900 — GENERAL 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS CATEGORY 900 MATERIALS SECTION 900 — GENERAL
900.01 General
Sample, test, and inspect all materials included in this Category as specified in the most recently published cited standards. The specification limits for each material are established and deviations from these limits are prohibited except when, in the judgment of the Engineer, the deviation will not be detrimental to the work. In these cases, refer to the appropriate specification governing price adjustments for nonconformance. Within 30 days after receipt of notification of award of the Contract, submit in writing, to the Office of Materials Technology (OMT), the proposed sources of all materials to be incorporated into the project. Update and submit all nursery stock sources to OMT 45 days prior to the planting season in which the planting is to begin. Do not introduce material into the work until sources are approved. The Administration reserves the right to completely or partially test any material for Specification compliance. Sample according to the Administration’s Sample Testing and Frequency Guide unless otherwise directed. All source approvals are made subject to continuing production of materials conforming to these Specifications. Material sources may be rejected where it is evident that the material tends to be of marginal quality when compared to the Specification limits in any of its specified properties.
900.02 Technician Qualification Requirements
Technicians performing Quality Assurance (QA)/Quality Control (QC) sampling and testing shall be qualified through the certification program provided by the Administration. Private laboratories performing testing shall be in the AASHTO Accreditation Program or approved by the Administration. Technicians include those who work for inspection agencies, Contractors, consultants, producers, private laboratories, and State and local government employees.
900.03 Recycled Materials
900.03.01 CERTIFICATION. All recycled or rehandled material furnished or supplied for use
may require testing and certification to ensure compliance with all State and local applicable environmental and EPA regulations. The required testing may include, but not be limited to, the EPA Toxicity Characteristic Leaching Procedure (TCLP) or its successor. Provide testing and 900 — GENERAL 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS certification for all recycled materials at no additional cost to the Administration. Evaluation and interpretation of the test data will be made by an OMT QA Manager. The above requirements do not preclude the normal materials acceptance process, and the recycled material shall meet all applicable specifications. EPA regulations governing the use of the material, certified test results, and material safety data sheets shall accompany the source of supply letter and sample submitted for approval. Only highway demolition materials are to be used in constructing reclaimed/recycled concrete stockpiles for Administration projects. The use of building materials is prohibited. Refer to the Contract Documents for recycled materials not covered by this specification.
900.03.02 Reclaimed/Recycled Concrete (Rc)
Usage. Use RC for the following with written approval.
900.03.03 Recycled Asphalt Pavement (Rap)
Usage. Use RAP for Common, Select, Capping, or Modified Borrow. Do not use RAP as aggregate for the following.
204.03.07 Do not construct the control strip, or perform any subsequent construction, on frozen
subgrade. Compact the RAP for the control test strip with one pass of the roller. Measure the density after one pass with a nuclear density gauge (backscatter method) at the frequency for capping material at five random locations distributed across the length and width of the control test strip, as directed. Record the measurements and mark the locations for future reference. Compact the RAP for the control test strip with a second pass of the roller. Measure and record the density again at the exact locations previously tested and as described above. Prepare a plot of density versus the number of roller passes. Continue this process until the maximum dry density of the control strip is established. There should be no drop in average density during construction of the control test strip for each lift. A drop in the average density of greater than 2 pcf during construction of the control test strip is an indication that the material is not properly compacting, and a new test strip shall be constructed. The Engineer may require the Contractor to cut into the control test strip for visual inspection. All material, labor, equipment, tools, and incidentals necessary to provide an approved control test strip shall be at no additional cost to the Administration. Compaction Control. Use the roller pattern and number of passes determined from the construction of the test strip to compact the RAP for production placement. The density of the RAP compacted for production work shall be at least 97 percent of the maximum density obtained from the control test strip. Recheck the density of the production work if it is less than 97 percent of the maximum density obtained from the control test strip. Construct a new control test strip if the second density does not meet the 97 percent requirement. Construct a new control test strip if the measured density of the compacted RAP for production work exceeds 105 percent. 900 — GENERAL 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS Establish one rolling pattern to achieve maximum density for each use based on the control test strips. Samples or results produced prior to the construction of any new stockpiles will not be considered.
900.03.04 DREDGED MATERIAL (DM) and DREDGED MATERIAL BLENDS (DMB)
Definitions. Dredged Material (DM). Material excavated or dredged from the waters of the State as referenced in COMAR 26.04 and COMAR 26.10.13. The term "waters of this State" is also specifically defined in COMAR. It includes a wide range of surface and underground waters within Maryland's jurisdiction, such as surface and underground waters within state boundaries, the Chesapeake Bay and its tributaries, and various bodies of water and drainage systems like ponds, lakes, rivers, and streams. It also encompasses the portion of the Atlantic Ocean within the state's boundaries and the floodplain of free-flowing waters as determined by the Department based on the 100 year flood frequency. The DM includes Sand, Silt, Clay, Gravel, Mud, Muck, Rock or other sediment or material excavated or dredged from tidal, estuarine, or riverine waters of the State, including potentially dry areas at the time of excavation beneath the plane bounded by the normal high water line. DM includes but is not limited to dredged slurry, hydraulic fill, or dewatered dredged material from fresh, brackish, or saltwater environments. Dredged Material Blend (DMB): A homogeneous mixture of dredged material with other approved borrow materials. Corrosivity, Gradation and Toxicity Requirements. DM and DMB shall meet the following requirements: Parameter Acceptable Range Test Method Minimum resistivity (Ω·cm) > 3,000 T 288 pH 5.5 – 8.5 T 289 Sulfate content (ppm) < 500 T 290 Chloride content (ppm) < 400 T 291 PFOA and PFOS Organic Content < 4 ng/L (in leachate) < 8% EPA Method 1633 with D 3987 (Leaching) T 267 Gradation % Passing #200 Sieve ≤ 30% T 11 Notes: Ω·cm = Ohm·Centimeter, ppm = Parts per Million. PFAS = Perfluoroalkyl and Polyfluoroalkyl Substances PFOA = Perfluorooctanoic Acid PFOS = Perfluorooctane Sulfonate 900 — GENERAL 2026 STANDARD SPECIFICATIONS FOR CONSTRUCTION AND MATERIALS In addition to the above requirements, DM and DMB shall follow the procedures and meet the requirements of Category 1 – Residential Unrestricted Use Soil and Fill Material or Category 2 – Non-Residential Restricted Use Soil and Fill Material land use categories as specified by Maryland Department of the Environment (MDE) in the current Innovative Reuse and Beneficial Use of Dredged Materials (IRBDM). All MDE requirements shall be satisfactorily met, including but not limited to the screening process, sampling, frequency of sampling, and testing analysis with a listing of the appropriate test procedures. It is the contractor’s responsibility to obtain the MDE approval, whether directly or indirectly from the source vendor, satisfactorily demonstrating that all MDE requirements are met. DMB requires blending DM, as necessary, with soil, quarry fines or other materials to meet the above requirements. The DMB will be subject to a blending study done by the contractor or supplier. The blending study will be outlined in the Sampling and Analysis Plan (SAP) which will be reviewed and approved by MDE within 30 days. Test the blending material(s) in accordance with all MDE IRBDM testing requirements. SHA will only sample and test the final blend for the final approval of the material after receiving approval and test results per the IRBDM. Source submissions will be considered with an approved Sampling and Analysis Plan (SAP) from MDE if a blending study was conducted. Provide a declaration of potential environmental impacts to adjacent properties and a Confirmation of Suitability of use / Interim Receiving Site Form containing the following information: