to the Contract price for Maintenance of Traffic. When an item for Flagger is included in the Contract Documents, Flagger will be measured and paid for at the Contract unit price per hour. The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work.
104.16 Modification of Existing Signs
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.16 — MODIFICATION OF EXISTING SIGNS
104.16.01 Description
Relocate, remove, cover, modify copy, reinstall, or change existing highway signs relating to the construction activity. This work is in addition to the temporary traffic signs specified in 104.08.
104.16.02 Material
Sign Panel Supports and Hardware 909.07, 921.05, 921.06, 950.04, A123, A153, and A709 Reflective and Non-reflective Sheeting 950.03 Sign Materials 950.08 Use an approved opaque sign covering material.
104.16.03 Construction
Modify existing signs as specified.
104.16.04 Measurement and Payment
Modification of existing signs will be measured and paid for using one or more of the items listed below and specified in the contract documents. The payment will be full compensation for all excavation, backfill, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.
104.16 Modification of Existing Signs
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.17 Temporary Movable Type Concrete Traffic Barrier (Mctb)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.17 — TEMPORARY MOVABLE TYPE CONCRETE TRAFFIC BARRIER (MCTB)
104.17.01 Description
Furnish, place, assemble, maintain, move, and remove and dispose of movable interlocking type concrete traffic barrier. Movable barrier systems shall consist of individual units that remain connected for the total length when being moved in one continuous operation.
104.17.02 Material
Precast Movable Concrete Barrier and Transfer Device QPL Reflective Barrier Markers QPL MCTB shall conform to NCHRP Report 350 and/or MASH 2016 criteria for Test Level 3.
104.17.03 Construction
Perform all transfer shifts using the transfer device. The transfer device shall be capable of moving and transferring the barrier as required, and of operating on the curve and grades specified. Ensure that the device does not extend into traffic. The Engineer will inspect the movable barrier upon delivery and throughout the life of the project. Replace any damaged or defective units as directed. Install reflective barrier markers as specified. Maintain the barrier and reflective barrier markers in a like new condition. Perform all maintenance operations for the transfer device. Have sufficient spare parts and personnel available to ensure that the required lane configurations are in place at the required times. Failure to move the MCTB at the proper time will be cause for penalty under TC-4.02.
104.17.04 Measurement and Payment
The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work.
104.17 Temporary Movable Type Concrete Traffic Barrier (Mctb)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.18 Traffic Manager (Tm)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.18 — TRAFFIC MANAGER (TM)
104.18.01 Description
Provide a Traffic Manager (TM).
104.18.02 Materials
Not applicable.
104.18.03 Construction
Submit the TM’s name for approval at least 10 days prior to commencing any work on the project. Provide proof that the TM has completed an Administration approved Temporary Traffic Control training course within the last four years. A change in the appointment of any TM throughout the duration of the Contract will require a written submittal for approval. Any failure of the TM to perform the required duties will be grounds for replacement. The TM shall be available at all times and be on site within 1/2 hour during periods of active work in the work zone. The TM shall do the following:
104.18 Traffic Manager (Tm)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.18.04 Measurement and Payment
The Traffic Manager will not be measured but the cost will be incidental to the Contract price for Maintenance of Traffic.
104.19 Portable Variable Message Signs (Pvms)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.19 — PORTABLE VARIABLE MESSAGE SIGNS (PVMS)
104.19.01 Description
Furnish, install and relocate portable, self-contained, trailer mounted variable message signs.
104.19.02 Materials
PVMS QPL All materials shall be like new, corrosion resistant, and unaffected by water spray, salt, oil, gasoline, and all other contaminants in the quantities normally found along the edge of the traveled roadway. Construction, materials, and operation shall meet NFPA, UL, and NEC. Ensure that sign messages are visible and legible for a distance of 900 ft from any point along the traveled approach roadway at all times. The PVMS shall be equipped with a sighting device to provide alignment for maximum visibility.
104.19.03 Construction
104.19.03 01 Equipment.
Trailer. In accordance with Maryland Motor Vehicle Law. Structural Support. The structural support framework shall allow the system to be assembled into a unit and be mounted on the trailer and shall provide the support mechanism between the sign panel assembly, the power supply, and the controller. The framework shall provide sufficient support to prevent damage to any unit component when the sign is in down and locked position during normal highway travel. The deployed structure shall supply adequate support to allow complete sign operation, including raising and lowering of the sign panel, during sustained wind speeds of 85 mph. The display windows shall be made of impact-resistant clear Lexan or as approved. Sign Panel. Not to exceed 144 in. length, 90 in. height, 12 in. depth.
104.19 Portable Variable Message Signs (Pvms)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Display.
104.19 Portable Variable Message Signs (Pvms)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS PVMS UNIT. Lift Mechanism.
104.19 Portable Variable Message Signs (Pvms)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.19 Portable Variable Message Signs (Pvms)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.19.03 02 Set up and operate the PVMS on the project site 24 hours in advance of actual use.
Ensure that each unit is functioning properly and approved. Locate the PVMS as specified. Aim the PVMS at approaching traffic in accordance with the 900 ft minimum visibility and legibility requirement. Ensure that the PVMS is level and that the sign face is not obscured by highway alignment or glare from either sunlight or vehicle headlights.
104.19 Portable Variable Message Signs (Pvms)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.19.04 Measurement and Payment
Portable Variable Message Sign will be measured and paid for at the Contract price per unit day. A unit day will consist of any approved usage within a work shift, regardless of start time or whether the shift runs into another calendar day. Each portable variable message sign will be paid for only once per unit day, regardless of how many times it may be relocated. When a portable variable message sign is used for part of a day, it will be measured and paid for as a unit day. When operations require continuous 24 hour use of a portable variable message sign, the unit day will be measured as 24 hour periods from start to finish. The payment will be full compensation for the electrical power and hook up, setup and maintenance of computer programs, changing messages, and for all material, labor, equipment, tools and incidentals necessary to complete the work.
104.20 Temporary Orange Construction Fence
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.20 — TEMPORARY ORANGE CONSTRUCTION FENCE
104.20.01 Description
Furnish, install, and maintain new or like new temporary orange mesh construction fence. This fence is not to be used as a safety barrier.
104.20.02 Materials
Precast Concrete Blocks 903.05 Tie Wire, Tension Wires, Tension Wire Clips and Hardware 914.02 Orange Mesh Fencing As approved Fence posts shall be 4 ft high, 1.90 in. diameter round posts; or 5-1/2 ft high, 2 in. steel U channel posts, as specified herein. Submit samples of the fence fabric, fence posts, movable precast concrete blocks, tie wire, tension wires, and other miscellaneous hardware for approval.
104.20.03 Construction
Temporary orange construction fence shall be at least 4 ft high and with a maximum post spacing of 8 ft. When installed on a paved surface, support the fence by inserting the round post into a precast concrete block having a round hole through the center of the block. When installed in unpaved areas, use steel U channel fence posts driven 1-1/2 ft into the ground. Installation of the fence in any other manner will require approval. Secure the fabric to the posts by wrapping a tie wire around the horizontal fence strands and the posts. Install a top tension wire to prevent sagging. When installed on paved surfaces, the Engineer will determine if a bottom tension wire is required. Remove the fence when the Engineer determines that the fence is no longer required. The removed fence is the property of the Contractor. Damaged Construction Fence. Repair or replace damaged construction fence within four hours after notification.
