SECTION 652 - MAINTENANCE OF TRAFFIC 652.1 Description This work shall consist of furnishing, installing, maintaining and removing traffic control devices necessary to provide reasonable protection for motorists, pedestrians and construction workers in accordance with these Specifications, the applicable provisions of Section 105.4.5 – Maintenance of Existing Structuures. Traffic control devices include signs, signals, lighting devices, markings, barricades, channelizing, and hand signaling devices, traffic officers, and flaggers. 652.2 Materials All traffic control devices shall conform to the requirements of Part VI of the latest edition of the MUTCD, and MASH 16 guidelines. All signs shall be fabricated with high intensity fluorescent retroreflective sheeting conforming to ASTM D 4956 - Type VIII, or Type IX (prismatic). All barricades, drums, and vertical panel markers shall be fabricated with high intensity orange and white fluorescent retroreflective sheeting conforming ASTM D 4956 - Type VII, Type VIII, or Type IX (prismatic). Construction signs shall be fabricated from materials that are flat, free from defects, retroreflectorized, and of sufficient strength to withstand deflections using a wind speed of 80 miles/hr. All barricades, cones, drums, and construction signs may be constructed from new or recycled plastic. 6-148 652.2.2 Signs Only signs with symbol messages conforming to the design of the Manual of Uniform Traffic Control Devices shall be used unless the Resident approves the substitution of word messages. 652.2.3 Flashing Arrow Boardss Flashing Arrows must be of a type that has been submitted to AASHTO’s National Transportation Product Evaluation Program (NTPEP) for evaluation. Flashing Arrow Boards units shall meet requirements of the current Manual on Uniform Traffic Control Devices (MUTCD) for Type “C” as described in Section 6F.56 - Temporary Traffic Control Devices. A Flashing Arrow Board shall have matrix of a minimum of 15 low-glare, sealed beam, Par 46 elements capable of either flashing or sequential displays as well as the various operating modes as described in the MUTCD, Chapter 6-F. If a flashing Arrow Board consisting of a bulb matrix is used, each element should be recess-mounted or equipped with an upper hood of not less than 180 degrees. The color presented by the elements shall be yellow. Flashing Arrow Boards elements shall be capable of at least a 50 percent dimming from full brilliance. Full brilliance should be used for daytime operation and the dimmed mode shall be used for nighttime operation. Flashing Arrow Boards shall be at least 96 inches x 48 inches and finished in non-reflective black. The Flashing Arrow Boards shall be interpretable for a distance not less than 1 mile. Operating modes shall include, flashing arrow, sequential arrow, sequential chevron, flashing double arrow, and flashing caution. In the three arrow signals, the second light from the arrow point shall not operate. The minimum element on-time shall be 50 percent for the flashing mode, with equal intervals of 25 percent for each sequential phase. The flashing rate shall be not less than 25 nor more than 40 flashes per minute. All on-board circuitry shall be solid state. Primary power source shall be 12 volt solar with a battery back-up to provide continuous operation when failure of the primary power source occurs, up to 30 days with fully charged batteries. Batteries must be capable of being charged from an onboard 110 volt AC power source and the unit shall be equipped with a cable for this purpose. Controller and battery compartments shall be enclosed in lockable, weather-tight boxes. The Flashing Arrow Boards shall be mounted on a pneumatic-tired trailer or other suitable support for hauling to various locations, as directed. The minimum mounting height of an arrow panel should be 7 feet from the roadway to the bottom of the Flashing Arrow Boards. The face of the trailer shall be delineated on a permanent basis by affixing retro- reflective material, known as conspicuity material, in a continuous line as seen by oncoming drivers. 6-149 A portable changeable message sign may be used to simulate an arrow panel display. 652.2.4 Other Devices Vertical panel markers shall be orange and white striped, 8 inches wide by 24 inches high. On the Interstate System, vertical panel markers shall be orange and white striped, 12 inches wide by 36 inches high. Cones shall be orange in color, at least 28 inches high, and retro-reflectorized. Retro- reflection shall be provided by a white band of retro-reflective sheeting conforming to Section 719.01, 6 inches wide, no more than 3 to 4 inches from the top of the cone, and a 4 inch wide white band at least 2 inches below the 6 inch band. Drums shall be of plastic or other yielding material, and shall be approximately 36 inches high and a minimum of 18 inches in diameter. There shall be at least two retro- reflectorized orange and at least two retro-reflectorized white stripes at least 4 inches wide on each drum. Metal drums shall not be used. Warning lights and battery operated flashing and steady burn lights shall conform to the requirements Section 712.23 - Flashing Lights. Flaggers shall use a STOP / SLOW hand held paddle as the primary and preferred hand signaling device. Flags shall only be limited to emergencies. STOP / SLOW paddles shall have high intensity prismatic retro reflective sheeting, have an octagonal shape on a rigid handle and shall be at least 18 inches wide with letters at least 6 inches high and shall be constructed from light semi-rigid material. The STOP (R1-1) face shall have white letters and a white border on a red background. The SLOW (W20-8) face shall have black letters and a black border on an orange background. STOP / SLOW paddles shall also incorporate either white or red flashing lights on the STOP face and white or yellow flashing lights on the SLOW face of the paddle and always be in use. Paddles must conform to any of the following patterns:
A.Two white or red lights (colors shall be all white or all red), one centered vertically above and one centered vertically below the STOP legend; and/or two white or yellow lights (colors shall be all white or all yellow), one centered vertically above and one centered vertically below the SLOW legend;
B.Two white or red lights (colors shall be all white or all red), one centered horizontally on each side of the STOP legend; and/or two white or yellow lights (colors shall be all white or all yellow), one centered horizontally on each side of the SLOW legend;
C.One white or red light centered below the STOP legend; and/or one white or yellow light centered below the SLOW legend; 6-150
D.A series of eight or more small all white or all red lights no larger than 1/4 inch in diameter along the outer edge of the paddle, arranged in an octagonal pattern at the eight corners of the border of the STOP face; and/or a series of eight or more small all white or all yellow lights no larger than 1/4 inch in diameter along the outer edge of the paddle, arranged in a diamond pattern along the border of the SLOW face; or
E.A series of white lights forming the shapes of the letters in the legend. Flashing light patterns shall be compliant with Section 6E.03 Hand Signaling Devices in the most current version of the Manual on Uniform Traffic Control Devices. All flashing light patterns on the STOP / SLOW paddle shall be visible from a minimum distance of 1000 feet. Type I barricades shall be 2 feet minimum, 8 feet maximum in length with an 8 inch wide rail mounted 3 feet minimum above the ground. Type II barricades shall be 2 feet in length with two 8 inch wide rails, and the top rail shall be mounted 3 feet minimum above the roadway. Type III barricades shall be 8 feet in length with three 8 inch wide rails, and the top rail shall be mounted 5 feet minimum above the roadway. The cross members of all barricades shall be of ½ or ⅝ inch thick plywood or other lightweight rigid material such as plastic, fiberglass or fiber wood as approved by the Resident. The predominant color for supports and other barricade components shall be white, except that unpainted galvanized metal or aluminum components may be used. 652.2.5 Portable Changeable Message Sign Trailer mounted Portable Changeable Message Signs (PCMS) must be of a type that has been submitted to AASHTO’s National Transportation Product Evaluation Program (NTPEP) for evaluation. The PCMS unit shall meet or exceed the current specifications of the Manual on Uniform Traffic Control Devices (MUTCD), 6F.55. The front face of the sign should be covered with a low-glare protective material. The color of the LED elements shall be amber on a black background. The PCMS should be visible from a distance of 0.5 mile day and night and have a minimum 15º viewing angle. Characters must be legible from a distance of at least 650 feet. The message panel should have adjustable display rates (minimum of 3 seconds per phase), so that the entire message can be read at least twice at the posted speed, the off-peak 85th-percentile speed prior to work starting, or the anticipated operating speed. Each message shall consist of either one or two phases. A phase shall consist of up to eight characters per line. The unit must be capable of displaying at least three lines of text with eight characters per line. Each character shall be 18 inches high. Each character module shall use at least a five wide and seven high pixel matrix. The text of the messages shall not scroll or travel horizontally or vertically across the face of the sign. Units shall automatically adjust their brightness under varying light conditions to maintain legibility. 6-151 The control system shall include a display screen upon which messages can be reviewed before being displayed on the message sign. The control system shall be capable of maintaining memory when power is unavailable. Message must be changeable with either a notebook computer or an on-board keypad. The controller shall have the capability to store a minimum of 200 user-defined and 200 pre-programmed messages. Controller and battery compartments shall be enclosed in lockable, weather-tight boxes. PCMS units shall have the capability of being made programmable by means of wireless communications. PCMS units shall also be fully capable of having an on-board radar system installed if required for a particular application. PCMS’ primary power source shall be solar with a battery back-up to provide continuous operation when failure of the primary power source occurs. Batteries must be capable of being charged from a 110 volt AC power source. The unit must also be capable of being operated solely from a 110 volt AC power source and be equipped with a cable for this purpose. The PCMS shall be mounted on a trailer in such a way that the bottom of the message sign panel shall be a minimum of 7 feet above the roadway in urban areas and 5 feet above the roadway in rural areas when it is in the operating mode. PCMS trailers should be of a heavy duty type with a 2 inch ball hitch and a minimum of four leveling jacks (at each corner). The sign shall be capable of being rotated 360° relative to the trailer. The face of the trailer shall be delineated on a permanent basis by affixing retro-reflective material, known as conspicuity material, in a continuous line as seen by oncoming drivers. CONSTRUCTION REQUIREMENTS 652.3.1 Responsibility of the Department The Department will provide Project traffic requirements such as allowable lane or road closures, minimum temporary lane widths, work zone speed limits, timing limitations, and allowable special detours and temporary structures. No revisions to these requirements will be permitted unless the Contractor can thoroughly demonstrate an overall benefit to the public and a Contract Modification is approved. 652.3.2 Responsibility of the Contractor The Contractor shall provide continuous and effective traffic control and management for the Project that is appropriate to the construction means, methods, and sequencing allowed by the Contract and selected by the Contractor. 652.3.3 Submittal of Traffic Control Plan The Contractor shall submit, at or before the Preconstruction Meeting, a Traffic Control Plan (TCP) that provides the following information to the Department:
a.The name, telephone number, and other contact numbers (cellular phone, pager, if any) of the Contractor's Traffic Control Supervisor (TCS). The TCS is the person with 6-152 overall responsibility for insuring the contractor follows the TCP. and who has received Work Zone Traffic Control Training commensurate with the level of responsibility shown in the requirements of the Contract, and who is empowered to immediately resolve any work zone traffic control deficiencies or issues. Provide documentation that the Traffic Control Supervisor has completed a Work Zone Traffic Control Training Course (AGC, ATSSA, or other industry-recognized training), and a Supervisory refresher training every 5 years thereafter. Submit training certificates or attendance roster that includes the course name, training entity, and date of training. Traffic Control Training Course curriculum must be based on the standards and guidelines of the MUTCD and must include, at a minimum, the following:
1.Parts of Temporary Traffic Control Zone
2.Appropriate use and spacing of signs
3.Use and spacing of channelizing devices
4.Flagging basics
5.Typical examples and applications The Traffic Control Supervisor, or designee directly overseeing physical installation, adjustment, and dismantling of work zone traffic control, will ensure all personnel performing those activities are trained to execute the work in a safe and proper manner, in accordance with their level of decision-making and responsibility.
b.Proposed construction phasing or sequencing that reasonably minimizes traffic impacts. The Contractor shall conduct the Work such that traffic delays do not exceed 10 minutes unless longer periods are authorized by the Department. The Contractor shall provide advance signing to warn motorists of expected traffic backups or queues.
c.A written narrative and/or plan explaining how traffic and pedestrians will be moved through the Project Limits, including transitions during the change from one phase of construction to the next, as applicable.
d.Temporary traffic control treatments at all intersections with roads, rail crossings, businesses, parking lots, pedestrian ways, bike paths, trails, residences, garages, farms, and other access points, as applicable.
e.A list of all Contractor or Subcontractor certified flaggers to be used on the Project, together with the number of flaggers which will be used for each type of operation that flagging is needed. If the Contractor is using a flagging Subcontractor, then the name and address of the Subcontractor may be provided instead of a list of flaggers.
f.A procedure for notifying the Resident, local emergency officials, and local government officials (including the name and phone numbers of such officials) whenever significant traffic impacts are anticipated or occur and the plan for removing all lane restrictions in case of emergency or significant traffic impact. For a related provision, see Section 105.2.3 - Project Specific Emergency Planning. 6-153
g.A description of any special detours including provisions for constructing, maintaining, signing, and removing the detour or detours, including all temporary bridges and accessory features and complete restoration of the impacted land.
h.The maximum length of requested contiguous lane closure. The Contractor shall not close excessive lengths of traffic lane to avoid moving traffic control devices.
