a.Mechanically excavate an area of 25 square feet through the full depth of the pavement, taking care not to further rubblize. Notify the Engineer at least 2 hours before excavati on to allow verification of results for acceptance.
b.If the Engineer directs, perform spot inspections to the top of reinforcement using manual methods instead of mechanical methods. The inspections may be at the locations listed above (subsection 304.03.C. 2) or at other locations chosen by the Engineer. Use a shovel or pick to excavate an area of 25 square feet. Use a geologist ’s pick or mason ’s hammer to separate the concrete pieces above the reinforcing mat. Remove as much material as possible and clean the remaining surface with a stiff -bristled broom or brush to expose the reinforcing mat. The Department considers the mat debonded if at least 80% of the mat is visible after excavation and sweeping.
d.Restore inspection sites with filler aggregate and compact. The Engineer may adjust the inspection frequency. MDOT Standard Specifications for Construction Section 304 3-16 3. Ensure that the completed rubblized surface has a uniform appearance with no unbroken strips of pavement, exposed reinforcement, or visible joint filler and asphalt patching material.
D.Compaction . Before placing t he HMA mixture, compact the rubblized pavement with vibratory steel -wheeled and pneumatic -tired rollers in the following sequence:
1.At least two passes with a Z -grid vibratory roller or steel drum roller as approved by the Engineer;
2.All subsequent passes w ith a pneumatic -tired or steel drum roller; except
3.The final pass just before HMA placement , which is with a steel drum roller. The Department considers a pass down and back in the same path. Provide rollers with a nominal gross weight of at least 10 ton s. Operate vibratory rollers in a high vibration mode and at a speed no greater than 6 feet per second unless otherwise limited by the condition of the base, subbase, subgrade, or drainage features. The Contractor may apply water if the Engineer approves. After compaction and before placing HMA, ensure that the finished surface varies no more than ±1 inch when tested with a 10-foot straightedge. Fill voids and depressions with filler aggregate and compact.
E.Miscellaneous. Do not allow vehicular traffic on the rubblized pavement before HMA placement unless otherwise required for construction and maintenance of traffic, as approved by the Engineer. Maintain the compaction of portions of the rubblized pavement with no exposed reinforcement for crossroad or ramp traffic. In part -width construction areas, rubblize the pavement to the limits of the required overlay for that stage. Saw cut the longitudinal joint deep enough to cut the tie bar unless rubblizing in a prior stage extended beyond t he centerline and past the tie bar. Do not damage items that are required to remain, including drainage structures and monument boxes.
F.Acceptance Criteria. The Engineer will observe quality control checks described in subsection 304.03.C and base acceptanc e on the following criteria:
1.PCC pavement shattered to full depth; MDOT Standard Specifications for Construction Section 304 3-17 2. Non-reinforced PCC pavement and concrete pavement patches reduced to unbound particles with diameter s less than 10 inches;
3.Reinforced PCC pavement and concrete pavement patches above the reinforcement reduced to unbound particles with a nominal diameter from 2 inches to 6 inches;
4.Reinforced PCC pavement and concrete pavement patches below reinforcement exhibit sporadic particles greater than 10 inches, provided the Engineer verifies debonding of reinforcement near the particle;
5.No oversized particles at the surface for PCC pavements;
6.Debonding of reinforced pavement achieved if the required particle size is met;
7.Exposed reinforcement has been cut off below the surface and removed. Embedded reinforcement may remain in place;
8.No visible joint sealant or asphalt patching material on the compacted surface , and voids filled with filler aggregate;
9.Joints and cracks greater than ¼ inch wide at the surface are not distinguishable; and
10.No displacement of underlying base, subgrade, or underdrains.