104.20 Temporary Orange Construction Fence
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.20.04 Measurement and Payment
The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work. Temporary Orange Construction Fence will be measured and paid for at the Contract unit price per linear foot for the actual number of linear feet measured to the centers of end posts. Remove and Reset Temporary Orange Construction Fence will be measured and paid for at the Contract unit price per linear foot.
104.22 Automated Flagger Assistance Device (Afad)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.22 — AUTOMATED FLAGGER ASSISTANCE DEVICE (AFAD)
104.22.01 Description
An automated flagger assistance device (AFAD) is designed for remote operation by a certified flagger. AFADs shall only be used in situations where there is only one lane of approaching traffic in the direction to be controlled. The AFAD shall be either Type I ‘STOP/SLOW’ Sign system or Type II ‘Red/Yellow’ Lens system. Furnish, install, and maintain a portable, self-contained, AFAD for temporary traffic control as specified in the Contract Documents or as directed. The AFAD shall be crashworthy as specified in Section 104. Furnish certified flagger(s) per 104.15.01 to operate the AFAD(s). Install AFAD related signs and channelizing devices as specified in the Book of Standards for Highways and Incidental Structures.
104.22.02 Materials
AFAD QPL Cones for Maintenance of Traffic 104.14.02 Reflectorization 950.03 Sign Material 950.08 The AFAD shall be capable of being operated from the controller cabinet mounted on the unit. The unit shall have the ability for manual override in case of remote failure.
104.22.02 01 General System Requirements.
104.22 Automated Flagger Assistance Device (Afad)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS shall be programmable to control either one unit or two units and be able to control units over the required range.
104.22.02 02 Type I ‘STOP/SLOW’ Sign AFAD Requirements.
104.22 Automated Flagger Assistance Device (Afad)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.22.02 03 Type II ‘Red/Yellow’ Lens AFAD Requirements.
104.22.03 Construction
104.22.03 01 AFAD. Place the AFAD unit as shown in the Contract Documents or as directed,
with all signs and traffic control devices visible to the driver of the initial approaching vehicle. Install advance warning signs and install cones along the road center line and around the AFAD according to the Book of Standards and the Contract Documents. Ensure that the AFAD is operational for the duration of the lane closure. The AFAD shall be like new, corrosion resistant, and unaffected by water spray, salt, oil, gasoline, and all other contaminants in the quantities normally found along the edge of the traveled roadway. Construction, materials, and operation shall be according to NFPA, ULI, and NEC. When used at night, the AFAD location shall be adequately illuminated.
104.22.03 02 Operation.
104.22 Automated Flagger Assistance Device (Afad)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.22.03 03 Flaggers. Provide certified flaggers on-site and use one of the following methods
to operate the AFAD(s):
104.22.03 04 Cones. Install cones according to the MdMUTCD, the Book of Standards, the
Contract Documents, and the following:
104.22.04 Measurement and Payment
104.22.04 01 Automated Flagger Assistance Device will be measured and paid for at the Contract
price per unit day per each Automated Flagger Assistance Device. A unit day will consist of any approved usage within a work shift, regardless of start time or whether the shift runs into another calendar day. Each Automated Flagger Assistance Device will be paid for only once per unit day, regardless of how many times it may be relocated. When an Automated Flagger Assistance Device is used for part of a day, it will be measured and paid for as a unit day. The payment will be full compensation for the Automated Flagger Assistance Device, and for all material, labor, equipment, tools, and incidentals necessary to setup and operate the Automated Flagger Assistance Device at the site as required and at any relocated site as specified or as directed. When operations require
104.22 Automated Flagger Assistance Device (Afad)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS continuous 24 hour use of an automated flagger assistance device, the unit day will be measured as 24 hour periods from start to finish.
104.22.04 02 Certified flaggers to operate the Automated Flagger Assistance Device will be
measured and paid for at the Contract unit price per hour as specified in 104.15.04.
104.22.04 03 Cones to delineate the center line in the approach to the Automated Flagger
Assistance Device and form the taper in front of the Automated Flagger Assistance Device will not be measured but the cost will be incidental to the Contract unit price for Automated Flagger Assistance Device.
104.22.04 04 Automated Flagger Assistance Device related signs (R1-7, R1-8, R10-6, R10-6a)
will not be measured but the cost will be incidental to the Contract unit price for Automated Flagger Assistance Device.
104.23 Protection Vehicle (Pv)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.23 — PROTECTION VEHICLE (PV)
104.23.01 Description
Furnish a PV as required. The PV shall consist of a work vehicle with approved flashing lights as required by the standard TCP’s and either:
104.23 Protection Vehicle (Pv)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Impact Performance. TMA/TTMAs manufactured prior to January 1, 2005, shall have passed NCHRP Report 350 Tests 50 and 51 Level 3. TMA/TTMAs manufactured after January 1, 2005, shall have passed NCHRP Report 350 Tests 50, 51, 52, and 53 Level 3. Dimensions.
104.23.02 Materials
The size of the work vehicle and the method of attachment shall be as specified in the TMA/TTMA manufacturer's specifications, and as tested according to NCHRP Report 350 and/or MASH 2016 at Test Level 3. The gross vehicle weight rating (GVWR) of the work vehicle shall be a minimum of 14 000 lb, and any fuel tank or container of hazardous materials shall be at least 10 1/2 ft from the rear of the work vehicle.
104.23.03 Construction
Not applicable.
104.23.04 Measurement and Payment
Protection Vehicle will be measured and paid for at the Contract price per unit day. A unit day will consist of any approved usage within a work shift, regardless of start time or whether the shift runs into another calendar day. Each protection vehicle will be paid for only once per unit day, regardless of how many times it may be relocated. When a protection vehicle is used for part of a
104.23 Protection Vehicle (Pv)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS day, it will be measured and paid for as a unit day. When operations require continuous 24 hour use of a protection vehicle, the unit day will be measured as 24 hour periods from start to finish. The payment will be full compensation for the complete protection vehicle, including the truck mounted attenuator/trailer truck mounted attenuator and arrow panel, licensed work vehicle operator, unless a separate pay item has been established for the Operator, relocating the protection vehicle, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.
104.24 Workers Present Trailer (Wpt)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.24 — WORKERS PRESENT TRAILER (WPT)
104.24.01 Description
A Workers Present Trailer (WPT) is designed to enhance motorists’ situational awareness when entering a work zone where workers are present. When activated, a WPT will display alternating flashing YELLOW signal heads (beacons). Furnish, install, operate, and relocate a portable, self-contained, WPT with flashing beacons and ‘Work Zone - Fines Higher When Flashing’ (R2-6(5)) sign as specified or as directed.
104.24.02 Materials
Each WPT unit shall include the trailer, structural support system, sign panel assembly, lift mechanism, power supplies, trailer mounted controller, flashing beacons, communications, and ancillary equipment. All materials for the WPT shall be like new, corrosion resistant, and unaffected by water spray, salt, oil, gasoline, and all other contaminants in the quantities typically found along the edge of a traveled roadway. Construction, materials, and operation shall be in accordance with NFPA, UL, and NEC. The WPT trailer shall be painted orange and shall comply with Maryland Motor Vehicle Law.
104.24.02 01 Equipment.
104.24 Workers Present Trailer (Wpt)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS reflectorized as specified in 950.03. The sign shall be mounted to the WPT at a minimum mounting height of 5 ft measured from the bottom of the sign to the road surface and in a manner that allows for easy removal when necessary for maintenance. The minimum mounting height shall be increased to 7 ft if the trailer is placed in business, commercial, or residential areas.
