558.01 Description
This work is constructing reinforced concrete shafts cast in cylindrically excavated holes that extend into soil or rock to support the structure and externally applied loads at the locations and to the lines and grades shown in the contract.
558.02 Materials
558.02.1 Drilled Shaft Concrete
Use Drilled Shaft Concrete for all concrete placed between the bottom of the shaft and the top of the casing, unless otherwise shown in the contract. Obtain the Project Manager’s approval before using a SCC mix design.
558.02.2 Permanent Drilled Shaft Casing
Furnish casing in accordance with the size and thickness requirements specified and casing material that meets the requirements of AASHTO M 270, Grade 36. Furnish, fabricate, and inspect casing materials in accordance with Section 556.
558.02.3 Reinforcing Steel
Furnish all reinforcing steel in accordance with Section 555 and Subsection 711.01.
558.03 Construction Requirements
558.03.1 Submittals
Submit the following information.
558.03.2 Shaft Pre-construction Meeting
Schedule a shaft pre-construction meeting with the Project Manager for a time 7 to 14 calendar days prior to drilling. The minimum required attendees are the superintendent, concrete supplier, and Project Manager. The purpose of the meeting is to review the requirements of this specification, discuss the drilled shaft installation plan, and to discuss logistical and contingency plans.
558.03.3 Geotechnical Logging
The Department may provide a geotechnical representative on-site during drilling and installation operations to log the excavation. Notify the Project Manager at least 7 calendar days prior to start of drilled shaft excavation so that the Project Manager may schedule the on-site representative.
558.03.4 Shaft Excavation
Use excavation methods that provide contact with firm, undisturbed soil or rock with the sides and bottom of the drilled shaft. Do not excavate holes larger than the outside diameter of permanent casings.
558.03.5 Shaft Locations, Alignment and Tolerances
Drill all shafts to the bottom elevations specified or as directed by the Project Manager. Construct the shaft so the vertical centerline axis of the finished shaft is within 3 inches (75 mm) of the plan location at the top of the shaft. Drill all shafts to within 2% of vertical the entire depth of the shaft excavation.
558.03.6 Sloughing and Caving
Use tools and tool withdrawal rates that will not cause suction effects that result in soil intrusion or instability of the excavation. Use construction methods that will ensure no sloughing or caving of the shaft side walls. In the event any sloughing or caving does occur, remove all sloughed material. Ensure that concrete completely fills the shaft. If caving occurs during placement of drilled shaft concrete, immediately stop the flow of concrete, and undertake corrective measures to completely remove the sloughed materials from the shaft. If necessary, to facilitate material removal, remove the concrete and reinforcing steel already placed in the shaft.
558.03.7 Permanent Casing
558.03.8 Excavation Stability
Do not use slurry construction methods as an alternative to or in conjunction with temporary casing unless specified in the contract. Use casing to facilitate shaft construction and prevent sloughing and caving of the shaft sidewalls. The contract may specify temporary casing minimum elevations. Place the temporary casing deeper, if necessary, to prevent material from entering the shaft excavation. Use casing with an outside diameter no less than the specified diameter of the shaft. Limit the excavation in advance of the casing tip to no more than 10 feet (3
558.03.9 Obstructions
An obstruction is defined as a specific object (including, but not limited to, boulders, logs, and man-made objects) encountered during the shaft excavation which prevents the advance of the shaft excavation. If an obstruction is encountered promptly notify the Project Manager. Submit a proposed obstruction removal method for approval within 2 business days of encountering the obstruction.
558.03.10 Cleaning
Remove all loose or disturbed material from the bottom of the shaft excavation immediately prior to placing reinforcing steel and concrete. After cleaning, no more than 1-inch (25 mm) of loose or disturbed material is permitted in the bottom of the shaft. For wet shafts founded in rock, use an air lift to demonstrate that the shaft is clean. Use an air-lift system meeting the following requirements:
558.03.11 Installation of Cross-hole Sonic Logging (CSL) Tubes
Use 1½-inch (38 mm) nominal diameter schedule 40 steel CSL access tubes. Provide an end plug at the lower end of the pipe and make all joints watertight. Install the CSL access tubes evenly spaced around the reinforcing cage and inside of hoops and spiral reinforcing steel shown in the contract, using connectors that will allow the tubes to slide through them when force is applied. Position the connectors so that couplings will not prevent the tubes from sliding. Ensure tubes extend to the shaft bottom. After inserting the shaft reinforcing steel, drive each tube down until contact is made with the shaft bottom. Fill the CSL access tubes with potable water prior to or immediately after placing concrete in the drilled shaft. Temporarily cap the top of the tubes to prevent debris or concrete from entering the tubes.
