109.01 Measurement of Quantities. The measurement and determination of the number of units of each pay
item will be made in general as prescribed hereinafter and specifically as set out under the “measurement” Subsection of the Section for each pay item. Unless otherwise specified, measurement will be made when the work is in place, complete, and accepted, measurements will be made of the actual work performed, except work outside the design limits or other adj usted or specified limits (staked limits) will not be measured. Structures will be measured to the neat lines shown on the plans or to approved lines that have been adjusted to fit field conditions. After the items of work are completed and before final p ayment is made, the quantities of the various items of work performed will be determined as the basis for final settlement for all other than lump sum contracts. In the case of unit price items, the actual amount of work performed and materials used will b e paid for according to these specifications, as shown by the final measurements, unless otherwise specified. Actual authorized quantities of work satisfactorily completed under the contract will be measured according to International System of Units (SI) measures for metric unit contracts, and United States Standard Measures for English unit contracts. Unauthorized wasting of material will be deducted and only such quantities as are actually incorporated in the completed work will be included in the final progress payment. Unless otherwise specified, longitudinal measurements for area computations will be made horizontally and no deductions will be made for individual fixtures having an area of 1 m2 (9 ft2) or less. Unless otherwise specified, transverse measurements for area computation will be the neat dimensions shown on the plans or ordered in writing. In computing volumes of excavation, embankment and borrow, the average end area method will be used unless otherwise specified. All items which are measured by the linear meter (linear foot) such as pipe culverts, underdrains, guardrails, etc., will be measured parallel to the base or founda tion upon which such structures are placed, unless otherwise shown on the plans. When water meters are requir ed, the accuracy of the meters will be checked by comparing the actual mass of approximately 4,000 L (1,000 gal), or 4 m3 (125 ft3), as metered with the calculated mass using as a reference density 1.00 kg/L (8.33 lb/gal) or 1,000 kg/m3 (62.4 lb/ft3 ). Unl ess otherwise specified, provide water meters accurate to within 2% of the indicated amount. The frequency of checking water meters will be determined. The term “metric ton” shall mean 1,000 kg. The term “ton” shall mean the short ton consisting of 2,000 lb avoirdupois. Weigh all materials which are specified for measurement by the metric ton (ton) on certified scales set at designated locations. Weigh all materials on platform scales with the following exception: In lieu of platform scales, provide an aut omatic printer system which will print the masses of the material delivered, provided the system is used in conjunction with an approved automatic batching control system. Such evidence shall be evidenced by a weigh ticket for each load. Provide not less t han ten 25 kg (50 lb) standard masses for testing the scales. Furnish scales with a certificate of inspection by the Bureau of Weights and Measures. The scales shall be tested and inspected by the Bureau of Weights and Measures and a new inspection certif icate required every twelve months or as often as deemed necessary, and after each scale move, in order to insure the accuracy of the scales. The cost of the initial scale inspection will be borne by the Department. Additional inspections shall be at own expense. Notify the Engineer a minimum of 10 working days before the date needing a scale inspection. The Engineer will verify the scale is ready for inspection and notify the Bureau of Weights and Measures. Provide platform scales of sufficient size and c apacity to weigh, in one operation, the entire loaded vehicle. Combination vehicles may be weighed as separate units, provided the connecting device between vehicles is so constructed that no mass other than that of the device itself is transmitted to eith er vehicle. When combination vehicles are used, level approaches to and from the scale platform for sufficient distance to accommodate that portion of the combination vehicle that is off the scale platform. In instances where combination vehicles are weigh ed, level the approaches to and from the scale platform with the scale platform for a minimum distance of 15 m (50 ft) from each end of the scale platform. 109 MEASUREMENT AND PAYMENT 66 For determining pay quantities provide automated scales that print delivery tickets with gross weight, tare weight, net weight, accumulated total, date, pit description, description of material, and contract number. The automated scale software shall be capable of handling multiple bid items. If combination vehicles are utilized, make provisions to insure that all braking devices are disengaged during weighing operations as insurance against stresses being transmitted between either vehicle. Construct the scale pit of sufficient width to permit access to all scale components for purposes of inspect ion, repair, cleaning, and adjusting. Use support members for platform scales per the manufacturers recommendations. Equip platform scales with weatherproof housing so constructed as to protect the recording device and permit the weighmaster convenient a ccess to all beams and dials. Provide housing not less than 1.8 m (6 ft) wide, 2.4 m (8 ft) long and 2.1 m (7 ft) high, and with 2 windows, adjustable for ventilation, one facing the scales, and equip with a suitable shelf. Provide heating, cooling, and el ectric lights when requested. A hopper weight system of an approved type may be used. Furnish the hopper weight system with one master counter to run continuously and one remote counter which will print the mass in individual loads, then reset to zero automatically. Place the remote unit in a weatherproof house with 2 windows. One window shall face the point of loading and the hopper weight system. Also equip this window with a suitable shelf. Supply a controlled method of heating for cold weather operatio ns. If a hopper weight system is used, adhere to the following procedures:
a.Calibrate the hopper weight system against the platform scales, which must have a certificate of inspection.
b.At the beginning and middle of each shift, or as requested, r eweigh 2 consecutive loads of material weighed over the hopper weight system on the platform scales. The total mass indicated by the hopper weight system on the 2 loads must check with the platform scale mass within 0.5%. If the hopper weight system weigh out of this tolerance, weigh all loads on the platform scales until the condition is rectified.