104.24 Workers Present Trailer (Wpt)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS with a lockable door with hasp/lock setup installed in a manner to maximize its effectiveness in stopping unauthorized access to the beacon controls. Other physical locking devices may be approved by the Engineer.
104.24 Workers Present Trailer (Wpt)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.24 Workers Present Trailer (Wpt)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.24.03 Construction
Furnish, install and test the WPT on the project site 24 hours in advance of actual use to ensure that each unit is functioning properly. Place the WPT unit as shown in the Contract Documents or as directed and aim WPT at approaching traffic to ensure sign panel and flashing beacons are visible and legible for a distance of 900 ft from any point along the travel approach roadway. Ensure the WPT is level and that the sign face is not obscured by highway alignment or glare from either sunlight or vehicle headlights. Install temporary concrete traffic barrier or drums around the WPT according to the Book of Standards and the Contract Documents. Activate the WPT when workers are present in the work zone. Deactivate the WPT when workers are not present. Ensure that the WPT is operational for duration while workers are present in the work zone.
104.24 Workers Present Trailer (Wpt)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS The WPT shall be able to withstand wind of 80 mph.
104.24.04 Measurement and Payment
104.24.04 01 Workers Present Trailer will be measured and paid for at the Contract price per unit
day for each Workers Present Trailer unit. A unit day will consist of any approved usage within a work shift, regardless of start time or whether the shift runs into another calendar day. Each Workers Present Trailer will be paid for only once per unit day, regardless of how many times it is relocated. When a Workers Present Trailer is used for part of a day, it will be measured and paid for as a unit day. When operations require continuous 24 hour use of a Workers Present Trailer, the unit day will be measured as 24 hour periods from start to finish. The payment will be full compensation for the Workers Present Trailer and for all material, labor, equipment, tools and incidentals necessary to furnish, install, operate, and maintain the Workers Present Trailer at the site as required and at any relocated site as specified or as directed.
104.24.04 02 Workers Present Trailer related sign R2-6(5) will not be measured but the cost will
be incidental to the Contract unit price for Workers Present Trailer.
104.24.04 03 The signal heads/beacons will not be measured but the cost will be incidental to the
Contract unit price for the Workers Present Trailer.
104.26 Removable Rumble Strips
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.26 — REMOVABLE RUMBLE STRIPS
104.26.01 Description
Furnish, install, maintain, and remove removable rumble strips.
104.26.02 Materials
Removable Rumble Strips QPL Rumble strips shall be white in color, 4 in. wide, and 0.250 in. thick.
104.26.03 Construction
104.26.03 01 Quality Assurance/Quality Control. Perform quality control testing using
technicians certified by the Administration.
104.26.03 02 Warranty Period. Maintain the rumble strips and repair defects for a period of
180 days from the date of application. Replace as necessary within this period as directed at no additional cost to the Administration. Refer to GP-5.11. At least 90 percent of the total number of rumble strips in any lane shall be free from signs of failure due to blistering, excessive cracking, discoloration, smearing or spreading under heat, chipping, spalling, or poor adhesion to the pavement. Replace rumble strips showing wear or a thickness less than 0.20 in.
104.26.03 03 Application and Removal. The pavement surfaces shall be completely dry and
free of oil, grease, sand, dirt, dust, loose aggregate, soil, salt, and other contaminants. Apply the rumble strips in accordance with the manufacturer’s recommendations and the Contract Documents. Place perpendicular to the flow of traffic and located as specified. Space the strips between 4 ft and 10 ft on center, with a pattern of at least 10 but not more than 12 strips per set. Decrease the spacing within each set as motorists approach the work zone. The spacing between the sets shall be as specified. Do not place on sharp horizontal or vertical curves. Use in conjunction with other traffic control devices or visual cues that will assist drivers in identifying the appropriate action to take.
104.26 Removable Rumble Strips
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS For installations where the roadway is wider than one lane in each direction, install in one-lane width segments utilizing butt joints. Do not overlap. Continue at least 1 ft onto each shoulder. Do not install over pavement seams, joints, or deteriorating markings and substrates. When no longer required, remove rumble strips and residue. Return the pavement surface to its original condition.
104.26.04 Measurement and Payment
Removable Rumble Strips will be measured and paid for at the Contract unit price per linear foot. The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work. Removal and replacement required beyond the 180 day period will be measured and paid for at the Contract unit price for the Removable Rumble Strip item. Replacements made during the service life due to plowing will be paid for at the Contract unit price for the Removable Rumble Strip item.
104.26.04 01 Removal, Replacement, and Corrective Actions. Any additional cost, including
maintenance of traffic, for the removal of rumble strips that are installed inaccurately or incorrectly shall be at no additional cost to the Administration. In addition, the current road user fee will be applied when traffic disruption occurs during corrective actions.
104.27 Temporary Portable Rumble Strips (Tprs)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.27 — TEMPORARY PORTABLE RUMBLE STRIPS (TPRS)
104.27.01 Description
Furnish, install, maintain, adjust, and remove temporary portable rumble strips (TPRS). Work shall consist of preparing the road surface, installing, maintaining, adjusting, and removing temporary rumble strips in construction work zones at the locations shown in the Contract Documents or as directed.
104.27.02 Materials
Temporary Portable Removable Rumble Strips QPL
104.27.02 01 TPRS shall consist of thermoset cast urethane, engineered polymers, or rubber
materials. TPRS shall not curl or deform across the width of the strip, maintaining its rigidity. The face of the strips shall be a non-slip textured surface. Each strip shall be capable of being installed without adhesives or bolts.
104.27.02 02 TPRS shall consist of a single segment or be comprised of interlocking sections. The
color of the TPRS shall be white, orange, or black. Each TPRS segment shall be 3/4 in. to 1 in. thick, 10 ft to 12 ft long, and 8 in. to 15 in. wide. TPRS shall be deemed safe by the manufacturer for use by motorcycles and able to withstand tractor trailer traffic with minimal movement.
104.27.03 Construction
104.27.03 01 Installation, Monitoring, and Removal. Select the appropriate TPRS from the
QPL for the posted speed limit of the roadway. Provide a copy of the manufacturer’s installation guidelines to the Engineer. Install and remove according to the manufacturer’s recommendations and the Contract Documents. Verify placement with the Engineer prior to installation. Each segment shall be uniform in color throughout the work zone.
104.27.03 02 Installation. Do not use TPRS on loose gravel, bleeding asphalt, heavily rutted
pavements, milled or unpaved surfaces. Do not place TPRS through pedestrian crossings and railroad crossings. Do not use TPRS in rain, snow, or icy weather conditions. Do not extend TPRS onto the shoulder without the approval of the Engineer. Do not place TPRS on sharp horizontal or vertical curves; instead, install TPRS in advance of the curve so they are visible to approaching traffic.
104.27 Temporary Portable Rumble Strips (Tprs)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Clean the roadway to remove dust, sand, and other debris. Arrange the strips in an array consisting of three complete strips per lane spaced and configured according to the manufacturer’s recommendations and the Book of Standards. The length of each strip, whether comprised of one segment or interlocking segments, should be within 12 in. of the full lane width. Center TPRS in the lane.
104.27.03 03 Monitoring. Monitor, maintain alignment, and repair the TPRS if needed. Ensure
that the rumble strips are perpendicular to the lane and that the correct spacing between rumble strips is maintained at all times. Correct the positioning of the rumble strips if any strip moves by more than 1 ft in any direction during the work period. If any strip comes out of alignment, clean the strip on both sides, and reset the strip onto a clean roadway surface.
