513Retaining Walls

NJ · 2019 (rev. 2022-12-21) Standard Specifications✓ Full text on BuildSpecBook pages 296–298 Save this section

Ask about Section 513

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

513.01DESCRIPTION

This Section describes the requirements for constructing cast-in-place retaining walls, prefabricated modular wall systems, mechanically stabilized earth (MSE) wall systems, and other alternate retaining wall systems.

513.02MATERIALS

.01 Materials

Provide materials as specified: Coarse Aggregate (No. 57) ................................ ................................ ................................ ............................ 901.03 Soil Aggregate (I-9) ................................ ................................ ................................ ................................ ...... 901.11 Soil Aggregate (I-15) ................................ ................................ ................................ ................................ .... 901.11 Concrete ................................ ................................ ................................ ................................ ....................... 903.03 Mortar ................................ ................................ ................................ ................................ ..................... 903.08.01 Curing Materials ................................ ................................ ................................ ................................ ........... 903.10 Precast Concrete Units ................................ ................................ ................................ ................................ .. 904.02 Reinforcement Steel ................................ ................................ ................................ ................................ ...... 905.01 Welded Wire Reinforcement ................................ ................................ ................................ .................... 905.01.03 Structural Steel Plates and Bars ................................ ................................ ................................ ................ 905.01.04 High-Strength Steel Bolts ................................ ................................ ................................ .............................. 908.02 Coal Tar Epoxy Paint ................................ ................................ ................................ ............................... 912.01.03 Preformed Joint Filler ................................ ................................ ................................ ................................ ... 914.01 Joint Sealer (Hot-Poured) ................................ ................................ ................................ .............................. 914.02 Subsurface Drainage Geotextile................................ ................................ ................................ ..................... 919.01 HDPE Geomembrane ................................ ................................ ................................ ................................ .... 919.05 Waterstops ................................ ................................ ................................ ................................ .................... 919.06 Provide soil reinforcement strips according to ASTM A 572, Grade 65. Provide tie strips according to ASTM A 1011, Grade 50. For MSE Walls, use either Soil Aggregate, I-15 or Coarse Aggregate, No. 57. For Prefabricated Modular Retaining Walls and T-Wall, use either Soil Aggregate, I-9 or Coarse Aggregate, No. 57.

.02 Equipment

Provide equipment as specified: Vibrator ................................ ................................ ................................ ................................ ...................... 1005.04 Concrete Batching Plant ................................ ................................ ................................ .............................. 1010.01 263 Concrete Trucks ................................ ................................ ................................ ................................ .......... 1010.02

513.03CONSTRUCTION

.01 Retaining Walls

A.Working Drawings. At least 30 days before beginning the work, submit working drawings for approval that include,

at a minimum, the following:

1.Design calculations giving complete information as to the proposed method of fabrication and erection of

precast units and related components.

2.General notes, design parameters, soil characteristics, and factors of safety.
3.An elevation view of the wall showing elevations at the top of the wall, the beginning, and at the end.
4.Plan view of the wall showing the offset from the construction baseline to face of wall units at all changes in

horizontal alignment.

5.Distance from front of wall to the extreme limit of module.

6 Typical sections of the wall indicating how internal drainage and surface drainage behind the wall is handled. Typical cross sections of cut and fill sections. Limits and extent of select granular backfill material placed above original ground. Location of proposed ground line.

7.Panel or unit length and size and designations.
8.A numbered panel layout for fabrication and erection purposes.
9.Typical panels, as well as special panels, such as at bends; dimensions necessary to construct the member; the

location of reinforcement steel in the member; and th e location of reinforcement attachment devices that are embedded in the panels.

10.Designation of breaks in vertical alignments and elevations at whole stations and at 25 foot increments and

treatment.

11.All details for footings and leveling pads, including step details, locations, and elevations, and actual maximum

bearing pressure.

12.Architectural details, such as special facing finish, texture, and color.
13.The location of the proposed final ground line.
14.ROW limits and their relationship to the wall, with offsets and stations to corners.
15.Location of any noise walls or sign structures near the wall by station and offsets.
16.Centerline of any drainage structures or utilities behind and passing through or under walls.
17.Location of all piles on any adjoining structure’s foundation plans with details to avoid any conflict.
18.Connections to barriers, copings, signs, lights, railing, fences, noise barriers, or any other element.
19.Details for the construction of walls and soil reinforcemen t around obstructions including bridge supports,

drainage facilities, sign footings, or any other element.

20.Details for required electrical systems, including highway lighting bases, junction boxes, and conduit.
21.Limits and extent of common structure volume, such as excavation, volume of concrete, reinforcement steel,

and backfill.

22.Numbers and types of precast units/panels.
23.Manufacturer’s recommendations, including suggested sequence of construction.
B.Shipping, Handling, and Storing. Ensure that the precast units have cured for at least 72 hours and have attained

the minimum 28 day compressive strength before shipping. Provide galvanized handling devices according to ASTM A 123. Store, transport, hoist, and handle units to prevent cracking or damage. After galvanizing, coat attachment surfaces not to be embedded in concrete with coal tar epoxy paint. Replace or repair units damaged by improper storing, transporting, or handling.