c.Use consecutively numbered, individual weigh tickets with the hopper weight system masses stamped by the remote counter. Unless otherwise specified, weigh materials shipped by rail over the authorized project scales before incorporation into the work. Timber will be measured by the cubic meter (1,000 feet board measure, Mfbm) actually incorporated in the structure with no allowance for any waste except bev eled ends. Measurement will be based on nominal widths and thicknesses, and the extreme length of each piece. When a complete structure or structural unit (in effect, “lump sum” work) is specified as the unit of measurement, the unit will be construed to include all necessary fittings and accessories. Haul materials for which measurements are obtained by the cubic meter (cubic yard) “loose measurement” or “measured in the vehicle” in approved vehicles and measured therein at the point of delivery. No allowance will be made for the settlement of material in transit. Vehicles for this purpose may be of any acceptable size or type, provided that the body is of such shape that the actual delivered contents may be readily and accurately determined and will remain constant. Unless all approved vehicles on the work are of uniform capacity, each vehicle must bear a plainly legible identification mark, indicating its specified approved capacity. Load all vehicles to at least their water level capacity and level loads when the vehicles arrive at the point of delivery. Loads not hauled in approved vehicles or of a quantity less than the specific approved quantity for the hauling vehicle will be subject to rejection and no compensation will be allowed for the haulin g of the material. The unit of measurement for cutback asphalts, emulsified asphalts , and asphalt cements , when specified to be measured for payment, will be by the metric ton (ton) or liter (gallon). Quantities of bituminous binders wasted or disposed of in a manner not called for under these specifications, or remaining on hand after completion of the work, will not be paid for. MEASUREMENT AND PAYMENT 109 67 When permitted, pay quantities of bituminous binder may be determined from volumetric measurements of the bituminous binder , in which case deliver the bituminous binder in calibrated tanks and accompany each tank with its proper measuring stick and a calibration card signed by a sealer of weights and measures and pay quantities will be determined by the following procedure. The tank and stick calibrations shall be in English units for English unit contracts and metric units for metric unit contracts. Reduce volumetric measurements at any temperature to the volume the material would occupy at 15.6 °C (60 °F), before converting the volumetric measurements to mass. Use the following tables to convert volumes from liters (gallons) to mass: Average Masses and Volumes of Cutback Asphalt at 15.6 °C (60 °F) Grade MC or SC L/metric ton (Gal/ton) kg/L (lb/gal) 70, 70NV ................................ ............ 1,056 (253) ................................ .......... 0.947 (7.9) 250 ................................ ................ 1,039 (249) ................................ .......... 0.959 (8.0) 800 ................................ ................ 1,022 (245) ................................ .......... 0.983 (8.2) 3000 ................................ ............... 1,005 (241) ................................ .......... 0.995 (8.3) Average Masses and Volumes of Asphalt Cement at 15.6 °C (60 °F) Grade L/metric ton (Gal/ton) kg/L (lb/gal) PG 58 -28, PG 64 -16, PG 64 -22, PG 64 -28NV ................. 981 (235) ................................ ........... 1.019 (8.5) PG 64 -28NVTR, PG 70 -16, PG 76 -22NV .................... 977 (234) ................................ .......... 1.025 (8.55) PG 76 -22NVTR ................................ ........ 972 (233) ................................ ........... 1.031 (8.6) Average Masses and Volumes of Emulsified Asphalt at 15.6 °C (60 °F) Type L/metric ton (Gal/ton) kg/L (lb/gal) All grades ................................ ........... 1,005 (241) ................................ .......... 0.995 (8.3) When converting the volume of cutback asphalt, asphalt cement , or emulsified asphalt at any temperature to the volume at 15.6 °C (60 °F) use a conversion factor for correlation. Said conversion factors shall be those prescribed in “The Asphalt Institute” publication of “Manual Series No. 6.” Rental of equipment will be measured by time within 0.5 hours of actual working time and necessary traveling time of the equipment within the limits of the project. If equipment has been ordered on the job on a standby basis, half-time rates for the equipment will be paid. When special equipment has been ordered in connection with force account work, travel time and transportation to the project will be measured as hereinafter ou tlined. For the use of special equipment moved in on the work and used exclusively for extra work paid for on a force account basis, the rental rates determined as provided in Subsection 109.03, and the cost of transporting the equipment to the location of the work and its return to its original location will be paid, all according to the following provisions:
a.The original location of the equipment to be hauled to the location of the work will be agreed to in advance.
b.The State will pay the costs of loading and unloading such equipment.
c.The cost of transporting equipment in low bed trailers shall not exceed the hourly rates charged by established haulers.
d.The rental period shall begin at the time the equipment is unloaded at the site of t he extra work, shall include each day that the equipment is at the site of the extra work, excluding Saturdays, Sundays and legal holidays unless the extra work is performed on such days, and shall terminate at the end of the day on which the Engineer dire cts the Contractor to discontinue the use of such equipment.
e.Should the Contractor desire the return of the equipment to a location other than its original location, the State will pay the cost of transportation by the above provisions, provided such payment shall not exceed the cost of moving the equipment to the work.
f.Payment for transporting and loading and unloading equipment as above provided will not be made if the equipment is used on the work in any other way than upon extra work paid for on a force account basis. Material wasted or disposed of in a manner not called for under the contract, material not unloaded from the transporting vehicle, material placed outside of the limits indicated or given on the plans, or material remaining on hand after completion of the work will not be paid for except as otherwise provided. 109 MEASUREMENT AND PAYMENT 68 109.02 Scope of Payment. Unless otherwise provided under “Basis of Payment,” payments will be made for the actual quantities of contract items performed according to the pla ns and specifications, and if, upon completion of the construction, these actual quantities show either an increase or decrease from the quantities given in the proposal, the contract unit prices will still prevail, except as provided in Subsection 104.02. Except as provided in 107.16, accept the compensation, as herein provided, in full payment for the following:
a.The work complete, including all supervision, labor, material, tools, equipment and incidentals necessary for all work contemplated and emb raced under the contract;
b.Any loss or damage due to the nature of the work, the action of the elements, strikes or lockouts;
c.Accidents to employees or the public, or both;
d.Unforeseen difficulties or obstructions which may arise or be encount ered during the prosecution of the work;
e.All risks whatsoever connected with the work under contract until it is accepted;
f.All expenses incurred by or in consequence of, the suspension or discontinuance of the prosecution of the work as herein specified, and in completing the work and the whole thereof, including the carrying out of all the requirements of these “general requirements and covenants” in an acceptable manner according to the plans and specifications. If the “Basis of Payment” clau se in the specifications relating to any unit price in the proposal requires that the said unit price cover and be considered compensation for certain work or material essential to the item, this same work or material will not be measured or paid for under any other pay item except as provided for in Subsection 104.04. Any partial payment or payment of any retained percentage, except by and under the approved final progress payment and voucher, in no way shall affect the obligation to repair or renew any d efective parts of the construction or to be responsible for all damages due to such defects. Those Subsections containing pay items of bituminous materials are subject to the following requirements: It is agreed by the parties to the contract that (a) in case the bituminous material does not conform to the requirements set forth in Section 703, damage will be sustained by the Department, and that (b) it is extremely difficult to ascertain the actual damage which the Department will sustain; therefore, it is agreed the Contractor shall pay to the Department as liquidated damages or the Department, at its option, may deduct from any money due or to become due the Contractor from the Department an amount set forth in the following schedule: Number of Demerits Liquidated Damage, $ per metric ton (ton) *** From Section 703 Cutback Asphalts, Emulsions, PG Grades (a) PG Grades (b) 1-2 ................................ .................... 12 (10) ................................ ........................ 22 (20) 3-5 ................................ .................... 22 (20) ................................ ........................ 44 (40) 6-9 ................................ .................... 34 (30) ................................ ........................ 66 (60) 10-14 ................................ .................. 56 (50) ................................ ...................... 110 (100) 15-20 ................................ ................ 110 (100) ................................ .................... 220 (200) 21-30 * ................................ .......................... 75% of the cost of the asphalt product ** 31-40 * ................................ ......................... 100% of the cost of the asphalt product ** 41* or more ................................ ........................... Value and deduct to be determined
a.Performance Graded Asphalts 58 -28, 64 -16, 64 -22, and 70-16.
b.Performance Graded As phalts 64 -28NV, 64 -28NVTR, 76 -22NV, and 76-22NVTR. * Remove and replace material shown by test to have 21 or more demerits. At the option of the Engineer, material having 21 or more demerits may be left in place; if such material remains in place, the deme rits specified above shall be assessed as liquidated damages for said material. Material removed will not be paid for and the removal thereof will be at the Contractor's expense. ** Cost of the asphalt cement will be based on the prices established under Subsection 402.05.01. Cost of the cutback asphalt or emulsified asphalt will be based on the Engineer’s Estimate or the Contractors bid, whichever is greater, per metric ton (ton) of the asphalt product. When a bid item is not provided for cutback asphalt or emulsified asphalt , the cost of the asphalt product will be specified in the Special Provisions. *** Liquidated damages for emulsified asphalts will be assessed per the diluted ton nage used. When a bid item is not provided for the bituminous material, the liquidated damages will be assessed on the tonnage calculated from the theoretical application rate or the Job Mix Formula. MEASUREMENT AND PAYMENT 109 69 Those Subsections containing pay items of Type 2, Type 2C, or Type 3 plantmix products are subject to the following requirements: It is agreed by the parties to the contract that (a) in case the plantmix product does not conform to the Indirect Tensile Strength requirements set forth in Section 401, damage wi ll be sustained by the Department, and that
b.it is extremely difficult to ascertain the actual damage which the Department will sustain; therefore, it is agreed the Contractor will pay to the Department as liquidated damages or the Department, at its op tion, may deduct from any money due or to become due the Contractor from the Department, $0. 80 per metric ton ($0. 72 per ton) per demerit for each metric ton (ton) of plantmix product placed. Remove and replace material shown by tests to have 21 or more de merits. Material removed will not be paid for and removal thereof will be at the Contractor’s expense. At the option of the Engineer, material having 21 or more demerits may be left in place. If material having 21 or more demerits is allowed to remain in p lace, liquidated damages will be determined by the Department.
109.03 Force Account Work. On all force account work, submit the plan of work to be followed, the equipment
to be used, and the amount and class of labor to be employed for review. Do not beg in Force Account Work until receiving approval in writing. Work specified and performed on a force account basis will be paid for as follows:
a.Labor. The cost of labor will be paid for the workmen (including foremen when authorized by the Engineer), used in the actual and direct performance of the work. The cost of labor, whether the employer is the Contractor, subcontractor, or other forces, will be the sum of the following:
1.Actual Wages Plus Vacation Pay plus Zone Rates. The actual wages and zone rates paid, plus vacation pay, which shall not include any employer payments to, or on behalf of, workmen for health and welfare, pension, and similar purposes.
2.Labor Surcharge. To the actual wages, plus vacation pay, as defined above, will be added a labor surcharge, which shall constitute full compensation for all payments imposed by State and Federal laws. The labor surcharge will be calculated for each calendar year by the Department’s Construction Division. The percentage may be obtained by contac ting the Construction Division in the Department’s General Headquarters, 1263 South Stewart Street, Carson City, Nevada 89712, phone (775) 888-7460.
3.Fringe Benefits. To the sum of paragraph 1. “Actual Wages Plus Vacation Pay plus Zone Rates,” shall be added all other payments made to or on behalf of the workmen as required by collective bargaining agreements, or as otherwise provided in the Special Provisions. Provide a complete Fringe Benefit Statement (NDOT Form 0 52-062) for each job classification u tilized on the contract.
4.Subsistence and Travel Allowance. Subsistence and travel allowance paid to such workmen as required by collective bargaining agreements. To the total of the direct costs computed above, there will be added a markup of 25%.
b.Materials. Materials accepted and used in the work will be paid for at the actual cost of such materials, to which cost shall be added an amount equal to 20% of the sum thereof.
c.Equipment. For any machinery or special equipment, the use of which h as been authorized by the Engineer, the Contractor will be paid for the use of equipment in the manner hereinafter specified, regardless of ownership and any rental or other agreement, if such may exist, for the use of such equipment entered into by the Co ntractor. Rental rates will be determined as follows:
1.The base rates shall be those established by Penton Business Media, Inc. doing business as Equipment Watch thereto entitled “Enterprise Edition of Rental Blue Books” available from Equipment Watch, 1735 Technology Drive, Suite 410, San Jose, CA 95110 -1313, phone (408) 467 -6700 or at www.equipmentwatch.com. 109 MEASUREMENT AND PAYMENT 70 The hourly rate to be paid shall be the monthly rate multiplied by an average regional adjustment factor of 1.05, divided by 176, multiplied by the appropriate rate adjustment factor, plus the estimated operating cost per hour shown therein.
2.Attachments (e.g. tractor with ripper and dozer or tractor with loader and backhoe) will be included in the hourly rental rate only when deemed essential to the work as determined by the Engineer. When multiple attachments are approved for use and are being used interchangeably, the attachment having the higher rental rate shall be the only one included for payment.
3.No direct payment will be made for ne cessary accessories (including replenishing blades, augers, teeth, hoses, bits, etc.) if not listed in the Rental Rate Blue Book.
4.No compensation will be allowed for shop tools having a daily rental rate of less than $10 as set forth in Section 18 of t he Rental Rate Blue Book.
5.Equipment obtained through a third party rental agreement may be paid by the rate established by invoice plus a markup of 10% will be added thereto. Rental rate shall be comparable to other rental rates in the area. When the invoice specifies that the rental rate does not include fuel, lubricants, repairs and servicing, the Rental Rate Blue Book hourly operating cost for each hour the equipment is operated will be added. A copy of the “Rental Rate Blue Book for Construction E quipment” is available for inspection by interested parties at the office of the Resident Engineer and in the Headquarters Construction Division Office in Carson City. Additionally, a copy of the “Rental Rate Blue Book for Older Construction Equipment” is available for inspection in the Headquarters Construction Division Office. Interested parties desiring to purchase these publications should direct their inquiries directly to Equipment Watch at the address stated above. If ordered to use equipment not l isted in the aformentioned publications, a suitable rental rate for such equipment will be established. Furnish any cost data which might assist in the establishment of such rental rate. Except as provided in Subsection 109.01, payment will be made for th e actual time that such equipment is in operation on the work, to which rental sum 20% shall be added. Authorized standby time for idle equipment will be paid for at 50% of the “monthly rate multiplied by an average regional adjustment factor of 1.05, div ided by 176, multiplied by the appropriate rate adjustment factor,” rounded to the nearest $0.10. No operating cost, markup, overhead or profit will be added. The rental rates paid as above provided shall include the cost of fuel, oil, lubrication, suppli es, small tools, necessary attachments, repairs and maintenance of any kind, depreciation, storage, insurance and all incidentals. If performing force account work, supply a complete Force Account Equipment Listing (NDOT Form 040-033) for each piece of eq uipment utilized.
d.Subcontracted Work . Payment for subcontracted work may be made at the actual cost as evidenced by copies of invoices from the subcontractor performing the work. An additional 5% compensation will be paid on subcontracted work evidenc ed by invoice for administrative costs and profit. When payment for subcontracted work is made under paragraphs (a), (b) , and (c) above , reach agreement with subcontractor as to the distribution of the payment made. No additional payment will be made by reason that the work is performed by a subcontractor.
e.Bond Costs . An additional 1% of the total labor, material, equipment and subcontracted compensation will be paid for increase in bond cost due to the force ac count work. No additional allowance will be made for general superintendents, the use of small tools or other costs for which no specified allowance is herein provided. MEASUREMENT AND PAYMENT 109 71 At the end of each day the Contractor’s representative and the Engineer shall compare records of the cost of the work to be done as ordered on a force account basis. No payment will be made for labor performed on force account work until furnishing certified copies of payrolls covering that period when the force account work was pe rformed. The payrolls shall indicate name, classification, dates, daily hours and hourly rate for each workman. Furnish copies of the suppliers extended invoices, including transportation charges. However, if materials used on the force account work are n ot specifically purchased for such work, but are taken from the Contractor’s stock, then in lieu of the invoices, furnish an affidavit certifying that such materials were taken from stock, that the quantity claimed was actually used, and that the price and transportation claimed represent the actual cost.
109.04 Asphalt Escalation. The use of the price adjustment provisions as developed and implemented herein
are intended to minimize the cost effects of price uncertainty to the Contractor and the Departmen t for “Asphalt Cement” used in the construction of the contract. The price adjustment provisions are not intended to serve as a guarantee for full compensation for “Asphalt Cement” price fluctuations but are intended to be a sharing, by the Department, in a portion of the Contractor’s risk which could result from potentially volatile price fluctuations that might occur throughout the duration of the contract. The price adjustment provisions do not serve to relieve the Contractor of risks associated with fl uctuation in prices beyond the amount adjusted by the provisions. This adjustment will be full compensation for any and all price fluctuations, including but not limited to taxes, transportation, and delays. The price adjustment provisions are only applic able to “Asphalt Cement;” they are not applicable to cutback asphalt or emulsified asphalt. The term “Asphalt Cement” as used herein is applicable to PG grades as specified in Subsection 703.03.02. The progress payment will be adjusted upward or downward, as calculated by the "Total Bi -Weekly Adjustment." These adjustments will be determined by the Department and will be based on selling prices for asphalt cement in the Poten & Partners Asphalt Weekly Monitor report. The sources used by the Department to determine the asphalt cement price at any given time will be the selling prices for Utah/Idaho/Nevada for non-modified paving grades and the California paving grades. The average of the high and low selling price for each of the following areas will be used : Utah - Salt Lake City area; Idaho - Boise area, Eastern markets, Northern markets [includes E.WA]; Nevada - Las Vegas area, Reno area; California - San Francisco area, Los Angeles area, Bakersfield area. Each of these nine average area prices is then use d to calculate the weekly average price; the weekly average price is used to calculate the "Basic Materials Index." The adjustment will be made by comparing a "Basic Materials Index" to a "Bi -Weekly Materials Adjustment Index." The method for making this c omparison is described in the following paragraphs:
a.A “Basic Materials Index” will be determined by the Department on a weekly basis. The “Basic Materials Index” in effect for the week a contract bid opening occurs will be the “Basic Materials Index” for that contract. The “Basic Materials Index” will be arrived at by averaging the Monday posting of the current week and the Monday posting of the three previous weeks. The “Basic Material Index” price for “Asphalt Cement” will be available on an informational basis to interested parties but said prices will not be available prior to the first regular business day of the week of the bid opening. The price may be obtained by contacting the Department’s Construction Division.
b.During the time that the "Asphalt Cement" is used on this contract, the Department will maintain selling prices in $/English ton (short ton) for asphalt cement to be used to obtain a "Bi -Weekly Mat erials Adjustment Index." The “Bi -Weekly Materials Adjustment Index” will be arrived at by averaging the Monday posting of the current week and the Monday posting of the three previous weeks and will be compared with the “Basic Materials Index” price to de termine a “Bi -Weekly Material Price Adjustment.”
c.The adjustment for said "Asphalt Cement" will be subject to increase or decrease in accordance with the following provision for "Asphalt Cement" price fluctuations exceeding 10%. The adjustment will be determined in accordance with the following formula for “Asphalt Cement” used during the progress payment: Total Bi -Weekly Adjustment = AQ 109 MEASUREMENT AND PAYMENT 72 For an increase in the Bi -Weekly Materials Adjustment Index exceeding 10% of the Basic Materials Index: A = [Bp — Bi (1.10)] F For a decrease in the Bi -Weekly Materials Adjustment Index exceeding 10% of the Basic Materials Index: A = [Bi (0.90) — Bp] F Where: A = “Bi-Weekly Material Price Adjustment” in dollars per metric ton (ton) of “Asphalt Cement” rounded to the nearest dollar. Bi = “Basic Materials Index” for the week in which the bid opening for the contract occurred (US $/short ton). This is calculated as noted in paragraph (a) above. Bp = “The Bi -Weekly Materials Adjustment Index” (US $/short ton) calculated for the progress payment period. This is calculated as noted in paragraph (b) above. F = 1.102311 = Factor to convert $/short ton to $/metric ton (1.00 to remain $/short tons). Q = Quantity in metric tons (tons) of “Asphalt Cement” calcula ted from the amount of plantmix paid for during the progress payment period. The quantity, in metric tons (tons), of “Asphalt Cement” will be calculated using the approved mix design and the following formula: Q = Wet tons used x % Asphalt / 100 [1 + (% Asphalt + % Mineral Filler) / 100]
d.The adjustment in compensation will also be subject to the following:
1.The compensation adjustments provided herein, will be shown separately on the progress payment. The Contractor shall be liable to the State for decreased compensation adjustments and the Department may deduct the amount thereof from any monies due or that may become due the Contractor.
2.The Department reserves the right to cancel the contract whenever the “Bi -Weekly Materials Adjustment Index” exceeds the “Basic Materials Index” by 75%. The contract may be canceled in part or in whole by the Department. If the Department elects to cancel the contract, in part or in whole, price adjustments will not be allowed for other than major bid items. Adjustments to major bid items will be in accordance with Subsection 104.02.
109.05 Fuel Escalation. The Fuel Escalation Clause, as described herein, may be enacted when requested by
the Contractor or deemed necessary by the Department. Enactment of the Fuel Escalation Clause will only be considered when the increase or decrease of the “Contract Price” for fuel as defined herein exceeds 25%. The use of the price adjustment provisions developed for the Fuel Escalation Clause are intended to minimize the cost effects of price uncertainty to the Contractor and the Department, for fuel used in the construction of this contract. The price adjustment provisions are not intended to compensate the Contractor for what would be considered normal da y-to-day fluctuations or seasonal changes. The price adjustment provisions are not intended to serve as a guarantee for full compensation for fuel price fluctuations but are intended to provide for a sharing, by the Department, in a portion of the Contract or’s risk which could result from unusual price fluctuations. The price adjustment provisions do not serve to relieve the Contractor of risks associated with fluctuation in prices beyond the amount adjusted by the provisions. If the Fuel Escalation Clause is activated, the clause will apply from the period of time the unusual price for fuel began, until the end of the contract. Fuel Escalation Clause Contract fuel costs will be adjusted upward or downward on a bi -weekly basis. To accomplish this adjustme nt the Department will determine, for each contract, a “Fuel Factor Percentage” that represents an estimated percent of fuel cost by type of construction. The “Fuel Factor Percentage” will be applied to each bi -weekly progress payment balance due (excludin g payments for stockpiled materials) to determine a “Bi -weekly Fuel Cost.” The bi -weekly fuel adjustment will be calculated by comparing a “Contract Price” to an “Adjustment Price” to determine a percent of increase or decrease. The adjustment will be det ermined by the Department using the average diesel (No. 2 fuel oil) price postings for Reno and Las Vegas as provided by Oil Price Information Services. The method for calculating the “Bi -weekly Fuel Adjustment” will be as described in the following paragr aphs: MEASUREMENT AND PAYMENT 109 73 (a) Fuel Factor Percentage (Ffp). The “Fuel Factor Percentage” (Ffp) will be an estimated fuel factor as a percentage of cost by type of construction as determined by the Department. The “Fuel Factor Percentage” will be specified in the Special Provi sions.
b.Bi-Weekly Fuel Cost (Bfc). The “Bi -Weekly Fuel Cost” (Bfc) will be the contract bi -weekly progress payment balance due (excluding payments for stockpiled materials) multiplied by the “Fuel Factor Percentage.”
c.Base Price (Bp). The “Base Pri ce” (Bp) for fuel will be determined weekly using the prices posted on Monday of each week.