558.03.12 Reinforcing Steel
Tie bars at all intersections. After inspection and approval of the drilled shaft excavation by the Project Manager, place the reinforcing steel cage into the shaft as one unit. Support the steel cage from the top so that racking and distortion are prevented. Remove internal stiffeners as necessary as the steel cage is placed in the excavation to prevent interference with the placement of concrete. Use non-corroding, roller-type spacers or other non-corroding devices as approved by the Project Manager along the steel cage length and around the steel cage perimeter to align and maintain clearance from reinforcing cage to edge of casing during concrete placement. Begin placing the drilled shaft concrete immediately after the Project Manager has inspected and approved the location and alignment of the cage within the drilled shaft. Remove the steel cage and re-inspect the excavation as directed by the Project Manager if the concrete placement is not started within 3 hours of placing the steel cage in position.
558.03.13 Concrete Placement Record
Complete the Department’s Drilled Shaft Concrete Placement Log. Accurately record all data required on the form as the concrete is placed. After the drilled shaft concrete has been placed and before the end of the day submit the completed form. The Department will provide copies to the Contractor upon request.
558.03.14 Drilled Shaft Concrete
Place concrete in the drilled shaft as specified for either dry excavations or wet excavations.
558.03.15 Shaft Testing and Acceptance
558.04 Method of Measurement
558.04.1 Drilled Shaft
Drilled shaft will be measured by the linear foot (m) of shaft between the actual bottom elevation of the drilled shaft and the top of shaft elevation shown on the contract.
558.04.2 Drilled Shaft Concrete
Drilled shaft concrete will be measured by the cubic yard (m
558.04.3 Reinforcing Steel
Drilled shaft reinforcing steel will be measured by the pound (kg) in accordance with Subsection 555.04. 558 – DRILLED SHAFTS 2020 EDITION V5.1 558-6
558.04.4 Drilled Shaft Casing
Permanent drilled shaft casing will be measured by the pound (kg) of permanent casing installed as shown in the contract or as directed by the Project Manager in writing. If the Contractor elects to oversize the casing diameter, measurement will be based on the diameter shown in the contract.
558.04.5 Temporary Casing
When the Contract contains the pay item Temporary Drilled Shaft Casing, temporary drilled shaft casing will be measured by the linear foot (m) of temporary casing measured from the higher of the ground or water surface elevation down to the bottom elevation of the installed temporary casing.
558.04.6 CSL Tubes and Testing
Include all costs associated with furnishing and installing, and grouting CSL access tubes and any required extensions and providing a power source in the Drilled Shaft pay item. No measurement or payment will be made for construction delays resulting from the initial CSL drilled shaft testing. The Department will extend the contract time by 1 day for each day over 12 calendar days required to complete the CSL drilled shaft testing. The Department will pay the costs for the initial CSL drilled shaft testing. If a defect is found based on the CSL drilled shaft testing, coring, or other physical investigation, the contractor is responsible for all costs associated with the physical investigation, engineering design, shaft repairs and any construction delay costs. Pay the costs of CSL drilled shaft retesting of the repaired drilled shafts. If no defect is found in the drilled shaft based on the physical investigation, the investigation will be considered extra work and paid for in accordance with Subsection 109.04 , and considered for time adjustment in accordance with Subsection 108.07.
558.05 Basis of Payment
Payment for the completed and accepted quantities is made under the following: Pay Item Pay Unit Drilled Shaft Linear Foot (m) Reinforcing Steel Pound (kg) Drilled Shaft Casing Pound (kg) Drilled Shaft Concrete Cubic Yard (m3) Temporary casings remain the property of the Contractor. If the Contract contains the pay item Temporary Drilled Shaft Casing, all costs associated with temporary casing including, but not limited to, procurement, fabrication, transportation, installation, and removal, are included in the pay item Temporary Drilled Shaft Casing. If the Contract does not contain the pay item Drilled Shaft Temporary Casing, no measurement or payment will be made. Include all costs associated with temporary casing including, but not limited to, fabrication, providing, transporting, installation and removal in the Drilled Shaft pay item. Payment for obstruction removal will be made on a force account basis. Air-lifting is not measured separately for payment. Include costs for all airlifting in the Drilled Shaft Item.