302Processing, Placing, and Compacting Existing Pavement

NM · 2019 Standard Specifications✓ Full text on BuildSpec Save this section

Ask about Section 302

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

SECTION 302: PROCESSING, PLACING, AND COMPACTING EXISTING PAVE MENT

302.1 Description

This Work consists of processing , placing, and compacting exist ing pavements.

302.2 Materials

The following gradation requirements apply: Table 302.2:1 Gradation Requirements Sieve size (inch) % passing 2 95–100 1 1/2 90–100

302.3 Construction Requirements

The Contractor shall: 1. Process the existing pavement in place to a homogeneous mixt ure and a depth in accordance with the Plans. 2. Mix the existing pavement and underlying aggregate to a homo geneous mixture and a depth in accordance with the Plans. 3. Compact existing processed material to at least 96% of maxim um density as determined by AASHTO T 180 (Modified Proctor), Method D (TTCP M odified). The Department will take field density tests and gradation samples at random locations. The Department will use nuclear testing methods to determine i n-place densities in accordance with AASHTO T 310 and TTCP procedures for wet densit y moisture correction.

302.3.1 Surface Tolerance

The Department will allo w a surface tolerance of ½ inch within ten (10) feet.

302.3.2 Sampling and Testing

The Department shall sample and test the existing processed mat erial in accordance with the Department’s “Minimum Testing Requirements” for Processing, Placing and Compacting Existing Pavement “Section 302.”

302.4 Method of Measurement

The Department will measure Processing, Placing, and Compacting Existing Pavement using the dimensions shown in th e Contract or approved modifica tions.

302.5 Basis of Payment

Pay Item Pay Unit Processing, Placing, and Co mpacting Existing Pavement Square Yard

302.5.1 Work Included in Payment

The Department will consider as included in the payment for th e pay item(s) listed in this Section 302: Processing, Placing, and Compacting Existing Pavem ent Page 129 section and will not measure or pay separately for the followin g Work: 1. All labor, materials, equipment and any other incidentals wi ll be included in this pay item. Section 303: Base Course Page 130

Referenced in this section

Get an email when 302 changes

New Mexico revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: New Mexico Standard Specifications for Highway and Bridge Construction, 2019 Edition. View official source ↗

Ask about this section

Scoped to New Mexico 2019 NMDOT Standard Specifications for Highway & Bridge Construction, Section 302 — Processing, Placing, and Compacting Existing Pavement. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.