B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
Pavements & Surfacing (400-499)

421MICROSURFACING

OH · 2019 Standard SpecificationsBook pages 00View official source ↗

411.05 210 Ensure that the moistu res of the delivered material are less than 2 percent above saturated surface dry condition; if not, the Department will base payment on the dry densities and dry weights. Furnish freight bills or certified weight bills according to 109.

411.05 Basis of Pa yment. The Department will pay for accepted quantities at

the contract price as follows: Item Unit Description 411 Cubic Yard Stabilized Crushed Aggregate (Cubic Meter) ITEM 421 MICROSURFAC ING

421.01 Description

421.02 Materials

421.03 Proportioning

421.04 Quality Control Program

421.0 5 Weather Limitations 421.0 6 Mixing Equipment

421.07 Equipment Calibration

421.08 Spreading Equipment

421.09 Surface Preparation

421.10 Test Strip

421.11 Application

421.12 Quality Control

421.1 3 Acceptance

421.14 Performance Review

421.15 Method of Measurement

421.16 Basis of Payment

421.01 Description . This work consists of constructing a cold laid polymer

modified emulsified asphalt pavement course to fill ruts or provide a leveli ng and/or surface course for existing pavements. Warrant the microsurfacing for two years.

421.02 Materials . Use a polymer modified emulsified asphalt binder (Binder)

consisting of the following: Use a quick -traffic CSS -1hM modified emulsified asphalt (Binder) meeting the requirements in Table 421.02 -1. Use only Binder certified according to Supplement 1032. Do not use port addition of the polymer to the emulsified asphalt. Provide to the Engineer certified test data and a statement from the Binder supplier with each load of Binder that the Binder is the same base asphalt binder, polymer, polymer percentage as formulated and used in the mix design. Include the percent residue on the Bill of Ladin g. Ensure the Binder meets the following and specification limits will be producible for at least 30 days from sample date: 421.02 211 TABLE 421.02 -1 Tests on emulsion, AASHTO T 59, unless otherwise designated: CSS-1hM [1] Viscosity, Saybolt Furol at 77 °F (25 °C) (SFS) 20 to 100 Storage Stability Tests, 24 -hr (% difference), max. 1 Particle Charge Test Positive Sieve Tests (%) (Distilled Water), max. 0.10 Distillation to 177 °C, Residue % solids, min.[2] 62 Tests on distillation residue: Penetration, 25 °C, 100 g, 5 sec (dmm) AASHTO T 49 40 to 90 Ductility, 25 °C, 5 cm/min, (cm), min. AASHTO T 51 40 Solubility in trichloroethylene, (%), min. AASHTO T 44 [3] 97.5 Elastic Recovery, 10 °C, 20 cm (%), min. AASHTO T 301 [4] 50 Softening Point, Ring & Ball (°C), min. AASHTO T 53 60 [1] Pre-blend only: Use a minimum of 3.0% SBR solids based on weight of the asphalt binder. Use Natural SBR latex modifier or synthetic SBR latex modifier conforming to 702.14. Use only one type of latex. Mill or blend the SBR Emulsion into the emulsified solution prior to the emulsification process. [2] See Supplement 1013. For natural latex, use the Oven Evaporation method in AASHTO T 59 in place of distillation and use this residue for further testing. [3] On the base as phalt only. Solubility in N -Propyl Bromide (ASTM D7553) can be used in place of trichloroethylene. [4] Straight molds. Hold at test temperature for 90 minutes. Place in ductilometer and elongate 20 cm at 5 cm/min. Hold for 5 minutes and cut. After 1 hour r etract the broken ends to touch and measure the elongation (X) in centimeters to the nearest 0.01 cm. Use the following formula to calculate the elastic recovery: Percent Recovery = ((20 -X)/20) x 100. Report results to nearest 0.1%. Conform to 703.01 and 703.05 for aggregate, except as follows: TABLE 421.02 -2 Percent by weight of fractured pieces 100 Sand Equivalence ( AASHTO T176 ) 55 minimum Conform to Table 421.02 -3 Gradation A for the aggregate for surface courses , Gradation B for the aggregate for rut fill courses , and Gradation A or B for the aggregate for leveling courses. Stockpile tolerance will be based on target gradation stated in the mix design but will not exceed design gradatio n band for No. 200 sieve. TABLE 421.02 -3 Sieve Size Total Percent Passing A B Stockpile Tolerance 3/8 inch (9.50 mm) 100 100 No. 4 (4.75 mm) 85 to 100 70 to 90 ± 5.0% No. 8 (2.36 mm) 50 to 80 45 to 70 ± 5.0% No. 16 (1.18 mm) 40 to 65 28 to 50 ± 5.0% No. 30 (600 µm) 25 to 45 19 to 34 ± 5.0% No. 50 (300 µm) 13 to 25 12 to 25 ± 4.0% No. 100 (150 µm) – 7 to 18 ± 3.0% No. 200 (75 µm) 5 to 15 5 to 18 ± 2.0% Screen the aggregate for oversize material prior to use using a 3/8 inch (9.5 mm) screen size. When a blend of aggregates is to be used to meet gradation A or B, proportion the aggregates in a separate stockpile and blend to a uniform consistency 421.03 212 prior to screening. Screen the aggregate to complete the blendin g process and to remove any oversize material prior to use. If oversize material becomes present in the mixture, screen the aggregate directly into material support units. For mineral filler, use Portland cement conforming to ASTM C 150, Type I. Adjustment s in the quantity of mineral filler added to the mixture are permitted to improve mixture consistency, mix time, or set time. Do not exceed ± 0.5% from the mix design during placement. Use water conforming to 499.02. Add water to the mixture to control mix ture consistency only and not to control mix time. Use mix set additives as stated in the mix design to control the mixture’s mix and set time. If mix set additives are used during production of mixture, include as part of the mix design. Ensure ad ditives are compatible with the other components of the mix.

421.03 Proportioning. Develop a mix design to comply with the mix design

criteria and submit to OMM on approved forms, at least two weeks prior to the start of calibration, for preliminary JMF approval. OMM may require additional time prior for preliminary approval to perform tests on lab materials to ensure mix compliance. OMM will notify the Contractor if additional time for testing is required. Final JMF approval will be granted upon success ful placement in the field. OMM may require the Contractor to design and submit for a new JMF for lack of mix compliance or lack of field performance. Submit the mix design and proposed materials to OMM. Include a minimum of 11 pounds (5,000 g) of each a ggregate, one quart (1 L) sample of Binder , 3.5 ounces (100 g) of mineral filler, and one pint (0.5 L) of additive, if used, and a complete mix design packet prepared by an AASHTO -accredited laboratory in Pavement Preservation. P repare the mix design by designing the mixture using the minimum, mid-point, and maximum residual binder content for gradations A or B and present all test data for all tests specified in Table 421.03 -1. Determine the residual binder content and present re lated proportioning of total water (includes moisture in aggregate), mineral filler, and additive with tolerances for each in the final designed mixture. Verify during the mix design the compatibility of the aggregate, Binder, mineral filler, and other ad ditives. Produce the mix design using the same materials that will be used on the project. Approved JMF’s expire on December 31st.

A.Ensure that the mix design:
1.Has aggregate meeting the gradation specified.
2.Has residual asphalt by dry weight of aggregate of 7.0 to 8.5 percent for leveling and surface courses or 6.5 to 8.0 percent for rut fill courses.
3.Has a mineral filler content of 0. 3 to 2.5 percent by dry weight of aggregate and a tolerance of not greater than ± 0.5 percent of the mix design within the required minimum and maximum .
4.Has mix times and wet cohesion requirements based on specific minimum and maximum percent mineral filler, total water, and additive.
5.Has a total water content with a tolerance not greater than ± 1.5 percent. 421.04 213 6. Has a total non -diluted additive content with a tolerance not greater than ± 0.2 percent. Verify that the additive dilution rate with water specified in the mix design is consistent with the paving machine being used.
7.Meets th e specified properties of the following International Slurry Seal Association (ISSA) tests: TABLE 421.03 -1 ISSA Test No. Description Specification TB-139 Wet Cohesion 30 minutes min. (set time) 12 kg -cm min. 60 minutes min. (traffic) 20 kg -cm min or near spin TB-114 Wet Stripping 90 percent min. TB-100 Wet Track Abrasion Loss 1-hour soak 6 day soak 450 g/m² max. 650 g/m² max. TB-144 Saturated Abrasion Compatibility 2 g loss max. TB-113 Mix Time @ 25 C Controllable to 120 seconds Mix Time @ 40 C Controllable to 60 seconds TB-147 Lateral Displacement (For Leveling and Rut Fill courses only) 5%, max. TB-109 Excess Asphalt by LWT Sand Adhesion 538 g/m² max. Check the ISSA TB -139 (set time) and ISSA TB -113 (mix time) tests at the highest temperature expected during construction. For the ISSA TB -113 test at 104 °F (40 °C), preheat all ingredients and containers.
B.Report the following in the mix design (all percentages are based on the dry weight of the aggregate) :
1.Source and location of each individual material. Provide percentage of each aggregate source if multiple aggregate sources are used .
2.Aggregate gradation, washed and dry (dry for field QC). Provide aggregate gradation of each source and final combined if multiple sources are used.
3.Sand equivalence of the aggregate.
4.Percentage of mineral filler and tolerance.
5.Percentage of total water and tolerance and acceptable pH range.
6.Percentage and Type of mix set additives (if required ) and tolerance.
7.Percentage of Binder and residual asphalt content in the mixture .
8.Quantitative effects of moisture content on the unit weight of the aggregate per AASHTO T 19 .

421.04 Quality Control Program (QCP). Create and implement a Quality

Control Program (QCP) for each construction season. The QCP will cover processes 421.04 214 conducted to pr ovide a microsurface mixture at the project site that is uniform in composition, conforms to the specification requirements and project mix design, and that when placed is free of any defects (lack of mixing, inconsistent texture, inconsistent profile, exc essive overlap at joints, streaking, drag marks, roughness, raveling, rutting, holes, and debris, etc.) within the Contractor’s control at project completion. Submit a hard copy of the proposed QCP to OMM for review and acceptance. Submit by February 28 or a minimum of five (5) weeks before calibration. Submit a hard copy and a digital copy (if available) of the QCP acceptance letter and accepted QCP to District Testing a minimum of two weeks prior to calibration. Keep copies of the letter and the QCP with each Contractor’s Quality Control Manager and provide a copy of both to the Engineer. Digital copies of the QCP and letter in pdf format are allowed with the following requirements: The file icon must be appropriately labeled and be on the computer desktop . The QCP must contain page numbering and a Table of Contents inside the front cover locating all sections by page number and out of date QCPs must be removed from the computer desktop. Failure to comply with the approved QCP may result in work stoppage an d adversely affect the Contractor’s Prequalification rating. The QCP is a reflection of a Contractor’s sincerity and ability in producing a quality product. Development of this program beyond the minimum requirements specified below is encouraged. Include in the program:

A.The assignment of quality control responsibilities. Quality control includes all efforts required to achieve a product meeting specifications. List individuals as required below and note their designated responsibilities to meet QCP req uirements. Provide a Quality Control Manager who is a company employee who is routinely and usually at the paving site during placement of any microsurfacing. Provide a list designating technician responsibilities and expected actions. Ensure only trained personnel handle and test samples at all times. Define who is responsible at the project site and specific methods for ensuring mixing equipment, haul vehicles, etc. meet requirements.
B.Means for annual training of company and consultant technicians and their supervisors in ethical conduct according to company expectations. Document how and when training is given, what the expectations are, how expectations are communicated, and list all personnel trained. Describe the QC Manager’s and technician supervi sor’s responsibilities and methods in ensuring ethical conduct is maintained throughout the year.
C.Provisions to meet the Department mix specifications.
D.Procedures for extra testing (e.g., job start, responses to poor test results or field mix probl ems, aggregate stock testing, moistures) and any other testing necessary to control materials not already defined in these Specifications.
E.Methods to maintain all worksheets, including all handwritten records, and other test and sample records from the project for the duration of the contract or five years, whichever is longer. Define the test record process. Define company records 421.05 215 retention requirements. Provide copies of all test reports and forms used in the quality control process.
F.Procedures for calibration and documentation for all testing equipment. Procedures for calibration record storage. Procedure to supply documentation record s of testing equipment calibration at the request of the engineer.
G.Method of performing mixing equipment calibrations including scales to be used, yield checks, and documentation for each project.
H.Procedure for random sampling to be used at the pr oject and documentation method. Procedures for sample taking, tracking, handling, and documentation method for all samples taken at the project paving site.
I.Procedure for ensuring that every Contractor employee involved in the testing of aggregates and microsurfacing mix and operation of the mixing equipment has read the QCP and has on site access to all applicable Department specifications, proposals, policies, and the current approved JMF.
J.Procedure for ensuring binder Bills of Lading with BOL loa d number, binder source and grade, and binder percent residue are reviewed against running mix designs and record of review listing the above information be kept with the QC Manager for the duration of the project. Means to meet the handling and storage requirements of the Binder and tack coat suppliers.
K.Means to meet placed mixture uniformity and hauling/trucking requirements.
L.Define the roles and responsibilities of the QC Manager.
M.Signature of the Quality Control Manager and, if different, th e person in authority to enforce all operations covered by the QCP as outlined in this subsection.

421.05 Weather Limitations . Apply the mixture only when it is not raining,

pavement has no standing water, and the existing pavement surface and atmospheric temperature is a minimum of 45 F (7 C) and rising and there is no forecast of an atmospheric temperature below 32 F (0 C) within 24 hours from the time the mixture is applied. Between September 30 and May 1, do not apply the mixture if the existing pav ement surface temperature is less than 50 F (10 C).