d.Contract Price (Cp). The “Contract Price” (Cp) for fuel will be established for the week during which the bid opening is held. The “Contract Price” will be det ermined using the “Base Price” of fuel for the week of the bid opening averaged with the “Base Price” of fuel recorded for the previous three weeks.
e.Adjustment Price (Ap). The “Adjustment Price” (Ap) will be the average of the “Base Prices” recorded d uring the bi -weekly progress payment period.
f.Compensation Formula. The compensation payable as part of each bi -weekly progress payment will be subject to increase or decrease in accordance with the following provisions for fuel price fluctuations exceeding 10%. The bi -weekly fuel adjustment will be determined in accordance with the following formula: For an increase in fuel adjustment prices that exceed 10% of the “Contract Price” (Cp): A = [(Ap/Cp) - 1.10] Bfc For a decrease in fuel adjustment prices that exceed 10% of the "Contract Price" (Cp): A = [0.90 - (Ap/Cp)] Bfc Where: A = Bi-weekly fuel adjustment in dollars rounded to the nearest dollar. Ap = "Adjustment Price" Cp = "Contract Price" Bfc = "Bi-Weekly Fuel Cost"
g.Compensation Adjustment. The adjustment in compensation for fuel shall also be subject to the following:
1.Payment of compensation provided herein will be made as part of the progress payment. The Contractor shall be liable to the state for decreased compensation ad justments and the Department may deduct the amount thereof from any monies due or that may become due the Contractor.
2.The Department reserves the right to cancel the contract whenever the "Adjusted Price" exceeds the "Contract Price" by 75%. The contra ct may be canceled in part or in whole by the Department. If the Department elects to cancel the contract, in part or in whole, price adjustments shall not be allowed for other than major bid items. Adjustments to major bid items shall be in accordance wit h Subsection 104.02.
109.06 Partial Payment. Progress payments will be made once each month as the work satisfactorily
progresses. The progress payments will be based upon material in place, or on the job site and invoiced, and labor expended thereon. The total amount of the partial payment ascertained as allowable for payment will be paid each month until such time as a total of 85% of the contract price has been paid. The contract price will be adjusted upward or downward according to approved changes th roughout the life of the contract. Once 85% of the adjusted contract price has been paid, the Department may withhold retention in the amount of 5% of said adjusted contract price or $50,000, whichever is less, until the entire contract is completed satisf actorily and accepted by the Director. If the work in progress is being performed on a satisfactory basis, the Director may reduce the percentage retained if he finds that sufficient reasons exist for additional payment and has obtained written approval fr om every surety furnishing bonds for the work. Any remaining money must be retained until the entire contract is completed satisfactorily and accepted by the Director. Retention on Federal -Aid projects will be in accordance with 49 CFR 26.29(b)(2). 109 MEASUREMENT AND PAYMENT 74 Control of retent funds under the contract: Contract retent funds will be deposited with the State Treasurer in a Contract Retent Holding Account, identified by the contract number. The retent will be invested by the State Treasurer and interest earned on the balance will be credited to the retent account. If a Contractor wishes the retent funds to be placed in a bank designated by him, pursuant to NRS 408.383, he must notify the Department in writing at the preconstruction conference. The Contractor must us e a bank in the State of Nevada that meets the State Treasurer’s collateralization requirements as set forth in NRS 356.020. Upon receiving the Contractor’s choice of a bank to be used, the Department will submit the request to the State Treasurer for a de termination that the bank meets their collateralization requirements. If the bank does not meet the requirements, the Contractor will be required to select a bank that does. The funds will be deposited into a time certificate of deposit or a money market a ccount identified as “Nevada Department of Transportation Retent Funds for Contract No. * .” (* Contract number as assigned to each contract). A Contractor may substitute securities as specified in NRS 408.383(5) of a market value at least equal in value to the amount of the retent and receive payment of the retent. The Department will remain in control of the retent balance, including substituted securities, and the interest earned thereon, until final acceptance of the project and all certificates, guar antees, releases, affidavits and all other documentation required in the general provisions are received. Upon final acceptance, the retent and accrued interest thereon will be released to the Contractor. At the time of release of the contract retent princ ipal, interest earned through the end of the previous calendar quarter will also be paid. Interest earned in the final quarter will be paid within 30 days after the end of the final quarter. The interest paid to the Contractor is for the Contractor’s benefit and is income to the Contractor for income tax purposes. If part of the retent is to be returned to the Department, the interest earned will likewise be prorated between the amount going t o the Contractor and the amount being returned to the Department. Pay administrative charges, if any, in connection with a requested deposit of the retent or a deposit by the Contractor of securities as provided by NRS 408.383, out of the interest accruin g on the deposit or on the securities deposited. The above deposit will be closed out and forwarded when the contract is accepted and determination made that the contract should be finalized and final payment made. No payments will be made when the work is not satisfactorily proceeding according to the provisions of the contract. Do not construe any progress payment to be an acceptance of any defective work, improper materials, or perishable materials that exceed the manufacturer’s date of expiration pri or to application. Be responsible for any material that has been included in the progress payment. The cost of materials conforming to the plans and specifications (“materials” being those which are required to be contained and incorporated in a finished contract bid item) and not at the time incorporated in the work, may also be included in the payment. In no case shall the amount paid exceed the amount bid for a particular bid item. Partial payment will be made on manufactured materials which have been purchased and stockpiled for use on the project provided said materials are stockpiled within boundaries of the State of Nevada and subject to the following limitations:
a.Stockpiled separate and apart from materials that are not to be used on this con tract.
b.Tagged or marked in such a manner that they are easily identified as materials for this contract.
c.Kept safe from theft and vandalism.
d.Allowed access to during normal working hours for periodic inspections by representatives of the Sta te.