C.Wall Foundation. Excavate as specified in 202.03.03. Shape and compact the underlying material to produce a

firm, even surface. Obtain RE approval before finishing excavation. If the RE determines that the bottom of the excavation is unstable, undercut, backfill, and compact as directed by the RE. Grade the foundation for the structure level for a width that exceeds the length of the soil reinforcement by at least 2 feet. Place concrete, as specified in 504.03.02.D, for an unreinforced concrete leveling footing, or provide a precast concrete leveling pad according to the manufacturer’s recommendations. Before placing wall units, install underdrains and drainage pipes. 264

D.Installing. Provide 2 copies of the manufacturer’s recommendations to the RE. If a section of wal l is to be

cast-in-place, construct the section as specified 504.03.02.D. Obtain RE approval of the foundation for the structure before beginning erection. Install the units according to the manufacturer’s recommendations. For erection, handle units with lifting devices set into the upper edge of the panels. Place units in a horizontal course. Do not place the subsequent course until the previous course is backfilled within 2 inches of the top of the course. Provide external bracing for the initial course. While erecting each course, examine line, and grade, and correct deviations to prevent cumulative inaccuracies in alignment. Ensure vertical tolerance and horizontal ali gnment tolerance does not exceed 1/2 inch, when measured along a straightedge. Install joint filler and rubber pads according to the manufacturer’s recommendations. Close joints at corners or angle points. Ensure that all wall units above the first cours e interlock with the lower courses. Ensure vertical joint openings on the wall’s front face do not exceed 3/4 inch. Ensure the front face vertical joints has 12 inch wide strips of subsurface drainage geotextile behind each joint starting 2 feet below grade.

E.Back of Wall Drainage. Place a stone pocket, subsurface drainage geotextile, and an 8 inch corrugated steel

underdrain pipe as shown on the Plans. When constructing weep holes, place ports or vents for equalizing hydrostatic pressure below low water. Use 4 inch PVC or unreinforced concrete drain pipe as forms for weep holes through concrete.

F.Backfilling. For MSE walls, place reinforcement perpendicular to the face of the wall , unless otherwise shown on

the Plans or directed. Before placing soil reinforcement, compact the backfill material as specified in 513.03.01.G. For modular bin walls, fill wall units 4 feet o r less in height in 1 lift and then thoroughly compact with a vibratory tamping device. Fill wall units more than 4 feet in height in 2 approximately equal lifts and thoroughly compact after each layer is placed. Backfill after erecting each course of wal l units. Verify that the reinforcements and wall units are not damaged, disturbed, or misaligned while backfilling. Correct misalignment and remove and replace damaged units of the wall units before placing the next course. Backfill using one of the following materials:

1.Soil Aggregate. Do not exceed 10 inches loose measurement for the maximum lift thickness of the backfill.

Decrease this lift thickness to obtain the specified density. The ME will determine the optimum moisture content as specified in AASHTO T 99, Method C. Ensure that the moisture content of the backfill is uniform throughout each layer and has a placement moisture content that is less than or equal to the optimum moisture content. Remove and rework backfill that has a placement moisture content in excess of the optimum moisture content until the moisture content is uniformly acceptable throughout the entire layer. Ensure that backfill placed within 1 foot of a drainage structure or utility does not have any particle greater than 3 inches in maximum dimension.

2.Coarse Aggregate. Do not exceed 8 inch lift thickness of coarse aggregate. Place subsurface drainage

geotextile at the interface of the coarse aggregate and regular roadway materials and embankments. At each reinforcement strip level, level and compact the coarse aggregate before placing the reinforcement.

G.Compacting. Compact backfill material without damaging, disturbing, or misaligning the wall units before placing

the next block level. Roughly level each course of backfill to an elevation approximately 2 inches above the level of the next course of units. Compact in a direction parallel to the wall.. For MSE walls, do not use sheepsfoot or grid-type rollers for compacting backfill within the limits of the soil reinforcement. Compact for the specified material as follows:

1.Soil Aggregate. With the exception of the 5 foot zone directly behind the units, compact soil aggregate with

large, smooth drum, vibratory rollers using the density control method as specified in 203.03.02.B.4. Within 5 feet of the wall, use small, single or double drum, hand operated, walk -behind vibratory rollers, or walk-behind vibrating plate compactors. Make at least 3 passes.

2.Coarse Aggregate. To provide the proper density of the broken stone, compact by making at least 4 passes

with a vibratory roller that has a total operating weight of 8 to 10 tons. Set the roller in the vibratory mode between 1.5 and 2.5 miles per hour.

Get an email when 513 changes

New Jersey revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Road and Bridge Construction, 2019 (rev. 2022-12-21) Edition. Pages 296–298 of 651. View official source ↗

Ask about this section

Scoped to New Jersey 2019 Standard Specifications for Road & Bridge Construction, Section 513 — Retaining Walls. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.