104.27.03 04 Removal. Remove TPRS from the roadway when lane restrictions are removed or
as directed. After removing the TPRS, clean and restore pavement to normal condition.
104.27.04 Measurement and Payment
The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work.
104.27.04 01 The initial installation of Temporary Portable Rumble Strips will be measured and
paid for at the Contract unit price per each array per unit day. A unit day will consist of any approved usage within a 24 hour calendar day period. When a temporary portable rumble strip array is used for part of a day, it will be measured and paid for as a unit day. An array consists of three complete temporary portable rumble strips spanning a single lane. Payment will be full compensation for cleaning the roadway surface, installing the rumble strip, and maintaining the strip through the duration of each day’s use, including cleaning and resetting of the strip if it comes out of alignment.
104.27.04 02 Remove and Relocate Temporary Portable Rumble Strips will be paid for at the
Contract unit price per each array. The payment includes removal of the temporary portable rumble strip array, relocating the array to a new location, cleaning the roadway surface, installing the rumble strips, and maintaining the strips through the duration of each day’s use, including cleaning and resetting the strip if it comes out of alignment.
104.27.04 03 Removal of the temporary portable rumble strips at the end of each workday and
final removal will be incidental to the item Temporary Portable Rumble Strips, including cleaning and restoring the pavement to normal conditions.
104.28 Speed Display Trailer (Sdt)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.28 — SPEED DISPLAY TRAILER (SDT)
104.28.01 Description
Furnish, install, operate, maintain, relocate, and remove a portable, self-contained, trailer mounted, speed display trailer (SDT) with static speed limit sign. The SDT includes a static speed limit sign and a speed feedback sign (dynamic radar speed display). The SDT shall be compliant with the Maryland Manual on Uniform Traffic Control Devices (MdMUTCD) and Maryland Standard Sign Book.
104.28.02 Materials
Speed Display Trailer QPL Reflectorization 950.03 Sign Material 950.08 Each SDT shall include the trailer, structural support system, sign panel assembly, lift mechanism, power supplies, trailer mounted controller, non-invasive speed detection device, and ancillary equipment. All materials for the SDT shall be like new, corrosion resistant, and unaffected by water spray, salt, oil, gasoline, and all other contaminants in the quantities typically found along the edge of a traveled roadway. Construction, materials, and operation shall be in accordance with NFPA, UL, and NEC. The SDT trailer shall be painted orange and shall comply with Maryland Motor Vehicle Law.
104.28.02 01 Equipment.
104.28 Speed Display Trailer (Sdt)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Book. Reflective sheeting shall be as specified in 950.03. The sign shall be rectangular in shape.
104.28 Speed Display Trailer (Sdt)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.28 Speed Display Trailer (Sdt)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.28.03 Construction
Furnish, install and test the SDT on the project site 24 hours in advance of actual use to ensure that the unit is functioning properly. Coordinate location with Administration and its Automated Speed Enforcement Contractor for Automated Speed Enforcement. Place the SDT unit as shown in the Contract Documents or as directed and aim SDT at approaching traffic to ensure sign panel is visible for a minimum distance of 600 ft for nighttime conditions and 800 ft for normal daylight conditions from any point along the travel approach roadway. Ensure the SDT is level and that the sign face is not obscured by highway alignment or glare from vehicle headlights. Install temporary concrete traffic barrier or drums around the SDT according to the Book of Standards and the Contract Documents. The SDT shall be able to withstand wind of 80 mph. When deployed, the mounting height to the bottom of the speed limit sign shall be a minimum of 7 ft from near edge of traveled roadway in accordance with the MdMUTCD. The mounting height to the bottom of the SFS shall be high enough to ensure traffic barrier, devices, or other obstructions will not block visibility of the SFS. The Contractor is responsible for continuous operation of the SDT including any maintenance, repair, troubleshooting, or replacement.
104.28.04 Measurement and Payment
104.28.04 01 Speed Display Trailer will be measured and paid for at the Contract price per unit
day for each Speed Display Trailer unit. Each Speed Display Trailer will be paid for only once per unit day, regardless of how many times it is relocated. When a Speed Display Trailer is used for part of a day, it will be measured and paid for as a unit day. When operations require continuous 24 hour use of a Speed Display Trailer, the unit day will be measured as 24 hour periods from start to finish. The payment will be full compensation for the Speed Display Trailer and for all material, labor, equipment, tools, and incidentals necessary to furnish, install, operate, and maintain the Speed Display Trailer as specified or as directed.
104.28.04 02 Signs attached to the Speed Display Trailer will not be measured but the cost will be
incidental to the Contract unit price for the pertinent Speed Display Trailer item.
104.28 Speed Display Trailer (Sdt)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.28.04 03 Drums for Maintenance of Traffic. Drums will be measured and paid for as specified
in 104.12.
104.28.04 04 Temporary Concrete Traffic Barrier and Reset Temporary Concrete Traffic Barrier
shall be measured and paid for as specified in 104.04.04. Reflective Barrier Markers and Vertical Panels shall be measured and paid for as specified in 104.04.04.
104.28.04 05 Temporary Traffic Barrier End Treatments, Remove and Reset Temporary Traffic
Barrier End Treatments and Repairing Temporary Traffic Barrier End Treatments will be measured and paid for as specified in 104.09.04
104.29 Truck Mounted Variable Message Sign (Tvms)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.29 — TRUCK MOUNTED VARIABLE MESSAGE SIGN (TVMS)
104.29.01 Description
Furnish, install and relocate a portable, self-contained, truck mounted, variable message sign.
104.29.02 Materials
Each unit shall contain the work vehicle structural support system, sign panel assembly, lift mechanism, power supplies, sign mounted controller, and ancillary equipment. All materials for TVMS shall be like new, corrosion resistant, and unaffected by water spray, salt, oil, gasoline, and all other contaminants in the quantities normally found along the edge of the traveled roadway. The TVMS construction, materials, and operation shall meet NFPA, UL, and NEC. Ensure that sign messages are visible and legible for a distance of 900 ft from any point along the traveled approach roadway at all times. The TVMS shall not block the driver’s rear view vision when either in the transport or the deployed position.
104.29.03 Construction
104.29.03 01 Equipment.
Truck. The work vehicle size and the method of attachment shall be as specified in the manufacturer's specifications. All vehicles shall be in accordance with Maryland Motor Vehicle Law. Structural Support. The structural support framework shall allow the system to be assembled into a unit and be mounted on the truck and shall provide the support mechanism between the sign panel assembly, the power supply, and the controller. The framework shall provide sufficient support to prevent damage to any TVMS components when the sign is in the down and locked position during normal highway travel. The sign panel shall be mounted as a permanent fixture of the truck and provide a minimum height of 7 ft from the bottom of the sign to the surface of the roadway when in its operating position. Affixing a trailer mounted unit to a truck is prohibited.
104.29 Truck Mounted Variable Message Sign (Tvms)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS The deployed structure shall supply adequate support to allow complete sign operation including raising and lowering of the sign panel during sustained wind speeds of 85 mph. The display windows shall be made of impact-resistant clear Lexan or as approved. Sign Panel. Sign panel dimensions shall not exceed 92 in. wide by 54 in. high unless approved. The TVMS shall be capable of displaying three lines of text with the following requirements:
104.29 Truck Mounted Variable Message Sign (Tvms)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.29 Truck Mounted Variable Message Sign (Tvms)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.29.03 02 Operation. Set up and operate the TVMS 24 hours in advance of actual use to
ensure that each unit is functioning properly and approved. Variable Message Sign Mode. Use the TVMS in variable message sign mode on roadways where the posted speed limit is less than or equal to 40 mph. The TVMS is intended for mobile operations. If used for stationary construction or maintenance operations, do not leave the TVMS in place for more than eight consecutive hours. Arrow Panel Mode. The TVMS may be used in lieu of a Type C arrow panel on any roadway as long as the TVMS is capable of displaying a left arrow, right arrow, double arrow, and a four- corner caution mode and as specified in 104.07.03. Lights with a preflash option of white strobe or pulsed lighting shall not be displayed. Use the TVMS only as a supplement to other required traffic control devices. When closing a through travel lane on a multilane roadway, use the “Arrow” mode only. Only one TVMS in the “Arrow” mode shall be used for each stationary lane closure. Moving work operations may utilize one or more TVMS for a single lane closure.
104.29 Truck Mounted Variable Message Sign (Tvms)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS adequate recognition distance is available. The vehicle carrying the TVMS shall be equipped with signing and lighting as required by the standard TCPs.
104.29.04 Measurement and Payment
Truck Mounted Variable Message Sign will be measured and paid for at the Contract price per unit day. A unit day will consist of any approved usage within a work shift, regardless of start time or whether the shift runs into another calendar day. Each truck mounted variable message sign will be paid for only once per unit day, regardless of how many times it may be relocated. When a truck mounted variable message sign is used for part of a day, it will be measured and paid for as a unit day. When operations require continuous 24 hour use of a truck mounted variable message sign, the unit day will be measured as 24 hour periods from start to finish. The payment will be full compensation for the vehicle, setup and maintenance of computer programs, changing messages, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.
104.30 Portable Traffic Signal (Pts)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.30 — PORTABLE TRAFFIC SIGNAL (PTS)
104.30.01 Description
Furnish, install, and maintain a portable, self-contained, trailer mounted traffic signal for maintenance of traffic operations as specified in the Contract Documents or as directed by the Engineer.
104.30.02 Materials
Portable Traffic Signal (PTS) As Approved by Office of Traffic and Safety
104.30.03 Construction
Place PTS trailers in the closed lane during alternating one-lane, two-way traffic operations, without intruding into the travel lane, or as directed by the Engineer. The Contractor is responsible for all setup procedures necessary for the PTS including setting up the trailers, setting up and testing the remote monitoring system notification, aiming signal heads, interconnecting the signal controllers, aiming, and adjusting vehicle detection units, and installing the timing provided by the Office of Traffic & Safety.
104.30.03 01 Equipment.
Each PTS shall be a trailer mounted unit. A PTS system shall consist of two or more trailers. Each unit shall be self-contained battery powered with solar assist, consist of two signal heads per trailer, and a solid state signal controller. One signal head should be mounted on an overhead mast arm capable of extending over the travel lane. The other signal head shall be mounted on a vertical upright. The PTS system shall have non-intrusive vehicle detectors and each PTS must be interconnected to each other at all times with a twisted pair shielded cable or wireless radio link with sufficient range, as specified in the Contract Documents or as directed. Trailer. The trailer shall conform to Maryland Motor Vehicle Law governing trailers. Support Structure. The PTS trailer shall be capable of accommodating a vertical upright and a horizontal mast arm. The trailer and all mounted equipment shall be structurally adequate for unlimited, normal operation in wind velocities typically encountered on the roadway (gusts of 80 MPH). No additional ballast shall be used to achieve the structural stability required for normal operation. Additional ballast includes but is not limited to, sandbags, concrete/cement blocks and
104.30 Portable Traffic Signal (Pts)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS steel, cast, or iron weights (secured or unsecured). PTS trailers shall be manufactured to accommodate the option of transporting two signal trailers with one vehicle. Each signal trailer shall be equipped with four stabilizing/leveling jacks, one on each corner of the trailer. The PTS trailer shall have adequate structural integrity to facilitate lifting and placing the PTS trailer as required. Lift Mechanism. The PTS shall contain a lift mechanism that is electric or electrically-assisted hydraulic, as well as a manual mechanism capable of raising and lowering the mast arm. The mast arm shall extend a minimum of 9 ft from the side of the trailer. Signal Heads/Display Requirements. The PTS shall meet the physical display and operational requirements of conventional traffic signals according to Part IV of the MdMUTCD. Signal Heads shall be cast aluminum and have three, 12 in. LED indications, conforming to ITE Specifications for “Vehicle Traffic Control Signal Heads” and NEMA Standards TS1 and TS2. Signal heads shall be equipped with visors which extend beyond the signal head a minimum of 10 in. All signal housings shall have a black face and yellow housing. The signal heads shall have the ability to accommodate back plates and rotate horizontally 180 F. The PTS shall have a reversible signal head mounting feature which will allow two trailers to be placed in the same lane of traffic. Both signal heads shall be able to be rotated and locked into position to provide the optimum visibility to motorists. The overhead signal shall have a minimum clearance height of 17 ft and a maximum clearance height of 19 ft, measured from the bottom of the green indication to the road surface. The lower signal head shall be mounted to a vertical upright at a minimum height of 8 ft measured from the bottom of the green indication to the road surface. Power Requirements. Each PTS Trailer shall be equipped with batteries sufficient to operate the signal for a minimum of 21 days at 72 F without charging. The charging system shall include 390 watts (minimum) of solar collection capability and an onboard battery charger capable of being used with a 110 volt power source. The system shall also include an onboard monitoring system capable of regulating and providing a visual display of the battery voltage and solar input. Operational Requirements. Each PTS shall be equipped with an operating system having the following capabilities:
104.30 Portable Traffic Signal (Pts)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.30 Portable Traffic Signal (Pts)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Monitoring System Requirement. Furnish and install PTS monitoring system capable of reporting signal location, battery voltage and system default. The monitoring system shall have the ability to communicate system default via text or email to responsible individuals. As specified in GP-2.04 verify available communications at the site, e.g., cellular or satellite, and select an appropriate PTS monitoring system that works with that communication method. Coordinate the installation of monitoring system with the ADE-T to develop an acceptable plan for monitoring signal operations and reporting on system default. Actuation Requirements. The PTS systems shall be capable of utilizing non-invasive detectors for traffic actuation. Acceptable non-invasive detectors include microwave motion sensors and video detection cameras. Acceptable PTS systems shall have the capability of being operated with both a motion and true presence actuation system. Communication Requirements. The PTS systems shall have the capability of being operated using hardwired or wireless communication. Field conditions will determine the method used for interconnection of the PTS system. The communication cable shall be deployed in a manner that will not intrude in the direct work area of the project or obstruct vehicular and pedestrian traffic. If a radio link communication option is utilized, a clear line of sight must be maintained between PTS units. The radio system shall conform to the applicable Federal Communication Commission requirements and all applicable state and local requirements. Should there be a failure in the communication link between the two signals, both signals shall be display solid red indications. Default Requirements. PTS systems shall have the capability of reverting to a solid red, red flash, or yellow flash mode upon system default. The default setting shall be solid red unless otherwise stated in the project specifications or as directed by the Engineer. Upon default the PTS system shall immediately contact a minimum of three responsible individuals via the remote monitoring system described in the Operational Requirement section. The PTS system repairs shall be the responsibility of the contactor and rendered in a manner that will return to PTS to full operation condition in the most expeditious manner. Field Operations. Set up, program, relocate, and maintain the PTS as per the Contract Documents or as directed by the Engineer, as recommended by the PTS manufacturer. Notify the Assistant District Engineer Traffic and the Office of Traffic and Safety at least three weeks prior to starting work. There will be no programming or timing changes to the PTS without written approval from the Office of Traffic and Safety. The contractor shall adjust or reconfigure the PTS operation only as directed by the Engineer, with approval from the Office of Traffic and Safety and the Assistant District Engineer Traffic. Operate the PTS as noted on the Maintenance of Traffic signalization plans, when available. Provide SHA with the name and telephone number of an emergency contact person to maintain and operate or repair the signals. Make provisions to have certified flaggers who have completed the SHA approved flagger training course and make provisions to have appropriate signing in place to maintain traffic at the PTS location in case of a PTS failure. Notify the Engineer, the Statewide
104.30 Portable Traffic Signal (Pts)
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Operations Center (SOC), and the ADE-T in the event of a failure. Maintain daily log at the signal site and record equipment malfunction.
