4-38 Section 405. Pump Station Construction

405.01 Description

This work consists of constructing pump stations in accordance with the contract.

405.02 Materials

Provide material as required by the contract.

405.03 Construction

Construct pump houses as required by the contract.

405.04 Measurement and Payment

The Engineer will measure and the Department will pay for pump houses in accordance with the contract.

Sections that cite this one

Get an email when 405 changes

Michigan revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Michigan Standard Specifications for Construction, 2020 Edition. Pages 244–244 of 1,146. View official source ↗

Ask about this section

Scoped to Michigan 2020 Standard Specifications for Construction, Section 405 — Pump Station Construction. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.