2358.1DESCRIPTION

This Work consists of treating a prepared base with bituminous Material prior to placing a bituminous pavement.

2358.2MATERIALS

A Medium Curing Liquid Asphalt ........................................................................................ 3151.2B MC-30 or MC-70

2358.3CONSTRUCTION REQUIREMENTS

A Restrictions A.1 Base Moisture Content Place bituminous prime coat on a prepared base when the base moisture content of the upper 3 inches is less than 65 percent of Optimum Moisture Content. A.2 Traffic If Road is open to traffic, maintain traffic in at least one direction and only close a portion of the Traveled Way for construction, not to exceed 50 percent.

B Equipment B.1 Distributor ................................................................................................... 2360.3B.2.d C Application Apply the bituminous prime coat at a continuous uniform spread rate of 0.1 gallons per square yard to 0.3 gallons per square yard. D Bituminous Temperature Apply MC-30 bituminous prime coat at temperatures from 85°F to 145°F. Apply MC-70 bituminous prime coat at temperatures from 120°F to 180°F.

2358.4METHOD OF MEASUREMENT

The Engineer will measure Bituminous Material for prime coat by volume at 60°F.

2358.5BASIS OF PAYMENT

The Contract gallon price for Bituminous Material for prime coat includes the costs of providing and applying the Material as required by the Contract. The Department will pay for bituminous prime coat on the basis of the following schedule. Item No. Item Unit

2358.506 Bituminous Material for Prime Coat gallon

Get an email when 2358 changes

Minnesota revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Minnesota Standard Specifications for Construction, 2025 Edition. Pages 282–0 of 1,081. View official source ↗

Ask about this section

Scoped to Minnesota 2025 Standard Specifications for Construction, Section 2358 — Bituminous Prime Coat. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.