104.30.04 Measurement and Payment
The Portable Traffic Signal will be measured and paid for at the Contract price per unit day. A unit day will consist of any approved usage within a normal work shift, regardless of start time or whether the shift runs into another calendar day. Each portable traffic signal will be paid for only once per unit day. When a portable traffic signal is used for part of a day, it will be measured and paid for as a unit day. When operations require continuous 24 hour use of a portable traffic signal, the unit day will be measured as 24 hour periods from start to finish. The payment will be full compensation for the provision, installation, operation, interconnection, monitoring system, maintenance, reconfiguration, adjustments, flaggers, signing, repair technicians, relocation as required by the Traffic Control Plan or as directed by the Engineer, and for all materials, labor, equipment, tools, training by the portable traffic signal manufacturer, and incidentals necessary to complete the work. Where other Contract pay items for Maintenance of Traffic are specified in the Contract Documents, measurement and payment shall conform to the pertinent items.
104.31 Accessible Pedestrian Maintenance of Traffic
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.31 — ACCESSIBLE PEDESTRIAN
104.31.01 Description
Provide and maintain an accessible pedestrian route, to the “maximum extent feasible”, throughout the project’s limits. When an existing pedestrian access route within the public right of way is blocked by construction, alteration, or maintenance activity, an alternate accessible pedestrian route shall be provided. The phrase, “maximum extent feasible”, applies in areas where the nature of an existing facility or site conditions makes it virtually impossible to comply fully with applicable accessibility standards through a planned alteration. In these circumstances, the alternate accessible pedestrian route shall provide the maximum physical accessibility that is feasible, or a design waiver must be approved by SHA’s Office of Highway Development.
104.31.02 Materials
Not applicable.
104.31.03 Construction
Consider the following items when addressing accessible pedestrian maintenance of traffic:
104.31 Accessible Pedestrian Maintenance of Traffic
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.31.04 Measurement and Payment
Unless otherwise specified, Accessible Pedestrian Maintenance of Traffic will not be measured but the cost will be incidental to the Lump Sum item for Maintenance of Traffic. The payment will be full compensation for all materials, labor, equipment, tools, and incidentals necessary to complete the work.
104.32 Static Automated Speed Enforcement
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.32 — STATIC AUTOMATED SPEED ENFORCEMENT
104.32.01 Description
Coordinate with the Administration and its Automated Speed Enforcement Contractor for Automated Speed Enforcement (ASE) in the work zone. Provide work zone signage, workers present trailer(s), speed display trailer(s), and protection devices to accommodate ASE in the work zone. Contact the Office of Traffic and Safety Traffic Development and Support Division (OOTS TDSD) ASE program representative (410-787-5860) at least two weeks prior to fabricating and installing ASE signs to determine exact locations for the ASE unit(s), ASE signs, workers present trailer(s), and speed display trailer(s).
104.32.02 Materials
Temporary Concrete Traffic Barrier (TCB) for Maintenance of Traffic 104.04.02 Temporary Traffic Signs (TTS) 104.08.02 Temporary Traffic Barrier End Treatments 104.09.02 Temporary Crash Cushion Sand Filled Plastic Barrels (SFPB) 104.10.02 Drums for Maintenance of Traffic 104.12.02 Cones for Maintenance of Traffic 104.14.02 Protection Vehicle (PV) Section 104.23 Speed Display Trailer (SDT) 104.28.02 Aggregate for Maintenance of Traffic 105.02 Reflectorization 950.03 Workers Present Trailer (WPT) 104.24.02
104.32.03 Construction
104.32.03 01 General. Refer to Standard No. MD 104.06-26A. Static Automated Speed
Enforcement (ASE) will be used in the work zone to enhance safety for the workers and traveling public. The Administration will provide a mobile ASE system, including speed enforcement equipment, ASE unit(s), and labor for ASE system operation. The Contractor will provide (furnish, install, relocate and remove) all of the applicable ASE signing, the workers present trailer(s), the speed display trailer(s), and protection devices as required.
104.32 Static Automated Speed Enforcement
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Coordinate and cooperate with the Project Engineer and the ASE program representative to implement the ASE system on this project throughout construction. The ASE program representative is located in the Office of Traffic and Safety, Traffic Development and Support Division. Obtain approval from the ASE program representative for the ASE unit location(s), ASE sign locations and sizes, workers present trailer location(s), and speed display trailer location(s). At least two weeks prior to the start of the project, arrange a field meeting with the Project Engineer and the ASE program representative to verify the sign types, sizes and locations. At this meeting, jointly identify locations for the ASE unit(s), workers present trailer(s), and speed display trailer(s) with the ASE program representative. Contact the Project Engineer and the ASE program representative a minimum of two weeks prior to all phase changes or construction activities that require relocation of the ASE unit(s). When activities occur that require relocation of the ASE unit(s), arrange a field meeting with the Project Engineer and the ASE program representative to verify the suitability of existing and/or identify new location(s) for the ASE unit(s), advance warning signs, workers present trailer(s), speed display trailer(s), and all required protection devices. Where feasible, provide bathroom facilities in a location that can be used by construction personnel and the ASE unit operators. Make the bathroom facilities available and accessible to the ASE unit operators twenty-four hours a day, seven days a week. Provide the bathroom facilities at a location within a reasonable walking distance of the ASE unit deployment location and where the ASE unit operator does not have to cross travel lanes to access the facilities. Inform the Administration within 30 minutes of starting and ending work the exact start time(s) and exact end time(s) when workers are present in the work zone.
104.32.03 02 Temporary Traffic Signs for ASE. Refer to 104.08.03. Provide automated speed
enforcement advanced warning signs on each approach to the work zone, including ramps. These signs shall consist of ASE advance notice signs and ASE speed limit signs, as shown on the plans and/or as directed by the ASE program representative. Additional ASE signs may be requested by the ASE program representative based on project needs. Prior to sign acquisition, coordinate with the Project Engineer and the ASE program representative a minimum of two weeks in advance to verify the sign types, colors of sign background and legend, materials, sizes, and locations of signs. Relocate and/or install new ASE signs as needed throughout construction.
104.32.03 03 Aggregate for Maintenance of Traffic. Refer to 105.03. Where the ASE unit
deployment location is not on hard surface, construct a level stone entrance and pad adjacent to the roadway for the ASE enforcement unit. Provide a safe means for the ASE unit operators to enter/exit the enforcement area.