421.06 Mixing Equipment. Produce the mixture in a self -propelled, front feed,

continuous loading mixing machine equipped with a conveyer belt aggregate delivery system and an interconnected positive displacement, water jacketed asphalt emulsion gear pump to accurately proportion a ggregate and asphalt emulsion or a variable displacement computerized rate control to accurately proportion aggregate and asphalt emulsion . Locate the mineral filler feed so the proper amount of mineral filler is dropped on the aggregate before discharge i nto the pugmill. Provide a spray bar to completely prewet the aggregate dropping into the pugmill with additive and water before introduction of asphalt emulsion. Ensure that the twin -shaft, multi - blade pugmill is a continuous flow type and minimum of 49 inches (1.25 m) long. Ensure that the blade size and side clearances meet the equipment manufacturer’s recommendations. Introduce the emulsion within the first one -third of the mixer length to ensure proper mixing of all materials before exit from th e pugmill. 421.07 216 Equip the machine with opposite side driving stations to allow full control of the machine from either side. Equip the mixer with a remote forward speed control at the back mixing platform so the operator controlling the mixture placement can control forward speed and level of mixture in the spreader or rut box. Provide material control devices that are readily accessible and positioned so the amount of each material used can be determined at any time. Equip the mixing machine with a water pressure system and nozzle type spray bar to provide a water spray ahead of and outside the spreader box when required. Apply water at a rate that will dampen the surface, but will not create free flowing water ahead of the spreader box. The Contract or may use truck -mounted batch machines with a conveyer belt aggregate delivery system and without the front feed, continuous loading feature on projects of less than 15,500 square yards (13,000 m2), on spot repairs, on projects with multiple routes where every route is less than 15,500 square yards (13,000 m2), or where specified in the plans .

421.07 Equipment Calibration. Before mix production, calibrate the mixing

equipment to the approved JMF in the presence of the Engineer according to Supplement 104 0. Verify that the project calibration is not affected by any previous calibrations and scale factors by removing or resetting prior to starting a new calibration . Generate documentation for the Engineer, including individual calibrations of each material at various settings. Perform a calibration for each JMF used on the project. Following calibration , do not make any further calibration adjustments to the mixing equipment without the Engineer’s approval. The Engineer may require additional calibrations following any equipment break down related to the aggr egate delivery belt, asphalt emulsion gear pump, or mixture performance issues. Submit the approved mix design information and JMF(s) to the Engineer and District Testing at least 48 hours prior to start of calibration .

421.08 Spreading Equipment. If a leveling or surface course is specified, apply

the mixture by means of a conventional spreader box attached to the mixer. If a rut fill course is specified, apply the mixture with a 5 to 6 foot (1.5 m to 1.8

m.width V-shaped rut filling spreader box attached to the mixer. Equip the rut filling spreader box with a steel strike -off. If a leveling course is specified, apply the mixture with a spreader box equipped with a steel or rubber strike -off that is designed to fill wheel path ruts. A secondary strike -off may be used to reduce roughness of the leveling course but will not remove mixture in wheel path ruts or affect desired cross section. Equip the spreader box with paddles or augers mounted on an adjustable shaft to continually agitate and dis tribute the materials throughout the box. Ensure that the equipment provides sufficient turbulence to prevent the mix from setting in the rut fill or spreader box or causing excessive side build -up or lumps. To prevent loss of the mixture from the spreader box, attach flexible seals, front and rear, in contact with the road. Operate the spreading equipment in such a manner as to prevent the loss of the mixture on superelevated curves. 421.09 217 For surface courses, attach a secondary strike -off to the spreader and a djust as required to provide a uniform mixture texture. The Contractor may use burlap drags or other drags, if necessary, to obtain the desired finish. Replace drags having excessive build -up.

421.09 Surface Preparation. Before applying the mixture, thoroughly clean the

surface. Remove raised pavement markers according to 621.08, when specified. Remove all existing pavement markings, e xcept 740.02 (traffic paint), using an abrasion method conforming to 641.10. Seal visible joints and cracks longer than 2 feet ( 600 mm ) in length and any joint or crack greater than 1/4 inch (6 mm) in width no matter the length using Item 423 TYPE II OR TYPE III SEALANT ONLY. Apply crack sealant material at a width of 2 to 4 inches (50 to 100 mm) and at a thickness of not less than 1/16 inch (2 mm) and not greater than 3/16 inch (5 mm). Apply a tack coat to the existing pavement surface conforming to ITEM 407 CSS- 1H OR 421.02 CSS -1HM , consisting of a minimum of 15% asphalt residue achieved by diluting with water. Apply the tack coat at a rate of 0.06 to 0.12 gallons per square yard (0.25 to 0.45 L/m ²) that provides uniform coverage without excess run -off and allow tack to break before releasing to construction traffic. Adjust application rate of tack coat based on surface texture and porosity. Apply the tack coat only to areas that will be covered by the microsurface during the same day. Do not apply tack coat on top of a leveling course prior to placing the surface course. Protect drainage structures, monument boxes, water valve, etc. during material application .

421.10 Test Strip. Construct a co ntinuous 1000 foot (300 m) long by lane width

test strip for each approved JMF(s) for the project. The test strip will demonstrate the mix and set time of the material and ability to perform under full traffic. If handwork will be performed on the project, include handwork in the test strip. Construct the test strip at the same time of day or night the full production will be applied. Perform a yield check to ensure the proper spread rate, surface quality requirements and compliance with JMF components are met. Submit results to the Engineer. The Engineer will evaluate the completed test strip and yi eld check report after a minimum of 12 hours under traffic , to determine if the mix design and application is acceptable. The Contractor may begin full production after the Engineer accepts the test strip. If the microsurfacing is being applied between May 1 and October 15 , the Department may waive the test strip if the Contractor has constructed a Department accepted test strip during the same time frame with the same materials and JMF(s) and with no documented project performance issues. Provide documentation (Project Number, District, Route, Test Strip Date, Engineer, etc.) and history from the previous test strip(s) and calibration(s) to the Engineer . 421.11 218 421.11 Application. Apply the microsurface mixture to the prepared surface in a manner to fill cracks, shallow potholes, and minor surface irregularities and achieve a uniform textured surface without causing streaking, drag marks, skips, lumps or tears. Carry a sufficient amount of material at all times in all parts of the spreader box to ensure complete and uniform coverage. Avoid overloading of the spreader box. Do not allow lumping, balling, or unmixed aggregate in the spreader box. When specified, place leveling courses to cover the entire pavement area as specified. Place the leveling course in a manner to maintain or improve the ride quality of the existing pavement. Provide a completed leveling course with no drag marks or tears g reater than 1/2 inch (13 mm) wide, 1/4 inch (6 mm) deep, or 12 inches (25 mm) in length. Provide a completed leveling course free of flushing, bleeding, or added roughness. The completed leveling course may exhibit minor raveling upon opening to traffic b ut will not exhibit any continued raveling after the first four hours of traffic. When specified, apply rut fill courses in widths from 5 to 6 feet (1.5 to 1.8 m) for each wheel path. Apply enough material to fill the wheel paths without excess crowning (overfilling). An excess crown is defined as 1/8 inch (3 mm) after 24 hours of traffic compaction. If rut depth exceeds 1.0 inches (25 mm), apply rut fill course in multiple courses . Provide a s mooth, neat seam where two rut fill passes meet. Take care to restore the designed profile of the pavement cross -section. After compaction by traffic, ensure the completed rut fill does not result in deviations in excess of 1/4 inch (6 mm) as measured across each wheel path using a 6 foot (1.8

m.straight edge. Do not place microsurfacing surface course material until wheel path deviations in excess of 1/4 inch (6 mm) are correc ted. Place the rut fill course in a manner to maintain or improve the ride quality of the existing pavement. Provide a completed rut fill course with no drag marks or tears greater than 1/2 inch (13 mm) wide, 1/4 inch (6 mm) deep, or 12 inches (25 mm) in length. Provide a completed rut fill course free of flushing, bleeding, or added roughness. The completed rut fill course may exhibit minor raveling upon opening to traffic but will not exhibit any continued raveling after the first four hours of traffic. If a leveling course and a surface course are specified, apply the microsurface mixture at a minimum of 14 pounds per square yard (7.6 kg/m2) of dry aggregate weight for the leveling course and 18 ± 1 pounds per square yard ( 9.8 ± 0.5 kg/m2) of dry aggregate weight for the surface course. Apply the two courses at a minimum combined rate of 32 pounds per square yard ( 17.4 kg/m2) of dry aggregate weight. If a surface course is specified a nd it is not placed on a microsurfacing leveling course, apply the microsurface mixture at a rate of 22 ± 0.5 pounds per square yard (11.9 ± 0.3 kg/m2) of dry aggregate weight. Apply the mixture in a manner to produce a uniform surface texture across the entire paving pass. For leveling and surface courses, provide a smooth, feathered, neat seam of 1 to 3 inches (25 to 75 mm) where two passes meet at the pavement centerline and at edge of shoulder. In variable width pav ement sections minimize overlap and feather overlapping pass on to the completed surface. Construct overlaps such that cross slope drainage is maintained. Immediately remove excess material from the ends of each run. 421.12 219 Construct surface courses at a width to cover the outside edges of rut fill and leveling courses. Construct seams at or near edge of lane but do not construct seams in wheel paths. Maintain straight edge lines along curbs and shoulders. Do not allow runoff in these areas. Ensure tha t lines at intersections are straight. Use squeegees and lutes using similar material as the secondary strike -off to spread the mixture in areas inaccessible to the spreader box and areas requiring hand spreading. The Contractor may adjust the mix set addi tive to provide a slower setting time if hand spreading is needed. Do not adjust the water content to adjust the setting time. If hand spreading, pour the mixture in a small windrow along one edge of the surface to be covered and spread it uniformly by a h and squeegee or lute. Provide uniform appearance of the entire surface area regardless of the means used to spread material. Ensure that the microsurfacing cures at a rate that will permit traffic on the pavement within one hour after application without damaging the pavement surface. However, should the Contractor experience a curing condition that does not allow the opening to traffic within one hour , work out an arrangement agreeable to the Engineer before releasing traf fic on the pavement. If the final surface course is not uniform in texture, free of streaks, drag marks, lumps or tears , stop applying the mixture and take steps to correct the problem. Do not resume work until the Engineer is satisfied the problem has been corrected.

421.12 Quality Control . Use the methods described in this section to control

the quality of the mixture and application, and to measure compliance. If any test results or measures of compliance exceed any of the identified quality control tolerances or specification requirements, stop placement and immediately notify the Engineer and District Testin g. Identify the cause of exceeding any of the identified quality control tolerances and document in detail the corrective action necessary to bring the deficiency into compliance. Implement the corrective action and resume work and immediately perform a t est or measure to confirm corrective action has resolved the deficiency. If upon resuming work the tolerances are exceeded, stop the work. Present a revised corrective action plan to, and obtain the Engineer’s approval before resuming work. Upon resuming work, immediately perform a test or measure to confirm corrective action has resolved the deficiency. The Department can obtain samples of materials at any time. Aggregate samples can be taken from sources, on -hand stockpiles, or from the mixing equipment. Work can be stopped and materials and JMF can be rejected on the basis of poor Department test results. If the Department reports non -compliance on any material test, the Department will compare results with the Contractors Quality Control Manager. The E ngineer will determine if the tests or compliance measurement has been satisfactory corrected. Prior to starting placement, verify the pH of the water to be used is within the acceptable range on the JMF. Verify again if source of water changes. Perform a minimum of four yield checks daily with one occurring within the first 1000 linear feet (300 linear meter) of continuous placement and the last occurring in the last 1000 linear feet (300 linear meter). Perform at least one yield check for each course a pplied. For cross -overs, driveways, and any other irregular areas, 421.12 220 determine yield checks by a means acceptable to the Engineer. Ensure yield checks are a minimum of 500 linear feet (150 linear meter) for continuous loading mixing machines or one full -loaded truck -mounted machine. Ensure yield checks meet and include documentation of compliance for sections 421.03, 421.05, 421.09, 421.11, and 421.13.

A.Binder. Within one hour of the start of production obtain and label a Binder sample from supply tanker and diluted tack coat sample from the distributor truck and give the samples to the Engineer the same day. Provide and sample the Binder and diluted tack coat in one quart (1 L) plastic containers with plastic screw tops. Label and retain one sample per each additional day for the Department. Take more samples when requested by the Engineer. Visually inspect Binder in supply tanker(s) to ensure uniform materia l with no separation or contamination. Verify temperature of Binder and tack coat. Monitor and verify proportioning of asphalt emulsion and water into distributor and proper mixing before use or sampling. Perform a minimum of one Binder and tack coat cook -off each production day to determine the residue content of the Binder and tack coat and verify compliance.
B.Aggregate. Ensure the aggregate stockpile gradation does not vary by more than the stockpile tolerance in Table 421.02 -3 compared to the approv ed JMF and does not exceed the design gradation band for No. 200 (75 µm) sieve. Ensure the percent passing does not change from the high end to the low end of the range for any two consecutive sieves. Verify the blending and screening of aggregates at the stockpile site and sample the blended and screened aggregate for QC testing. Stockpile a minimum of 10 percent of the project aggregate or 200 tons (180 metric tons) of aggregate whichever is less at a staging area. Obtain three (3) aggregate samples from the stockpile and perform gradation testing on each sample according to AASHTO T 2, AASHTO T 248, Supplement 1004 (AASHTO T 11 where required), and moisture content per AASHTO T 255. Use dry gradations for determining the No. 200 (75 µm) sieve. Determin e the percent passing for each sieve size listed in Table 421.02 -3. Calculate the average of each sieve for all three tests. Ensure the average value for each sieve is within the requirements of Table

421.02 3. Do not begin production if not in compliance with gradation band and

stockpile tolerance. At a minimum test one sample taken from the stockpile randomly during each production day. Include additional testing when directed to sample and test by the Engineer. The Contractor may perform an additional aggregate test to verify results if first test is not in compliance with stockpile tolerance. Report and track all test results and monitoring trending of the aggregate gradation within the stockpile. Reject aggregate that does not meet the stockpile to lerance in Table 421.02 -3 compared to the approved JMF. Do not exceed the design gradation band for No. 200 sieve. For data collection by the Department, if requested by the Engineer, obtain a mix sample randomly during the day by dragging a tube sampler a cross material 421.12 221 under the mixer but before the spreader box as it moves forward. Obtain a 10 pound (4535 gram) minimum mix sample, put in a suitable plastic container, and provide to the Engineer.

C.Mixture Application. Ensure the Quality Control Manager a nd trained technicians perform and use the methods described in this section to control quality and measure compliance.
1.Supervise the mixing machine calibration, test strip application, and verify compliance before production begins.
2.Establish with the mix operator restrictive operating limits for use of total mixture water, additive, and mineral filler subject to weather conditions and course applied.
3.Maintain all calibration records and compare calibration results for each project through con struction season.
4.Direct all material input settings required to produce mix design compliance.
5.Verify mixture meets required mix time, set time and mix consistency.
6.Perform an aggregate moisture test at the start of each production day.
7.Communicate and direct any desired adjustments with the Binder supplier (asphalt emulsion) for mix and set time properties.
8.Evaluate roadway for determination of planned application rates and maintain direct communication with Department personnel, appli cation personnel, and Engineer on all compliance issues.
9.Verify and document that all cracks greater than 1/4 inch (6 mm) in width and all cracks longer than two feet (50 mm) have been filled and that the crack sealant is in compliance with thickness r equirements.
10.Monitor roadway during application for proper surface cleaning.
11.Monitor application of tack coat for proper coverage and document application rate.
12.Monitor mixture placement for consistency, uniformity of thickness across paving pass, and use of water spray bars.
13.Monitor mixture application rate and finishing methods to ensure uniform surface.
14.Monitor cross section compliance subject to course type specified.
15.Monitor set properties for opening to traffic and durability under traffic.
16.Monitor daily production reports for compliance with mix design tolerances.
17.Maintain each material usage by ticket weight and verify consistency to mixing machine calibrated use. 421.12 222 18. Direct adjustments of material settings and mixture subject to material test results and field performance.
19.Monitor haul trucks, mixing machine, and allied equipment for oil drippings, aggregate spillage and other factors that may affect the adherence or performance of the applied mixture.
D.Documentation . Provide the Engineer a daily report no later than the next calendar day (excluding Sundays) with the following:
1.A printout from the mixing machine showing the total pounds of aggregate, emulsion, and cement as well any other materials capable of being printed used for the day as part of the daily production report.
2.Project number, county, and route.
3.Date, air temperature, pavement temperature, and humidity.
4.Binder temperature, percent residue, and pounds per gallon (grams per liter)
5.Production report with course(s) applied, lane(s) completed, location of work, daily summary of each material used, application rate for each course and lane and total area per course.
6.Yield checks on application rate and complianc e with application placement requirements (four per day, minimum).
7.Gradation and moisture content (one random sample during the day and any other samples when directed by the Engineer).
8.Total gallons (L) of tack cost used and residual asphalt con tent.
9.Quality Control Tests and Reports.
10.Contractor representative’s signature. Provide a Bill of Lading for Binder and aggregate as requested or at project completion. . 421.1 3 Acceptance . Maintain continuous control of the Binder to dry aggregate proportioning to conform to the approved JMF(s) within a tolerance of ± 1.5 gallons per ton (± 6.3 L/metric ton). Control the spread rate to not less than the specified quantity of agg regate per square yard (square meter) on a dry weight basis. The Engineer will base acceptance of the binder -to-dry aggregate proportion and spread rate o n the Engineer’s summary of quantities used each day. The Engineer will approve and accept a day’s application of microsurfacing provided:
A.The Engineer’s summary indicates conformance with the above control requirements for pr oportioning and spread rate .
B.The course(s) applied are in compliance with the application requir ements of this specification.
C.The pavement cracks are sealed prior to p lacement of the microsurface.
D.The Quality Control requirements are met. 421.00 223 E. The pavement is uniform in composition and texture, free from excessive scratch marks, tears, rippling and other surface irregularities (segregation, raveling, rutting, holes, debris, etc.), longitudinal joints and lane edges coincide with any lane lines and edge lines a nd transverse joints are uniform, neat and provide a smooth transition. The spread rate requirement does not apply to rut fill courses if the Contractor filled the wheel paths according to this specification ..

421.14 Performance Review . Perform remedial actions for any defect

exceeding the threshold levels in Table 421. 14-1 for a period of two years from the date of substantial work complete as documented on the Department’s Form C -85. Contact the Department to schedule a final performance revi ew at least 60 days prior to the end performance review period. The Department will review the pavement before the end of the two -year performance review period to determine if remedial action is required. The Department will issue the results in writing t o the Contractor upon completion of the performance review. Remedial Actions. Perform Remedial Actions by October 15th of the same year as the review. If the Department determines that immediate repairs are necessary, due to a potential haza rd to the traveling public, the Department will notify the Contractor and establish a date that all repairs are to be finished. Provide construction traffic control when performing any work required or allowed by this specification in accordance with curr ent Department policy and the Ohio Manual of Uniform Traffic Control Devices. Obtain Department approval for the time the work will be performed. Provide approved materials, equipment, and labor to perform Remedial Actions at no additional cost to the Depa rtment. Prior to performing a Remedial Action, submit a Remedial Action plan to the DCE for approval. State in the plan when and how the Remedial Action will be performed; what material will be used; and how traffic will be controlled. Warrant Remedial Action work for the remainder of the warranty period. Use only microsurfacing for permanent repair and resurfacing areas. Perform temporary repairs using material approved by the DCE . Replace temporary repairs with a permanent repair as soon as weather permits. Replace pavement markings or raised pavement markers (RPM) removed, obliterated, or damaged while performing a Remedial Action with equivalent approved pavement markings or RPM products at no cost to the Department. The Contractor is not re sponsible for pavement damage beyond the Contractor’s control (i.e., car fire, oil spill, structural issues etc.). 421.15 224 TABLE 421.14 -1 Defect Type Threshold Level (6) (allowable distress levels) Non-uniform texture (1) 300 square feet (28 m2) Surface Loss (2) 20 square feet (1.8 m2) Raveling (3) 300 square feet (28 m2) Rutting (4) (5) 0.25 inch (6.5 mm) continuous in any Segment. Notes:

1.Texture inconsistencies in either the transverse and or longitudinal direction.
2.Loss of surface by traffic wear, debonding, or delamination.
3.“Moderate” level raveling as defined in the Strategic Highway Research Program (SHRP) “Distress Identification Manual for the Long -Term Pavement Performance Project” (SHRP - P-338).
4.Measure the wheel path with a 4 foot (1.2 m) straight edge.
5.Only applies during the first 120 days of Warranty or after any Warranty work.
6.Based on 1000 foot (300 m) lane Segment. The beginning of a Segment is the beginning of any distress typ e. If any 1000 foot (300 meter) lane segment has repairs or defects greater than 5 percent of the area, resurface with a full lane width of microsurfacing meeting the requirements of this specification.

421.15 Method of Measurement. The Department wil l measure

Microsurfacing, Surface Course and Microsurfacing, Leveling Course by the number of square yards (square meters), complete and accepted in place. The Department will base the width of the pavement course on the width shown on the plans, specified in this specification, or directed by the Engineer. The Department will measure the length along the centerline of each roadway or ramp. The Department will measure the number of raised pavement markers removed. The Department will measure Microsurfacing, Rut Fill Course by the number of tons (metric tons) of dry aggregate used, complete and accepted in place. The Department will base the weight of the dry aggregate used on the calibrated unit weight as reported from the aggregate delivery belt .

421.16 Basis of Payment. The cost of tack coat and Item 423 Crack Sealing is

incidental to microsurfacing. The Department will pay for removal of existing pavement markings according to 421.08 under Items 643, 644, 645, 646, 647, and 648 as specified. The Department will pay for removal of existing raised pavement markers according to Item 621 Raised Pavement M arkers Removed. The Department will pay for the construction of accepted test strips at the individual bid prices for the courses constructed. The Department will pay for accepted quantities at the contract prices as follows : Item Unit Description 421 Square Yard Microsurfacing, Surface Course (Square Meter) 422.01 225 421 Square Yard Microsurfacing, Leveling Course (Square Meter) 421 Ton Microsurfacing, Rut Fill Course (Metric Ton) ITEM 422 CHIP SEAL

422.01 Description

422.02 Materials

422.03 Equipment

422.04 Weather Limitations

422.05 Test Strip

422.06 Surface Preparation

422.07 Binder Application

422.08 Cover Aggregate Application

422.09 Construction Operation

422.10 Quality Control

422.11 Acceptance

422.12 Performance Review

422.13 Method of Measurement

422.14 Basis of Payment

422.01 Description. This work consists of preparing and applying a single or

double chip seal. Warrant exposed chip seals for two years.

422.02 Materials. Use polymer emulsified binder conforming to 702.16 Type

A. Provide aggregate consisting of washed limestone or washed dolomite conforming to 703.05. Do not use an aggregate source designated with “SR” on the Aggregate Source Group list in accordance with 703.01.F. Additionally the following requirements apply: Stockpile the materia l to be used for the chip seal at the aggregate source. Obtain five (5) samples from the stockpile and perform gradation testing on each sample and determine the percent passing for each sieve size listed in Table 422.02 -

A.Calculate the total range for the No. 8 (2.36 mm) sieve for all five samples. The range will not exceed 6%.
B.Calculate the percent passing the No. 200 (75 µm) sieve for each sample. No single sample value will exceed 2.0 percent.
C.Calculate the average of each sieve for all five s amples. Ensure the average value for each sieve is within the requirements of Table 422.02 -1. Submit a letter to the Engineer and District Testing containing the JMF gradations and the calculations to show the cover aggregate meets requirements. If a stag ing location will be used for the chip seal aggregate first move the initially tested aggregates from the aggregate source stockpile to the staging location and 422.03 226 construct a staging stockpile. Then obtain five (5) aggregate samples from the staging location stockpile and perform gradation testing on each sample to determine the percent passing for each sieve size listed in Table 422.02 -1. Evaluate the staging location aggregate samples the same as the aggregate source samples except allow an average for the No. 200 (75 µm) sieve not greater than 1.7 percent. Submit the JMF gradations from the staged stockpile and the calculations to show the cover aggregate meets requirements in letter form to the Engineer and District Testing. If the chip seal aggregates fai l to meet requirements, either at the aggregate source or the staging location, re -wash and/or rework the aggregate materials and retest the new stockpiles. TABLE 422.02 -1 Sieve Size Total Percent Passing Type A Type B 1/2 inch (12.5 mm) 100 3/8 inch (9.5 mm) 85 to 100 100 No. 4 (4.75 mm) 5 to 25 85 to 100 No. 8 (2.36 mm) 0 to 10 5 to 30 No. 16 (1.18 mm) 0 to 5 0 to 10 No. 200 (75 µm) 0 to 1.5 [1] 0 to 1.5 [1] [1] Washed gradation value The District may obtain and test verification samples of the JMF aggregates at any time. If a single verification sample is either outside the values in Table 422.02 - 1 with the exception that the No. 200 (75 µm) value is not greater than 2.0 percent, the district will obtain five (5) samples and retest to determ ine if the aggregate JMF falls within the limits of Table 422.02 -1. If the JMF verification test doesn’t meet the source or staging location limits the stockpile is not acceptable.

422.03 Equipment. Provide equipment conforming to the requirements of this

section. Obtain approval of equipment before starting the job. Use equipment for binder distribution conforming to 407.03, except ensure that it has a computerized rate control that automatically adjusts the binder pump to the unit ground speed and has a g auge or meter in plain view for reading gallons (liters). Use appropriate spray nozzles for the material and rate specified. Adjust spray bar and nozzles to provide triple lap coverage. Use Type II pneumatic tire rollers conforming to 401.13 with the excep tion of the requirements of Table 401.13 -1 Roller Capacity. Use a minimum of 3 Type II pneumatic tire rollers capable of ballast loading. The roller weight must be between 6 to 8 Tons (5 to 7 metric tons) each to achieve a minimum contact pressure of 80 psi (550 kPa). Tires must be inflated to the proper pressure as specified by the roller manufacturer. Use self -propelled aggregate spreaders with a variable width aggregate hopper capable of placing from 8 to 16 feet (2.4 to 4.8 m) in any increment and a com puterized rate control that automatically adjusts the aggregate output to the unit ground speed. Equip spreaders with pneumatic tires, a screen to remove 422.04 227 oversized material, revolving cylinders, and adjustments necessary to produce a uniform distribution o f particles at the specified rate. Furnish power sweepers, pickup sweepers, or rotary brooms as required for the initial surface preparation and for removing loose aggregate particles. Furnish accurate thermometers for determining any of the applicable te mperature requirements of this specification.

422.04 Weather Limitations. Place the chip seal when the pavement

temperature is between 60 F (16 C) and 140 F (60 C). Do not schedule the performance of this work for the time period before May 1 or after September 15. Do not place chip seal if any of the following conditions exist:

A.The atmospheric temperature is below 70 °F (21 °C).
B.Impending weather conditions do not allow for proper curing.
C.If temperatures are forecasted below 50 °F (10 °C) with in 24 hours from the time of work.

422.05 Test Strip. Construct a continuous 1000 foot (300 m) long by lane width

test strip in the presence of the Engineer. Do not waive test strips regardless if the same materials have been used on another project. Determine the initial binder application rates and aggregate application rates for the test strip to achieve 2/3 aggregate embedment. For a single chip seal, Type A, an initial target rate of 0.37 ±0.03 gallon per square yard (1.68 L/m²) is recommended for the test strip. For a single chip seal, Type B, an initial target rate of 0.35 ±0.03 gallon per square yard (1.58 L/m²) is recommended for the test strip. For double chip seal, a target rate of 0.36 ±0.03 gallon per square yard (1.63 L/m²) for the first c ourse and 0.33 ±0.05 gallon per square yard (1.49 L/m²) for the second course is recommended for the test strip. Notify the Engineer of the initial target rates. Calibrate the aggregate spreader to ensure a uniform application rate in both the transverse and longitudinal directions. Verify the application rates with a one square yard (one square meter) piece of cardboard or other material to collect and weigh the aggregate. Adjust spreader rates to maintain application rate within 10% of the target rate. Do not over apply cover aggregate relying on vacuum and broom sweeping to pick up all excess. Amounts of loose aggregate that create a nuisance to the public will result in work stoppage. If work is stopped by the Engineer recalibrate the aggregate spreader determining a new application rate and apply cover aggregate at the new rate. Verify the aggregate gradation meets 422.10.C. during the test strip and provide the results to the Engineer. The Engineer and Contractor will review the test strip the next wo rkday for streaking, ridging, bleeding, aggregate loss or other problems. If the review shows the test strip meets the requirements of 422.11 and the application rate and quality control tests show all is in control compared to the JMF, then progress with the work. Should problems be noted, the Engineer may require another test strip. 422.06 228 JMF gradation targets may be adjusted once within the limits of Table 422.02 -1 based on results of the approved test strip. Provide adjusted gradation targets to the Engineer and the DET prior to progressing with the work.

422.06 Surface Preparation. Clean the pavement according to 407.05. If

necessary, clean areas of the pavement with a hand broom. Remove all existing pavement markings, except 740.02 (traffic paint), using an abrasion method conforming to 641.10. Remov e the raised pavement markers according to 621.08 . Do not place material until the Engineer approves the existing surface.

422.07 Binder Application. Before applying binder, ensure that sufficient

cover aggregate is available for immediate application. Apply the binder at the target rate(s) established from a successful test strip. Ensure distributor spray bar and nozzles are set to provide triple overlap coverage with no streak or drill patterns on the road surface. Maintain the binder temperature from 15 0 to 185 F (65 to 85 C) during construction, including the start of each day. Reheat the binder at a rate of no more than 25 F (14 C) per hour, when the binder is allowed to cool below 150 F (65 C). If the target application rates are not the optimum application rates to achieve proper stone embedment during the actual application, immediately notify the Engineer. Proper stone embedment is 2/3 of the stone chip height and can be checked by pulling out several chips by hand. Adjust and document the new application rate by stationing. Recheck stone embedment after adjustment and obtain the Engineer’s approval of the new rate. Do not allow the binder to streak on the road surface. If the Engineer determines that streaking is occurring, cease operations until the Engineer is satisfied that streaking has been eliminated. At the beginning and at the end of a contract section, start and stop the application on a removable protective cover (paper, metal sheets, or other suitable material) sufficiently wide en ough to allow full application on the surface being treated. Make transverse and longitudinal laps in such manner to ensure that the texture of the finished surface is uniform and continuous. To prevent lapping at transverse junctions, promptly shut off th e binder spray at the end of the application. Before continuing the application, place a removable protective cover a sufficient distance back from the joint on the cover aggregate so the sprayers are operating at full force when the distributor has attain ed the predetermined speed upon reaching the uncovered surface. Upon completion, remove all removable protective covers.

422.08 Cover Aggregate Application. Verify the application rate with a one

square yard (one square meter) piece of cardboard or other m aterial to collect and weigh the aggregate before placing binder. Adjust if necessary and re -verify. Record final results and inform the Engineer. Immediately after applying the binder, apply cover aggregate uniformly without ridges or laps at the specifie d rate adjusted as directed by the Engineer to produce a minimum of excess loose particles. Spread the 422.09 229 material in such manner that the tires of the truck or aggregate spreader at no time contact the uncovered and newly applied binder. Before rolling, corr ect deficiencies in the application of cover aggregate in a manner satisfactory to the Engineer. After rolling, protect the surface from traffic damage during the period required for the binder to cure sufficiently and prevent dislodging of the aggregate p articles by normal traffic. During this period and as directed by the Engineer, correct deficiencies in cover aggregate by spreading additional aggregate or by light brooming. Apply cover aggregate at a rate necessary to provide full coverage of the binder and to avoid tracking. Do not over apply cover aggregate relying on vacuum and broom sweeping to pick up all excess. Nuisance to the public amounts of aggregate will result in work stoppage. If work is stopped by the Engineer recalibrate the aggregate spr eader determining a new application rate and apply cover aggregate at the new rate. If the target rate needs adjustment due to the gradation of the aggregate or due to existing surface conditions of the pavement, immediately notify the Engineer and documen t the new rate by stationing.

422.09 Construction Operation. Establish stations at 1000 foot (300 m)

intervals on the entire project before placing materials. Clearly identify and maintain the stations until project completion. Keep the binder distributor , aggregate spreader, and rollers as close to each other as possible. Do not allow the binder distributor to be more than 150 feet (45 m) ahead of the aggregate spreader. Perform rolling immediately after placing the aggregate, but before the binder sets u p. Do not leave aggregate unrolled for more than 5 minutes. Perform a minimum of two complete roller passes over the aggregate. A single complete pass is forward and backward over the same path. For each new pass, overlap the previous pass by about one -half the width of the roller. Use a minimum of three rollers, and roll in a longitudinal direction at a speed not greater than 5 miles per hour (8 km/h). Do not operate rollers at speeds that cause pick -up or dislodging of aggregate particles. Within 4 hours of placement but after the binder sets, sweep the pavement as needed to remove all loose aggregate. Use pickup sweepers in curbed areas and where aggregate shoulders do not exist. Do not sweep loose aggregate onto lawns, curbed areas, or intersections. If the pavement cannot be swept within the 4 -hour period due to problems associated with the stone moisture, binder, breaking, humidity, or other unknown, the Engineer may suspend the operation until the problem is resolved or more suitable conditions are obt ained to maintain the 4 -hour time frame for sweeping. Extend sweeping 1 foot (0.3 m) beyond the edge of the chip seal to help prevent migration of loose aggregate back onto the pavement. Do not re -use aggregate from a chip seal that is swept from the pavem ent or that is already loose off the pavement edge. Perform a final sweeping immediately before application of permanent pavement markings or a fog seal, if a fog seal is required. Use pickup sweepers in curbed areas and where aggregate shoulders do not e xist. Do not sweep loose aggregate onto 422.10 230 lawns, curbed areas, or intersections. The Contractor is responsible for claims of damage to vehicles prior to the final sweeping. Wait at least 24 hours before placing the second course of a double chip seal. Ensure the first course of a double chip seal meets the gradation of Table 422.02 -1 Type A and the second course meets the gradation of Table 422.02 -1 Type B. Ensure that the first course meets requirements of this specification and is cured and capable of withs tanding construction traffic without damage. If loose aggregate is evident, sweep the first course again just prior to placing the second course. Correct damage to the underlying chip seal before placing the second course. Place the longitudinal constructi on joint on a lane line or as directed by the Engineer. For double chip seal, place the longitudinal construction joint for the first course 6 inches (150 mm) off the centerline and place the second course so the longitudinal joint is at the centerline. Before opening to traffic, post the roadway with “Loose Gravel/Fresh Tar ” signs and a “35 mph” speed plaque mounted below the sign. Ensure that signs conform to Item 614. Place these signs in the advance warning area and just beyond each intersecting road throughout the length of the activity area . Remove the signs as directed by the Engineer . On two -lane roads or pavements where traffic is maintained on a chip seal constructed that workday, provide a traffic con trol pilot vehicle operated at no more than 25 miles per hour (40 km/h) in the immediate work area. Protect all utility castings, monument boxes, and other similar items using tarpaper or other approved material. Remove protection before sweeping and openi ng to traffic.

422.10 Quality Control

A.General . Use the methods described in this section to measure compliance. If test results exceed any of the identified quality control tolerances, stop placement and immediately notify the Engineer and District Testing. Identify the cause of exceeding any of the identified quality control tolerances and document in detail the corrective action necessary to bring the deficiency into compliance. Obtain the Engineer’s approval before resuming work. Upon resuming wor k, take another sample and immediately provide the test results to the Engineer. If the tolerances are exceeded, stop the work. Do not resume work until approved by the Engineer and District Testing. The Department can obtain samples of materials at any ti me. Aggregate samples can be taken from sources, on -hand stockpiles or the aggregate spreader box. Work can be stopped and materials can be rejected on the basis of poor Department test results. Any deficient materials found to be incorporated in the proje ct will be evaluated per Supplement 1102.
B.Binder. Within one hour of start of production obtain and label a binder sample from the distributor truck and give the sample to the Engineer the same day. Provide and sample the binder in one quart plastic con tainers with plastic screw tops. Label and retain one sample per each additional day for the Department. Take more samples when requested by the Engineer. 422.10 231 For the binder application rate, as determined by a yield check, do not exceed a tolerance of ±0.02 gallon per square yard (0.09 L/m²) from the established application rate.
C.Coarse Aggregate. At a minimum test one sample taken from the aggregate spreader box at production start and sample and test one sample from the aggregate spreader box randomly du ring the day. Provide the Engineer with a split sample that is a minimum of 22lbs (10,000g) from each day’s random sample for verification testing. An aggregate spreader box sample may be taken by laying a piece of suitable material under the spreader as i t moves forward. Include additional testing when directed to sample and test by the Engineer. Sample and test aggregate according to AASHTO T 2, AASHTO T 248, and Supplement 1004 (AASHTO T 11 where required). Use washed gradations for determining the perce nt passing the No. 200 (75 µm) sieve. Submit daily test results to the Engineer prior to beginning the next day’s production. The Contractor may use additional tests. These may include dry gradations for control purposes but acceptance of on -hand aggregate will be based on washed gradations only. Reject and do not use aggregate creating dusting nuisance to the public on the project. Reject truckloads of aggregate if water is seen coming from the truck bed. Reject aggregate that does not meet the following r equirements: No. 4 (4.75 mm) sieve from JMF ±5.0% No. 8 (2.36 mm) sieve from JMF ±3.0% No. 200 (75 µm) sieve from JMF ±1.0%, 2.05% upper limit Aggregate moisture content (by dry weight) 4.0% max. for aggregates with an Absorption > 2.0%, 3.0% max. for aggregates with an Absorption ≤ 2.0%
D.Documentation. Provide the Engineer a daily report with the following:
1.Project number, county, route.
2.Date, air temperature, pavement temperature, and humidity.
3.Binder temperature.
4.Beginning and ending stations.
5.Target binder and aggregate application rates.
6.Yield checks on binder (three per day, minimum).
7.Yield checks on aggregate (three per day, minimum).
8.Gradation, moisture content, and station (One sample from spreader box at production s tart, one random sample during the day and any other samples when directed by the Engineer).
9.Length, width, and total area.
10.Condition of “Loose Stone” signs with “35 mph” speed plaques.
11.Contractor representative’s signature. 422.11 232 Provide a bill of lading for binder and aggregate when requested or at project completion.

422.11 Acceptance . Inspect the chip seal daily for deficiencies resulting from

poor workmanship, flushing, tracking from equipment, surface patterns, loss of stone, and sweeping. Insp ect workmanship for untreated areas, minimum overlap on longitudinal joints, and minimum overlap on construction joints. Verify the following for daily acceptance:

A.Finished surface has no more than four tears or untreated areas greater than 1 inch (25 m m) wide and 4 inches (100 mm) long in any 120 square yard (100 m2) area.
B.Joints appear neat and uniform without buildup, uncovered areas, or unsightly appearance.
C.Longitudinal joints have less than a 2 inch (50 mm) overlap on the adjacent passes.
D.Transverse joints have no more than 1/4 -inch (6 mm) difference in elevation across the joint as measured with a 6 foot (2 m) straightedge.
E.Chip seal edge is neat and uniform along the roadway lane, shoulder, and curb lines.
F.Chip seal edge has no m ore than 2 inch (50 mm) variance in any 100 feet (30 m), along the roadway edge or shoulder.
G.Typical stone chip embedment is 2/3 of typical stone chip height. For project acceptance, the Contractor and Engineer will review the completed work 25 to 35 d ays after placement. The finished work must meet the following requirements: Defect [1] Severity Surface patterns Alternate lean and heavy lines (Ridges or streaking over the surface) Bleeding/flushing Distinctive appearance (Excess binder on surface) Loss of cover aggregate Patches or lines of aggregate lost from surface [1] No more than 20% of any 120 square yard (100 m2) area can contain any defect. The measurement of the 120 square yard (100 m2) area begins at the start of the defect. Perform all corrective work to the satisfaction the Engineer.

422.12 Performance Review . Perform remedial actions for any defect

exceeding the threshold levels in Table 422.12 -1 for a period of two years from the date of substantial work complete as documented on the Department’s Form C -85. Contact the Department to schedule a final performa nce review at least 60 days prior to the end performance review period. The Department will review the pavement before the end of the two year performance review period to determine if remedial 422.13 233 action is required. The Department will issue the results in w riting to the Contractor upon completion of the performance review. Remedial Actions . Perform Remedial Actions between May 1 and September 1. If the Department determines that immediate repairs are necessary, due to a potential hazard to the traveling publ ic, the Department will notify the Contractor and establish a date that all repairs are to be finished. Provide construction traffic control when performing any work required or allowed by this specification during the warranty period in accordance with c urrent Department policy and the Ohio Manual of Uniform Traffic Control Devices. The Department will approve when the work is performed. Provide approved materials, equipment, and labor to perform Remedial Actions at no additional cost to the Department. Prior to performing a Remedial Action, submit a Remedial Action plan to the DCA for approval. State in the plan when and how the Remedial Action will be performed; what material will be used; and how traffic will be controlled. Warrant Remedial Action work for the remainder of the warranty period. Replace pavement markings or raised pavement markers (RPM) removed, obliterated, or damaged while performing a Remedial Action with pavement markings or RPMs equal approved products at no cost to the Department. The Contractor is not responsible for pavement damage beyond the Contractor’s control (i.e., car fire, oil spill, structural issues, etc.). TABLE 422.12 -1 Each segment will be 300 ft (91 m) in length and the width of the lane. The beginning point of a 300 f t (91 m) segment starts at the beginning of any individual defect type. For loss of aggregate, the beginning point of a 300 ft (91 m) lane segment will exclude locations where vehicles turn from or onto other state highways. Defect Severity Threshold Leve ls Surface Patterns Severe - light and heavy lines over the pavement surface 40% of segment length affected, continuous or localized Bleeding/ Flushing Moderate - excess binder on surface (loss of stone/tire contact) not subject to wearing off quickly 5% of segment length affected continuously or total of 20% localized problems Loss of Aggregate Moderate - patches of aggregate loss 10% of segment length affected continuously or total of 20% localized problems

422.13 Method of Measurement. The Depart ment will measure Single Chip

Seal or Double Chip Seal by the number of square yards (square meters), completed and accepted in place. The Department will determine the width by measuring the actual width of the chip seal. The Department will determine the length along the centerline of each roadway or ramp. 422.14 234 The Department will measure the number of raised pavement markers removed .

422.14 Basis of Payment. The Department will not pay for materials,

equipment, or labor to m ake corrections. The Department will pay for removal of existing pavement markings according to Items 643, 644, 645, 646, 647, and 648 as specified. The Department will pay for removal of existing raised pavement markers according to Item 621 Raised Pavement Markers Removed . The Department will pay for accepted quantities at the contract prices as follows: Item Unit Description 422 Square Yard Single Chip Seal, Type __ (Square Meter) 422 Square Yard Double Chip Seal (Square Meter) ITEM 423 CRACK SEALI NG, HOT APPLIED

423.01 Description

423.02 Materials

423.03 Equipment

423.04 Weather Limitations

423.05 Preparation

423.06 Mixing Type II and III

423.07 Application of Sealant

423.08 Opening to Traffic

423.09 Method of Measurement

423.10 Basis of Payment

423.01 Description. This work consists of preparing and sealing pavement

cracks with a hot applied crack sealant.

423.02 Materials. Furnish hot applied crack sealant, of the type specified,

conforming to: Type I ................................ ................................ ..... 705.04 Type II ................................ ................................ 702.17.B Type III ................................ ............................... 702.17.C Type IV ................................ ............................... 702.17.D Furnish Type I crack sealant material according to the Department’s TE -24 system before shipping to the project. Obtain approval of other crack sealants according to 702.17.

423.03 Equipment. Equipment used in the performance of this work is subject

to the Engineer’s approval and to the requir ements of 108.05. For Type I crack sealant, heat the sealant in a kettle or melter constructed as a double boiler, with the space between the inner and outer shells filled with oil or 423.04 235 other heat -transfer fluid. Use a kettle or melter with positive temperat ure control of the oil bath, and provide a mixing vat, mechanical agitation, and recirculating pumps. Do not apply direct heat to the sealant. For Types II, III, and IV crack sealants, heat the sealant in a kettle or melter constructed as a double boiler, with the space between the inner and outer shells filled with oil or other heat -transfer fluid. Use a kettle or melter with separate thermometers for the oil bath and mixing vat. Equip the kettle with a full sweep type agitator. Also, equip the kettle with a 2-inch (50 mm) minimum recirculating pump to provide circulation of the materials when not applying the crack sealant. Do not apply direct heat to the sealant. For Types I and IV crack sealants, use a mechanical applicator wand capable of continuously f eeding the sealant through nozzles shaped to penetrate the cracks. A positive sealant flow shutoff mechanism is required. Ensure that the wand produces a band according to the tolerances of 423.07. For Types II and III crack sealants, use a mechanical appl icator wand head capable of placing the crack sealant according to the tolerances of 423.07 while filling the cracks. A positive sealant flow shutoff mechanism is required. Use portable air compressors capable of furnishing at least 100 pounds per square inch (690 kPa) of air pressure at the nozzle. Use compressors equipped with traps that maintain the compressed air free of oil and water. Use water cleaning equipment capable of delivering water at 2000 pounds per square inch (14 MPa) of pressure from a noz zle to the crack being cleaned. Use a propane lance unit capable of producing a blast of hot air that operates at 1000 F (538 C) and a gas velocity of 2000 feet per second (600 m/s). Use mechanical and power driven routing and sawing equipment capable of following close to the path of cracks and of widening the cracks to the required dimension without causing excessive spalling or damage to the adjacent pavement. For sawing equipment, use diamond saw blades with a diameter of 8 inches (200 mm) or less.

423.04 Weather Limitations. Do not seal cracks if the surface is visibly damp

or the temperature is below 45 F (7 C).

423.05 Preparation. Fill all visible cracks according to 423.07 or as directed by

the Engineer. If routing is specified, rout cracks with an opening less than 3/4 inch (19 mm) to provide a sealant reservoir with a nominal size of 3/4 inch (19 mm) wide by 1 inch (25 mm) deep. If sawing is specified, saw all cracks to 3/4 to 7/8 inch (19 to 22 mm) wide and 7/8 to 1 inch (22 to 25 mm) deep. Use hand tools or a lightweight chipping hammer to remove all slivers of asphalt concrete less than 1 inch (25 mm) wide remaining along the crack after sawing. Immediately before sealing, sandblast both faces of the sawed crack to remove all contamination and to texture the faces. If the crack below the sealant reservoir is greater than 3/8 inch (10 mm) wide, insert a backer rod into the crack to form the bottom of the reservoir at the proper depth. 423.06 236 Before applying the hot sealant, clean cracks by an approved method or methods to remove dust, dirt, moisture, vegetation, and other foreign material. Keep the cracks clean and dry until all sealing operations are completed.

423.06 Mixing Type II and III. Use weigh tickets in determining the specified

proportion of fiber to blend into the binder. Add fibers to the binder, and mix thoroughly in the kettle. Do not allow the temperature of the sealant in the field application to exceed the safe heating temperature recommended by the manufacturer. Do not heat Type III crack sealant to greater than 295 F (146 C).

423.07 Application of Sealant. Perform the crack sealing operation within 250

feet (76 m) of the cleaning operation. Seal only cracks that are wide enough to permit entry of sealant. Seal tightly closed cracks (less than 1/4 -inch (6 mm) wide) only if they show signs of raveling or spalling. Do not seal cracks greater than 1 -inch (25 mm) wide, and do not seal spalls or cavities greater than 4 inches (100 mm) wide, unless otherwise directed. For Types I and IV crack sealants, fill the entire crack reservoir with the sealant from the bottom up to approximately 1/16 inch (2 mm) above the pavement surface. Immediately scrape the filled cracks with a V -shaped or U -shaped squeegee, or similar hand tool, to smooth the overfill. This may require more than one application of sealant. The Engineer will not accept the work if the band of sealant on the pavement surface is greater than 2 inches (50 mm) wide. For Types II and III crack sealants, place the sealant such that it fills the cracks with a band of sealant within 2 to 4 inches (50 to 100 mm) wide. The Engineer will not accept the work if the thickness on the pavement is greater than 3/16 inches (5 mm).

423.08 Opening to Traffic. Do not allow traffi c on the sealant until it has cured

and the possibility of tracking no longer exists. However, if the Engineer determines it is necessary to allow traffic to pass over the sealant before adequate curing, dust Portland cement or other approved material over sealed cracks to eliminate pickup or tracking.

423.09 Method of Measurement. The Department will measure Crack Sealing,

of the type specified, by the number of pounds (kilograms) of hot applied sealant in place, completed, and accepted. The Department wil l measure Crack Sealing, of the type specified, by the square yards of sealing completed and accepted.

423.10 Basis of Payment. The Department will pay for accepted quantities at

the contract prices as follows: Item Unit Description 423 Pound (Kilogram) Crack Sealing, Type I or Square Yard (Square Meter) 423 Pound (Kilogram) Crack Sealing with Routing, Type I or Square Yard (Square Meter) 424.01 237 423 Pound (Kilogram) Crack Sealing with Sawing, Type I or Square Yard (Square Meter) 423 Pound (Kilogram) Crack Sealing, Type II or Square Yard (Square Meter) 423 Pound (Kilogram) Crack Sealing, Type III or Square Yard (Square Meter) 423 Pound (Kilogram) Crack Sealing, Type II or III or Square Yard (Square Meter) 423 Pound (Kilogram) Crack Sealing, Type IV or Square Yard (Square Meter) ITEM 424 FINE GRADED POLYMER ASPHALT CONCRETE

424.01 Description

424.02 Composition

424.03 Materials

424.04 Mixing

424.05 Weather Limitations

424.06 Spreading, Compacting and Finishing

424.07 Surface To lerances

424.08 Acceptance

424.09 Method of Measurement

424.10 Basis of Payment

424.01 Description. This work consists of constructing a surface course of

aggregate and polymer modified asphalt binder mixed in a central plant and spread and compacted on a prepared surface. The requirements of 401 apply, except as modified by this specification.

424.02 Composition. For Type A mixes use 8.5 percent modified asphalt binder

by total mix weight. For Type B mixes, submit a proposed JMF according to 441.02 to t he Laboratory that meets the requirements of a Type 1 surface course, except as follows:

A.Minimum VMA, 15.0 percent
B.Minimum total binder content, 6.4 percent
C.Design air voids, 4.0 percent
D.For projects with less than 1500 trucks use 50 blows, for projects with greater than or equal to 1500 trucks use 75 blows. If multiple traffic segments occur on a project use 75 blows for the project.

424.03 Materials. Furnish clean, uncoated aggregate conforming to the

applicable requirements of Table 424. 03-1 and quality requirements of 703.05. 424.04 238 Use a PG 76 -22M asphalt binder; or a PG 64 -22 asphalt binder modified by adding 5.0 ±0.3 percent by weight Styrene Butadiene Rubber (SBR) solids and meeting the requirements of PG 76 -22. Provide SBR conforming to 70 2.14. Provide mineral filler conforming to 703.07. Provide binders conforming to 702.01. Ten percent RAP may be used in a Type B mix if all requirements of footnote [3] are met by the RAP. Do not use RAP in a Type A mix. TABLE 424.03 -1 - MIX GRADATION Sieve Size Total Percent Passing Type A [1][2] Type B [1][3][4] 1/2 inch (12.5 mm) 100 3/8 inch (9.5 mm) 100 95 to 100 No. 4 (4.75 mm) 95 to 100 85 to 95 No. 8 (2.36 mm) 90 to 100 53 to 63 No. 16 (1.18 mm) 80 to 100 37 to 47 No. 30 (600 µm) 60 to 90 25 to 35 No. 50 (300 µm) 30 to 65 9 to 19 No. 100 (150 µm) 10 to 30 -- No. 200 (75 µm) 3 to 10 3 to 8 [1] Gradation includes any mineral filler and is specified in percent passing. [2] Use natural sand with at least 50 percent silicon dioxide by weight according to ASTM C 146. Include with a JMF submittal certified test data from an AASHTO accredited laboratory showing conformance to the 50 percent silicon dioxide requirement. Ensure data is no more than one year old at time of submittal. [3] Fine Aggregate - Use natural sand with at least 50 percent silicon dioxide by weight according to ASTM C 146. Include with a JMF submittal certified test data from an AASHTO accredited laboratory showing conformance to the 50 percent silicon dioxide requireme nt. Ensure data is no more than one year old at time of submittal. For 50 blow mixes, use no more than 20 percent limestone sand, No. 10 limestone, or combination of both by weight of total aggregate. For 75 blow mixes, use 20 percent limestone sand, No. 1 0 limestone, air cooled slag sand or combination thereof by weight of total aggregate. If 10 percent RAP is used the silicon dioxide content of the total natural sand blend must be at least 50 percent. Contact OMM for guidance on submitting RAP aggregate s ilicon dioxide data. [4] Coarse Aggregate - For 50 blow mixes, for the final blend of all coarse aggregate use a minimum 10 percent two or more fractured faces aggregate. For 75 blow mixes, use 100 percent two or more fractured faces aggregate. Meet the t wo or more fractured faces aggregate criteria of ASTM D5821 -13.

424.04 Mixing. Ensure the mixing plant conforms to 402. Discharge the mix

from the plant at temperatures from 335 °F to 370 °F (168 °C to 188 °C) for hot mix asphalt or 300 °F to 340 °F (149 °C to 171 °C) for warm mix asphalt.

424.05 Weather Limitations. Do not place the asphalt concrete when the

surface of the existing pavement is less than 60 °F (15 °C) or the air temperature is less than 60 °F (15 °C).

424.06 Spreading Compacting and Finis hing. Compact Type A or B mixes

conforming to 401.13 and 401.16. If compacting a mixture 1 inch (25 mm) thick or less do not use a spreading rate that exceeds twice the total capacity of the rollers in use. Use a minimum of two rollers. Do not allow traffi c on the compacted mixture until it has cooled sufficiently to prevent damage.

424.07 Surface Tolerances. Ensure the completed surface course conforms to

401.19 424.08

239 Remove raised pavement markers according to 621.08. The Contractor may fill the depression cau sed by the removal of the casting with material meeting this specification.

424.08 Acceptance. For Type A mixes comply with acceptance requirements of

301. For Type B mixes comply with all requirements of 448.

424.09 Method of Measurement . For Type A mixes use a unit weight

conversion of 1.75 tons/cubic yard (2.08 metric tons/cubic meter). The Department will measure the number of raised pavement markers removed.