i.The proposed temporary roadway surface conditions and treatments. The Contractor shall provide an adequate roadway surface at all times; taking into account traffic speed, volume, and duration.
j.The coordination of appropriate temporary items (drainage, concrete barriers, barrier end treatments, impact attenuators, and traffic signals) with the TCP.
k.The plan for unexpected nighttime work, the contractor shall provide a list of emergency nighttime lighting equipment and safety personnel available on-site or have the ability to have them on site within an hour of the time of need.
l.The plan for meeting any project specific requirements contained in special provision 105 and/or 107
m.The lighting plan if night work is anticipated. The Department will review the TCP for completeness and conformity with Federal requirements, Contract provisions, the current edition of the MUTCD, and Department policy and procedures. The Department will review and provide comments to the Contractor within 14 days of receipt of the TCP. No review or comment by the Department, or any failure to review or comment, shall relieve the contractor of its responsibility to design and implement the plan in accordance with the Contract, or to shift any responsibility to the Department. If the TCP is determined by the Department to be operationally ineffective, the Contractor shall submit modifications of the TCP to the Department for review, and shall implement these changes at no additional cost to the Contract. Nothing in this Section shall negate the Contractor’s obligations set forth in Section 110 - Indemnification, Bonding, and Insurance. The creation and modification of the TCP will be considered incidental to the related 652 items. 652.3.4 General Prior to starting any work on any part of the project adjacent to or being used by the traveling public, the Contractor shall install the appropriate traffic control devices in accordance with the plans, specifications and the latest edition of Manual of Uniform Traffic Control Devices, Part VI. The Contractor shall continuously maintain the traffic control devices in their proper position, and they shall be kept clean, legible and in good repair throughout the duration of the work. If notified that the traffic control devices are not in place or not properly maintained, the Contractor may be ordered to immediately suspend work until all deficiencies are corrected. 6-154 No equipment or vehicles of the Contractor, their subcontractors, or employees engaged in work on this contract shall be parked or stopped on lanes carrying traffic, or on lanes or shoulders adjacent to lanes carrying traffic, at any time, except as required by ongoing work operations. Contractor equipment or vehicles shall never be used to stop, block, or channelize traffic. The Contractor shall not store material or park equipment within 15 feet of the edge of the established travel lanes. Equipment parked overnight between 15 and 30 feet of the edge of the travel lane shall be placed behind positive barriers if feasible, or clearly marked by channelizing devices or other reflective devices. Channelization devices shall include Vertical Panel Markers, Barricades, Cones, and Drums. These devices shall be installed and maintained at the spacing determined by the MUTCD through the work area. Channelization devices consisting of barricades or drums, at a maximum spacing of 50 feet, shall be used in guardrail areas when neither the existing guardrail nor the new guardrail is in place. The Contractor shall maintain existing guardrails and/or barriers until removal is necessary for construction. The Contractor shall use a temporary barrier or appropriate channelizing devices while the guardrails and/or barriers are absent. Permanent guardrails and barriers shall be installed as soon as possible to minimize risk to the public. All excavation areas adjacent to the roadway shall be channelized continuously in both directions for the length of the project in all areas where the centerline strip is not effective in accordance with the latest edition of the MUTCD. Where the roadway is adjacent to an area being excavated, a minimum 2 foot shoulder should be maintained and the effective slope of the earth excavation beyond the 2 foot shoulder shall not be steeper than a 1½ horizontal to 1 vertical. The effective slope of rock excavation shall not be steeper than 1 horizontal to 1 vertical beyond the 2 foot shoulder. In the case of cuts over 5 feet deep, a Concrete Barrier or other approved barrier shall be placed between the travel lane and the excavated area. In this instance, travel speeds shall be limited by specific advisory signing to 20 miles per hour in all cases. When excavation does not leave sufficient usable widths to maintain two-way traffic as provided in Section 105.4 - Maintenance of Work, one-lane traffic controlled by a traffic signal or continuous flagging may be considered. Closely spaced vertical panels, drums or other channelizing devices shall be used on any of these types of areas that are left exposed for short durations. When paving operations or shoulder grading leave a 3 inch or less exposed vertical face at the edge of the traveled way, channelization devices shall be placed 2 feet outside the edge of the pavement at intervals not exceeding 600 feet and a 48 inch by 48 inch W8-9 Low Shoulder sign shall be placed at a maximum spacing of ½ mile. When paving 6-155 operations or shoulder grading leave greater than a 3 inch exposed vertical face at the edge of the traveled way, the Contractor shall place shoulder material for a width of at least 4 feet to meet the pavement grade, and place channelizing devices as above, before the lane is opened to traffic. A temporary ramp shall be constructed with HMA at the ends of the roadway section paved or milled each day. The use of millings or RAP will not be allowed, but cold patch may be temporarily utilized until HMA plants are open for the season. The maximum ramp change in elevation shall not exceed 4” vertical. For Interstate Highways or roadways with speed limits equaling or exceeding 50 mph; temporary ramps shall be constructed at a length of eight feet per inch of transition depth. For roadways with speed limits less than 50 mph and greater than 25 mph, temporary ramps shall be constructed at a length of four feet per inch of transition depth. For roadways with speed limits 25 mph or less, temporary ramps shall be constructed at a length of two feet per inch of transition depth. Materials, placement, maintenance, and removal shall be incidental to contract items. Special Detours and temporary structures, if used, shall meet applicable AASHTO standards, including curve radii and grade. 652.3.5 Installation of Traffic Control Devices All traffic control devices shall be in conformance with NCHRP 350 requirements and installed as per manufactures recommendations. Portable signs shall be erected on temporary sign supports approved crashworthy devices so that the bottom of the sign is either 1) 12 inches or 2) greater than 5 feet above the traveled way. Post-mounted signs shall be erected so the bottom of the sign is no less than 5 feet above the traveled way, and 7 feet above the traveled way in business, commercial, and residential areas. Post-mounted signs must be erected so that the sign face is in a true vertical position. All signs shall be placed so that they are not obstructed in any manner and immediately modified to ensure proper visibility if obstructed. Signs may be mounted lower or higher to fit the situation when authorized by the Resident. Cones shall be either weighted or nailed. Tires will not be allowed as weights. Vertical panel markers shall be mounted with the top at least 4 feet above the traveled way. Drums shall not be weighted on the top. Drain holes shall be provided to prevent water from accumulating in the drums. Drums may be weighted with up to 6 inches of loose dry sand. The Contractor shall operate and maintain the flashing arrow board unit and trailer and shall continuously supply fuel and lubrication for dependable service during the life of the contract. The units shall remain in continuous night and day service at locations designated until the Resident designates a new location or discontinuance of service. The Contractor shall maintain the devices in proper position and clean them as necessary. Maintenance shall include the covering and uncovering of all signs when no 6-156 longer applicable (even if for a very short duration). The sign shall be considered adequately covered when no part of the sign face is visible either around or through the covering. The Contractor shall replace damaged traffic control devices with devices of acceptable quality, as directed by the Resident. 652.3.6 Traffic Control The Contractor shall provide a minimum roadway width of 22 feet for two-way traffic and 11 feet for one-way traffic. The existing travel way width shall be maintained to the maximum extent practical. Vertical panel markers, drums, cones, or striping shall be used to clearly delineate the roadway through the construction area. Two- way traffic operation shall be provided at all times that the Contractor is not working on the project. One-way traffic shall be controlled through work areas by flaggers, utilizing radios, field telephones, or other means of direct communication. The traffic control devices shall be moved or removed as the work progresses to assure compatibility between the uses of the traffic control devices and the traffic flow. Traffic control devices that become unnecessary shall be immediately removed from use. Pavement markings shall be altered as required to conform to the existing traffic flow pattern. Repainting of pavement marking line, if required to maintain the effectiveness of the line, shall be considered maintenance of traffic control devices. No separate payment will be made. Inappropriate existing pavement markings shall be removed whenever traffic is rerouted, and temporary construction pavement markings shall be placed. Obliteration and removal of non-applicable markings and placement of temporary construction pavement markings shall be considered maintenance of traffic control devices and will be paid for under the appropriate Contract item. Traffic changes shall not be made unless there is sufficient time, equipment, materials, and personnel available to complete the change properly before the end of the workday. This provision will not be required when traffic is rerouted for brief periods during daylight hours and the route can be clearly defined by channelizing devices, or flaggers, or both. 652.4 Flaggers The Contractor shall furnish flaggers as requi red by the TCP or as otherwise specified by the Resident. All flaggers must have successfully completed a flagger test approved by the Department and administered by a Department-approved Flagger-Certifier. All flaggers must carry an official certification card with them at all times while flagging. For daytime conditions, flaggers shall wear a top (vest, shirt or jacket) that is orange, yellow, yellow-green, or fluorescent versions of these colors meeting ANSI 107-2004, Class 2 or Class 3, along with a hardhat with 360 ˚ retro-reflectivity. For nighttime conditions, flaggers shall wear all Class 3 apparel, meeting ANSI 107- 2004, including a Class 3 top (vest, shirt or jacket) and a Class E bottom (pants or coveralls), shall be worn along with a hardhat with 360 ˚ retro-reflectivity and shall be visible at a minimum distance of 1000 ft. Flagger stations must be illuminated in nighttime conditions to assure visibility and will be specifically addressed in detail in the Contractor’s TCP. 6-157 Flagger stations shall be located far enough in advance of the workspace so that approaching road users will have sufficient distance to stop at the intended stopping point. While flagging, the flagger should stand either on the shoulder adjacent to the traffic being controlled, or in the closed lane. At a spot obstruction with adequate sight distance, the flagger may stand on the shoulder opposite the closed sections to operate effectively. Under no circumstances shall the flagger stand in the lane being used by moving traffic or have their back to oncoming traffic. The flagger should be clearly visible to approaching traffic at all times and should have a clear escape route. When conditions do not allow for proper approach sight distance of a flagger or storage space for waiting vehicles, additional flaggers shall be used at the rear of the backlogged traffic or at a point where approaching vehicles have adequate stopping sight distance to the rear of the backlogged traffic. All flagger stations shall be signed, even when in close proximity. The signs shall be removed or covered when flagger operations are not in place, even if it is for a very short duration. Flaggers shall be provided as a minimum, a 10 minute break, every 2 hours and a 30 minute or longer lunch period away from the work station. Flaggers may only receive 1 unpaid break per day; all other breaks must be paid. Sufficient certified flaggers shall be available onsite to provide for continuous flagging operations during break periods. If the flaggers are receiving the appropriate breaks, breaker flagger(s) shall be paid starting 2 hours after the work begins and ending 2 hours before the work ends. A maximum of 1 breaker per 6 flaggers will be paid. (1 breaker flagger for 2 to 6 flaggers, 2 breaker flaggers for 7 to 12 flaggers, etc). If a flagger station is manned for 10 hours or more, then ½ hour for lunch will be deducted from billable breaker flagger hours. 652.4.1 Traffic Officers Traffic officers will be uniformed police officers. 652.5 Warning Lights Warning lights shall be installed at loc ations designated by the Resident before any work is done on the portions of roadway being used by traffic. Upon installation, all warning lights shall remain in continuous operation during the life of the project, unless otherwise authorized by the Resident. When a suitable 120-volt AC power service source is available within 500 feet of the designated warning light location, power operated flashing lights shall be installed. Two alternately flashing lamps shall be mounted approximately 24 inches above the sign, spaced approximately 24 inches apart. When a suitable 120-volt AC power service source is not available, battery operated flashing lights may be erected. Four flashing lamps shall be mounted approximately 6 inches above the sign, spaced approximately 12 inches apart. The power service connections shall be installed to the satisfaction of both the power company and the Resident. The Contractor shall make all necessary arrangements for the power service connections and be responsible for all charges incurred thereby, including 6-158 power charges. The Contractor shall also be responsible for all outstanding bills from the electric power company for preliminary work done by the electric company for the power service connection. When batteries are required for battery operated flashing lights, they shall be provided and replaced by the Contractor as necessary. 652.5.1 Rumble Strip Crossing When lane shifts or lane closures require traffic to cross a permanent longitudinal rumble strip for 7 calendar days or less, the Contractor shall install warning signs that read “RUMBLE STRIP CROSSING” with a supplemental Motorcycle Plaque, (W8-15P). When lane shifts or lane closures require traffic to cross a permanent longitudinal rumble strip for more than 7 calendar days, the Contractor shall pave in the rumble strips in the area that traffic will cross, unless otherwise directed by the Resident. Rumble strips shall be replaced prior to the end of the project, when it is no longer necessary to cross them. 652.6.1 Daylight Work Times Unless otherwise described in the Contract, the Contractor is allowed to commence work and end work daily according to the Sunrise/Sunset times procured at: https://www.sunrisesunset.com/usa/Maine/ . If the Project town is not listed, the closest town on the list will be used as agreed at the Preconstruction Meeting. Any work conducted before sunrise or after sunset will be considered Night Work. 