104.32.04 04 Temporary Traffic Barrier. Refer to 104.04.03. Provide protection for the ASE
unit, either behind temporary concrete barrier or existing W-beam.
104.32.03 05 Speed Display Trailer. Refer to 104.28.03. Furnish, install, maintain, relocate and
remove a speed display trailer(s) as shown on the plans and/or as directed by the ASE program
104.32 Static Automated Speed Enforcement
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS representative. Construct a level area adjacent to the shoulder for placement of the speed display trailer(s) as needed. Periodically inspect the speed display trailer(s) and make adjustments as needed to ensure proper function. Relocate and/or install new speed display trailer(s) as needed throughout construction.
104.32.03 06 Maintenance of Traffic. Conduct maintenance of traffic as specified in 104.02.03
where required for installation, relocation, or removal of temporary traffic control devices for ASE activities.
104.32.03 07 Temporary Traffic Barrier End Treatments. Refer to 104.09.03.
104.32.03 08 Temporary Crash Cushion Sand Filled Plastic Barrels. Refer to 104.10.03.
104.32.03 09 Drums for Maintenance of Traffic. Refer to 104.12.03.
104.32.03 10 Cones for Maintenance of Traffic. Refer to 104.14.03.
104.32.03 11 Workers Present Trailer. Refer to 104.24.03.
Provide a workers present trailer(s) (furnish, install, maintain, relocate and remove) as shown on the plans and/or as directed by the ASE program representative. Construct a level area adjacent to the shoulder for placement of the workers present trailer(s) as needed. Periodically inspect the workers present trailer(s) and make adjustments as needed to ensure proper function. Relocate and/or install additional workers present trailer(s) as needed throughout construction. Activate the flashing lights on the workers present trailer(s) when workers are present in the work zone. Deactivate the flashing lights on the workers present trailer(s) when workers are not present in the work zone.
104.32.04 Measurement and Payment
The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work including relocating, turning, completely covering and uncovering or removing and resetting, maintaining in like new condition, and cleaning existing and temporary traffic signs and other traffic control devices related to the operation of the Automated Speed Enforcement. The pay item will include the following items unless otherwise specified.
104.32.04 01 Maintenance of Traffic for Automated Speed Enforcement will not be measured but
will be paid for at the Contract lump sum price. The payment will be full compensation for relocating, turning, completely covering and uncovering or removing and resetting, maintain in like new condition, and cleaning existing and temporary traffic signs and other traffic control devices related to the operation of the Automated Speed Enforcement. Included is the treatment of any other traffic control device not included in these Specifications but necessary for the fulfillment of the Contract requirements, and for all material, labor, equipment, tools and incidentals necessary to complete the work. Payment of the Contract lump sum price will be
104.32 Static Automated Speed Enforcement
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS prorated and paid in equal amounts on each monthly estimate. The number of months used for prorating will be the number estimated to complete the work.
104.32.04 02 Temporary Concrete Traffic Barrier and Reset Temporary Concrete Traffic Barrier
shall be measured and paid for as specified in 104.04.04. Reflective Barrier Markers and Vertical Panels shall be measured and paid for as specified in 104.04.04.
104.32.04 03 Temporary Traffic Signs will be measured and paid for as specified in 104.08.04.
When ASE advance warning and speed limit signs are furnished by the Administration or by the Administration’s ASE Contractor, the Contractor will be responsible for set-up, take down and relocation of these signs. Signs shall be placed per the direction of the ASE program representative and in accordance with the requirements of Section 104.08. Signs furnished by the Administration or by the Administration’s ASE Contractor and provided to the Contractor will be measured and paid for at the Contract unit price per square foot as specified in 104.08.04. The payment will be full compensation for furnishing the supports, installation, relocation, maintenance, cleaning, removal, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.
104.32.04 04 Temporary Traffic Barrier End Treatments, Remove and Reset Temporary Traffic
Barrier End Treatments and Repairing Temporary Traffic Barrier End Treatments will be measured and paid for as specified in 104.09.04.
104.32.04 05 Temporary Crash Cushion Sand Filled Plastic Barrels shall be measured and paid for
as specified in 104.10.04.
104.32.04 06 Drums for Maintenance of Traffic shall be measured and paid for as specified in
104.12 04.
104.32.04 07 Cones for Maintenance of Traffic shall be measured and paid for as specified in
104.14 04.
104.32.04 08 If requested, the Protection Vehicle shall be measured and paid for as specified in
104.23 04.
104.32.04 09 Speed Display Trailer will be measured and paid for as specified in 104.28.04.
104.32.04 10 Supply of materials for, installation of, and removal of stone construction entrance(s)
and pad(s) for ASE units will be measured and paid for as specified in 105.04.
104.32.04 11 Workers Present Trailer will be measured and paid for as specified in 104.24.
104.33 Flexible Automated Speed Enforcement
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 100 PRELIMINARY SECTION 104.33 — FLEXIBLE AUTOMATED SPEED ENFORCEMENT
104.33.01 Description
Flexible Automated Speed Enforcement (ASE) deployments are used when work activity is 60 days or less and may include different ASE deployment locations for each work shift. Projects using flexible ASE generally require set up and removal of maintenance of traffic items at the start and end of each shift. Example projects include resurfacing, restoration and rehabilitation projects, maintenance projects, etc. Coordinate with the Administration and its Automated Speed Enforcement Contractor for ASE in the work zone. Provide work zone signage, workers present trailer(s), speed display trailer(s), and protection devices to accommodate ASE in the work zone. Contact the Office of Traffic and Safety Traffic Development and Support Division (OOTS TDSD) ASE program representative (410-787- 5860) at least two weeks prior to fabricating and installing ASE signs to determine exact locations for the ASE unit(s), ASE signs, workers present trailer(s), and speed display trailer(s).
104.33.02 Materials
Temporary Traffic Signs (TTS) 104.08.02 Drums for Maintenance of Traffic 104.12.02 Protection Vehicle (PV) Section 104.23 Speed Display Trailer (SDT) 104.28.02 Reflectorization 950.03 Aggregate for Maintenance of Traffic 105.02 Workers Present Trailer (WPT) 104.24.02
104.33.03 Construction
104.33.03 01 General. Refer to Standard No. MD 104.06-26B. Flexible Automated Speed
Enforcement (ASE) will be used in the work zone to enhance safety for the workers and traveling public. The Administration will provide a mobile ASE system, including speed enforcement equipment, ASE unit(s), and labor for ASE system operation. The Contractor will provide, furnish, install, maintain, relocate, and remove all the applicable ASE signing, the workers present trailer(s), the speed display trailer(s), and protection devices including the protection vehicle(s) for ASE activities as required.
104.33 Flexible Automated Speed Enforcement
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Coordinate and cooperate with the Project Engineer and the ASE program representative to implement the ASE system on this project throughout construction. The ASE program representative is located in the Office of Traffic and Safety, Traffic Development and Support Division. Obtain approval from the ASE program representative for the ASE unit location(s), protection vehicle location(s), ASE sign locations and sizes, workers present trailer locations(s), and speed display trailer location(s). At least two weeks prior to the start of the project, arrange a field meeting with the Project Engineer and the ASE program representative to jointly identify locations for the ASE unit(s), the protection vehicle dedicated to ASE, the workers present trailer(s), and the speed display trailer(s). During the project, contact the Project Engineer and the ASE program representative a minimum of 48 hours prior to any changes not approved during the initial field meeting or due to unforeseen changes. Contact the Project Engineer and the ASE program representative a minimum of four hours before any work cancellations. Inform the Administration within 30 minutes of starting and ending work the exact start time(s) and exact end time(s) when workers are present in the work zone.