e.Removed and utilized on this contract only. MEASUREMENT AND PAYMENT 109 75 (f) Stockpile materials subject to expiration dates according to the manufacturer’s recommendations. Provide all applicable expiration dates for perishable materials. Partial payment will also be made for stockpiled materials for Item No. 506 0 100, “Structural Steel,” stockpiled either within or outside the State of Nevada at the supplier’s or Contractor’s storage site. Partial payments for structural steel shall be subject to the preceding conditions i n paragraphs (a) through (e) and in addition thereto, the following conditions in paragraphs (a) through (c):
a.Roll steel plates to the proper dimensions for a particular girder.
b.Provide invoices for labor and materials with the request for partia l payment.
c.All stockpiled plates shall be checked and verified against invoices by the on -site State inspector. Partial payments will be made on “Class * ............. Concrete (Major)” and “Class * ............ Concrete, Modified (Major),” for false work, forming, and for labor and materials involved, up to but not to exceed 70% of the plan quantity for the concrete item being formed. Up to 35% may be allowed of the plan quantity for the applicable concrete item as the falsework or earth shoring progr esses. Also up to an additional 35% may be allowed as the deck forming progresses. *(Class(es) to be as indicated in the proposal.) In cases where there is minimal or no falsework, up to 70% may be allowed of the applicable major concrete item as the form ing progresses. Partial payments may be made on “local materials” meeting the requirements hereinafter outlined:
a.Stockpile materials on or in the vicinity of the proper project, (generally on land adjacent to the project).
b.Store materials in an approved manner in areas where damage from flood waters is not likely to occur. If at any time stored materials are lost or become damaged by floods or in any other manner, repair and replace such damaged materials. If payment has been made before such dam age, the amount so allowed, or a proportionate part thereof, will be deducted from the next progress payment and withheld until satisfactory repairs or replacements have been made.
c.Partial payments will be made only on materials that conform to plans and specifications (not to be construed as final acceptance). The quantities will be determined by volume measurement and converted to tons if the contract unit price of the item is in tons. In the case of “Portland cement concrete pavement,” the unit pric e will be converted to square meter per metric ton (square yards per ton). However, partial payments shall not exceed the actual cost to provide the material.
d.No payment will be made on any commercial stockpile or on any stockpile from which materials are being used for any purpose whatsoever other than incorporation into the project.
e.Stockpile payment will be made at the contract unit price for the percentage of material allowed. The quantity in stockpile, or windrow, to be considered shall not e xceed that required for the project.
1.Not more than 40% of the unit bid price of Class A and Class B aggregate base courses and shouldering material in the stockpile may be allowed. Not more than 85% of the quantity of cement treated base roadmix in the processed windrow on the roadway may be allowed.
2.Not more than 30% of the unit bid price of cement treated base aggregate (roadmix or plantmix) in the stockpile may be allowed. Not more than 85% of the quantity of cement tre ated base roadmix in the processed windrow on the roadway (before adding cement) may be allowed.
3.Not more than $ 10.00 per metric ton ($ 9.00 per ton) for plantmix surface or open -graded surface aggregate in the stockpile may be allowed. When 40% of the unit bid price is less than $ 10.00 per metric ton ($ 9.00 per ton), not more than 40% of the unit bid price for plantmix surface or opengraded surface aggregate in the stockpile may be allowed. 109 MEASUREMENT AND PAYMENT 76 4. Not more than 85% of the unit bid price of roadmix bitumin ous surface aggregate in the processed windrow on the roadway (before adding bituminous material) may be allowed.
5.Not more than 40% of the unit bid price of screenings in the stockpile may be allowed.
6.Not more than 85% of the unit bid price of sele cted material base conforming to all the requirements, in windrow may be allowed.
7.Not more than 20% of the unit bid price of Portland cement concrete pavement aggregates in the stockpile may be allowed. The stockpiled quantity shall be converted to squ are meters (square yards) of “Portland cement concrete pavement” for pay purposes.
8.Not more than 40% of the unit bid price of graffiti coating may be allowed once the coating has been stockpiled and expiration dates of the product have been provided.
9.Not more than 25% of the unit bid price of living or perishable plant material may be allowed once the plants are delivered to the project. If materials are not specifically purchased for the work, but are taken from the Contractor’s stock, then in li eu of invoices, submit statements accompanied by an affidavit, certifying such materials were taken from stock and the price and transportation claimed represent the actual cost. Unless otherwise specified, all material and work covered by partial payment s shall thereupon become the property of the State, but do not construe this provision as relieving the responsibility for all materials and work upon which payments have been made or the restoration of any damaged work, or as a waiver of the right of the Department to require the fulfillment of all terms of the contract. No payment, partial or otherwise, will be made for the item of “watering.” Consider full compensation for developing and maintaining an adequate water supply included in other items of wo rk. No stockpile payments will be made on rent traffic control devices. When construction signs and rent traffic control devices are listed as separate items according to Section 625, partial payments will be made as hereinafter outlined:
a.Constructi on Signs. When construction signs are placed on the project, according to the plans and specifications, 50% of the contract price per square meter (square foot) of acceptable signs in place will be paid for on the next progress payment after placing. The r emaining percent will be prorated according to job progress. However, if signing becomes inadequate for job requirements, an adjustment downward will be made on the first progress payment following such inadequacy.