652.6.2 Night Work When Night Work occurs (either scheduled or unscheduled), the Contractor shall provide and maintain lighting on all equipment, at all work stations, and all flagger stations. The lighting facilities shall be capable of providing light of sufficient intensity to permit good workmanship, safety and proper inspection at all times. The lighting shall be cut off and arranged on stanchions at a height that will provide perimeter lighting for each piece of equipment and will not interfere with traffic, including commercial vehicles, approaching the work site from either direction. The Contractor shall have available portable floodlights for special areas. The Contractor shall utilize padding, shielding or other insulation of mechanical and electrical equipment, if necessary, to minimize noise, and shall provide sufficient fuel, spare lamps, generators, etc. to maintain lighting of the work site. The Contractor shall submit, as a subset of the Traffic Control Plan, a lighting plan at the Preconstruction Conference, showing the type and location of lights to be used for night work. The Resident may require modifications be made to the lighting set up in actual field conditions. 6-159 Prior to beginning any Night Work, the Contractor shall furnish a light meter for the Residents use that is capable of measuring the range of light levels from 5 to 20 foot- candles. Horizontal illumination, for activities on the ground, shall be measured with the photometer parallel to the road surface. For purposes of roadway lighting, the photometer is placed on the pavement. Vertical illumination, for overhead activities, shall be measured with the photometer perpendicular to the road surface. Measurements shall be taken at the height and location of the overhead activity. Night Work lighting requirements: Mobile Operations: For mobile-type operations, each piece of equipment (paver, roller, milling machine, etc) will carry indirect (i.e. balloon type) lights capable of producing at least 10 foot-candles of lighting around the work area of the equipment. Fixed Operations: For fixed-type operations (flaggers, curb, bridge, pipes, etc.), direct (i.e. tower) lighting will be utilized capable of illuminating the work area with at least 10 foot-candles of light. Hybrid Operations: For hybrid-type operations (guardrail, sweeping, Inslope excavation, etc.), either direct or indirect lighting may be utilized. The chosen lights must be capable of producing at least 10 foot-candles of light around the work area of the equipment Inspection Operations: Areas required to be inspected by the Department will require a minimum of 5 foot-candles of lighting. This may be accomplished through direct or indirect means. All workers shall wear safety apparel labeled as meeting the ANSI 107-2004 standard performance for Class 3 risk exposure. The Contractor shall apply 2- inch wide retro-reflective tape, with alternating red and white segments, to outline the front back and sides of construction vehicles and equipment, to define their shape and size to the extent practicable. Pickup trucks and personal vehicles are exempt from this requirement. The Contractor shall furnish approved signs reading "Construction Vehicle - Keep Back" to be used on trucks hauling to the project when such signs are deemed necessary by the Resident. The signs shall be a minimum of 30 inches by 60 inches, Black and Orange, ASTM D 4956 - Type VII, Type VIII, or Type IX (prismatic). All vehicles used on the project, including pickup trucks and personal vehicles, shall be equipped with amber flashing lights, visible from both front and rear, or by means of single, approved type, revolving, flashing or strobe lights mounted so as to be visible 360º. The vehicle flashing system shall be in continuous operation while the vehicle is on any part of the project. The Resident or any other representative of the Department reserves the right to suspend the work at any time and request a meeting to discuss violations and remedies. The 6-160 Department shall not be held responsible for any delay in the work due to any suspension under this item. Failure to follow the approved Lighting Plan will result in a Traffic Control violation. Payment for lighting, vehicle mounted signs and other costs accrued because of night work will not be made directly but will be considered incidental to the related contract items. 652.7 Method of Measurement Signs and panel markers will be measured by the square foot for all signs authorized and installed. Flashing arrow boards, portable-changeable message signs, and flashing and steady burn lights, will be measured by each unit authorized and installed on the project. Barricades, drums, and cones will be measured by each unit authorized. No additional payment will be made for devices that require replacement due to poor condition or inadequate retroreflectivity. The accepted quantity of traffic officer and flagger time will be the number of hours the designated station is occupied. The number of hours authorized for payment will be measured to the nearest ¼ hour. Maintenance of traffic control devices will be measured by the calendar day or as one lump sum for all authorized and installed traffic control devices. Warning lights will be measured by the group of lights furnished. 