104.33.03 02 Maintenance of Traffic. Conduct maintenance of traffic as specified in 104.02.03
where required for installation, relocation, or removal of temporary traffic control devices for ASE activities.
104.33.03 03 Temporary Traffic Signs for ASE. Refer to 104.08.03. Provide automated speed
enforcement advanced warning signs on each approach to the work zone, including ramps. These signs shall consist of ASE advance notice signs and ASE speed limit signs, as shown on the plans and/or as directed by the ASE program representative. Additional ASE signs may be requested by the ASE program representative based on project needs. Prior to sign acquisition, coordinate with the Project Engineer and the ASE program representative a minimum of two weeks in advance to verify the sign types, colors of sign background and legend, materials, sizes, and locations of signs. Relocate and/or install new ASE signs as needed throughout construction.
104.33.03 04 Drums for Maintenance of Traffic. Refer to 104.12.03. When delineation of the
speed display trailer(s) or workers present trailer(s) is needed, provide 7 drums to form the shoulder taper to delineate the trailer(s) per MD 104.01-22. When the speed display trailer(s) or workers present trailer(s) is within the lane closure, additional delineation is not needed.
104.33.03 05 Protection Vehicle Dedicated to ASE Deployment. Refer to Section 104.23.
Provide a protection vehicle with a truck or trailer-truck mounted attenuator as specified in Section 104.23 dedicated to protecting each ASE unit. Coordinate placement of the protection vehicle with the ASE program representative. Position the protection vehicle prior to the arrival of the ASE operator. The protection vehicle must remain in place until the end of the automated speed enforcement and the ASE unit has left the enforcement location. Ensure that the appropriate roll ahead distance (per manufacturer’s recommendation) between the protection vehicle and the ASE unit is always maintained and access/egress for the ASE operator is provided.
104.33.03 06 Speed Display Trailer. Refer to 104.28.03. Furnish, install, maintain, relocate, and
104.33 Flexible Automated Speed Enforcement
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS remove a speed display trailer(s) as shown on the plans and/or as directed by the ASE program representative. Construct a level area adjacent to the shoulder for placement of the speed display trailer(s) as needed. Periodically inspect the speed display trailer(s) and adjust it as needed to ensure proper function.
104.33.03 07 Aggregate for Maintenance of Traffic. Refer to 105.03. Where the ASE unit
deployment location is not on hard surface, construct a level stone entrance and pad adjacent to the roadway for the ASE enforcement unit. Provide a safe means for the ASE unit operators to enter/exit the enforcement area.
104.33.03 08 Workers Present Trailer. Refer to 104.24.03. Provide a workers present trailer(s)
(furnish, install, maintain, relocate and remove) as shown on the plans and/or as directed by the ASE program representative. Construct a level area adjacent to the shoulder for placement of the workers present trailer(s) as needed. Periodically inspect the workers present trailer(s) and make adjustments as needed to ensure proper function. Relocate and/or install additional workers present trailer(s) as needed throughout construction. Activate the flashing lights on the workers present trailer(s) when workers are present in the work zone. Deactivate the flashing lights on the workers present trailer(s) when workers are not present in the work zone.
104.33.03 09 Temporary Traffic Barrier. Refer to 104.04.03. Provide protection for the ASE
unit, either behind a temporary concrete barrier or existing W-beam.
104.33.03 10 Temporary Traffic Barrier End Treatments. Refer to 104.09.03.
104.33.03 11 Temporary Crash Cushion Sand Filled Plastic Barrels. Refer to 104.10.03.
104.33.04 Measurement and Payment
If the Automated Speed Enforcement Representative has scheduled a deployment but the Automated Speed Enforcement unit does not show up at the scheduled deployment the Contractor will still get paid as specified in this section. The payment will be full compensation for all material, labor, equipment, tools, and incidentals necessary to complete the work including relocating, turning, completely covering and uncovering or removing and resetting, maintaining in like new condition, and cleaning existing and temporary traffic signs and other traffic control devices related to the operation of the Automated Speed Enforcement. The pay item will include the following items unless otherwise specified.
104.33.04 01 Temporary Traffic Signs for Automated Speed Enforcement. The signs will be
measured and paid for as specified in 104.08.04.
104.33.04 02 Drums for Maintenance of Traffic. Drums will be measured and paid for as specified
in 104.12.
104.33 Flexible Automated Speed Enforcement
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS
104.33.04 03 Protection Vehicles dedicated to Automated Speed Enforcement deployment. The
Contractor will be responsible for providing a dedicated protection vehicle for the protection of the Automated Speed Enforcement unit for the duration of the deployment shift. The protection vehicle shall be as specified in Section 104.23. Provide a licensed protection vehicle operator to drive and position the protection vehicle at the start of the deployment location and to remove the protection vehicle at the end of the shift. The protection vehicle operator does not need to remain in the vehicle for the duration of the deployment shift. The protection vehicle will be measured and paid per for per unit day. A unit day will consist of one shift of Automated Speed Enforcement deployment (not to exceed 9 hours). A deployment shift crossing midnight into the following calendar day will be paid for as one unit day (e.g., 9 PM to 5 AM counts as one unit day). The payment will be full compensation for the complete protection vehicle, including the truck mounted attenuator/trailer truck mounted attenuator and arrow panel, licensed work vehicle operator, relocating the protection vehicle, and for all material, labor, equipment, tools, and incidentals necessary to complete the work.
104.33.04 04 Speed Display Trailer. The Contractor will be responsible for the set-up, operation,
and removal/relocation of the speed display trailer(s) at the start and end of each deployment shift. The speed display trailer(s) will be measured and paid for as specified in Section 104.28.
104.33.04 05 Maintenance of Traffic. The Contractor will be responsible for providing
maintenance of traffic as specified in 104.02.03 where required for installation, relocation, or removal of temporary traffic control devices for Automated Speed Enforcement activities.
104.33.04 06 Supply of materials for installation of, and removal of pad(s) for Automated Speed
Enforcement units will be measured and paid for per 105.04.
104.33.04 07 Temporary Concrete Traffic Barrier and Reset Temporary Concrete Traffic Barrier
shall be measured and paid for as specified in 104.04.04. Reflective Barrier Markers and Vertical Panels shall be measured and paid for as specified in 104.04.04.
104.33.04 08 Temporary Traffic Barrier End Treatments, Remove and Reset Temporary Traffic
Barrier End Treatments and Repairing Temporary Traffic Barrier End Treatments will be measured and paid for as specified in 104.09.04
104.33.04 09 Temporary Crash Cushion Sand Filled Plastic Barrels shall be measured and paid for
as specified in 104.10.04.
104.33.04 10 Refusal of Payment. The Contractor will not be paid as specified in this section
under these circumstances:
104.33 Flexible Automated Speed Enforcement
2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS representative will communicate the cancellation to the Project Engineer who will notify the Contractor a minimum of 8 hours in advance.
104.33.04 11 Workers Present Trailer. The Contractor will be responsible for the set-up,
operation, and removal/relocation of the workers present trailer(s) at the start and end of each deployment shift. The Workers Present Trailer(s) will be measured and paid for as specified in