b.Rent Traffic Control Devices. When t raffic control devices are placed on the project according to the plans and specifications, 50% of the contract bid price per linear meter (linear foot) or per each, as the case may be, of the traffic control devices thus in use will be paid for on the nex t progress payment after placing. The remaining percent will be prorated according to job progress. However, if traffic control devices become inadequate for job requirements, an adjustment downward will be made on the first progress payment following such inadequacy. When the proposal contains the item “Rent Traffic Control Devices (Lump Sum)” according to Section 625, partial payments will be made as hereinafter outlined: The Engineer will determine the reasonable payment percentage of the Rent Traffic Control Devices (Lump Sum) for each payment cycle. The payment percentage will be based on the progress of the work and the quantity of traffic control devices placed on the project according to the approved traffic control plans. The amount paid on the ne xt progress payment will be 50% of the amount determined. The remaining percentage will be prorated according to job progress. However, if traffic control devices become inadequate for job requirements, an adjustment downward will be made on the first prog ress payment following such inadequacy. A maximum amount of 10% of the original contract amount will be paid during the progress of the work. Upon completion of all work on the project, payment of any amount bid for Rent Traffic Control Devices (Lump Sum) in excess of 10% of the original contract amount will be paid. MEASUREMENT AND PAYMENT 109 77 Partial payments will be made on the items of fence, guardrail, bridge rail, mobilization, signal systems and/or highway lighting systems, cattle guards, and trenching for irrigation systems a s hereinafter noted provided that materials and equipment are satisfactorily supplied:
a.Fence. When fencing material is stored on the project, invoice prices may be paid as outlined herein. When the fence posts have been placed, 50% of the partially co mpleted fence will be eligible for payment at the contract unit bid price. The remaining 50% will be eligible for payment when the item is complete. The cost of wire and posts conforming to the plans and specifications which are required to be contained and incorporated in a finished contract bid item delivered to the project and not at the time incorporated in the work, may be included in the partial payment.
b.Guardrail and Bridge Rail. Guardrail and bridge rail materials stored on the project accordi ng to this Subsection may be included for stockpile payment. When posts for guardrail or reconstruct guardrail are complete in place, 50% of the partially completed guardrail will be eligible for payment at the contract unit bid price. The remaining porti on of the contract unit bid price will be eligible for payment when the item is complete.
c.Mobilization. Partial payments will be made by the following schedule:
1.When 5% of the original contract amount is earned from other than mobilization, 50% of the amount bid for mobilization, or 5% of the original contract amount, whichever is less, will be paid.
2.When 10% of the original contract amount is earned from other than mobilization, 100% of the amount bid for mobilization, or 10% of the original c ontract amount, whichever is less, will be paid.
3.Upon completion of all work on the project, payment of any amount bid for mobilization in excess of 10% of the original contract amount, will be paid.
d.Signal Systems and/or Highway Lighting Systems. The cost of materials for luminaries, poles and mast arms, controllers and cabinets, signal heads, and detector units, conforming to the plans and specifications (“materials” being those which are required to be contained and incorporated in a finished co ntract bid item) delivered to the project and not at the time incorporated in the work, may also be included for stockpile payment. Other items will not be included for partial payment until incorporated in the work.
e.Cattle Guards. The first progress payment after the cattle guard has been completed, but the wings not yet installed, will show this item 90% complete. The remaining 10% shall be eligible for payment on the first progress payment after the wings have been installed.
f.Trenching for Irri gation Systems. When trenches for irrigation pipe distribution lines have been excavated and the pipe has been placed but not backfilled, 50% of the partially completed irrigation pipe will be eligible for payment on the next progress payment at the contra ct unit price. Payment will be based on that length of the pipe partially complete. The remaining 50% will be eligible for payment on the first progress payment following complete installation of the pipe.
110.01 Description. The provisions pertaining to wages and conditions of employment shall apply to all work
performed (on the contract) by the Contractor with his own organization and with the assistance of workmen under his immediate superintendence, and to all work performed on the contract by subcontractors. Minimum wage rates determined by the Labor Commissioner of the State of Nevada and by the Secretary of Labor, if applicable, are set forth in the contract documents. Do not pay wage rates less than the minimum wage rates. Forfeit, as a penalty to the Department, the amount stipulated in NRS Chapter 338 when workmen are paid less than the minimum wage rate. The laborers shall have access to the pertinent minimum wage schedules at all times. Provide and erect a weatherproof bulletin board at the job site and post all minimum wage schedules and other required information thereon. Construct the weatherproof bulletin board so that the material thereon is adequately protected from the elements. It is a condition of the contract, and shall be made a condition of each subcontract entered into pursuant to the contract, that the Contractor and any subcontractor shall not require any laborer or mechanic employed in performance of the contract to work in surroundings or under working conditions which are unsanitary, hazardous, or dangerous to his health or safety as determined under construction safety and health standards (Title 29, Code of Federal Regulations, Part 1926 —published in the Federal Register on December 16, 1972, and subsequent revisions) promulgated by the United States Secretary of Labor, according to Section 107 of the Contract Work Hours and Safety Standards Act, (83 Stat. 96). The minimum wage rates apply to workmen working upon the “site of the work.” The term “site of the work” is defined as follows: The “site of the work” is defined as the physical place or places where work called for in the contract is performed by either the Contractor o r the Contractor’s agents. Material sources controlled by the Department and staging areas set up to construct portions of the work are considered to be the “site of the work.” Not included in the “site of the work” are permanent home offices, batch plant establishments, fabrication plants, and tool yards of an employer whose locations and continuance in operation are determined without regard to the work. In addition, fabrication plants, batch plants, borrow pits, job headquarters, tool yards, or other like locations of a commercial supplier or materialman which are established by a supplier of materials for the project before opening of bids are not incl uded in the “site of the work.” The Contractor and subcontractors compliance with Title 29, subtitle A, 3.3, Code of Federal Regulations and NRS 338 will be required on this contract. These regulations require submittal of a tally of weekly payroll and statement of compliance with respect to each employee engaged in work on the project. Submit these payrolls and statement of compliance to the Nevada Department of Transportation and the State of Nevada Labor Commissioner. Submit payrolls electronically via the internet into the Department’s contracted payroll tracking system. The system information and access fee will be listed in the Special Provisions. This requirement will apply to every lower-tier subcontractor and vendor required to provide certified payroll reports by NRS 338.010 to 338.090 inclusive. Upon issuance of the Notice to Proceed, the Department will provide the Contractor with the website addresses and a Login Identification and Password to access the payroll system.
Source: Nevada Standard Specifications for Road and Bridge Construction, 2014 Edition. Pages 71–84 of 610.