652.8 Basis of Payment The accepted quantity of signs and panel markers will be paid for at the contract unit price per square foot. Such payment will be full compensation for furnishing and installing all signs, sign supports, and all incidentals necessary to complete the installation of the signs. The accepted quantity of flashing arrow boards, portable-changeable message signs, barricades, battery operated flashing and steady burn lights, drums, and cones will be paid for at the contract unit price each for the actual number of devices authorized, furnished, and installed. Such payment shall be full compensation for all incidentals necessary to install and maintain the respective devices. Failure by the contractor to follow the Contracts 652 Special Provisions and Standard Specification and/or the Manual on Uniform Traffic Control Devices (MUTCD) and/or the Contractors own Traffic Control Plan will result in a violation letter and result in a reduction in payment as shown in the schedule below. The Resident or any other representative of the Department reserves the right to suspend the work at any time and request a meeting to discuss violations and remedies. The Department shall not be held responsible for any delay in the work due to any suspension under this item. Any reduction in payment under this Special Provision will be in addition to forfeiting payment of maintenance of traffic control devices for that day. ORIGINAL CONTRACT 6-161 AMOUNT From Up to and Amount of Penalty Damages per Violation More Than Including 1 st 2 nd 3 rd & Subsequent $0 $1,000,000 $250 $500 $1,250 $1,000,000 $2,000,000 $500 $1,000 $2,500 $2,000,000 $4,000,000 $1,000 $2,000 $5,000 $4,000,000 and more $2,000 $4,000 $10,000 652.8.1 Maintenance of Traffic Control Devices 652.8.1.1 Payment by Calendar Day Maintenance of Traffic Control Devices will be paid for at the contract unit price per calendar day for each calendar day that the Contractor maintains traffic as specified herein. Such payment will be full compensation for moving devices as many times as necessary; for replacing devices damaged, lost, or stolen; and for cleaning, maintaining, and removing all devices used for traffic control, including replacing temporary pavement marking lines. The contract unit price per calendar day for Maintenance of Traffic Control Devices shall be full payment each day for such maintenance, encompassing all areas of the contract, regardless of whether or not the work areas or projects are geographically separated. 652.8.1.2 Payment by Lump Sum Maintenance of Traffic Control Devices will be paid at the contract lump sum price. Such payment will be full compensation all days that the Contractor maintains traffic as specified herein, and for moving devices as many times as necessary; for replacing devices damaged, lost, or stolen; and for cleaning, maintaining, and removing all devices used for traffic control, including replacing temporary pavement marking lines. The contract lump sum price for Maintenance of Traffic Control Devices shall be full compensation for all days for such maintenance, encompassing all areas of the contract, regardless of whether or not the work areas or projects are geographically separated. 652.8.2 Other Items The accepted quantities of flagger hours will be paid for at the contract unit price per hour for each flagging station occupied excluding lunch breaks, and for each approved breaker flagger. Overtime hours, as reported on the certified payrolls, will be paid an additional 30% of the bid price for 652.38. The computation and additional payment for overtime hours will occur during the project close-out process and will be paid as additional hours of 652.38 to the nearest ¼ hour. The contract unit price shall be full compensation for hiring, transporting, equipping, supervising, and the payment of flaggers and all overhead and incidentals necessary to complete the work. There will be no payment made under any 652 pay items after the expiration of the adjusted total contract time. 6-162 The accepted quantities of traffic officer hours will be paid for at the contract unit price per hour for each station occupied, with no additional payment for overtime. This price shall be full compensation for supplying uniformed officers with police cruisers, and all incidentals necessary to complete the work; including transportation, equipment, and supervision. The accepted quantities of warning lights will be paid for at the contract unit price, per group, complete in place including the necessary power, and remaining in operation during active work of the project or as otherwise directed. Upon completion of the work, the lamps, fixtures, and the framework required to properly mount the lamps shall remain the property of the Contractor. Payment for temporary pavement marking lines and pavement marking removal will be made under the respective pay item in Section 627 - Pavement Markings. Payment for temporary traffic signals will be made under Section 643 - Traffic Signals. There will be no payment made under any 652 pay items after the expiration of the adjusted total contract time. Payment will be made under: P a y I t e m P a y U n i t
652.30 Flashing Arrow Each
652.31 Type I Barricade Each
652.311 Type II Barricade Each 652.312 Type III Barricades Each
652.32 Battery Operated Light Each
652.33 Drum Each
652.34 Cone Each
652.35 Construction Signs Square Foot
652.36 Maintenance of Traffic Control Devices Calendar Day
652.361 Maintenance of Traffic Control Devices Lump Sum