424.10 Basis of Payment. The Department will pay for removal of existing

raised pavement marker s according to Item 621 Raised Pavement Markers Removed. The Department will make payment for accepted quantities, completed in place, at the contract price as follows: Item Unit Description 424 Cubic Yard Fine Graded Polymer (Cubic Meter) Asphalt Concrete, Type A 424 Cubic Yard Fine Graded Polymer (Cubic Meter) Asphalt Concrete, Type B ITEM 441 ASPHALT CON CRETE - MIX DESIGN A ND QUALITY CONTROL

441.01 Description

441.02 Composition

441.04 Antistrip Additive

441.05 JMF Field Adjustment

441.06 Monitoring

441.07 Quality Control Program

441.08 Testing Facilities

441.09 Quality Control Tests

441.10 Control Charts

441.11 Quality Control Reports

441.12 Mixture Deficiencies

441.13 Acceptance

441.14 Basis of Payment

441.01 Description . This work consis ts of constructing a surface course or an

intermediate course of aggregate and asphalt binder mixed in a central plant and compacted on a prepared surface. This specification includes general requirements applicable to all types of asphalt concrete pavemen ts where the Contractor is responsible for performing the mix design and quality control. Deviations from these general requirements will be covered in the specific requirements for each type. The requirements of Item 401 apply, except as follows. 441.02 240 Control all production processes to assure the Engineer that the mixture delivered to the paving site is uniform in composition, conforms to the specification requirements and that the placed mixture is free of any defect (e.g. segregation, tenderness, lack of mix ture and texture uniformity, raveling, flushing, rutting, holes, debris etc.) within the Contractor’s control at project completion. When specified, provide anti -segregation equipment for all courses of uniform thickness in accordance with 401.12.

441.02 Composition. Compose the asphalt concrete of approved aggregates,

asphalt binder and, if required, other modifiers. Develop a JMF to comply with the mix design criteria and submit it to OMM on approved forms at least two weeks prior to the start of product ion for preliminary approval. OMM may require additional time prior to preliminary approval to perform tests on lab or plant produced mixtures to ensure adequate mix performance. OMM will notify the Contractor if additional time for testing is required. Based on the results of this testing, OMM may require the Contractor to design a new JMF. Perform the mix design and supply all required data in a manner taught in Level 2 Asphalt Technician School, Level 3 Asphalt Mix Design School and in the Asphalt Instit ute Manual Series No. 2. OMM may visit the Level 3 mix design lab for review. Use a 2 hour cure for all mix samples. Ensure the cure temperature and specimen compaction temperature are the same. Select the JMF asphalt binder content using the Design Air V oids and ensure the JMF meets the other requirements of Table

441.02 1. Determine Air Voids from specimens prepared and tested according to

Supplement 1036. Provide a mix design with at least four asphalt binder content points, including a minimum of two p oints above and two points below the JMF asphalt binder content. Submit no more than two JMFs for each asphalt concrete pay item per project. Additional submittals are at the discretion of OMM. Unless otherwise directed submit a 5 pound (2500 g) minimum u ncompacted sample (all mixes) representing the JMF. Submit additional samples as requested by OMM. Do not start mix production without a preliminary JMF approval and 48 hour notification of District Testing. Final approval of a JMF will be based upon field verification. According to 441.12 the JMF can be rejected for failure to verify in the plant or at the project. Do not apply the gradation requirements of 703.05 for fine aggregate. If the F/A ratio using total asphalt binder content is greater than 1.0 recalculate it using the effective asphalt binder content. Calculate the effective asphalt binder content according to the Asphalt Institute Manual Series No. 2. The value (calculated to the nearest percentage point) of the Fifty to Thirty (F -T) value, is the percent of total aggregate retained between the No. 50 (300 m) and No. 30 (600 m) sieves, minus the percent of total aggregate retained between the No. 30 (600 m) and No. 16 (1.18 mm) sieves. Use a PG 64 -22 asphalt binder for a Type 1 Intermediate course unless RAP and/or RAS used according to 401.04 require a virgin binder grade change. Use a PG 64 -22 asphalt binder for a Type 2 intermediate course unl ess RAP and/or RAS used according to 401.04 require a virgin binder grade change. Use a PG 64 -22 441.02 241 asphalt binder and Type 1 surface gradation for asphalt concrete for driveways and under guardrails. Identify the PG Binder supplier, as well as the polymer ty pe if applicable, on the JMF submittal. A change in polymer asphalt binder or polymer source will require a redesign. Provide on one page neatly summarized, dated test results for the requirements of Table 702.01 -1. Ensure data is no more than two months o ld. If SBR polymer is added at the asphalt concrete mixing plant, provide in the JMF data from the SBR polymer supplier for total solids (percent) and ash (percent) according to the 702.14. As well, provide the target amount of SBR polymer greater than or equal to 3.5 percent to achieve the properties specified. Include a letter of certification from the polymer supplier verifying percent butadiene in the SBS or SBR polymer. Report in the JMF submittal results of temperature -viscosity testing for mixing and compaction temperatures. For polymer asphalt binders, supplier recommended temperatures may be used in lieu of the temperature -viscosity results, but the temperature -viscosity results must still be reported. 441.03 242 TABLE 441.02 -1 Asphalt Mixture Composition Property Type 1 Surface Type 1 Intermediate Type 2 Intermediate 1 1/2 inch (37.5 mm)[1] 100 1 inch (25.0 mm)[1] 95-100 3/4 inch (19.0 mm)[1] 85-100 1/2 inch (12.5 mm)[1] 100 100 65-85 3/8 inch (9.5 mm)[1] 90-100 90 to 100 No. 4 (4.75 mm)[1] 45-57 50-72 35-60 No. 8 (2.36 mm)[1] 30-45 30 to 55 25-48 No. 16 (1.18 mm)[1] 17-35 17 to 40 16-36 No. 30 (600 m)[1] 12-25 12 to 30 12-30 No. 50 (300 m)[1] 5-18 5 to 20 5 to 18 No. 100 (150 m)[1] 2-10 2 to 12 2 to 10 No. 200 (75 m)[1] Asphalt Binder[2] 5.8-10.0 5.0 to 10.0 4.0 to 9.0 F/A Ratio, max.[3] 1.2 1.2 1.2 F-T Value[4] +2 +2 Blows[5] 50 50 50 Stability, min., pounds[5] (N) 1200 (5338) 1200 (5338) 1200 (5338) Flow, 0.25 mm[5] 8 to 16 8 to 16 8 to 16 Design Air Voids[6] 3.5 3.5 4.0 VMA, min.[7] 16 16 13 [1] Sieve, percent passing [2] Percent of total mix [3] Using effective asphalt binder content [4] Percentage points maximum [5] T 245 [6] Percent, Supplement 1036 [7] Percent, Supplement 1037

441.03 Use of Reclaimed Pavement . Comply with the requirements of 401.04.

441.04 Antistrip Additive . If the proposed JMF contains any gravel coarse

aggregate, or contains more than 25 percent natural sand, or contains more than 20 percent reclaimed asphalt concrete pavement conta ining gravel coarse aggregate, or is designed according to Item 442 conduct the following tests: Moisture damage potential test Supplement 1051 Washed gradation AASHTO T 11 as modified by Supplement 1004 Adherent fines test for each component ASTM D 5711 441.05 243 Modify the mix with one of the following antistrip additives if the results of the moisture damage potential test show the Tensile Strength Ratio (TSR) of the asphalt concrete mix to be less than 0.80 for 442 mixes or 0.70 for all other mix types: Liquid Antistrip Material. Include liquid antistrip material at a rate of 0.5 to 1.0 percent by weight of the asphalt binder. However, if 442 is specified, include liquid antistrip material at a rate of 0.50 to 1.25 percent by weight of the asphalt binder. Ensure the TSR of the asp halt concrete mix is greater than or equal to 0.80 after the addition of the liquid antistrip material. Hydrated Lime. Include hydrated lime in the dry form at a rate of 1.0 percent by the dry weight of aggregate for asphalt concrete. Conform to AASHTO M 3 03, Type 1 for hydrated lime. Ensure the TSR of the asphalt concrete mix is greater than or equal to 0.80 after the addition of the hydrated lime. Provide the Engineer the following information for each shipment of hydrated lime: Letter of certification, Production date, Shipment date, Shipment destination, Batch or lot number and Net weight. The Laboratory may obtain samples of the hydrated lime at any time to verify quality. If the quality of the hydrated lime is in question, the Laboratory may require in dependent laboratory testing. Include the antistrip additive in the mix design. Submit the following to OMM with the proposed JMF:

A.All TSR data (before and after the addition of the antistrip additive).
B.Rate of addition of the liquid antistrip mater ial, if used.
C.If using liquid antistrip material submit product information, information on use by other State DOTs using the liquid antistrip material, and a letter of certification. If using hydrated lime submit certified test data showing the hydrate d lime conforms to AASHTO M 303, Type 1.
D.Results of the washed gradation test of the individual components of the mix used in determining the combined gradation.
E.Results of the adherent fines testing for each component. OMM may perform additional te sts on lab or plant produced mix according to Supplements 1004, 1051, and 1052. If a change in the aggregate production is suspected, the Laboratory may require the Contractor to perform washed gradations on components and calculate adherent fines to deter mine the need for additional TSR review. Store and introduce antistrip additives into the plant according to Supplement 1053. Obtain Laboratory approval of the antistrip additive storage and feed systems prior to the start of production. Provide delivery tickets to the Engineer at the end of the project and at the end of each construction year on a multiple year project. The Engineer will verify the number of pounds of antistrip additive used is within 10 percent of the calculated amount of antistrip addit ive required for the total weight of asphalt binder, based on the JMF, used in the asphalt concrete.

441.05 JMF Field Adjustments. During the first three days of production the

Contractor may adjust the JMF gradation within the below limits without a redes ign of the mixture. For projects with less than 3 days of production, give District Testing 441.06 244 written notice of any JMF gradation adjustments within 1 workday following the last day of production. Limit adjustments of the JMF to conform to actual production, without a redesign of the mixture, to 3 percent passing each of the 1/2 inch (12.5 mm), No. 4 (4.75 mm), and No. 8 (2.36 mm) sieves and 1 percent passing the No. 200 (75 m) sieve. Do not exceed the limits in Table 441.02 -1 and Table 442.02 -2 in the adju sted JMF. The adjustment on the 1/2 inch (12.5 mm) sieve applies only to Type 2 mixes. Determine the need for any JMF gradation adjustments in the time specified. Should no adjustments be made, the Department will base acceptance on conformance to the orig inal JMF. After the time period specified, the Department will allow no further adjustment of the JMF . Should a redesign of the mixture become necessary, submit a new JMF according to the requirements for the initial JMF. A new acceptance lot will begin wh en a new JMF established by a redesign of the mixture becomes effective. Make any adjustment of this new JMF as provided for the original JMF. Record both the design JMF and the adjusted JMF in effect during production of an acceptance lot on the Quality C ontrol Report for that lot. In the event that a new JMF is proposed and approved, also make a notation on the ticket for the first load produced under the new JMF.

441.06 Monitoring. The Department will establish District Monitoring Teams

for the purpose o f verifying all Contractor mixture production processes. Verification may be accomplished by obtaining split samples from Contractor QC or independent samples from the plant or roadway. If independent samples are taken split them for Contractor testing. If the mixture quality verifies then production may continue. If mixture quality does not verify then the Monitoring Team and Contractor will cooperatively investigate and resolve the problem. Whenever results are disputed OMM will investigate and conduct ad ditional testing to resolve. Based on their review, the Monitoring Team may at any time disallow production to continue.

441.07 Quality Control Program. Submit a QCP according to 403.03. Include

an example control chart according to 441.10 with the QCP. Use quality control technicians working in the plant lab during all mixture production and that are approved by the Department. Technician approval will be according to Supplement 1041.

441.08 Testing Facilities. Provide testing facilities at the plant sit e conforming

to Supplement 1041.

441.09 Quality Control Tests. Perform quality control tests to control the asphalt

concrete mix within the specifications. As required by mix type, ensure that these quality control tests measure the asphalt binder content , gradation, air voids, and Maximum Specific Gravity (MSG) according to the Contractor’s QCP. Perform each quality control test a minimum of one time each half of a production day or night (two tests per production day or night), or one each 1400 tons (130 0 metric tons), whichever is less. Perform more sampling and testing than the minimum specified at the start of production. Additionally perform more sampling and testing than the minimum during production when the quality control tests show the asphalt concrete being 441.09 245 produced is outside the warning bands as shown in the Contractor’s QCP. Immediately resolve problems indicated by any test result exceeding the warning bands and immediately retest to validate corrections have returned the materials to within the warning band limits. The Contractor may determine the method of testing of the asphalt concrete beyond the minimum speci fied, and will detail the methods technicians will follow in the Contractor’s QCP. Should additional testing as required above not be performed District Testing, after consultation with OMM, will require the testing frequency be increased to all tests eve ry two hours of production for the remainder of the project. If this occurs, District Testing will request an opinion from the QCQC for action(s) against the technician and/or Contractor including but not limited to warning, removal and/or a change of the facility to Unconditional Acceptance. Record the results of every test performed. Perform the required quality control tests as follows:

A.Asphalt Binder Content. Determine the asphalt binder content of a sample of asphalt concrete by performing an Asph alt Content (AC) Gauge test according to Supplement 1043. Make all printouts available for review by the Monitoring Team at any time. Offset the AC Gauge for each JMF on each project at the project’s start. Perform the offset using the solvent extraction m ethod for every QC sample according to Supplement 1038 and the AC Gauge Verification and Offset Record until the offset is established. Use solvent extraction according to Supplement 1038 when an AC Gauge problem exists and for testing cooled samples that cannot adequately be tested in an AC Gauge test. Total, for each day’s production, the flow meter printouts for SBR polymer added at the asphalt concrete mixing plant. Calculate the percent of polymer versus neat asphalt binder in the mix each day and reco rd on the TE -199. Hold calculation worksheets and printouts in the plant laboratory for review by the Monitoring Team. A +/- 0.2 percent tolerance from the target amount of SBR polymer will be used as a guide for an acceptable amount of SBR polymer, but co nsistently low will not be acceptable. Only take SBR PG -Modified Binder samples using a five gallon (19 L) bucket. Take 1 gallon (4 L) to clean the valve port and discard. Take 2 gallons (7.5 L) again, stir its contents and transfer to the required sample containers. Determine the moisture content of the asphalt concrete for each AC Gauge test. Maintain the moisture content at 0.8 percent or less.
B.Gradation. Perform at least one gradation test each production day on aggregate remaining after removing the asphalt binder with a solvent from an asphalt concrete sample used in an AC Gauge test (solvent sample) or on aggregate remaining after removing the asphalt b inder with a preapproved asphalt ignition oven according to Supplement 1054 and from an asphalt concrete sample used in an AC Gauge test (ignition oven sample). Use only an asphalt ignition oven to obtain an aggregate sample from an asphalt concrete sample having a polymer modified PG Binder. District Testing may make an exception to this for SBS polymer as long as no issues arise. Correct each solvent sample for ash. Perform all other gradations on solvent samples, ignition oven samples, or on samples obta ined according to the Contractor’s QCP. 441.09 246 The gradation results of all the sieves must be representative of the JMF. If the Contractor fails to control the entire gradation, the Laboratory may require a redesign according to 441.02. When the F -T value is sp ecified for a mix in 441.02 calculate it for each gradation analysis. Maintain the F -T value at +4 percentage points or less for these mixes. Calculate the F/A ratio for every solvent sample or ignition oven sample analysis. Maintain the F/A ratio so no F/ A ratio is greater than 1.2 for all mixes. Use the asphalt binder content determined by the AC Gauge for calculating the F/A ratio. If the F/A ratio is greater than 1.0, recalculate the F/A ratio using the effective asphalt binder content. Calculate the ef fective asphalt binder content on the calculation sheet using the asphalt binder content determined by the AC Gauge and attach it to the Quality Control Report. Use bulk and effective aggregate specific gravities and remaining values needed in the calculat ion from the approved JMF. Do not deviate from these values without OMMs approval. If the F/A ratio is greater than 1.0 for ignition oven samples, calculate the F/A ratio using the percent passing the No. 200 (75 m) sieve from a washed gradation of the ig nition oven sample according to AASHTO T 30.
C.Air Voids and MSG. Determine the air voids of the asphalt concrete by analyzing a set of compacted specimens and a corresponding MSG determination according to Supplement 1036. Ensure that the cure temperatur e and specimen compaction temperature are the same. Use a 1 -hour cure for all mix samples used in voids analysis. The Contractor may use a 2 -hour cure time if voids are consistently near the low void warning band. In this case, use the 2 -hour cure for all voids testing through the remainder of the project. For hot mix asphalt use the JMF lab compaction temperature. For warm mix asphalt according to 402.04 use a lab compaction temperature 30.0 ºF (16.7 ºC) less than the JMF lab compaction temperature for hot mix asphalt. Use a compaction temperature tolerance of +/ - 5.0 ºF (3.0 ºC). Record on the TE -199 if the mixture produced was ran at the asphalt plant as a hot mix asphalt (HMA) or as a warm mix asphalt (WMA) produced according to 402.04 or another approve d method. Calculate the Voids in Mineral Aggregate (VMA) value for every set of compacted specimens according to Supplement 1037. Calculate the average of all the MSG determinations performed each production day and report this average on the Quality Contr ol Report. When the range of three consecutive daily average MSG determinations is equal to or less than 0.020, average these three average MSG determinations to determine the Maximum Theoretical Density (MTD). After the MTD is established, compare all ind ividual MSG determinations to the MTD. Whenever compacted specimens are to be made and an MSG determination is to be run, take a sample of sufficient size to run a corresponding AC Gauge test. When the air void and MSG test results are recorded reference t hem to the AC Gauge test of the sample.
D.Other Requirements. Supply proper containers and take two 1 quart (1 L) asphalt binder samples from the first transport truck load of each different asphalt 441.10 247 binder grade of the project before incorporation into th e storage tank. Label the samples with binder grade, supplier, project number and date and retain them in the plant laboratory for future reference by the Department. Discard the samples at project finaling if not taken by the Monitoring Team. Retain a sp lit sample for each AC Gauge test and MSG test and all compacted specimens for monitoring by the Department. Maintain MSG samples in the state described in ASTM D 2041, Section 9.2. The Contractor may dispose of the AC Gauge test samples after two days and all other split samples after seven days if the Department does not process the split samples. Measure the temperature of the mixture and record. Validate the results on the load tickets at least once during each hour of production. The Contractor may con duct additional testing of any type. Record such additional testing along with all other quality control records and have these records readily available for the Monitoring Team’s review. The Laboratory may observe, review, and approve the procedures at an y time.

441.10 Control Charts. Maintain up to date control charts showing each

individual test result and also the moving accumulative range as follows:

A.Plot tests showing the percent passing for the 1/2 inch (12.5 mm), No. 4 (4.75 mm), No. 8 (2.36 mm) , and No. 200 (75 µm) sieves, the percent asphalt binder content, the MSG, and the percent air voids. Round all percentages to the nearest whole percent; except, round asphalt binder content, the No. 200 (75 µm) sieve, and air voids to the nearest 0.1 perc ent.
B.Show the out of specification limits specified in Table 441.10 -1 and QCP Warning Band Limits on the control charts.
C.Label each control chart to identify the project, mix type and producer.
D.Record the moving accumulative range for three test s under each test point on the chart for air voids and asphalt binder content. Accumulative range is defined as the positive total of the individual ranges of two consecutive tests in three consecutive tests regardless of the up or down direction tests tak e. If more than the minimum required testing (i.e. two tests per production day or night, 441.09 first paragraph) is performed do not include the result in accumulative range calculations. Stop production and immediately notify the Monitoring Team when either E or F occurs:
E.Any two tests in a row or any two tests in two days are outside of the specification limits of Table 441.10 -1.
F.Any four consecutive moving accumulative ranges greater than specification limits of 2.50 percent for air voids or 0.60 percent for asphalt binder content occur. Any mixture sent to the paving site without stopping production and notifying the Monitoring Team, when required by this specification, will be considered non - specification material. Do not restart productio n until an adequate correction to remedy problems is in place and the Monitoring Team is satisfied. Following a shutdown restart 441.11 248 production in a manner acceptable to District Testing. When production problems cannot be solved within one day after a plant s hut down a Contractor’s representative holding Level 3 Asphalt Department approval is required to be at the asphalt plant until a full production day is achieved with results satisfactory to the Monitoring Team. TABLE 441.10 -1 Mix Characteristic Out of Sp ecification Limits[5] Asphalt Binder Content[1] -0.3% to 0.3% 1/2 inch (12.5 mm) sieve[1] -6.0% to 6.0% No. 4 (4.75 mm) sieve[1] -5.0% to 5.0% No. 8 (2.36 mm) sieve[1] -4.0% to 4.0% No. 200 (75 m) sieve[1] -2.0% to 2.0% Air Voids[2] 2.5% to 4.5% Air Voids[3] 3.0% to 5.0% MSG[4] -0.012 to 0.012 [1] deviation from the JMF [2] for Design Air Voids of 3.5% [3] for Design Air Voids of 4.0% [4] deviation from the MTD [5] unless otherwise restricted by mix type specification

441.11 Quality Control Reports. Use Contractor Form TE -199 for the Quality

Control Report. Record all test results on the Quality Control Report. Document all decisions regarding responses to test results on the Quality Control Report (referring to the particular test), includin g reasons why a particular problem may exist, what action was taken to correct the problem (plant operation or testing), and what communication with Department personnel took place. Submit one Quality Control Report to District Testing no later than specif ied. Retain copies of all records documenting the quality control inspections and tests throughout the life of the Contract and furnish them to District Testing on request.

441.12 Mixture Deficiencies. Control all production processes to assure the

Engine er that the mixture delivered to the paving site is uniform in composition; within the specification requirements and limits; conforms to the JMF: and that the placed mixture is free of any defect (ex. segregation, tenderness, lack of mixture and/or textur e uniformity, raveling, flushing, rutting, holes, debris etc.) within the Contractor’s control. Correct obvious pavement problems according to 401.15. If the Department has any suspicion that other mixture composition or pavement problems exist, the Monito ring Team will conduct an initial investigation through review of data and/or sampling of the asphalt pavement. Should a Department investigation determine that the Contractor’s QCP is not controlling the mixture in a manner to achieve mixture quality as d escribed above, the Contractor quality control data may be rejected. In that case the Department will conduct a thorough investigation by testing samples from the roadway and use those test results in determining disposition of the non -specification materi al. 441.13 249 A mixture is not uniform in composition if multiple random non -specification individual tests or any four consecutive non -specification moving accumulative ranges exist. The mixture can be rejected, production can be stopped and/or a redesign can be ca lled for by the Department. OMM will not approve any redesign it determines is unsatisfactory to provide acceptable mix performance. Submit this new design for approval according to 441.02 and at no additional cost to the Department. When any out of speci fication material, based on quality control tests not within the limits of Table 441.01 -1, is sent to the paving site the Engineer will determine disposition of the material according to Supplement 1102.

441.13 Acceptance . The Department will base accepta nce of the asphalt concrete

mix on the item specified in the Contract item description. (i.e., 446, 447, 448).

441.14 Basis of Payment . The Department will pay for accepted quantities at the

contract prices as follows: Item Unit Description 441 Cubic Yard Asphalt Concrete Surface Course, (Cubic Meter) Type ___, (___), PG64 -22 441 Cubic Yard Asphalt Concrete Surface Course, (Cubic Meter) Type ___, (___), PG70 -22M 441 Cubic Yard Asphalt Concrete Intermediate Course, (Cubic Meter) Type 1, (448) 441 Cubic Yard Asphalt Concrete Intermediate Course, (Cubic Meter) Type 2, (___) 441 Cubic Yard Anti-Segregation Equipment (Cubic Meter) ITEM 442 SUPERPAVE A SPHALT CONCRETE

442.01 Description

442.02 Type A Mix Design

442.03 Type B Mix Design

442.04 Asphalt Binder

442.05 Quality Control

442.06 Compaction

442.07 Acceptance

442.08 Basis of Payment

442.01 Description. This work consists of gyratory mix design, material, and

quality control requirements for constructing a Superpave asphalt concrete pavement surface or intermediate course. The asphalt concrete pavement course consists of aggregate, and asphalt binder mixed in a central plant and spread and compacted on a prepared surface. The requirements of Item 441 apply, except as modified by this specification. When specified, provide anti -segregation equipment for all courses of uniform thickness in accordance with 401.12. 442.02 250 442.02 Type A Mix Design. Design the mixture composition for a Type A mix according to 441.02 and the most recent Asphalt Institute Manual Series No. 2 (MS -

2.for design procedures and material properties except as modified by this subsection. Include in the JMF submittal the standard Departme nt cover and summary page; all printouts from the gyratory compactor (all gyratory points not necessary); and analysis covering the required mix properties. Unless otherwise directed submit one compacted gyratory sample and loose mix for compaction of another sample, in addition to a 5 pound (2000 g) loose sample, for each JMF . The Contractor may use the Marshall flow test in design as an indicator of potential for excess tenderness. Supply aggregate according to the lane current average daily truck traffi c (Lane ADTT) as follows unless otherwise shown on the plans: Lane ADTT = Current ADT × T 24 × 0.45 Where: Current ADT = current average daily traffic count from the plans T24 = percent trucks per day from the plans TABLE 442.02 -1 GYRATION LEVEL AND M ATE RIAL REQUIREMENTS Lane ADTT Nini Ndes Nmax Coarse Aggregate Angularity Fine Aggregate Angularity Flat and Elongated Particles Sand Equivalent <4000 7 65 105 95 [1] /90 [2] 44 10 45 ≥4000 7 65 105 100 [1] /100 [2] 44 10 50 [1] Percent fractured (one or more faces) according to ASTM D5821 [2] Percent fractured (two or more faces) according to ASTM D5821 Submit aggregate to be used to OMM for approval a minimum of 3 weeks before submitting a JMF for approval. If fine aggregate is from crushed carbonate stone or air -cooled blast furnace slag, the Department will not require the fine aggregate angularity (FAA) test. The Department will allow a blend of a material not meeting the FAA with a material that meets the FAA, but calculate the FAA result based on the individual Department FAA results and actual blend percentages. Obtain OMM approval of any blends. The restricted zone does not apply. Use control points according to MS-2, except as specified in Table 442.02 -2. 442.03 251 TABLE 442.02 -2 AGGREGATE GRADATION R EQUIREMENTS Sieve Size 9.5 mm mix 12.5 mm mix 19 mm mix Total Percent Passing 1 1/2 inch (37.5 mm) – – 100 3/4 inch (19 mm) – 100 85 to 100 1/2 inch (12.5 mm) 100 95 to 100 90 max 3/8 inch (9.5 mm) 90 to 100 96 max – No. 4 (4.75 mm) 70 max 52 to 6 0[1] – No. 8 (2.36 mm) 34 to 52 34 to 45 28 to 45 No. 200 (75 µm) 2 to 8 2 to 8 2 to 6 [1] For the No. 4 sieve do not exceed 63 in production. Ensure that the F/A ratio is a maximum of 1.2. Use a 2 -hour cure for the mix design. If more than 15 percent fine aggregate not meeting FAA is used, perform a loaded wheel test (LWT) according to Supplement 1057. To estimate a LWT sample mix volume, use the bulk density from gyratory specimens at N des. Results less than 0.20 inch (5.0 mm) at 120 F (49 C) are considered passing. The Contractor may use reclaimed asphalt concrete pavement according to

401.04 Test design volumetric properties at N des. Test N max for the required criteria.

Ensure that the VMA is not less than the minimum values of Table 442.02 -3. TABLE 442.02 -3 VMA CRITERIA Mix VMA (percent minimum) 9.5 mm 15.0 12.5 mm 14.0 19.0 mm 13.0

442.03 Type B Mix Design. Apply the mix design specified in 442.02 for a

Type A mix except as modified by this subsection: Modify the Coarse Aggregate Angularity of Table 442.02 -1 according to Table

442.03 1.

