SECTION 681 - ROADWAY LIGHTING SYSTEM
681.01 Description. This work consists of furnishing; installing, testing, erecting,
constructing and assembling all materials to ensure a properly operating roadway lighting system in accordance with the plans and specifications.
681.02 General Provisions.
681.02.1 Tests and Inspection. The complete job shall be, during and/or after
construction, subject to the supervision of the Engineer. Inspections and tests shall be conducted by the Engineer or in the presence of the Engineer prior to acceptance of the project and shall consist of the following tests:
681.02.2 Material Warranty. The following Contractor warranty stipulations are in
addition to those covered by Subsection 106.01.2 of the Standard Specifications. All roadway lighting equipment and related components shall be fully operational at the final inspection of the project. The Contractor shall warrant and guarantee all roadway lighting equipment and related components for a minimum period of six (6) months. This warranty period begins after the day of partial release from maintenance or at th e start of continuous use as referenced in Subsection 681.02.8. Regardless of when the warranty period begins, the Contractor shall warrant and guarantee the roadway lighting equipment and related components (1) at least up to and including the day of final inspection and (2) during the Contractor’s warranty period. Final acceptance will not be made until after the warranty period expires. It is the intent of the preceding paragraph to provide for equipment that performs as intended by the manufacturer. It is the further intent to obtain from the Contractor a level of workmanship that assures the Department of an operational system devoid of Contractor laxities. Failure to perform as indicated shal l require the Contractor to replace in kind or repair, the equipment or workmanship in question at no additional cost to the State. All materials and labor cost resulting from the replacement or repair of equipment or correction of poor workmanship shall be borne by the Contractor. The Contractor shall not be responsible for outages occurring during the warranty period due to vandalism, traffic accidents or any problem not related to materials or workmanship. The Contractor will be required to make the n ecessary repairs but the cost of such repair shall be borne by the Department. All manufacturer's standard warranties or guarantees on all electrical and mechanical equipment provided as customary trade practice shall be delivered to the Engineer at the final inspection. All warranties and guarantees shall be made out to the Department.
681.02.3 General Information. Plans are diagrammatic and care shall be exercised to
install all electrical work in a manner that functions in accordance with plans, specifications and manufacturer's recommendations. Exact location of all equipment shall be determined from dimensions on the plans, manufacturer's shop plans, or as directed by the Engineer. Conduit runs, cable runs and circuit groupings are indicated diagrammatically with number of conductors shown in each run to clarify the operation and function of the system. The Contractor shall provide the number of conductors and conduits to produce an operative system as specified herein. All materials shall be new and of equal or superior quality to those specified. All equipment or materials shall conform to the latest requirements and/or additions to the Underwriter's Laboratories, National Electrical Code, or National, State or local agency having jurisdiction. All materials, devices, equipment, etc. shall be installed, tested, and connected in strict compliance with the manufacturer's recomme ndations, and, where sp ecified, under the direct supervision of a manufacturer's representative. All materials, devices, equipment, lighting, etc. shall be installed as required by the plans, specifications and manufacturer's recommenda tions. The Contractor shall use only experienced labor to do all trenching and jacking. All equipment and apparatus furnished shall be protected from damage by the Contractor. All items marred or damaged shall be replaced or repaired to the complete satisfaction of the Engineer solely at no additional cost to the State. Any piece of equipment, switch, device, etc., shown to be mounted on and/or adjacent to any existing equipment, which if installed may impair the proper operation of that equipment, shall be moved by the Contractor as required in order that existing equipment shall function properly. The Engineer shall be notified if any such condition exists. It shall be the responsibility of the Contractor to provide training in the operation and maintenance of all parts of the roadway lighting system to any person, or persons designated by the Engineer. The training shall consist of a minimum of eight (8) hours of on-site instructions and shall be conducted near the end of completion of all work, but prior to final acceptance of the project. The Contractor shall furnish the Engineer three (3) bound sets of the manufacturer's publications relating to the installation, operation and maintenance of all component parts of the roadway lighting system. The Contractor shall maintain a complete and accurate set of as-built plans throughout the project. At the final inspection, one (1) set each of full scale and 1/2 scale as-built blueprints shall be furnished to the Engineer. The Contractor shall submit eight (8) copies of a letter of certification from the high mast manufacturer on manufacturer's letterhead, certifying that all of the lowering devices, poles and luminaires have been installed in accordance with the manufacturer's guidelines. As referenced in Section 683 regarding high mast lighting assemblies, the following shall be provided from the same manufacturer.
681.02.4 Corrosion Protection. It is the intent of these specifications to have all joints,
connections, etc. completely water and moisture tight.
681.02.5 Coordination of Existing Utilities. It shall be the responsibility of the
Contractor to coordinate work near all existing utilities, both overhead and underground, and to verify utility locations with the various utilities companies prior to commencing any work. Failure to do this shall not relieve the Contractor of any responsibility and will not be justification for requesting additional money from the Department due to damage of any of these utility lines.
681.02.6 Removal of Salvaged Material and Debris. It shall be the responsibility of the
Contractor to have all salvaged materials, debris, etc. resulting from the Contractor’s operations completely removed from the project site continually during construction.
681.02.7 Initial Power Cost. The Contractor will make all application and contacts
necessary to obtain power from the local utility company. All costs relating to obtaining, providing and using electrical power during the entire life of the contract will be absorbed by the Contractor, with exception noted in Subsection 681.02.8.
681.02.8 Operation of the System. After the final electrical inspection is completed and
all noted deficiencies have been corrected, the system may be placed in operation at the request of the Engineer. This shall be accomplished before the complete removal of any temporary lighting system. When the system is placed into operation at the request of the Engineer, the Department will begin assuming all power costs. The Contractor will submit to the Department original bill(s) received from the Utility Company after the day the Department assumes the power cost. The Department will pay for only the cost of power used during and after that billing period. The Contractor will continue to warrant and maintain the system up to and including the day of final inspection. The date the system is placed in operation at the request of the Engineer, shall be considered the commencement of the warranty period, otherwise material warranties will be in accordance with Subsection 681.02.2.
681.03 Codes and Standards. The Contractor shall strictly comply with the latest edition
of the National Electrical Code, Federal, State or local codes having jurisdiction and shall notify the Engineer of any conflict between any of these codes and the plans and/or specifications before bid date or correct same at no additional cost to the State. The following Codes shall be complied with in each and every respect as though fully written herein:
681.04 Basic Materials and Methods. The Contractor shall submit to the Engineer eight
Get an email when 681 changes
Mississippi revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.