1205Examination of Proposal Package and Site of Work

MN · 2025 Standard Specifications✓ Full text on BuildSpecBook pages 41–0 Save this section

Ask about Section 1205

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

1205.1PROPOSAL PACKAGE AND SITE OF WORK

Before submitting a Proposal, the Bidders shall carefully examine the Proposal Package and perform a reasonable investigation of the site of Work. Submitting a Proposal is considered an affirmative statement that the Bidder has examined the Proposal Package and performed a reasonable investigation of the site of Work, and is satisfied as to the character, quality, quantities, and conditions to be enc ountered in performing the Work. A reasonable site investigation includes investigating or reviewing the following:

(1)Project Site
(2)Borrow sites
(3)Haul routes
(4)Utility property in accordance with 1507, “Utility Property and Service”
(5)All other locations related to the performance of the Work
(6)Any additional information the Department makes available in accordance with 1205.2,

“Additional Information” The Bidder shall immediately notify the Department of any apparent defect in the Proposal Package. The Department will determine if a defect exists and, if necessary, will issue an Addendum to all prospective Bidders to address the correction.

1205.2ADDITIONAL INFORMATION

When available, the Department may make the following additional information available to Bidders:

(1)All Department boring logs and other records of subsurface investigation
(2)Record drawings
(3)Results of other preliminary investigations
(4)Other documents

A review of this additional information is not a substitute for a Bidder’s own evaluation, interpretation, or judgment in preparing a Proposal. Bidders shall understand that this additional information is not part of the Proposal Package and will not become part of the Contract . The Department makes this additional information available for the Bidders’ information only and warns the Bidders not to rely on any included estimates or quantities. If not included in the Proposal Package, the additional information may be available upon request, and Bidders shall be deemed to have knowledge of the availability of this additional information. Bidders are solely responsible for all assumptions, deductions, and conclusions that they may reach. The Department does not make or imply a warranty as to the accuracy, sufficiency, or reliability of this additional information. If the Department has taken test borings on the Project, the Department may or may not include the test boring information on the Plans. If the Department includes test boring information on the Plans, the Bidders shall understand the following with regard to the test boring information:

(1)The Department takes borings by ordinary and conventional methods and with care

deemed adequate for the Department's design purposes.

(2)The logs of the borings may have been edited or abridged and may not reveal all

information that might be useful or of interest to the Contractor.

(3)The Department will make any field logs and laboratory logs relating to the borings

available to the Bidders or Contractor.

(4)The Department may have taken some borings to gather information for purposes other

than those related to the construction of the Project.

(5)The Department does not warrant that the information is complete, but believes that

the information as to the conditions and materials reported within each test hole was accurate at the time the boring was taken.

(6)The Department does not warrant that conditions adjacent to test borings will

necessarily be the same as shown on the logs because subsurface conditions outside of each individual test hole are unknown to the Department, and soil, rock, and water conditions cannot be relied upon to be consistent and uniform.

(7)The Department will not be responsible for any interpretations made by the Contractor.
(8)The absence of notations on the logs regarding water does not necessarily mean that

the borings were dry or that the Contractor will not encounter subsurface water during the course of construction.

Get an email when 1205 changes

Minnesota revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Minnesota Standard Specifications for Construction, 2025 Edition. Pages 41–0 of 1,081. View official source ↗

Ask about this section

Scoped to Minnesota 2025 Standard Specifications for Construction, Section 1205 — Examination of Proposal Package and Site of Work. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.