TABLE 442.03 -1 Lane ADTT Coarse Aggregate Angularity <4000 65 [1] /65 [2] ≥4000 75 [1] /70 [2] [1] Percent fractured (one or more faces) according to ASTM D5821 [2] Percent fractured (two or more faces) according to ASTM D5821 Ensure that at least 50 percent by weight of virgin fine aggregate is aggregate meeting FAA or is crushed carbonate stone or air -cooled blast furnace slag. Modify the No. 8 (2.36 mm) sieve requirement for a 12.5 mm mix in Table 442.02 -2 to 34 to 40 percent. Apply an F -T value of +2 according to 441.02 and 441.09.

442.04 Asphalt Binder. Use a PG 70 -22M asphalt binder for surface courses

and a PG 64 -28 asphalt binder for intermediate courses. The minimum total asphalt binder content for a surface course is 5.7 percent. 442.05 252 442.05 Quality Control. Conform to 441.09, except as specified in this subsection. Ensure that plant operation and quality control testing conform to the Contractor’s Quality Control Program (QCP). For 12.5mm mi xes ensure the percent passing the No. 4 sieve does not exceed 63 in production. If two tests in a row or any two tests in two days (QC and/or 448 sublot) exceed 63 stop production and notify District Testing . Use a gyratory compactor conforming to the requirements of Superpave. If the gyratory compactor was moved to the plant before production, calibrate it and present the results to District Testing. Determine bulk gravity for air voids determination on specimens compacted to Ndes. If the design gradation requires an LWT test, take a sample sufficient to run a LWT test once each day for the first 3 days and test it according to Supplement 1057. The Cont ractor may perform the LWT test in the Contractor’s Level 2 laboratory, but must compact the sample the same day the sample was taken, cure it overnight, and test it the following day. Give the test result and sample density to District Testing the day of the LWT test. Report the LWT data on the Quality Control Report.

442.06 Compaction . Cease production if compaction causes bumps in the mix

or the mix is excessively tender.

442.07 Acceptance . The Department will base acceptance of the asphalt

concrete mix on the method specified in the Contract line item description (i.e., 446, 447, 448).

442.08 Basis of Payment . The Department will pay for accepted quantities at

the contract prices as follows: Item Unit Description 442 Cubic Yard Asphalt Concrete Surface Course, (Cubic Meter) (____ mm), Type ____ (___) 442 Cubic Yard Asphalt Concrete Intermediate Course, (Cubic Meter) (____ mm), Type ___ (___) 442 Cubic Yard Anti-Segregation Equipment (Cubic Meter) ITEM 443 STONE MATRI X ASPHALT CONCRETE

443.01 Description

443.02 Quality Control Program

443.03 Composition

443.04 Mixing

443.05 Storage

443.06 Quality Control

443.07 Construction

443.08 Acceptance

443.09 Basis of Payment 443.01

443.01 Description. This work consists of constructing a stone matrix asphalt

concrete (SMA) course consisting of aggregate, asphalt binder, and additives. The requirements of 442 and 446 apply except as follows. Do not use the warm mix asphalt method (402.04) for this item.

443.02 Quality Control Program. Update the Quality Control Program

meeting 403.03 to include a section for how the quality control, production and placement of SMA will meet this specification. Submit the revised program to OMM with the SMA mix design to be approved.

443.03 Composition. Discuss the mix design approach with OMM during the

mix design process and prior to submittal.

A.Design Limits . Submit a JMF to the Laboratory which meets the requirements of Table 443.03.1 and Table 443.03 -2. TABLE 443.03 -1 MIX GRADATION Sieve size Total Percent Passing 3/4 inch (19.0 mm) 100 1/2 inch (12.5 mm) 85 to 100 3/8 inch (9.5 mm) 50 to 75 No. 4 (4.75 mm) 20 to 28 No. 8 (2.36 mm) 15 to 24 No. 50 (300 µm) 10 to 20 No. 200 (75 µm) 8 to 12 TABLE 443.03 -2 MIX PROPERTIES Property Description Specification Binder, % [1] 5.8 to 7.5 VMA, % [2] 16.0 to 19.0 Draindown Test, % [3] 0.3 Design Air Voids, % 3.5 Design Gyrations [4] 65 VCA MIX / VCA DRC [5] < 1.0 TSR [6] 0.80 F/A NA [1] By total mix [2] Based on bulk gravity [3] AASHTO T305 conducted at mix production temperature (not compaction temperature) [4] Nini and N max do not apply [5] VCA = Volume of Coarse Aggregate (Calculated for mix and dry rodded conditions according to AASHTO PP41 - 02 or newer versio n.) [6] Unconditioned specimens will have a minimum 65 psi (450 kPa) retained strength. Compact specimens at 300 °F (149 °C) for PG 70 -22M and 310 °F (154 °C) for PG 76 -22M.
B.Asphalt Binder . Provide asphalt binder conforming to 702.01.
C.Coarse Aggrega te. Use approved coarse aggregates. Ensure coarse aggregates meet 703.05 and Table 443.03 -3. 443.03 254 TABLE 443.03 -3 AGGREGATE REQUIREMEN TS Tests Description Specification ASTM D 4791 % Flat and Elongated Ratio at 3:1, (max. to min.) 5:1, (max. to min.) 20 max 5 max ASTM D 5821 % Crushed, one / two faces 100 / 90 min AASHTO T 96 LA Abrasion (stone or gravel) 35 max
D.Mineral Filler . Conform to 703.07. Use mineral filler in the JMF with a plasticity index (AASHTO T 90) not greater than 4 (does not apply to hydrated lime). Reclaimed asphalt concrete pavement passing the 5/8 inch (16 mm) sieve may be used as filler only. Do not account for reclaimed asphalt concrete pavement binder content. Do not use quicklime (CaO). Do not premix filler with another aggregat e. Cover mineral filler piles to protect from rain. Blend the mineral filler, asphalt binder and fiber stabilizer into a homogenous mixture and test the mortar for the following properties of Table 443.03 -4. TABLE 443.03 -4 MORTAR TEST REQUIREM ENTS Tests Description Specification AASHTO T315 Unaged DSR, G*/ sin  (kPa) 5 minimum AASHTO T315 & T240 RTFO Aged DSR, G*/ sin  (kPa) 11 minimum AASHTO R28 & T313 PAV Aged BBR, Stiffness (MPa) 1500 maximum
E.Reclaimed Asphalt Concrete Pavement . Do not use reclaimed asphalt concrete pavement except as described in D above.
F.Fiber Stabilizer. Choose and meet the requirements of one of the following fiber stabilizers. Submit with the JMF submittal the fiber manufacturer’s most recent actual test data and a c ertification of compliance for the fiber type to be used. Protect the fiber stabilizer from moisture or other contamination. Cellulose Fibers. Add the fiber at a dosage rate of 0.3 to 0.4 percent by weight of the total mix as directed by District Testing t o control draindown in production.
1.Fiber Length (max) 0.25 inches (6.35 mm)
2.Sieve Analysis – Alpine Sieve Method Sieve size Total Percent Passing No. 100 (150 µm) 60 to 80 Sieve Analysis – Ro-Tap Sieve Method Sieve size Total Percent Passing No. 20 (850 µm) 80 to 95 No. 40 (425 µm) 45 to 85 No. 100 (150 µm) 5 to 40
3.Ash Content 18% non -volatiles (±5%)
4.pH 7.5 (±1.0)
5.Oil Absorption (times fiber weight) 5.0 (±1.0)
6.Moisture Content (max) 5.0% Cellulose Pellets . Cellulose pellets consist of cellulose fiber and may be blended with 0 to 20 percent asphalt binder. Meet the cellulose fiber requirements above. If no asphalt binder is used, add the pellet at a dosage rate of 0.3 to 0.4 percent 443.04 255 by weight of the total mix as directed by Di strict Testing to control draindown in production. Adjust the fiber dosage to maintain the desired fiber amount when fiber is pre -blended with binder. Maximum Pellet size 1/4 cubic inch (4000 mm3) Binder 25 to 80 pen. Mineral Fiber. Use mineral fibers m ade from virgin basalt, diabase, or slag treated with a cationic sizing agent to enhance disbursement of the fiber as well as increase adhesion of the binder to the fiber surface. Add the fiber at a dosage rate of 0.3 to 0.4 percent by weight of the total mix as directed by District Testing to control draindown in production. Average Fiber length (max) 0.25 in (6.35 mm) Average Fiber thickness (max) 0.0002 in (0.005 mm) Shot content (ASTM C612) Percent Passing No. 60 (250 µm) sieve Percent Passing No. 230 (63 µm) sieve 90 to 100 65 to 100 Degradation (max)[1] 30 percent [1] (GeorgiaDOT -124/McNett) - copy available from OMM .

443.04 Mixing. Conform to the following additional requirements.

A.Fiber Stabilizer. Furnish feeder equipment specifically m anufactured to uniformly feed fiber into the plant and that is automated through connection with plant controls. Include a low level and no -flow indicator, print out the feed rate of the feeder supply system, and include a transparent pipe section for obse rving flow consistency. District Testing will approve the fiber feed system prior to the start of production by a trial load of SMA and inspection of the bag house collected material. Conduct and document a weekly quick check of the fiber feed calibration according to the Quality Control Plan. Conduct a daily check of fiber usage by calculating and documenting on the TE 199 that fiber usage is within 10 percent of the intended usage. In drum plants, add the fibers in loose form, by an automated calibrated feed system, such that the fibers are coated by asphalt binder before being caught in the drum air flow. In batch plants, distribute the fiber uniformly before injecting asphalt binder and increase mixing time a minimum of 5 seconds.
B.Mineral Filler. Filler may be fed through a hopper if consistency of flow is achieved. If a problem in feeding consistency occurs a pneumatic system will be required. Feed filler into the weigh hopper or pug mill of a batch plant, or at a point away from the flame on a drum plant.

443.05 Storage. Do not store the SMA at the plant for more than 2 hours. Do

not exceed a mix temperature of 350 °F (180 °C). Provide SMA at a minimum of 300 °F (148 °C) when it arrives at the paver, unless otherwise approved by OMM. If draindown occ urs shorten the storage time and increase the fiber dosage.

443.06 Quality Control. Ensure an employee of the Contractor with a Level 3

rating is at the plant or construction site during production of the SMA for any test strips and through at least one fu ll production day satisfactory to the District. 443.07 256 Perform quality control tests every 3 hours of production. The increased frequency of quality control testing may require additional quality control personnel at the plant. Determine the asphalt binder conten t, gradation, moisture content, air voids, VMA, and MSG of the SMA. For each test series calculate the VCAMIX / VCADRC. If the limit of 1.0 is exceeded stop production until resolved. Perform a draindown test once each day of production and raise fiber dos age 0.1 percent if the test limit is exceeded. Do not exceed the No. 200 (75 µm) sieve design bands by the moving average of three tests. Compact specimens at 300 °F (149 °C) for PG 70 - 22M and 310 °F (154 °C) for PG 76 -22M. Due to sample variability with S MA, a larger than usual sample size from which material is obtained for the various tests is required.

443.07 Construction. At least 24 hours prior to beginning a test strip meet with

the Engineer and District Testing and provide a written summary of steps taken to assure mix quality and construction practices account for the special needs of SMA production and placement. Send a copy of the written summary to OMM.

A.Test Strips and JMF Adjustment . Do not begin full production of the SMA until receiving authorization from District Testing. This authorization will be based on the successful construction of one or more test strips. Test strips consist of 50 to 100 tons of SMA produced and placed in accordance with these specifications. Cease SMA production that day unless another test strip is needed. Place test strips in one continuous mat. The test strip will be included in the first lot for determining density for payment. During the construction of a test strip, perform one set of quality control tests as described above and obtain and test 3 random cores of the compacted pavement. Within 1 working day after a test strip is completed, the Laboratory and the Contractor's Level 3 employee will determine if any changes in the SMA JMF, production, or placemen t procedures are needed. A redesign of the JMF or another test strip may be required. OMM will notify District Testing of any JMF adjustments. Do not start production until notified by District Testing.
B.Compaction. Start compaction immediately after the SMA has been placed. Use only steel wheel rollers. Vibratory rollers in vibratory mode, set at a high frequency and low amplitude, can be used as the breakdown roller only. Always operate the breakdown roller immediately behind the paver. If isolated, sma ll fat spots develop, apply sand immediately during compaction. If continuous and/or large fat spots develop, cease production until resolved. Do not compact SMA that is below 230 °F (110 °C).
C.Hauling. Do not allow trucks to dump any mix on the project mat after delivering mix to the paver. Provide a suitable place for bed cleaning off of the mat.

443.08 Acceptance. After accepting the test strips, the Department will accept

SMA according to 446.04.

443.09 Basis of Payment. The Department will pay for ac cepted quantities of

Stone Matrix Asphalt Concrete, complete in place, including test strip, at the contract price as modified by 446.04, as follows:

Source: Ohio Construction and Material Specifications, 2019 Edition. Pages 00 of 928.